High Court of KeralaDivision BenchWrit Appeals allowed; judgment of the learned S...

Green Track Engineers and Construction v. Kerala Minerals and Metals Ltd. (KMML) & TVK Construction & Deepthi Transport Service

Case / Petition Number:W.A. Nos.1338 & 1354 of 2013; W.P.(C) Nos.9984/2013, 10095/2013, 21923/2013

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • K. T. Sankaran
  • M. L. Joseph Francis
Judgment Date
2014-01-15
Court Decision / Holding
Division Bench allowed the writ appeals, set aside the learned single judge’s judgment, and allowed W.P.(C) Nos.9984 and 10095 of 2013. It held that KMML’s award to TVK was vitiated by illegality, arbitrariness and malice, particularly due to improper timing in tender issuance and potential involvement of an KMML employee with TVK. The Court left W.P.(C) No.21923/2013 open for future consideration and did not convert the PIL into a challenge to the contract’s terms. The judgment clarifies that the remedy is to annul the award and potentially direct re-tender; corrected the final paragraph to ensure the reliefs granted were specified “to the extent indicated above.”
Final Disposition
Writ Appeals allowed; judgment of the learned Single Judge set aside; W.P.(C) Nos. 9984 and 10095 of 2013 allowed; W.P.(C) No.21923 of 2013 left open for future consideration; correction issued to last paragraph for precision in relief granted.

Parties to the Case

Appellants / Petitioners

  • M/S. Green Track Engineers and Construction, VII/143 A, Panmana, Karunagappally, Kollam District (represented by its Operation Manager, Pradeep R.)

Respondents

  • Kerala Minerals and Metals Ltd. (KMML) - Mineral Separation Unit, Kovilthottam, Chavara, Kollam
  • TVK Construction, Aramam, Padanayarkulangara North, Karunagappally, Kollam
  • Deepthi Transport Service, Vadakkidam Building, Karithura, Chavara, Kollam

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri. Grashious Kuraiakoose (Sr.)
  • • Sri. George Mathews

Counsels for Respondents

  • • Sri. K. Anand (Sr.)
  • • Smt. Latha Krishnan
  • • Sri. S. Sharan

Case Synopsis & Summary

The Kerala Minerals and Metals Ltd. (KMML), a Government of Kerala undertaking, invited sealed tenders for excavation and transportation of 2,73,000 MT of mineral sand for one year. Tender notice dated 21.2.2013 appeared in two Malayalam dailies; tenders were to be issued from 4.3.2013 to 14.3.2013 and bids with EMD were due by 15.3.2013. Three bids were submitted: Green Track (lowest at ₹350/MT), TVK Construction (₹410/MT) and Deepthi Transport (₹413/MT). The commercial bid of Green Track was opened, but their tender was eventually rejected after a legal opinion. Green Track challenged KMML’s award of the contract to TVK, seeking quashal of the award and mandamus to accept Green Track’s bid. Renjith Babu also filed separate petitions questioning the process. The learned single judge dismissed the petitions, holding that Ext.P4 circular (9.9.2004) was not applicable to this excavation contract, and that the price hike could be justified. The Division Bench reversed, holding that the tender process was vitiated by illegality, arbitrariness and malice, in particular due to the involvement of KMML employee Sri K. Radhakrishnan who joined TVK, and the timing abnormalities in issuing tender forms (11.3.2013 start, 15.3.2013 closing, etc.). The court quashed KMML’s proceedings awarding the contract to TVK and allowed W.P.(C) Nos. 9984 and 10095 of 2013, while leaving PIL-related contentions in W.P.(C) No. 21923 of 2013 open for future consideration.

Provisions of Law Cited

Constitution of India Article 14Constitution of India Article 21Constitution of India Article 19(1)(g)

Legal Doctrines & Maxims

  • Level playing field doctrine (Article 19(1)(g))
  • Reasonableness and rationality under Article 14
  • Judicial review: illegality, irrationality, and procedural impropriety
  • Public auction/public tender as a cornerstone of transparency
  • Trust doctrine in disposal of public property
  • Public interest litigation limits (BALCO)
  • Non-discrimination under Article 14

Submissions & Arguments

Contentions of Appellants / Petitioners

Green Track contended that its bid was the lowest (₹350/MT) and was improperly rejected after the price bid. It argued that the tender was issued with insufficient notice (deadline misalignment), that the pre-qualification criteria were not adequately communicated, and that KMML’s internal dealings—especially the involvement or influence of KMML employee K. Radhakrishnan in TVK’s favor—tainted the process. It stressed the need for a fair, transparent tender process and that the circular Ext.P4, though intended for employee engagements, should be read to apply to all contracts, not just transport contracts. It urged quashing the award to TVK and directing a fresh, fair bidding process consistent with constitutional guarantees of equality and non-discrimination.

Contentions of Respondents

KMML defended its actions, asserting Green Track failed to satisfy eligibility criteria and that the tender process had appropriate safeguards. It argued that Ext.P4 circular was an internal control measure, not a blanket prohibition, and that any alleged malafide was unproven or insufficient to warrant interference. KMML contended that rights of third parties and procedural requirements were observed, and that extending deadlines was not a violation per se. It also argued that PIL petitions were not maintainable for challenges to contractual terms and that the court should refrain from scrutinizing tender terms except on established grounds.

