Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 2016Division BenchAppeal disposed of; No order as to costs; Appel...

GOVT. OF NCT OF DELHI AND ANOTHER v. MAHENDER SINGH AND OTHERS

Case / Petition Number:
Civil Appeal No. 9596 of 2016
Neutral Citation:[2016] 6 S.C.R. 986

Case Synopsis & Summary

The appeal concerns whether a stay on land acquisition under a Section 4(1) notification issued under the 1894 Act, for one parcel, could extend to other parcels within the same notification after enactment of the 2013 Act. Facts: Land acquisition under the 1894 Act began with Section 4(1) notification dated 04.03.2003, Section 6 declaration on 04.02.2004, and a Section 11 award on 03.02.2006. No possession was taken and no compensation paid within five years prior to 01.01.2014, when the 2013 Act came into force. The High Court declared the proceedings elapsed under Section 24(2) of the 2013 Act. The appellants contended that a stay granted in respect of adjoining land under the same Section 4(1) notification should be extended to all lands so as to exclude the stay period while computing the five‑year window under Section 24(2). They relied on Om Prakash v. Union of India. The Court, in a two‑judge Bench, distinguished Om Prakash and held that the lapse under Section 24(2) is post‑award and land‑specific — it affects only the land referred to in the award, not the entire lands covered by the Section 4(1) notification. Nevertheless, the Court allowed the appellants one year to initiate fresh proceedings under the 2013 Act and disposed of the appeal with no order as to costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • KURIAN JOSEPH
  • R. F. NARIMAN
Judgment Date
2016-09-22
Court Decision / Holding
Appeal disposed of. The Court held that Section 24(2) of the 2013 Act operates to deem the land acquisition proceedings in respect of the lands covered by the award under Section 11 as lapsed where possession was not taken or compensation not paid within five years prior to 01.01.2014; this lapse is post‑award and land‑specific, not automatic for all lands under the Section 4(1) notification. Om Prakash was distinguished. The Court granted the appellants a period of one year to initiate fresh proceedings under the 2013 Act in respect of the land covered by the notification, and directed that pending applications be disposed of; there shall be no order as to costs.
Final Disposition
Appeal disposed of; No order as to costs; Appellants given one year to initiate fresh proceedings under the 2013 Act.

Parties to the Case

Appellants / Petitioners

  • GOVT. OF NCT OF DELHI AND ANOTHER

Respondents

  • Mahender Singh and Others

Legal Representation & Advocates

Counsels for Petitioners

  • • Ms. Pinki Anand, ASG
  • • Kailash Vasudev
  • • Neeraj Kumar Jain
  • • R. C. S. Sethi, Sr. Adv
  • • R. K. Rathore

Counsels for Respondents

  • • Vibhu Shankar Mishra
  • • Shailender Saini
  • • Gunwant Dara
  • • Harish Khinchi
  • • Shadman Ali
  • • D. S. Mahra
  • • Atulesh Kumar
  • • Meenesh Kumar Dubey
  • • M. K. Maroria
  • • T. N. Singh
  • • Govind Goel
  • • Ankit Goel
  • • Vaibhav Anand
  • • Ram Naresh Yadav
  • • Zeeshan Diwan
  • • T. Mahi Pal
  • • Archana Kumari
  • • Sumit Bajaj
  • • Girish Chandra
  • • Sukrit R. Kapoor
  • • Sumeer Sodhi
  • • Arjun Nanda
  • • Arvind Verma

Provisions of Law Cited

Land Acquisition Act, 1894 - Section 4(1)Land Acquisition Act, 1894 - Section 6Land Acquisition Act, 1894 - Section 9Land Acquisition Act, 1894 - Section 11Land Acquisition Act, 1894 - Section 11ARight to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Section 24(2)

Legal Doctrines & Maxims

  • Post‑award lapse under s.24(2) of the 2013 Act is land‑specific to the land referred to in the award, not the entire land covered by the 4(1) notification.
  • Difference between lapse under s.11A (pre‑award) and lapse under s.24(2) (post‑award) clarified; the latter pertains to the land acquisition proceedings culminating in an award where possession is not taken or compensation not paid within the relevant period.
  • Om Prakash v. Union of India distinguished: stay in one matter under 4(1) does not automatically extend to all lands under the same notification.

