High CourtDivision BenchAppeal allowed; High Court’s order set aside; N...

GOVT. OF NCT OF DELHI & ANR. v. SH. NARENDER & ANR.

Case / Petition Number:Civil Appeal No. 740 of 2023
Neutral Citation:[2023] 1 S.C.R. 413

Case Details & Bench

Court
High Court
Hon'ble Judges
  • M. R. Shah
  • C. T. Ravikumar
Judgment Date
2023-02-09
Court Decision / Holding
Appeal allowed. No costs. The High Court’s judgment declaring lapse under Section 24(2) of the 2013 Act is quashed. The land acquisition proceedings are not deemed to have lapsed; the matter is to be governed by the 2013 Act in light of the Indore Development Authority decision.
Final Disposition
Appeal allowed; High Court’s order set aside; No costs; Pending applications disposed of.

Parties to the Case

Appellants / Petitioners

  • Govt. of NCT of Delhi & Anr.

Respondents

  • Sh. Narender
  • Anr.

Legal Representation & Advocates

Counsels for Petitioners

  • • Huzefa Ahmadi, Sr. Adv.
  • • Ms. Sujeeta Srivastava
  • • Shivam Singh
  • • Rohan Sharma
  • • Ms. Shaswati Parhi
  • • Gopal Singh
  • • Ms. Iti Sharma
  • • Rahul Bhatia
  • • Mishra Saurabh
  • • Ms. Manika Tripathy
  • • Ashutosh Kaushik
  • • Manish Vashist
  • • Roshan Kumar
  • • Nitin Mishra
  • • Sahil Tagotra
  • • Abhishek Pandey
  • • Ms. Abhivyakti Banerjee
  • • Ms. Sakshi Garg
  • • Ms. Sunieta Ojha

Case Synopsis & Summary

This Civil Appeal concerns whether land acquisition proceedings initiated under the 1894 Land Acquisition Act lapse under Section 24(2) of the 2013 Act. The Delhi High Court had held that the land acquisition stood lapsed under Section 24(2) because of inaction, relying on Pune Municipal Corporation v. Harakchand Misrimal Solanki. The Supreme Court corrects this position, clarifying that the constitutional bench decision in Indore Development Authority v. Manoharlal (2020) governs the interpretation of Section 24(2). It reiterates that lapse is not automatic; two conditions matter—possession and payment of compensation—and both must be absent for five years prior to 1-1-2014 for lapse to operate. Here, possession of the land was taken on 14.09.2007, before 2014, and the Court holds that there is no deemed lapse under Section 24(2). The judgment overrules Pune Municipal and related precedents that had treated lapse more broadly. It also clarifies that the proviso to Section 24(2) is part of Section 24(2), and non-deposit of compensation in court does not by itself cause lapse. Following Indore Development Authority, the appeal is allowed, the High Court’s order is quashed, and the land acquisition proceedings are not deemed to have lapsed.

Provisions of Law Cited

Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013Section 24(1)(a) of the 2013 ActSection 24(1)(b) of the 2013 ActProviso to Section 24(2)Section 31 of the Land Acquisition Act, 1894Section 34 of the Land Acquisition Act, 1894Section 4 of the Land Acquisition Act, 1894Section 16 of the Land Acquisition Act, 1894

Legal Doctrines & Maxims

  • Twin-condition principle for lapse under Section 24(2): possession and compensation (or their absence)
  • Interpretation of the word 'or' between possession and compensation as potentially 'nor' or 'and' (to decide lapse)
  • proviso to Section 24(2) forms part of Section 24(2) rather than Section 24(1)(b)
  • Non-deposit of compensation in court does not by itself cause lapse; if compensation is tendered under Section 31(1), liability to pay is discharged
  • Lapse under Section 24(2) applies to proceedings pending as on 1-1-2014 and requires inaction for five years or more prior to that date; interim orders’ period is excluded
  • Overruling of Pune Municipal Corporation by Constitution Bench in Indore Development Authority; subsequent affirmations/clarifications guiding the interpretation of Section 24(2)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contended that the High Court erred in holding that the land acquisition proceedings under the 1894 Act lapsed under Section 24(2) of the 2013 Act, relying on Pune Municipal. They emphasized that possession of the land was taken on 14.09.2007, and that the Constitution Bench in Indore Development Authority overruled Pune and clarified the correct interpretation of Section 24(2). They argued that if possession is taken, or if compensation is paid, there is no lapse; the proviso to Section 24(2) and the five-year inaction window prior to 1-1-2014 determine the lapse, with interim order periods excluded. They urged applying Indore Development Authority to hold that the lapse did not occur, and thus quashing the High Court’s judgment is appropriate.