Cited Precedents (16)

Case NameCitationTreatmentExplanation
Nagar Nigam, Meerut v. Al Faheem Meat Exports (P) Ltd. and others(2006) 13 SCC 382PositiveUsed to emphasize that government contracts should be awarded through public auction/tender with broad publication to ensure transparency and competition.
Reliance Energy Ltd. and another v. Maharashtra State Road Development Corpn. Ltd. and others(2007) 8 SCC 1PositiveSupports the 'level playing field' doctrine and the need for non-discriminatory, transparent tender processes.
Ramana Dayaram Shetty v. The International Airport Authority of India and othersAIR 1979 SC 1628PositiveCited for principles of how public bodies must deal fairly with the public; non-arbitrary action.
E. P. Royappa v. State of Tamil Nadu(1974) 2 SCR 348; AIR 1974 SC 555PositiveSupports the requirement that state action must be rational and non-arbitrary under Article 14.
Maneka Gandhi v. Union of India(1978) 1 S.C.C. 248; AIR 1978 SC 597PositiveReinforces reasonableness and due process under constitutional guarantees.
Jagdish Mandal v. State of Orissa and others(2007) 14 SCC 517PositiveGuides judicial review standards to assess mala fides, arbitrariness, and public interest.
Tejas Constructions and Infrastructure Private Limited v. Municipal Council, Sendhwa and another(2012) 6 SCC 464PositiveAffirms three-pronged test for judicial intervention in contractual matters.
Michigan Rubber (India) Limited v. State of Karnataka and others(2012) 8 SCC 216PositiveAffirms level playing field and objectivity in tender processes.
Villianur Iyarkkai Padukappu Maiyam v. Union of India and others(2009) 7 SCC 561PositiveNotes PIL cannot be used to challenge purely financial/economic government decisions.
BALCO Employees' Union (Regd.) v. Union of India(2002) 2 SCC 333PositiveLimits the use of public interest litigation against financial/economic government decisions.
Air India Ltd. v. Cochin International Airport Ltd. and others(2000) 10 SCC 1; AIR 2000 SC 801PositiveJudicial review of decision-making process to prevent arbitrariness.
Rajasthan State Industrial Development and Investment Corporation v. Diamond & Gem Development Corporation Limited and another(2013) 5 SCC 470PositiveContract terms/choices cannot be compelled by writ; tender terms are contractual.
Meerut Development Authority v. Association Management Studies and another(2009) 6 SCC 171PositiveTender process terms are embedded in contract; scrutiny limited in writs.
Reliance Airport Developers (P) Ltd. v. Airports Authority of India(2006) 10 SCC 1PositiveJudicial review scope and objective standards in procurement.
Tata Cellular v. Union of India(1994) 6 SCC 651PositiveFoundational principles for intervention in contractual matters.
B.S.N.L. Ltd. and another v. Bhupender Minhas and othersA.I.R. 2008 S.C. 1988PositiveIllustrates cautions in governmental decisions affecting tenders.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Green Track Engineers and Construction v. Kerala Minerals and Metals Ltd. (KMML) & TVK Construction & Deepthi Transport Service and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT: THE HONOURABLE MR.JUSTICE K.T.SANKARAN & THE HONOURABLE MR.JUSTICE M.L.JOSEPH FRANCIS WEDNESDAY, THE 15TH DAY OF JANUARY 2014/25TH POUSHA, 1935 ## **WA.No. 1338 of 2013** AGAINST THE JUDGMENT IN WP(C) NO.9984/2013 OF HIGH COURT OF KERALA DATED 05-08-2013 ## **APPELLANT/PETITIONER:** M/S. GREEN TRACK ENGINEERS AND CONSTRUCTION VII/143 A, PANMANA, KARUNAGAPPALLY KOLLAM DISTRICT REPRESENTED BY ITS OPERATION MANAGER, PRADEEP.R. S/O.RADHAKRISHNAN. BY ADVS.SRI.GRASHIOUS KURIAKOSE (SR.) SRI.GEORGE MATHEWS ## **RESPONDENTS/RESPONDENTS** : 1. THE KERALA MINERALS AND METALS LTD. ( A GOVERNMENT OF KERALA UNDERTAKING) MINERAL SEPARATION UNIT KOVILTHOTTAM, CHAVARA, KOLLAM-691 583 REPRESENTED BY ITS MANAGING DIRECTOR. 2. TVK CONSTRUCTION ARAAMAM, PADANAYARKULANGARA NORTH, KARUNAGAPPALLY, KOLLAM DISTRICT. ## 3. DEEPTHI TRANSPORT SERVICE - VADAKKIDAM BUILDING, KARITHURA, CHAVARA KOLLAM. R3 IS DELETED FROM PARTY ARRAY AS PER THE ORDER DATED 3.9.2013 IN W.A.NO.1338 OF 2013. R1 BY ADV. SRI.K.ANAND (SR.) R1 BY ADV. SMT.LATHA KRISHNAN R2 BY ADV. SRI.S.SHARAN THIS WRIT APPEAL HAVING BEEN FINALLY HEARD ON 21/10/2013, ALONG WITH WA. 1354/2013 AND WPC. 21923/2013, THE COURT ON 15.01.2014, DELIVERED THE FOLLOWING: **APPENDIX IN W.A.NO.1338/2013** ## **APPELLANT'S EXHIBIS** : ANNEXURE I: TRUE COPY OF THE LETTER DATED 19.8.2013 GIVEN BY THE FIRST RESPONDENT TO ONE MR.RENJITH BABU UNDER THE RIGHT TO INFORMATION ACT. ANNEXURE II: TRUE COPY OF THE PROCEEDINGS OF THE FIRST RESPONDENT IN TENDER NO.KMML/MS/MINES/RS/KV/02/2013, DATED 21.2.2013. //TRUE COPY// AHZ/ **K.T.SANKARAN & M.L.JOSEPH FRANCIS, JJ.** **------------------------------------------------------------W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M ------------------------------------------------------------Dated this the 15[th] day of January, 2014** ## **JUDGMENT** ## **K.T.Sankaran, J.** The Kerala Minerals and Metals Ltd., (hereinafter referred to as the 'KMML'), which is a Government of Kerala Undertaking, invited sealed competitive tenders from experienced contractors for the work of excavation and transportation of mineral sand from Kovilthottam area of the company for a period of one year. Tender notice dated 21.2.2013 was published in two Malayalam dailies on 24.2.2013. The tender notice showed that tender forms could be had from the office of Dy.General Manager (MS) of KMML on any working day from 4.3.2013 to 14.3.2013. Duly filled up tender alongwith EMD of Rupees Two lakhs was to be submitted before 2 pm on 15.3.2013. The tender notice also provided that the Commercial part of the tender would be opened at 2.30 pm on 15.3.2013. ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 2 :: 2. Three tenders were submitted. They were by (1) M/s.Deepthi Transport Services; (2) M/s.TVK Constructions; and (3) M/s.Green Track Engineers and Construction (hereinafter referred to as 'Deepthi', 'TVK' and 'Green Track' respectively). The commercial part of the tender was opened on 15.3.2013 and it was found that 'Deepthi' and 'TVK' could be considered as qualified. In respect of the tender submitted by 'Green Track', various discrepancies were noticed and therefore legal opinion was sought. On the basis of the legal opinion, the tender submitted by 'Green Track' was rejected. 3. 'Green Track' filed W.P.