Submissions & Arguments

Contentions of Appellants / Petitioners

The applicants contend that a stay granted in respect of one item covered by the Section 4(1) notification cannot be confined to that single item if the notification covers multiple lands; they urge that the period of stay should be excluded under Section 24(2) of the 2013 Act when calculating the five‑year window; they rely on Om Prakash to argue that the relief should extend to all lands covered by the same notification.

Contentions of Respondents

The respondents submit that the lapse under Section 24(2) is post‑award and land‑specific to the land that has an award under Section 11; they argue that Om Prakash is distinguishable and that extension of stay to all lands would be inappropriate; lapse must be assessed for the lands that were actually awarded under the 1894 Act.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
Laxman Pandya and others v. State of Uttar Pradesh and others(2011) 14 SCC 94PositiveSupports the principle that lapse is land‑specific to the land under the award.
Mulchand Khanumal Khatri v. State of Gujarat and others(2012) 5 SCC 365PositiveAffirms that lapse under Section 24(2) is limited to the land under the award.
Singareni Collieries Company Limited v. Vemuganti Ramakrishnan Rao and others(2013) 8 SCC 789PositiveReinforces the land‑specific nature of lapse under the 2013 Act.
Om Prakash v. Union of India and others(2010) 4 SCC 17; 2010 (2) SCR 447DistinguishedHeld to be distinguishable on the facts; its ratio not applicable to the present case.
Delhi Development Authority v. Sukhbir Singh(2016) SCALE 655Mentioned OnlyCited as a reference point for keeping stay considerations in view, but not controlling on the present ratio.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,095 words•~15 min read

