High CourtDivision BenchPetition dismissed

Gram Panchayat and Anr. v. Shree Vallabh Glass Works Ltd. and Ors.

Case / Petition Number:Civil Special Leave Petition (Civil) No. 14395 of 1989
Neutral Citation:/

Case Details & Bench

Court
High Court
Hon'ble Judges
  • K. Jagannath Shetty
  • R. M. Sahai
Judgment Date
1990-03-15
Court Decision / Holding
Petition dismissed; High Court’s order quashing the property tax and related recovery proceedings upheld; no order as to costs.
Final Disposition
Petition dismissed

Parties to the Case

Appellants / Petitioners

  • Gram Panchayat Salwad
  • Chairman of the Gram Panchayat

Respondents

  • Shree Vallabh Glass Works Ltd.

Legal Representation & Advocates

Counsels for Petitioners

  • • V. N. Ganpule

Counsels for Respondents

  • • P. Chidambaram
  • • Mrs. Rani Karanjawala
  • • N. H. Seervai
  • • Karanjawala
  • • Ravinder Kumar

Case Synopsis & Summary

Gram Panchayat Salwad (first petitioner) and the Chairman of the Gram Panchayat (second petitioner) challenged a Bombay High Court order restraining recovery of property tax and other dues from M/s Shree Vallabh Glass Works Ltd. under the Sick Industrial Companies (Special Provisions) Act, 1985 (SICA). The company had been declared sick by the Board for Industrial and Financial Reconstruction (BIFR) under Section 16, with an operating agency appointed under Section 17(3) to prepare a rehabilitation scheme. The Board also directed further proceedings under the Act. Section 22 of SICA provides that, when a sick-company inquiry is pending or a scheme is under preparation or an appeal is pending, proceedings for winding up or execution against the company’s properties shall be suspended except with the Board’s consent. The High Court quashed the Panchayat’s recovery proceedings, concluding that consent of the Board was necessary. The Supreme Court dismissed the Special Leave Petition, upholding the High Court’s view that, given the Board’s actions and the moratorium under Sections 16, 17 and 22, recovery against the company’s properties cannot proceed without Board consent. The decision clarifies the balance between local revenue rights and rehabilitation objectives under SICA, and emphasizes that creditors may seek relief or consent only through the Board.

Provisions of Law Cited

Section 16 of the Sick Industrial Companies (Special Provisions) Act, 1985Section 17(2) of the Sick Industrial Companies (Special Provisions) Act, 1985Section 17(3) of the Sick Industrial Companies (Special Provisions) Act, 1985Section 22(1) of the Sick Industrial Companies (Special Provisions) Act, 1985Section 22(5) of the Sick Industrial Companies (Special Provisions) Act, 1985Section 18 of the Sick Industrial Companies (Special Provisions) Act, 1985Section 19 of the Sick Industrial Companies (Special Provisions) Act, 1985Section 25 of the Sick Industrial Companies (Special Provisions) Act, 1985Bombay Village Panchayat Act, Section 129Companies Act, 1956

Legal Doctrines & Maxims

  • Principles of equity

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioners contend that Section 22(1) of SICA requires suspension of winding up and related proceedings only while a sick-company inquiry is pending, a scheme is under preparation or an appeal under Section 25 is pending. They argue that recovery of property tax by a local body is a revenue matter not automatically encompassed by the moratorium and does not require the Board’s consent, so the High Court erred in restraining such recovery. They seek to preserve local revenue rights and argued that the Board’s involvement should not indiscriminately block these remedies.

Contentions of Respondents

The respondents contend that once a company is declared sick and the Board orders a scheme under Section 17(3) and appoints an operating agency, all proceedings for execution or distress against the company’s properties are automatically suspended, except with the Board’s consent or the Appellate Authority. They argue this moratorium is essential to the rehabilitation process and that the High Court correctly quashed the recovery proceedings under Section 22(1). The Board’s consent is necessary to resume any such action, ensuring coherence with the rehabilitation scheme and protection of the company’s value for creditors.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Gram Panchayat and Anr. v. Shree Vallabh Glass Works Ltd. and Ors. and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