(C) No.9984 of 2013 for the issue of a writ of certiorari or any other appropriate writ, order or direction to quash the order of 'KMML' leading to the acceptance of the tender submitted by 'TVK' and to declare that the non-acceptance of the tender submitted by 'Green Track' was illegal, arbitrary and unjustifiable. There is also a prayer for the issue of a writ of mandamus directing 'KMML' to accept the tender submitted by 'Green Track'. It is stated in the Writ Petition filed by 'Green Track' that they submitted tender in the prescribed form along with the ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 3 :: required earnest money deposit and solvency certificate. They quoted the rate of `350/- per metric tonne, while 'TVK' quoted the rate of `410/- per metric tonne and 'Deepthi' quoted `413/- per metric tonne. On 15.3.2013, 'Green Track' was told by the officials of 'KMML' that the commercial bid of 'Green Track' was in order and the price bids would be opened on 3.4.2013. A representative of 'Green Track' was present before the first respondent when the price bids were opened. However, on that day, he was told that the tender submitted by 'Green Track' was rejected. 'Green Track' filed a representation dated 4.4.2013 before 'KMML' seeking to review its decision rejecting the tender. It is alleged in the Writ Petition that some of the top ranking officers of 'KMML' colluded with 'TVK' and acted in an arbitrary manner which is detrimental to the best interest of 'KMML' and the public. The rate quoted by 'Green Track' was the lowest and still the contract was awarded to 'TVK' who quoted a much higher amount of `410/- per metric tonne. 4. W.P.(C) No.10095 of 2013 was filed by one Renjith Babu to quash the proceedings accepting the tender of 'TVK' and to issue a ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 4 :: writ of mandamus commanding 'KMML' to invite a fresh tender for the work in question. There is also a prayer to issue a writ of mandamus commanding 'KMML' to consider Ext.P6 representation dated 5.4.2013 submitted by Renjith Babu. 5. In W.P.(C) No.10095 of 2013 filed by Renjith Babu, he alleged the following among other. The petitioner was very much interested in participating the tender. As per the tender notification, tender forms were to be issued from 4.3.2013 to 14.3.2013. The petitioner went to the office of 'KMML' to purchase tender form on 4.3.2013 itself. He frequently visited the office of 'KMML' to purchase a tender form and he was informed that the tender date will be extended. 'KMML' started issuing tender forms only on 11.3.2013. Renjith Babu, the petitioner, did not purchase the tender form since it was not possible for him to collect the details and to produce the documents required for pre-qualification before the last date fixed for submitting tender. Renjith Babu claims that he is a Government approved 'A' class contractor and he has completed many prestigious projects of civil, mechanical and mining works for ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 5 :: public and private undertakings, including the Government of Kerala. He has large infrastructure facilities and machinery for doing big projects. Renjith Babu contended that as per the norms and regulations of 'KMML', the tender proceedings should have at least thirty days' time and the tender forms should be issued at least fifteen days before the last date for submitting the tender. The 'KMML' commenced issuing tender forms only on 11.3.2013 with an intention of “ousting the competitive contractors other than the existing contractors”. The existing contractors had got necessary information much in advance with respect to the documents required to be produced for pre-qualification. Renjith Babu submitted Ext.P2 representation dated 16.3.2013 to 'KMML' to cancel the tender and to invite new tender giving opportunity to the competent contractors to participate in the bid. Only three tenders were submitted and all the three tender forms were issued on or after 11.3.2013. Two out of the tenderers are existing permanent contractors of 'KMML' and the rates quoted by both of them were almost similar. The third tender submitted by another person was rejected for want of prequalification documents. It is also alleged that the rate quoted by ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 6 :: both the existing contractors is higher by more than 50% of the existing rate. Renjith Babu also alleged that Sri.K.Radhakrishnan, Technician Grade II of 'KMML' is the son of the Managing Partner of 'TVK'. There was violation of Ext.P4 circular dated 9.9.2004 issued by 'KMML' that relative of an employee should not normally be permitted to have business dealings with 'KMML'. Sri.Radhakrishnan, an employee of 'KMML' was personally involved in the tender and he was a partner of 'TVK'. 6. In the counter affidavit filed on behalf of 'KMML' in W.P.(C) No.9984 of 2013, the details were furnished regarding the grounds on which the tender submitted by 'Green Track' was rejected. It was contended that 'Green Track' did not satisfy the eligibility criteria in the tender conditions. In the counter affidavit filed on behalf of 'KMML' in W.P.(C) No.10095 of 2013, it was contended that Renjith Babu, the petitioner, has no locus standi to challenge the tender proceedings since he did not even purchase the tender form. It was contended that “assuming without conceding that there were any humanly impossible conditions, the petitioner could have purchased ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 7 :: the tender form and sought for appropriate release from the first respondent for satisfying such conditions”. With regard to the malafides alleged, 'KMML' stated in the counter affidavit thus: “Further Mr.Radhakrishnan, Technician Gr.II has resigned from the service of the company. Moreover, the father of Sri.Radhakrishnan is the contractor of the Company from 1981 onwards. Ext.P5 partnership is dated 18.12.2006 whereas the said Radhakrishnan who has ceased to be the employee is included as a partner and the amended partnership deed is also produced by the contractor.” 7. A reply affidavit was filed by Renjith Babu, the petitioner in W.P.(C) No.10095 of 2013, in which it was contended that 'KMML' did not specifically deny the allegation that tender forms were issued only on 11.3.2013 and therefore, the allegation in the Writ Petition should be treated as admitted. It was also averred that Sri.Radhakrishnan resigned from 'KMML' on 6.4.2013, after opening the tender on 4.4.2013, after ensuring that he would be awarded the tender. That information regarding resignation of Radhakrishnan was received by Renjith Babu under the Right to Information Act ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 8 :: and it was marked as Ext.P7. It was also alleged that after resigning from 'KMML', Sri.Radhakrishnan had taken charge as the Executive Director of 'TVK'. Sri.Radhakrishnan attended the meeting for settlement of memorandum with the unions of 'KMML'. As per the standing procedures in 'KMML', a tender for the work of such magnitude and nature as the present one has to be published in the official website of the company, but that was not followed in the present case. Ext.P8 application was submitted by Renjith Babu under the Right to Information Act for providing the details of approval of tender forms and also the copy of the approval. However, the Public Information Officer of 'KMML' refused to give the details on the ground that cases are pending before the High Court. 