In The Court Record

GOVT. OF NCT OF DELHI AND ANOTHER v. MAHENDER SINGH AND OTHERS

[2016] 6 S.C.R. 986 A- ## GOVT. OF NCT OF DELHI AND ANOTHER v. ## MAHENDER SINGH AND OTHERS B (Civil Appeal No. 9596of2016) SEPTEMBER 22, 2016 **[KURIAN JOSEPH AND R. F. NARIMAN, JJ.]** _Right to Fair Compensation and Transparency in Land_ - - _Acquisition, Rehabilitation and Resettlement Act, 2013 s.2./(2) Stay granted in respect of one of the lands covered by the s.4(1)_ c _notification of the 1894 Act_ - _Effect on the other lands covered by the same notification_ - _Jn the instant land acquisition proceedings, award was passed under the 1894 Act_ - _After passing the award u/s.11 of the 1894 Act, no compensation was paid and possession was also not taken within five years prior to 01.01.2014, wh_en_ D _2013 Act came into effect_ - _Therefore, in terms of s.24(2) of the 2013 Act, the acquisition proceedings under 1894 Act in respect of respondents' land have lapsed_ - _Since lapse u!s.24(2) is post-award, that would affect only the land referred to in the award and not the enlire land covered by the s.4(1) notification of the 1894 Act under_ - _which the proceedings for acquisition were initiated Therefore,_ E _effect of stay cannot be extended to entire land_ - _Land Acquisition Act, 1894_ - _ss.4(1), 6, 9, Jl, JJA._ c _Land Acquisition Act, 1894_ - _s.JJA_ - _Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013_ - _s.24(2)_ - _Difference between lapse ul_ F _s. JJA and lapse u!s.24(2)_ - _Discussed._ ## **Disposing of the appeal, the Court** **HELD: 1.1 Under the scheme of acquisition, an award u/ s.11 has to be passed in respect of each land owned by a person/** G **persons** intereste~. **Therefore, what is lapsed u/s.llA is not the entire land as declared u/s.6 but the particular land belonging to person/persons in whose favour an award u/s.11 had to be passed within two years of the declaration u/s.6 of the 1894 Act. [Para 10][992-B-C]** H 986 987 ## GOVT. OF NCT OF DELHI AND ANOTHER v. MAHENDER SINGH AND OTHERS 1.2 The lapse is limited only to the land covered by the particular award(s). [Para 11)(992-D-E] _Laxman Pandya and others v. State of Uttar Pradesh and others_ (2011) 14 SCC 94; _Mulchand Khanumal Khatri v. State of Gujarat and others_ (2012) 5 SCC 365: 2012 {2) SCR 586; _Singareni Collieries Company Limited v. Vemuganti Ramakrishan Rao and others_ (2013) 8 SCC 789: 2013 (9) SCR 658 - referred to. 2. The crucial difference between lapse u/s.llA of the 1894 Act and that u/s.24(2) of the 2013 Act is that the former is a preaward situation whereas the latter is post-award. In other words, what gets lapsed u/s.llA of the 1894 Act is the ... "entire proceedings for the acquisition of the land", whereas, u/s.24(2) of the 2013 Act, what gets lapsed is the land acquisition proceedings initiated under the Land Acquisition Act, 1894 which has culminated in passing of an award u/s.11 but where either possession is not taken or compensation not paid within five years prior to 01.01.2014. [Para 13)(993-B-D] > 3. Since lapse u/s.24(2) of the 2013 Act is post-award, that would affect only the land referred to in the award an<I not the entire lands covered by the s.4(1) notification under which the proceedings for acquisition were initiated. In the instant case, there is no dispute on facts that after passing the award u/s.11 of . the 1894 Act, no compensation has been paid and the possession also has not been taken within five years prior to 01.01.2014. Therefore, s.24(2) of the 2013 Act has to operate, and the acquisition proceedings in respect of respondents' lands where award u/s.11 of the 1894 Act had been passed, have lapsed. [Paras 15,J6J[993-1;_-GJ A B c D E F _Om Prakash v. Union of India and others_ (2010) 4 SCC 17 : 2010 (2) SCR 447 - held inapplicable. _Delhi Development Authority v. Sukhbir Singh_ 2016 (8) SCALE 655 - referred to. G ## Case Law Reference (2011) 14 sec 94 referred to Para 11 H [2016] 6 S.C.R. 988 SUPREME COURT REPORTS A **==> picture [263 x 68] intentionally omitted <==** **----- Start of picture text -----**<br> ||||| |---|---|---|---| |2012 (2)|SCR586|referred to|Para 11| |2013 (9)|SCR658|referred to|Para 11| |2016 (8) SCALE 655 referred to|Para 14| |2010 (2)|SCR447|held inapplicable|Para 15| **----- End of picture text -----**<br> B CIVIL APPELLATE JURISDICTION: Civil Appeal No. 9596 of2016. From the Judgment and Order dated 27.05.2014 of the High Court of Delhi afNew Delhi in