GRAM PANCHAYAT AND ANR. A _v._ SHREE VALLABH GLASS WORKS LIMITED AND ORS. MARCH 15, 1990 B [K. JAGANNATHA SHETTY AND R.M. SAHAI, JJ.] _The Sick Industrial Companies (Special Provisions) Act,_ _1985:_ _Ss._ _16,_ _17_ _&_ _22-Sick industrial company-Proceedings for recovery of_ _amount due-Validity of_ #### • ## c D #### E p G Section 16 of the Sick Industrial Companies (Special Provisions) Act, 1985 authorises the Board for Industrial and Financial Reconstruction established under the Act to make enquiry for determining whether any industrial company has become a sick industrial company. Section 17(2) empowers the Board to grant a reasonable time to such a company to make its net worth positive. Where such a course is not practicable s. 17(3) empowers the Board to appoint an operating agency to prepare a scheme for rehabilitation/revival of the company. Section 22(1) provides that in case the enquiry under s. 16 is pending or any scheme referred to under s. 17 is under preparation or consideration by the Board or any appeal under s. 25 is pending, then proceedings for winding np, execution, distress or the like are to be suspended or presumed to be suspended. The proceedings in respect of these matters could, however, be continued with the consent of the Board or of the appellate authority as tbe case may be. Section 22(5) provides for exclusion of the period during which the remedy remains suspended, in computing the period of limitation for enforcement of the right. The respondent company had been declared by the Board to be a sick industrial company under s. 16 of the Act and an operating agenc;i: had been appointed under s. 17(3) to prepare a scheme for rehabilitation/revival of the company. The respondent company owed a large sum to the petitioner Panchayat on account of property tax and other dues. When the petitioners initiated coercive proeeedings to recover that amount the company moved the High Court by way of a writ petition under Article 226 of the Act. The High Court restrained the petitioners from recovering the said amount ltithout the consent of the Board. B: Dismissing the special leave petition, the Court, 966 GRAM PANCHAYAT _v._ VALLABH GLASS WORKS {SHETTY, J.] 967 HELD: The High Court was justified in quashing the recovery proceedings taken against the properties of the company. [970G-H] The Board by order dated 27 August, 1987 had stated that it was satisfied that the company had become a sick industrial company and directed that further proceedings under the Act shall be taken. By another order made on the same day under s. 17(2) .the Board had found that it was not practicable for the company to make its net worth positive within a reasonable time and had proceeded to take action under s. 17(3) and appointed the ICICI as the operating agency to prepare a scheme for rehabilitation/revival of the company. In view of these steps taken by the Board under ss. 16 and 17 of the Act, no proceedings for execution, distress or the like against any of the properties of the industrial company shall lie or be proceeded with further by virtue of s. 22(1) except with the conseutof the Boai-d. [970A-D] The Board at its discretion may accord approval. If the approval is not granted the remedy is not extinguished. It is only postponed. Sub-section (5) of s. 22 provides for exclusion of the period during which the remedy is suspended while computing the period of limitation for recovering the dues. [970F-GJ CIVIL APPELLATE JURISDICTION: Special Leave Petition - (Civil) No. 14395 of 1989. From the Judgment and Order dated 18.7.1989 of the Bombay High Court in W.P. No. 6108of 1987. V .N. Ganpule for the Petitioners. A B ## c D E ~ P. Chidambmm, Mrs. Raian Karanjawala, N:H. Seer.bai, Karan- F jawala and Ravinder Kumar for the Respondents. The Judgment of the Court was delivered by K. JAGANNATHA SHETTY, J. The petitioners seek leave to appeal against the decision of the Bombay High Court in Writ Petition G No. 6108/87 quashing the proceedings for recovery of property tax and other expenses due from the first respondent-co~pany. The matter arises in this way: For the purpose of prevention and revival of sick industries, the Central Government has enacted the Act called "Tlt~i_ck Industri_al Coml'._anies (Special Provisions) Act, 1985 H A B Q 968 SUPREME COURT REPORTS [1990] 1 S.C.R. ('The Act'). The Act extends to the whole of India including the State of J ammu & Kashmir. It came into force (except sections 15 to 34) with effect from 15 May 1987. The Act covers only sick industrial companies or industrial companies which have the potential to become sick. The Act empowers the Central Government to establish a Board to be known as the Board for Industrial & Financial Reconstruction to exercise the jurisdiction and powers, and discharge the functions and duties imposed under the Act. The first respondent-company M/s Shree Vallabh Glass Works Ltd. has been declared to be a sick industrial company within the meaning of clause _(_ o) of sub-section _(_ 1) of Section 3 of the Act. 'Sick Industrial Company' "means an iridustrial company being a company registered for not less than seven years which has at the end of any financial year accumulated losses equal to or exceeding its entire net worth and has also suffered cash losses in such financial year and the financial year immediately preceding such financial year." #### \{ '· -I #### p The first petitioner is the Gram Panchayat, Salwad and second petitioner is the Chairman of the Gram Panchayat. The petitioners initiated coercive proceedings under. Section 129 of the Bombay Village Panchayat Act to recover a sum of Rs.9,47,539 stated to be the property tax and other amounts due from the company. Challenging that proceedings, the Company moved the High Court by way of Writ !