Contentions of Respondents

The respondents contended that the writ petitioner was entitled to seek a declaration that the acquisition proceedings lapsed under Section 24(2) of the 2013 Act, relying on Pune Municipal Corporation’s reasoning. They asserted that in the absence of both possession and payment for five years or more, the deemed lapse should apply. They relied on precedents prior to Indore Development Authority that had held the 2013 Act’s lapse provisions applicable. They argued that the High Court’s order was correct in declaring lapse or in maintaining a status that favored the 2013 Act regime until overruled by constitutional bench decisions.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
Indore Development Authority v. Manoharlal & Ors.(2020) 8 SCC 129PositiveConstitution Bench decision followed; used to overrule Pune and to guide interpretation of Section 24(2), including the conditions for lapse and the placement of proviso within Section 24(2).
Pune Municipal Corporation & Anr. v. Harakchand Misrimal Solanki & Ors.(2014) 3 SCC 183OverruledOverruled by the Constitution Bench in Indore Development Authority; its reasoning on deemed lapse under Section 24(2) is no longer good law.
Sree Balaji Nagar Residential Assn. v. State of Tamil Nadu(2015) 3 SCC 353OverruledCannot be said to be laying down good law; overruled in light of Indore Development Authority judgment.
Indore Development Authority v. Shailendra[(2018) 3 SCC 412]OverruledPrecedent that could not prevail in view of the Indore Development Authority decision and the discussion in this judgment.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against GOVT. OF NCT OF DELHI & ANR. v. SH. NARENDER & ANR. and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