8. The learned single Judge dismissed the Writ Petitions filed by 'Green Track' and Renjith Babu as per the judgment dated 5[th] August, 2013, which is under challenge in W.A.Nos.1338 and 1354 of 2013 filed by 'Green Track' and Renjith Babu respectively. The learned single Judge held that Ext.P4 circular dated 9.9.2004 issued by 'KMML', which was relied on by Renjith Babu in W.P.(C) ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 9 :: No.10095 of 2013, is not applicable to the tender invited as per Ext.P1 and it is something different “from the scope of the situation sought to be dealt with as per the said circular”. The learned single Judge also held that the circular is only an internal communication for the guidance of the company and it applies only to transporting contract. The circular is not applicable to the contract for excavation and transportation involved in the contract in question. The learned single Judge also held that “the circular does not impose any 'total ban' as such, but only places some restrictions with regard to the engagement of vehicles owned by the employees or members of their family”. The learned single Judge found that the hike in the rate was justifiable. 9. W.P.(C) No.21923 of 2013 is a public interest litigation. That Writ Petition was filed by Anil Kumar and two others for the issue of a writ of certiorari to quash all the proceedings with respect to Ext.P1 tender notice and for the issue of a writ of mandamus commanding 'KMML' to conduct re-tender. There is also a prayer to direct the State of Kerala to constitute a high level expert team ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 10 :: consisting of Technical Experts, Auditors and Cost Accountants to conduct an impartial and independent enquiry into the lapses, maladministration and corruption in 'KMML' in the matter of award of public contracts and to fix the responsibility and recover damages from the erring officials. In the alternative, the petitioners pray for conducting a vigilance enquiry in the matter of grant of public contracts in 'KMML'. The public interest litigation was filed after the disposal of the aforesaid Writ Petitions by the learned single Judge. 10. Since common questions are involved in the two Writ Appeals and in W.P.(C) No.21923 of 2013, all the cases were heard together. 11. Heard Senior Advocates Sri.N.Nandakumara Menon, Sri.Grashious Kuriakose and Sri.M.K.Damodharan appearing for the appellants and the writ petitioners and Senior Advocate Sri.Santhalingam for the successful bidder and Senior Advocate Sri.Anand for 'KMML'. 12. The relevant files with respect to the award of contract ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 11 :: was produced by 'KMML' for our perusal. 13. Certain facts are not in dispute. They are the following: - (i) The contract in question involves excavation and transportation of a total quantity of 2,73,000 MT of mineral sand for one year. Per month, a quantity of 22,750 MT of mineral sand is expected to be excavated and transported. - (ii) The tender notice is dated 21.2.2013. It was published in Malayala Manorama daily on 24.2.2013. In the tender notice, it is stated that detailed tender forms could be had from the office of 'KMML' on any working day from 4.3.2013 to 14.3.2013. The duly filled tender should be submitted along with EMD of Rupees Two lakhs before 2 pm on 15.3.2013. - (iii) Final approval for issuing tender forms was granted by 'KMML' on 11.3.2013. The tender forms were issued only from 11.3.2013 onwards. - (iv) The commercial bid was opened at 2.30 pm on 15.3.2013. - (v) Three persons submitted tenders: (a) 'Green Track' (`350/- per ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 12 :: MT), (b) 'TVK' (`410/- per MT) and (c) 'Deepthi' (`413/- per MT). - (vi) The tender submitted by 'Green Track' was rejected as they did not satisfy the pre-qualification conditions. - (vii) The price bid was opened on 4.4.2013. - (viii) In the negotiation with 'TVK' they reduced the rate from `410/to `393/-. - (ix) 'TVK' was declared as the successful bidder. - (x) 'Deepthi' was the contractor for the same work during the last six months before issuing the tender notice. 14. The Writ Petitions were filed by Renjith Babu and 'Green Track' on 8.4.2013. An order of status quo was issued on 27.6.2013. The cases were posted on 2.7.2013 and they were heard on 4.7.2013 and judgment was reserved. The judgment was pronounced on 5.8.2013. However, the excavation work was commenced on 25.7.2013 and the work of transporting of sand was started on 1.8.2013. During the months of August and September, 2013, the successful bidder transported 39,500 and 41,000 MT of ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 13 :: mineral sand respectively. 15. Sri.K.Radhakrishnan was working as Technician Grade II in 'KMML'. As per the partnership deed, Sri.Radhakrishnan was a partner of 'TVK' and Sri.T.V.Kunjukrishnan, aged 82 years, was the Managing Partner. Sri.Radhakrishnan retired from the partnership on 18.12.2006. Sri.Radhakrishnan resigned from 'KMML' on 6.4.2013, after the date of opening of commercial bid and price bid (15.3.2013 and 4.4.2013 respectively). The partnership of 'TVK' was reconstituted on 8.5.2013. Sri.Radhakrishnan was inducted as Executive Director of 'TVK' and he participated in the meeting with the unions of the company for arriving at a memorandum of settlement. 16. In clause (4) of Vigilance Circular No.2/2011 dated 4.1.2011 (Ext.P8 in W.P.(C) No.21923 of 2013) under the heading “Inviting Tenders”, it is provided thus: “Ensure adequate time for submission of offers. A minimum time of 21 days, 30 days and 45 days ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 14 :: should be given for limited, press and global tenders respectively. Time should be counted from the date of publication of tender notice." 17. Ext.P4 circular produced in W.P.(C) No.10095 of 2013 reads as follows: ## **“THE KERALA MINERALS AND METALS LIMITED** TP/PD/PL-55/04 9.9.2004 ## **CIRCULAR** Sub: Involvement of Company employees in contract work arrangements of the company-reg. ....... It is reported that certain employees are getting involved directly or indirectly in the various contract works of the company for personal purposes. It is also indicated that with respect to hiring of vehicles etc. on contract in the company certain employees have provided vehicles which are in their own name or in the name of their family members etc. The above practice is highly detrimental to the interests of the company. It is informed that employees and their family members are prohibited from getting involved in any such activity ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 15 :: connected with the business of the company. In case of business dealing with the company by any relatives of any employee the employee concerned should invariably inform the same to the company in writing. Violation of above instructions will be viewed very seriously. ## Sd/JT. GENERAL MANAGER (P&A) For MANAGING DIRECTOR" 18. Ext.P4 circular was issued when it was reported that certain employees of 'KMML' were getting involved directly or indirectly in the various contract works of the company for “personal purposes”. Another reason indicated in the circular was with respect to hiring of vehicles on contract in the company, certain employees of the company had provided vehicles in their own name or in the name of their family members. 