WPC No. 1823 of2014. Ms. Pinki Anand, ASG, Kailash Vasudev, Neeraj Kumar Jain, R. c S. Sethi, Sr. Advs., R. K. Rathore, Ms. Vibhu Shankar Mishra, Shailender Saini, Ms. Gunwant Dara, Harish Khinchi, Shadman Ali, D. S. Mahra, Atulesh Kumar, Meenesh Kumar Dubey, (for Mrs. Sushma Suri), Minish Dubey, M. K. Maroria, ShadmanAli, Vikas K. Singh, T. N. Singh, Govind Goel, Ankit Goel, Vaibhav Anand, Ram Naresh Yadav, Kuna) Verma, D Prasanna Mohan, Ms. Yugandhara P. Jha, Ms. Uttara Babbar, Ms. Rachana Srivastava, Ms. Monika, Sukrit R. Kapoor, Gopal Sankara Narayan, Sumeer Sodhi, Arjun Nanda, Zeeshan Diwan, T. Mahi pal, Atul Kumar, Ms. Sweety Singh, Girish Chandra, Ms. Archana Kumari, Sum it Bajaj, Vishnu B. Saharya, Viresh B. Saharya, (for _Mis_ Saharya & Co.), .Rajiv Ghawana, T. V. S. Raghavendra Sreyas, Ashwani Kumar, Rahul E Bhatia, Anil Kaushik, Raghavinder Verma, Rajinder Singh, Abhishek Mishra, Ms. Arunima Dwivedi; Sachin Sood, Kailash Pandey, Ms. Kritika Arora, K. V. Sreekumar, Vinay Kumar Shailendra, Vaibhav Asthana, Chandra Bhushan Prasad, Amit Gupta, Sarwa Mitter, Ms. Asmita Singh, Ms. Mansi Kukreja, (for M/s Mitter & Mitter), Advs. for the appearing F parties. The Judgment of the Court was delivered by KURIAN, J.: I. Leave granted. 2. For the purpose ofoperation of Section 24(2) of the The Right G to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as "2013 Act"), whether the stay granted in one of the items covered by the very same Section 4( 1) notification could have the effect on other lands covered by the same notification, is the short question involved in this appeal. H GOVT. OF NCT OF DELHI AND ANOTHER v. MAHENDER SINGH AND OTHERS [KURIAN, J.] 989 ## **SHORT** FACTS 3. Land acquisition proceedings were initiated by publishing Section 4( I) notification under the 1894 Act on 04.03 .2003. Section 6 declaration was duly published on 04.02.2004 and the award was passed under Section 11 on 03.02.2006. It is not in dispute that neither physical possession has been taken nor compensation paid within five years prior to the implementation of2013 Act. 4. 2013 Act came into force into effect on 01.01.2014. The High Court rendered a declaration that the land acquisition proceedings have elapsed in terms of Section 24(2) of the 2013 Act. Thus aggrieved, the appellants are before this Court. 5. It is the main contention of the learned Counsel forthe appellants that in view of the stay order granted by the High Court in respect of the adjoining land covered by the Section 4(1) notification dated 04.03.2003, the acquisition proceedings could not be completed within time. The benefit of the operation of stay should be extended to the entire lands covered by Section 4(1) notification and that such period should be excluded wl)ile computing the period of five years referred to under Section 24 (2) of the 2013 Act. To buttress the point, the learned Counsel has relied on a decision of this Court in **Om Prakash v. Union oflndia and others•.** A B C D E 6. **Om Prakash** _(supra)_ was a case where stay operated for certain lands notified under Section 4( I) of 1894 Act, and on account of such stay, the declarations under Section 6 were made after the prescribed period. However, in view of the Explanation under Section 6, the period during which any action or proceeding to be taken in pursuance of the notification issued under Section 4(1) had been stayed by an order of the court, was liable to be excluded. It was held by this Court that the interim order of stay granted in some of the lands notified under Section 4( I) of the 1894 Act would put a complete restraint to proceed with the declaration under Section 6 of the 1894 Act, meaning thereby, the benefit of that interim stay could be extended to the entire lands covered by Section 4( I) notification. F G 7. Paragraphs-70 to 72 in **Om Prakash** case _(supra)_ have dealt with the issue and they are extracted herein below: H > 1 (2010) 4 sec 11 990 [2016] 6 S.C.R. SUPREME COURT REPORTS A B c D E F G > "70. Perusal of the opinion of the Full Bench in _B.R. Gupta!_ would clearly indicate with regard to interpretation of the word "any" in Explanation I to the first proviso to Section 6 of the Act which expands the scope of stay order granted in· one case of landowners to be automatically extended to all those landowners, whose lands are covered under the notifications issued under Section 4 of the Act, irrespective of the fact whether there was any separate order of stay or not as regards their lailds. The logic assigned by the Full Bench, the relevant portions whereof have been reproduced hereinabove, appear to be reasonable, apt, legal and proper. 