413 [2023] 1 S.C.R. 413 ## GOVT. OF NCT OF DELHI & ANR. A v. ## SH. NARENDER & ANR. (Civil Appeal No. 740 of 2023) FEBRUARY 09, 2023 B ## **[M. R. SHAH AND C. T. RAVIKUMAR, JJ.]** _Land Acquisition – Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 – s.24(2) – Land Acquisition Act, 1894 – Relying upon the decision of Supreme Court in the case of Pune Municipal Corporation, the High Court allowed writ petition preferred by respondent no.1 and declared that the land acquisition proceedings initiated under the Act, 1894 of the subject land is deemed to have lapsed under s.24(2) of the Act, 2013 – Decision in the case of_ Pune Municipal Corporation _has been specifically overruled by the Constitution Bench decision in the case of_ Indore Development Authority _– Accordingly, twin conditions namely, not taking possession and not paying compensation have to be satisfied and if one of the conditions is not satisfied there shall not be any lapse of the acquisition – Possession of land in question was duly taken on 14.09.2007 – High Court, thus, committed serious error in declaring that the acquisition with respect to the land in question is deemed to have lapsed u/s.24(2) of the Act, 2013 – Judgment of High Court unsustainable._ C D E F _Indore Development Authority vs Manoharlal & Ors._ **(2020) 8 SCC 129 : [2020] 3 SCR 1 – followed.** _Pune Municipal Corporation & Anr. v. Harakchand Misrimal Solanki & Ors_ **(2014) 3 SCC 183 – held overruled.** G ## **Case Law Reference** |**(2014)**|**3**|**SCC**|**183**|**held overruled**|**Para 2**| |---|---|---|---|---|---| |**[2020]**|**3**|**SCR**|**1**|**followed**|**Para 3**| H 413 414 SUPREME COURT REPORTS [2023] 1 S.C.R. A CIVIL APPELLATE JURISDICTION : Civil Appeal No.740 of 2023. From the Judgment and Order dated 02.08.2016 of the High Court of Delhi at New Delhi in Writ Petition (C) No.10670 of 2015. B Huzefa Ahmadi, Sr. Adv., Ms. Sujeeta Srivastava, Shivam Singh, Rohan Sharma, Ms. Shaswati Parhi, Gopal Singh, Ms. Iti Sharma, Rahul Bhatia, Mishra Saurabh, Ms. Manika Tripathy, Ashutosh Kaushik, Manish Vashist, Roshan Kumar, Nitin Mishra, Sahil Tagotra, Abhishek Pandey, Ms. Abhivyakti Banerjee, Ms. Sakshi Garg, Ms. Sunieta Ojha, Advs. C for the appearing parties. The Judgment of the Court was delivered by ## **M. R. SHAH, J.** 1. Feeling aggrieved and dissatisfied with the impugned judgment D and order passed by the High Court of Delhi at New Delhi in Writ Petition (C) No. 10670 of 2015 by which the High Court has allowed the said writ petition preferred by the respondent No. 1 herein – original writ petitioner and has declared that the land acquisition proceedings initiated under the Land Acquisition Act, 1894 (hereinafter referred to E as “Act, 1894”) with regard to the land in question is deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as “Act, 2013”), the Govt. of NCT of Delhi and Anr. have preferred the present appeal. F 2.From the impugned judgment and order passed by the High Court and even from the counter affidavit filed before the High Court, it appears that it was the specific case on behalf of the appellant and original respondents that the possession of the land in question was taken G on 14.09.2007. However, despite the above, relying upon the decision of this Court in the case of **Pune Municipal Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors., (2014) 3 SCC 183** , the High Court has allowed the said writ petition and has declared that the land acquisition proceedings initiated under the Act, 1894 of the subject land is deemed to have lapsed under Section 24(2) of the Act, 2013. H GOVT. OF NCT OF DELHI & ANR. v. SH. NARENDER & ANR. 415 [M. R. SHAH, J.] 3. However, it is required to be noted that the decision of this Court in the case of **Pune Municipal Corporation and Anr. (supra)** , which has been relied upon by the High Court while passing the impugned judgment and order has been specifically overruled by the Constitution Bench decision of this Court in the case of **Indore Development Authority Vs. Manoharlal and Ors., (2020) 8 SCC 129** . In paragraphs 365 and 366, the Constitution Bench of this Court has observed and held as under:- “ **365.** Resultantly, the decision rendered in Pune Municipal Corpn. [Pune Municipal Corpn. v. Harakchand Misirimal Solanki, (2014) 3 SCC 183] is hereby overruled and all other decisions in which Pune Municipal Corpn. [Pune Municipal Corpn. v. Harakchand Misirimal Solanki, (2014) 3 SCC 183] has been followed, are also overruled. The decision in Sree Balaji Nagar Residential Assn. [Sree Balaji Nagar Residential Assn. v. State of T.N., (2015) 3 SCC 353] cannot be said to be laying down good law, is overruled and other decisions following the same are also overruled. In Indore Development Authority v. Shailendra [(2018) 3 SCC 412], the aspect with respect to the proviso to Section 24(2) and whether “or” has to be read as “nor” or as “and” was not placed for consideration. Therefore, that decision too cannot prevail, in the light of the discussion in the present judgment. **366.** In view of the aforesaid discussion, we answer the questions as under: A B C D E F **366.1.