'KMML' took the view that the said practice is highly detrimental to the interests of the company and, therefore, the employees and their family members were prohibited from getting involved in any activity connected with the business of the company. On a fair reading of Ext.P4 circular dated 9.9.2004, we are of the view that the circular relates to all the business activities of ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 16 :: 'KMML' and it is not confined to transporting contract alone. The view taken by the learned single Judge that the circular applies only to transporting contract and it does not apply to the contract of excavation and transportation of mineral sand is erroneous. 19. The observation made by the learned single Judge that the circular does not impose any total ban as such, but only places some restrictions with regard to the engagement of vehicles owned by the employees or members of their family, also does not appear to be correct. Whether there is any total ban or not, the question to be considered is whether an employee of 'KMML', namely, Sri.K.Radhakrishnan, had unfair business dealings to the detriment of the interests of 'KMML' and the other tenderers other than 'TVK'. 20. From the facts narrated above, it is clear that Sri.K.Radhakrishnan, Technician Grade II of 'KMML', who was in the service of the company till 6.4.2013, became the Executive Director of 'TVK', the successful bidder, on 8.5.2013. It is also to be noted that the commercial bid was opened on 15.3.2013 and the price bid ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 17 :: was opened on 4.4.2013, while Sri.K.Radhakrishnan was in service of 'KMML'. The contention put forward by the writ petitioners that Sri.K.Radhakrishnan was able to influence the higher ups in 'KMML' to award the contract in favour of 'TVK' is not unfounded. It is also relevant to note that the contract in question involves excavation and removal of 2,73,000 MT of mineral sand. 21. As per the tender notification dated 21.2.2013, which was published in the newspaper on 24.2.2013, the tender forms should have been ready for issue from 4.3.2013 to 14.3.2013. However, it is an admitted case that final approval for issuing tender forms was granted on 11.3.2013 and tender forms were issued from 11.3.2013 onwards. This was clearly in violation of the tender notification. The contention raised by 'KMML' that extension of time could be sought for, for furnishing the details in the tender form, is without any substance. There is no provision for extension of time for furnishing the details required to be furnished along with the tender. No tenderer would be entitled to, as of right, seek for extension of time. The contention put forward on behalf of 'KMML' that approval was ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 18 :: granted by the Managing Director to reduce the period for submitting tenders and therefore nobody could complain that they did not get sufficient time, is without merit. After publishing the tender notification in which it was informed to the prospective tenderers that the tender forms would be available from 4.3.2013 to 14.3.2013 thereby providing them twelve days' time to submit the tender, 'KMML' was not justified in reducing that period by issuing the tender forms only on 11.3.2013. The privilege provided to the prospective tenderers to avail twelve days' time to collect all the necessary details to be furnished in the tender form and to collect all the necessary documents to be produced along with the same cannot be unilaterally withdrawn by 'KMML' to the detriment of the interests of the prospective tenderers. The file produced by 'KMML' shows that a decision was taken by 'KMML' that tender notice was to be published before 26.2.2013 and the tenderers should be provided time upto 15.3.2013 to submit tenders. It is also noted in the file that in order to finalise the tender and issue the work order by second week of April, to avoid stoppage of work, the tender period was reduced to twenty days. Normally the period to be provided was thirty days and ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 19 :: it was reduced to twenty days. Still, the tender forms were issued only four days before the last date for submitting tenders. The procedure adopted by 'KMML' was patently illegal. If the writ petitioners allege that such a procedure was adopted only to weed out eligible contractors and to favour some of the existing contractors, they cannot be blamed. 'KMML' did not act fairly, which resulted in prejudice to the tenderers and loss to 'KMML', that means, loss of public money. It is also relevant to note in this context that there was an increase by 59.26% in the total rate when compared to the existing rate. The files also would show that by such increase the estimated financial implication would increase from `7.45 crores to `12.55 crores. It was noted in the file that it would be better to invite re-tenders for getting a fair rate. However, the tender committee which met on 9.4.2013, recommended to the Managing Director for approval to negotiate the rates with the tenderer. Accordingly, 'TVK' reduced their rate from `410/- to `393/per metric tonne. The undisputed facts would clearly indicate that by reducing the time for submitting tenders from twelve days to four days by issuing the tender forms belatedly,'KMML' stood to lose and ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 20 :: the successful bidder got the contract at a very high rate than the existing rate. It is also relevant to note that 'Green Track' quoted `350/- per MT and 'TVK' quoted `410/- per MT, which was reduced to `393/- per MT after negotiation. We are of the view that the proceedings by which the contract was awarded to 'TVK' is vitiated by unreasonableness, arbitrariness and malice. We are also of the view that 'KMML' acted so due to the influence exerted by Sri.K.Radhakrishnan, an employee of the company who later became the Executive Director of the successful bidder. ## 22. In **Nagar Nigam, Meerut v. Al Faheem Meat Exports (P)** ## **Ltd. and others: (2006) 13 SCC 382** , the Supreme Court held thus: “16. The law is well settled that contracts by the State, its corporations, instrumentalities and agencies must be normally granted through public auction/public tender by inviting tenders from eligible persons and the notification of the public auction or inviting tenders should be advertised in well-known dailies having wide circulation in the locality with all relevant details such as date, time and place of auction, subject-matter of auction, technical specifications, estimated cost, earnest ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 21 :: money deposit, etc. The award of government contracts through pubic auction/public tender is to ensure transparency in the public procurement, to maximise economy and efficiency in government procurement, to promote healthy competition among the tenderers, to provide for fair and equitable treatment of all tenderers, and to eliminate irregularities, interference and corrupt practices by the authorities concerned. This is required by Article 14 of the Constitution..... 