71. It is also worth mentioning that each of the notifications issued under Section 4 of the Act was composite in nature. The interim order of stay granted in one of the matters i.e. _Munni Lal_ and confirmed subsequently ha:ve been reproduced hereinabove. We have also been given to understand that similar orders of stay were passed in many other petitions. Thus, in the teeth of such interim orders of stay, as reproduced hereinabove, we are of the opinion that during the period of stay the respondents could not have proceeded further to issue declaration/notification under Section 6 of the Act. As soon as the interim stay came to be vacated by virtue of the main order having been passed in the writ petition, the respondents, taking advantage of the period of stay during which they were restrained from issuance of declaration under Section 6 of the Act, proceeded further and issued notification under Section 6 of the Act. 72. Tims, in other words, the interim orderof stay granted in one of the matters of the landowners would put complete restraint on the respondents to have proceeded further to issue notification under Section 6 of the Act. Had they issµed the said notification during the period when the stay was operative, then obviously they may have been hauled up for committing contempt of court. The language employed in the interim orders of stay is also such that it had completely restrained the respondents fro11J proceeding further in the matter by issuing declaration/notification under Section 6 of the Act." H GOVT. OF NCT OF DELI-ii AND ANOTHER v. MAHENDER SINGH AND OTHERS [KURIAN, J.] 991 8. On the same analogy, it is contended that the benefit of stay preventing lapse of one or more of the acquisition proceedings by operation of Section 24 (2) of the 2013 Act should be extendableto entire lands for which the acquisition proceedings were initiated as per Section 4( I) notification under the 1894 Act. 9. There is one situation of lapse under the 1894 Act itself. In Section 11 A, as under Section 6, the Explanation has saved the period during which any action or proceeding to be taken in pursuance of the declaration under Section 6 was stayed by an order of the court. But what is lapsed under Section I IA are the proceedings for acquisition of the particular land for which an award under Section 11 of the 1894 Act had to be passed. Section 11 has to be preceded by a notice under Section 9 of the said Act to the persons interested in the land to be acquired. Section 9 of the 1894 Act reads as follows: "9. Notice to persons interested.-(!) The Collector shall then cause public notice to be given at convenient places on or near the land to be taken, stating that the Government intends to take possession of the land, and that claims to compensation for all interests in such land may be made to him. (2) Such notice shall state the particulars of the land so needed, and shall require all persons interested in the land to appear personally or by agent before the Collector at a time and place therein mentioned (such time not being earlier than fifteen days after the date of publication of the notice), and to state the nature of the\r respective interests in the land and the amount and particulars of their claims to compensation for such interests, and their objections (if any) to the measurements made under section 8. The Collector may in any case require such statement to be made in writing and signed by the party or his agent. (3) The Collector shall also serve notice to the same effect on the occupier (ifany) of such land and on all such persons known or believed to be interested therein, or to be entitled to act for persons so interested, as reside or have agents authorised to receive service on their behalf, within the revenue district in which the land is situate. A B c D E F G H 992 [2016] 6 S.C.R. SUPREME COURT REPORTS A ( 4) In case any person so interested resides elsewhere, and has no such agent the notice shall be sent to him by post in a letter addressed to hini at his last known residence, address or place of business and[37 ] [registered under sections 28 and 29 of the Indian Post Office Act, 1898 (6of1898)]." B J 0. Under the scheme of acquisition, an award under Section J J has to be