£ Petition under Article 226 of the Constitution claiming protection provided under Section 22 of the Act. The High Court has accepted the writ petition and restrained the petitioners from recovering the said amount without the consent of the Board. The question is whether the Panchayat could not recover the JI amount due to it from out of the properties of the sick industrial company without the consent of the Board? Section 22 provides, as far as material, as follows: "Section 22-Suspension of Legal Proceedings, contracts, etc. (1) Where in respect of an industrial company, an inquiry under Section 16 is pending or any scheme referred to under Section 17 is under preparation or consideration or a sanctioned scheme is under implementation or where an appeal under Section 25 relating to an industrial company GRAM PANCHAYAT v.·VALLABH GLASS WORKS !~HETTY, J.] 969 is pending, then, notwiihstanding anything contained in the Companies Act, 1956, or any other law or the memorandum and articles of association of the Industrial Company or any other instrument having effect under the said Act or other law, no proceedings for the winding up of the industrial company or for execution, distress or the like against any of the properties of the industrial company or for the appointment of a receiver in respect thereof shall lie or be proceeded with further,; except with the consent of the Board or, as the case may be, the Appellate Authority. 22(2) to 22(4) xxx xxx xxx 22(5) In computing the period of limitation for the enforcement of any right, privilege, obligation or liabiliiy, the period .during which it or the remedy for the enforcement thereof remains suspended under this section shall be exduded." Section 22(1) provides that in case the enquiry under Section 16 is pending or any scheme referred to under Section 17 is under preparation or consideration by the Board or any appeal under Section 25 is pending then certain proceedings against the sick industrial company A B ## c D are to be suspended or presumed to be suspended. The nature of the proceedings which are automatically suspended are: (1) Winding up of E the industrial company; (2) Proceedings for execution, distress or the like against the properties of sick industrial company, and (3) Proceedings for th~ .appointment of receiver. The proceedings in respect of these matters could, however, be continued against the sick industrial company with the consent or approval of the Board or of the Appellate Authority as the case may be. F ' Section 16 authorises the Board to make such enquiry as it may deem fit for determining whether any industrial company has become a sick industrial company. Where Board is satisfied that a company has become a sick industrial company, it could give a reasonable time to the company to make its net worth positive (Sec. 17(2)). Where it is G not practicable for sick industrial company to make its net worth positive within a reasonable time, Section 17(3) steps in authorising the Board to direct any operating agency to prepare a scheme in relation to the company. The Board may specify the various measures to be considered by the operating agency. These measures are detailed out in Section 18. The operating agency has to prepare a scheme as per the H order specified by the Board. #### 970 SUPREME COURT REPORTS [1990] 1 S.C.R. A In the instant case, the Board by order dated 27 August 1987 has stated that it was satisfied that the company has become a sick industrial company. The Board directed that further proceedings under the Act shall be taken with respect to the company. On the same day the Board after having heard the representatives of the ICICI, the company, the concerned Banks, the other public financial institutions and #### B the State Government of Gujarat, considered the entire material on record, held that it was not practicable for the company to make its net worth positive within a reasonable time and that further proceedings under sub-section (3) of Section 17 of the Act are, therefore, to be taken. Accordingly, in exercise of the powers conferred under Section 17(3) of the Act, the Board appointed the ICICI as the operating ### t agency to prepare a scheme for rehabilitation/revival of the company keeping in view of the provisions of Sections 18 and 19 and the guidelinef. At the same time the Board appointed Shri Y.V. Sivaramakrishnayya as the special director of the company for safeguarding its · financial and·other interests. It> In the light of the steps taken by the Board under Sections 16 and 17 of the Act, no proceedings for execution, distress or the like proceedings against any of the properties of the company shall lie or be proceeded further except with the consent of the Board. Indeed, there would be automatic suspension of such proceedings against the company's properties. As soon as the inquiry under Section 16 is ordered E by the Board, the various proceedings set out under sub-section (1) of Section 22 would be deemed to have been suspended. It may be against the principles of equity if the creditors are not allowed to recover their dues from the company, but such creditors may approach the Board for permission to proceed against the comF pany for the recovery of their dues/outstandings/overdues or arrears by whatever name it is called. The Board at its discretion may accord its approval for proceeding against the company. If the approval is not granted, the remedy is not extinguished. It is only postponed. Subsection (5) of Section 22 provides for exclusion of the period during which the remedy is suspended while computing the period of limitaG tion for recovering the dues. In our opinion, the High Court was justified in quashing the recovery proceedings taken against the properties of the company and we accordingly, reject this petition, with no order as to costs. H P.S.S. Petition dismissed. #