17. ...... ...... 18. The law is, thus, clear that ordinarily all contracts by the Government or by an instrumentality of the State should be granted only by public auction or by inviting tenders, after advertising the same in well-known newspapers having vide circulation, so that all eligible persons will have an opportunity to bid in the bid (sic auction), and there is total transparency. In our opinion this is an essential requirement in a democracy, where the people are supreme, and all official acts must be actuated by the public interest, and should inspire public confidence.” 23. In **Reliance Energy Ltd. and another v. Maharashtra State Road Development Corpn. Ltd. and others: (2007) 8 SCC 1** , ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 22 :: the Supreme Court held thus: “36. Standards applied by courts in judicial review must be justified by constitutional principles which govern the proper exercise of public power in a democracy. Article 14 of the Constitution embodies the principle of “non-discrimination”. However, it is not a free-standing provision. It has to be read in conjunction with rights conferred by other articles like Article 21 of the Constitution. The said Article 21 refers to “right to life”. It includes “opportunity”. In our view, as held in the latest judgment of the Constitution Bench of nine Judges in _I.R.Coelho v State of T.N. ((2007) 2 SCC 1)_ . Articles 21/14 are the heart of the chapter on fundamental rights. They cover various aspects of life. “Level playing field” is an important concept while construing Article 19(1)(g) of the Constitution. It is this doctrine which is invoked by REL/HDEC in the present case. When Article 19(1)(g) confers fundamental right to carry on business to a company, it is entitled to invoke the said doctrine of “level playing field”. We may clarify that this doctrine is, however, subject to public interest. In the world of globalisation, competition is an important factor to be kept in mind. The doctrine of “level playing field” is an important doctrine which is embodied in Article 19(1)(g) ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 23 :: of the Constitution. This is because the said doctrine provides space within which equally placed competitors are allowed to bid so as to subserve the larger public interest. “Globalisation”, in essence, is liberalisation of trade. Today India has dismantled licence raj. The economic reforms introduced after 1992 have brought in the concept of “globalisation”. Decisions or acts which result in unequal and discriminatory treatment, would violate the doctrine of “level playing field” embodied in Article 19(1)(g). Time has come, therefore, to say that Article 14 which refers to the principle of “equality” should not be read as a stand alone item but it should be read in conjunction with Article 21 which embodies several aspects of life. There is one more aspect which needs to be mentioned in the matter of implementation of the aforestated doctrine of “level playing field”. According to Lord Goldsmith, commitment to the “rule of law” is the heart of parliamentary democracy. One of the important elements of the “rule of law” is legal certainty. Article 14 applies to government policies and if the policy or act of the Government, even in contractual matters, fails to satisfy the test of “reasonableness”, then such an act or decision would be unconstitutional. ....... ....... ....... ....... “39. In _Reliance Airport Developers (P) Ltd. v._ ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 24 :: _Airports Authority of India: (2006) 10 SCC 1,_ the Division Bench of this Court has held that in matters of judicial review the basic test is to see whether there is any infirmity in the decision-making process and not in the decision itself. This means that the decision-maker must understand correctly the law that regulates his decisionmaking power and he must give effect to it otherwise it may result in illegality. The principle of “judicial review” cannot be denied even in contractual matters or matters in which the Government exercises its contractual powers, but judicial review is intended to prevent arbitrariness and it must be exercised in larger public interest. Expression of different views and opinions in exercise of contractual powers may be there, however, such difference of opinion must be based on specified norms. Those norms may be legal norms or accounting norms. As long as the norms are clear and properly understood by the decision-maker and the bidders and other stakeholders, uncertainty and thereby breach of the rule of law will not arise. The grounds upon which administrative action is subjected to control by judicial review are classifiable broadly under three heads, namely, illegality, irrationality and procedural impropriety. In the said judgment it has been held that all errors of law are jurisdictional errors. One of the important principles laid down in the aforesaid judgment is that ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 25 :: whenever a norm/benchmark is prescribed in the tender process in order to provide certainty that norm/standard should be clear. As stated above “certainty” is an important aspect of the rule of law. In _Reliance Airport Developers (P) Ltd. v. Airports Authority of India: (2006) 10 SCC 1_ , the scoring system formed part of the evaluation process. The object of that system was to provide identification of factors, allocation of marks of each of the said factors and giving of marks at different stages. Objectivity was thus provided.” ## 24. In **Ramana Dayaram Shetty v. The International Airport** **Authority of India and others: AIR 1979 SC 1628** , a three Judge Bench of the Supreme Court held thus: “20. Now, obviously where a corporation is an instrumentality or agency of Government, it would, in the exercise of its power or discretion, be subject to the same constitutional or public law limitations as Government. The rule inhibiting arbitrary action by Government which we have discussed above must apply equally where such corporation is dealing with the public, whether by way of giving jobs or entering into contracts or otherwise, and it cannot act arbitrarily and enter into relationship with any person it likes at its ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 26 :: sweet will, but its action must be in conformity with some principle which meets the test of reason and relevance. 