passed in respect of each land owned by a person/persons interested. Therefore, what is lapsed under Section I J A is not the entire land as declared under Section 6 but the particular land belonging to person/persons in whose favour an award under Section J J had to be passed within two years of the declaration under Section 6 of the 1894 c Act. D J I. Effect of lapse under Section J I A was subject matter of many decisions of this Court. In Laxman Pandya and others v. State of Uttar Pradesh and others[2] , Mulchand Khanumal Khatri v. State of Gujarat and others[3] , Singareni Collieries Company Limited v. Vemuganti Ramakrishan Rao and others\ etc., this Court has consistently taken the view thatthe lapse is limited only to the land covered by the particular award(s). E J 2. Section 24(2) of the 20 J 3 Act also deals with a similar situation oflapse. The provision reads as follows: "24. xxxx x.xxx x.xxx x.xxx (2) Notwithstanding anything contained in sub-section (I), in case of land acquisition proceedings initiated under the F Land Acquisition Act, 1894, where an award under the said section J J has been made five years or more prior to' the commencement of this Act but the physical possession of the land has not been taken or the compensation has not been paid the said proceedings shall be deemed to have lapsed and the appropriate Government, if it so chooses, G shall initiate the proceedings of such land acquisition afresh in accordance with the provisions of this Act: (2011) 14 sec 94 ' t2012i 5 sec 365 H '(2013)8SCC789 993 GOVT. OF NCT OF DELHI AND ANOTHER v. MAHENDER SINGH AND OTHERS [KURIAN, J.] Provided that where an award has been made and compensation in respect ofa majority of land holding has not been deposited in the account of the beneficiaries, then, all beneficiaries specified in the notification for acquisition under section 4 of the said Land Acquisition Act, shall be entitled to compensation in accordance with the provisions of this Act." 13. The crucial difference between lapse under Section 1 lA of the 1894 Act and that under Section 24(2) of the 2013 Act is that the former is a pre-award situation whereas the latter is post-award. In other words, what gets lapsed under Section 11 A of the 1894 Act is the ... "entire proceedings for the acquisition of the land", whereas, under Section 24(2) of the 2013 Act, what gets lapsed is the land acquisition proceedings initiated under The Land Acquisition Act, 1894 which has culminated in passing of an award under Section 11 but where either possession is not taken or compensation not paid within five years prior to 01.01.2014. A B c D 14. The land acquisition proceedings referred under Section 24 (2) of the 2013 Act would include the steps for taking physical possession of the land and payment of compensation, as held by this Court in **Delhi Development Authority v. Sukhbir Singh[5 ] •** 15. Since the lapse under Section 24(2) of the 2013 Act is postaward, that would affect only the land referred to in the award and not the entire lands covered by the Section 4( 1) notification under which the proceedings for acquisition were initiated. Therefore, the ratio in **Om Prakash** _(supra)_ is of no avail to the appellants. 16. In the case before us, there is no dispute on facts that after passing the award under Section 11 of the 1894 Act, no compensation has been paid and the possession also has not been taken within five years prior to 01.0l.2014. Therefore, Section 24(2) of the 2013 Act has to operate, and the acquisition proceedings in respect of respondents' lands where award under Section 11 of the 1894 Act had been passed, have lapsed. E F G . 17. However, the declaration as above and the consequent dismissal of this appeal is without prejudice to the liberty available to the appellants to initiate proceedings afresh for the acquisition of the subject '2016 (8) SCALE 655 H 994 [2016) 6 S.C.R. SUPREME COURT REPORTS A land under the provisions of the 2013 Act. 18. Jn the peculiar facts and circumstances of this case, the appellants are given a period of one year to exercise its liberty granted under Section 24(2) of the 2013 Act for initiation of the acquisition proceedings afresh. ## B 19. ·Pending applications, if any, stand disposed of. 20. The appeal is disposed of as above. There shall be no order · as to costs. - C Ankit Gyan Appeal disposed of.
End of Judgment Record
Browse All Supreme Court of India (2016) Decisions
2016-03-16