** Under the provisions of Section 24(1)(a) in case the award is not made as on 1-1-2014, the date of commencement of the 2013 Act, there is no lapse of proceedings. Compensation has to be determined under the provisions of the 2013 Act. G **366.2.** In case the award has been passed within the window period of five years excluding the period covered by an interim order of the court, then proceedings shall continue as provided under Section 24(1)(b) of the 2013 Act under the 1894 Act as if it has not been repealed. H 416 SUPREME COURT REPORTS [2023] 1 S.C.R. A B C D E **366.3.** The word “or” used in Section 24(2) between possession and compensation has to be read as “nor” or as “and”. The deemed lapse of land acquisition proceedings under Section 24(2) of the 2013 Act takes place where due to inaction of authorities for five years or more prior to commencement of the said Act, the possession of land has not been taken nor compensation has been paid. In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly, if compensation has been paid, possession has not been taken then there is no lapse. **366.4.** The expression “paid” in the main part of Section 24(2) of the 2013 Act does not include a deposit of compensation in court. The consequence of non-deposit is provided in the proviso to Section 24(2) in case it has not been deposited with respect to majority of landholdings then all beneficiaries (landowners) as on the date of notification for land acquisition under Section 4 of the 1894 Act shall be entitled to compensation in accordance with the provisions of the 2013 Act. In case the obligation under Section 31 of the Land Acquisition Act, 1894 has not been fulfilled, interest under Section 34 of the said Act can be granted. Non-deposit of compensation (in court) does not result in the lapse of land acquisition proceedings. In case of non-deposit with respect to the majority of holdings for five years or more, compensation under the 2013 Act has to be paid to the “landowners” as on the date of notification for land acquisition under Section 4 of the 1894 Act. F G **366.5.** In case a person has been tendered the compensation as provided under Section 31(1) of the 1894 Act, it is not open to him to claim that acquisition has lapsed under Section 24(2) due to non-payment or non- deposit of compensation in court. The obligation to pay is complete by tendering the amount under Section 31(1). The landowners who had refused to accept compensation or who sought reference for higher compensation, cannot claim that the acquisition proceedings had lapsed under Section 24(2) of the 2013 Act. H GOVT. OF NCT OF DELHI & ANR. v. SH. NARENDER & ANR. 417 [M. R. SHAH, J.] **366.6.** The proviso to Section 24(2) of the 2013 Act is to A be treated as part of Section 24(2), not part of Section 24(1)(b). **366.7.** The mode of taking possession under the 1894 Act and as contemplated under Section 24(2) is by drawing of inquest report/memorandum. Once award has been passed on taking possession under Section 16 of the 1894 Act, the land vests in State there is no divesting provided under Section 24(2) of the 2013 Act, as once possession has been taken there is no lapse under Section 24(2). **366.8.** The provisions of Section 24(2) providing for a deemed lapse of proceedings are applicable in case authorities have failed due to their inaction to take possession and pay compensation for five years or more before the 2013 Act came into force, in a proceeding for land acquisition pending with the authority concerned as on 1-1-2014. The period of subsistence of interim orders passed by court has to be excluded in the computation of five years. **366.9.** Section 24(2) of the 2013 Act does not give rise to new cause of action to question the legality of concluded proceedings of land acquisition. Section 24 applies to a proceeding pending on the date of enforcement of the 2013 Act i.e. 1-1-2014. It does not revive stale and time-barred claims and does not reopen concluded proceedings nor allow landowners to question the legality of mode of taking possession to reopen proceedings or mode of deposit of compensation in the treasury instead of court to invalidate acquisition.” 4. In view of the above and applying the law laid down by this Court in the case of **Indore Development Authority (supra)** and when it was the specific case on behalf of the appellant and original respondents that the possession of the land in question was taken on 14.09.2007, the impugned judgment and order passed by the High Court declaring that the land acquisition proceedings initiated under the Act, 1894 with respect to land in question is deemed to have lapsed under B C D E F G H 418 SUPREME COURT REPORTS [2023] 1 S.C.R. - A Section 24(2) of the Act, 2013 is unsustainable and deserves to be quashed and set aside and is accordingly quashed and set aside. Present appeal is accordingly allowed. No costs. Pending applications, if any, also stand disposed of. B Bibhuti Bhushan Bose Appeal allowed. (Assisted by : Abhishek Pratap Singh, LCRA) C D E F G H