21. This rule also flows directly from the doctrine of equality embodied in Art. 14. It is now well settled as a result of the decisions of this Court in _E. P. Royappa v. State of Tamil Nadu, (1974) 2 SCR 348 : (AIR 1974 SC 555) and Maneka Gandhi v. Union of India, (1978) 1 SCC 248 : (AIR 1978 SC 597)_ that Article 14 strikes at arbitrariness in State action and ensures fairness and equality of treatment. It requires that State action must not be arbitrary but must be based on some rational and relevant principle which is non-discriminatory : it must not be guided by any extraneous or irrelevant consideration, because that would be denial of equality. The principle of reasonableness and rationality which is legally as well as philosophically an essential element of equality or non-arbitrariness is projected by Article 14 and it must characterise every State action, whether it be under authority of law or in exercise of executive power without making of law. The State cannot, therefore act arbitrarily in entering into relationship, contractual or otherwise with a third party, but its action must conform to some standard or norm which is rational and non-discriminatory. ...... The State has the right to trade. The State has there the duty to observe ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 27 :: equality. An ordinary individual can choose not to deal with any person. The Government cannot choose to exclude persons by discrimination. .....” 25. It is well settled that the courts can scrutinise the award of contracts by the Government or its agencies in exercise of their power of judicial review to prevent arbitrariness or favouritism. However, there are inherent limits in the exercise of power of judicial review in such matters. The courts would interfere with the administrative policy decision only if it is arbitrary, discriminatory, malafide or actuated by bias. ( **See** _**Tata Cellular v. Union of India: (1994) 6 SCC 651 and B.S.N.L. Ltd. and another v. Bhupender Minhas and others : AIR 2008 SC 1988.**_ ). 26. As held in **Jagdish Mandal v. State of Orissa and others: (2007) 14 SCC 517,** before interfering with tender or contractual matters in exercise of the power of judicial review, the Court should pose to itself the following questions: (i) Whether the process adopted or decision made by the authority is mala fide or intended to favour someone; or (ii) Whether the process adopted or ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 28 :: decision made is so arbitrary and irrational that the court can say that 'the decision is such that no responsible authority acting reasonably and in accordance with relevant law could have reached'; (iii) Whether public interest is affected. These principles were followed in **Tejas Constructions and Infrastructure Private Limited v. Municipal Council, Sendhwa and another: (2012) 6 SCC 464** and **Michigan Rubber (India) Limited v. State of Karnataka and others** : **(2012) 8 SCC 216** . 27. Learned Senior Counsel appearing for 'TVK' and 'KMML' contended that the petitioners in W.P.(C) No.21923 of 2013 (the public interest litigation) cannot pray for re-tender since the petitioners therein did not participate in the tender. The counsel relied on the decision of the Supreme Court in **Villianur Iyarkkai Padukappu Maiyam vs. Union of India and others** : **(2009) 7 SCC 561** . In that case, neither the persons who had participated in the selection process nor any other person interested had come forward to challenge the selection procedure adopted by the Government or selection of respondent No.11 as Developer of the Pondicherry ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 29 :: Airport. The Supreme Court in that judgment relied on the decision in **BALCO Employees' Union (Regd.) vs. Union of India** : **(2002) 2 SCC 333,** wherein it was held that the public interest litigation was not meant to be a weapon to challenge the financial or economic decisions which are taken by the Government in exercise of their administrative power. In **BALCO Employees' Union (Regd.) vs. Union of India** : **(2002) 2 SCC 333,** it was held thus: “88. It will be seen that whenever the Court has interfered and given directions while entertaining PIL it has mainly been where there has been an element of violation of Article 21 or of human rights or where the litigation has been initiated for the benefit of the poor and the underprivileged who are unable to come to court due to some disadvantage. In those cases also it is the legal rights which are secured by the courts. We may, however, add that public interest litigation was not meant to be a weapon to challenge the financial or economic decisions which are taken by the Government in exercise of their administrative power. No doubt a person personally aggrieved by any such decision, which he regards as illegal, can impugn the same in a court of law, but, a public interest litigation at the behest of a stranger ought not to be entertained. Such a ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 30 :: litigation cannot per se be on behalf of the poor and the downtrodden, unless the court is satisfied that there has been violation of Article 21 and the persons adversely affected are unable to approach the court.” 28. Sri.M.K.Damodaran, the learned senior counsel appearing for the petitioners in the public interest litigation submitted that the prayer in the Writ Petition includes a prayer to conduct an impartial and independent enquiry by the State of Kerala with respect to the lapses, maladministration and corruption in 'KMML' in the matter of awarding of public contracts and to fix responsibility and to recover damages from the erring officials. There is also an alternative prayer to conduct a vigilance enquiry in the matter of grant of public contracts in 'KMML'. The learned senior counsel also submitted that the averments in the Writ Petition would justify the institution of a public interest litigation. 