Union of India v. Mis. Ambica Construction

This judgment addresses whether an arbitrator can award pendente lite interest when a contract expressly bars such interest, within the framework of Indian arbitration law. The Union of India approached this dispute after two arbitrators failed to publish an award and after a long procedural history in the Calcutta High Court and various SLPs. The core issue is whether pendente lite interest can be awarded where the contract contains explicit clauses barring such interest, and how this interacts with the implied terms of arbitration under the Arbitration Act, 1940 and, for post-1996 matters, the Arbitration and Conciliation Act, 1996. The Court traces a lineage of decisions (GC Roy; NC Budharaj; Sayeed Ahmed; Harish Chandra; Balimela; Engineers-De-Space-Age; Tehri Hydro) and clarifies that while arbitrators are generally creatures of the contract, their power to award pendente lite interest is bounded by express contractual bars. It concludes that no pendente lite interest can be awarded if the contract expressly prohibits it. The judgment also recognizes Tehri Hydro’s reasoning and clarifies the status of earlier decisions, holding certain observations as overruled or limited prospectively. The result is that the High Court and the award are to be modified to reflect the absence of pendente lite interest, with a reference answered and no costs awarded.”

2016-08-29

Madhya Pradesh State Road Transport Corporation v. Manoj Kumar & Anr.

This is a civil appeal challenging the voluntary retirement scheme (VRS) introduced by the Madhya Pradesh State Road Transport Corporation (MPSRTC) to downsize its workforce as the company faced losses and declining business. The scheme opened on July 1, 2005 and closed on August 1, 2005, with employees permitted to submit their option for voluntary retirement (VRS) within that window. The scheme included a clause stating that once an employee’s option was submitted it could not ordinarily be withdrawn, yet the scheme was a funded, time-bound arrangement requiring the employer to create a fund and to lay out a process for acceptance and settlement. In October 2006, the Corporation issued an amendment extending the period to October 28, 2006, prompting questions whether this extension created a new scheme or was merely an extension of the original. Several employees who had submitted applications sought withdrawal after August 1, 2005, and in some cases after the extension, while the Corporation accepted their VRS applications and disbursed terminal dues. The High Court of Madhya Pradesh upheld the employees’ right to withdraw within the relevant periods, but the Supreme Court concluded that VRS schemes, being contractual and funded, are invitations to offer governed by the Indian Contract Act, and withdrawals are permissible only within the valid period; the extension does not automatically grant a right to withdraw beyond the original window. The Court accordingly set aside some reinstatement orders and disposed of the appeals in favor of the Corporation in most respects.

2016-07-01

Mahipal Singh Rana, Advocate v. State of Uttar Pradesh

The appeal arises from a High Court of Allahabad judgment (Criminal Contempt Petition No.16 of 2004) finding the appellant, an advocate, guilty of criminal contempt for intimidating and berating a Civil Judge, Etah, on two dates (16 April 2003 and 13 May 2003). The Allahabad High Court sentenced him to two months’ simple imprisonment and imposed a fine, with a direction to Bar Council authorities to consider disciplinary action for professional misconduct. On admission to this Supreme Court, the matter was referred to a larger bench to decide whether a case of criminal contempt by a lawyer could also implicate professional misconduct beyond the contempt regime, and whether the Court could exercise suo motu jurisdiction under the Advocates Act if Bar Councils fail to act. The Court examined the separation of powers between contempt proceedings and Bar Council disciplinary processes, the scope of Article 142/129, and the ability to regulate appearance in courts (including the right to practice vs. the right to appear). It held that contempt conviction was justified and upheld the High Court’s finding, but set aside the imprisonment sentence due to the appellant’s advanced age. It sustained a two-year enrollment suspension under Section 24A of the Advocates Act and directed the Bar Councils to suspend the licence for an additional five years, with further appearance restrictions until the contemnor purges himself of contempt. The judgment emphasizes reform of regulatory mechanisms governing the legal profession and the State Bar Councils’ failings in acting on earlier notices.

2016-03-10

CHARANJIT KAUR v. BIKRAM SINGH & ANR.

Charanjit Kaur, wife of Bikram Singh, faced dowry-related harassment under sections 498A and 406 IPC. The trial court convicted the husband and imposed a one-year RI for each offence, with the sentences to run concurrently and a fine of Rs. 1,000/- with default imprisonment. The wife appealed against the conviction and also sought enhancement of punishment; the husband cross-appealed. The mother-in-law was acquitted; the father-in-law had died. The Sessions Court at Kapurthala modified the sentence by permitting the husband to deposit Rs. 2,50,000 payable to the appellant within one month, so that he could obtain the benefit of probation under Section 4(1) of the Probation of Offenders Act, 1958. The wife’s revision before the High Court of Punjab & Haryana at Chandigarh was dismissed in a summary manner, reportedly influenced by the deposit. The Supreme Court, noting the summary disposal and the deposit-driven rationale, held that the impugned order required setting aside so that the matter could be re-heard on merits. It directed remand to the High Court for a fresh decision strictly in accordance with law, without entering into the merits of rival submissions in this order. The decision was delivered by a Single Judge, Justice Shiva Kirti Singh, on March 10, 2016.