29. Relying on the decision of the Supreme Court in **Rajasthan State Industrial Development and Investment Corporation and another vs. Diamond & Gem Development Corporation Limited and another** : **(2013) 5 SCC 470** , it was ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 31 :: contended by the learned senior counsel for 'KMML' that the settled legal proposition is that matters or disputes relating to contract cannot be agitated nor terms of the contract can be enforced through writ jurisdiction under Article 226 of the Constitution. The writ court cannot be a forum to seek any relief based on terms and conditions incorporated in the agreement by the parties. On a perusal of the facts of the case in **Rajasthan State Industrial Development and Investment Corporation and another vs. Diamond & Gem Development Corporation Limited and another** : **(2013) 5 SCC 470** , it can be seen that the decision is not applicable to the facts of the present case. ## 30. In **Meerut Development Authority vs. Association of** **Management Studies and another** : **(2009) 6 SCC 171** , the Supreme Court held thus: “26. A tender is an offer. It is something which invites and is communicated to notify acceptance. Broadly stated it must be unconditional; must be in the proper form, the person by whom tender is made must be able to and willing to perform his obligations. The ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 32 :: terms of the invitation to tender cannot be open to judicial scrutiny because the invitation to tender is in the realm of contract. However, a limited judicial review may be available in cases where it is established that the terms of the invitation to tender were so tailor-made to suit the convenience of any particular person with a view to eliminate all others from participating in the bidding process. 27. The bidders participating in the tender process have no other right except the right to equality and fair treatment in the matter of evaluation of competitive bids offered by interested persons in response to notice inviting tenders in a transparent manner and free from hidden agenda. One cannot challenge the terms and conditions of the tender except on the abovestated ground, the reason being the terms of the invitation to tender are in the realm of the contract. No bidder is entitled as a matter of right to insist the authority inviting tenders to enter into further negotiations unless the terms and conditions of notice so provided for such negotiations. 28. It is so well settled in law and needs no restatement at our hands that disposal of the public property by the State or its instrumentalities partakes the character of a trust. The methods to be adopted for disposal of public property must be fair and transparent ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 33 :: providing an opportunity to all the interested persons to participate in the process.” 31. In **Air India Ltd. vs. Cochin International Airport Ltd. and others** : **AIR 2000 SC 801** , the Supreme Court held thus: “7. ...... But the State, its corporations, instrumentalities and agencies are bound to adhere to the norms, standards and procedures laid down by them and cannot depart from them arbitrarily. Though that decision is not amenable to judicial review, the Court can examine the decision making process and interfere if it is found vitiated by mala fides, unreasonableness and arbitrariness. The State, is corporations, instrumentalities and agencies have the public duty to be fair to all concerned. Even when some defect is found in the decision making process the Court must exercise its discretionary power under Article 226 with great caution and should exercise it only in furtherance of public interest and not merely on the making out of a legal point. The Court should always keep the larger public interest in mind in order to decide whether its intervention is called for or not. Only when it comes to a conclusion that overwhelming public interest requires interference, the Court should intervene.” ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 34 :: 32. From the facts narrated above, it is clear that 'KMML' did not adhere to the tender conditions. The intending tenderers were denied of an opportunity to participate in the tender and to submit the tender forms along with necessary documents, details and data. It would appear that 'KMML' was not interested in getting maximum number of bids so that the contract could be awarded at a reasonable rate. They were interested in choosing either of the existing contractors and in that process they chose 'TVK', though the rate quoted by them was very high when compared to the rate quoted for the previous year. 'Green Track' quoted the lowest rate. But their bid was not accepted and they were eliminated on opening the commercial bid. Specific averments were made by Renjith Babu that he did not think it fit to get the tender form since there was no sufficient and reasonable time to submit the tender incorporating the necessary details. Monetary stake involved is very high and 'KMML' accepted the tender of 'TVK' at a rate more than 50% above the existing rate, thereby 'KMML' chose to spend crores of rupees more. This was pointed out by the officials of 'KMML', but that was ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 35 :: apparently not accepted. We are of the view that the award of the work in favour of 'TVK' is vitiated by malafides, unreasonableness and arbitrariness. It was to favour the successful tenderer. In the larger public interest, the Court would not be justified in accepting the contention of 'KMML'. For the aforesaid reasons, we allow the Writ Appeals, set aside the judgment of the learned single Judge and allow W.P.(C) Nos.9984 and 10095 of 2013. Since the aforesaid Writ Petitions are allowed, we are of the view that, for the time being, it is not necessary to consider on merits W.P.(C) No.21923 of 2013. All the contentions put forward by the petitioners in W.P.(C) No.21923 of 2013 are left open and the petitioners would be entitled to approach this Court as and when occasion arises. ## **(K.T.SANKARAN) Judge** **(M.L.JOSEPH FRANCIS) Judge** ahz/ ## **W.A. NOS.1338 & 1354 OF 2013 and W.P.(C) NO.21923 OF 2013 M** :: 36 :: ## **20.1.2014** After the judgment was pronounced and certified copies were issued, it was brought to our notice by Sri.Grashious Kuriakose, the learned senior counsel appearing for the appellant in W.A.No.1338 of 2013 that in the last paragraph of the judgment, there is a mistake. Several reliefs were prayed for in W.P.(C) Nos.9984 and 10095 of 2013. We have allowed only the prayer to quash the proceedings of 'KMML' leading to the acceptance of the tender submitted by 'TVK'. Therefore, in the last paragraph of the judgment, after the words “allow W.P.(C) Nos.9984 and 10095 of 2013”, the words “to the extent indicated above” should be added. We correct the mistake and insert the words “to the extent indicated above” after the words “allow W.P.(C) Nos.9984 and 10095 of 2013” in the first sentence in the last paragraph of the judgment. The Registry will carry out the correction. The Registry will also carry out the corrections in the certified copies issued, if the certified copies are produced before the Registry. **(K.T.SANKARAN) Judge** **(M.L.JOSEPH FRANCIS) Judge**