Supreme Court of IndiaSupreme Court · 2013Division BenchAppeal dismissed.

Gayatri Project Ltd. v. Sai Krishna Construction

Case / Petition Number:
Civil Appeal No. 1854 of 2007
Neutral Citation:[2013] 14 S.C.R. 1138

Case Synopsis & Summary

This Supreme Court decision concerns an application under Section 11(5) and (6) of the Arbitration and Conciliation Act, 1996, filed by Sai Krishna Construction (the sub-contractor) challenging the order of the Andhra Pradesh High Court directing reference of disputes to arbitration. The contract between Gayatri Project Ltd. (main contractor) and Sai Krishna Construction, dated 29 January 2001, contained an arbitration clause and set out the manner of payments, deductions, and final settlement terms. The respondent claimed it had completed work to the satisfaction of the State Government and that the appellant had not paid the due amount after deducting commission and other recoveries. The appellant asserted that a full and final settlement dated 6 June 2003 had been reached, the accounts reconciled, and that the respondent had accepted the settlement, thereby extinguishing all arbitrable disputes. The respondent, however, did not accept the settlement, nor did it claim coercion or fraud; and it claimed additional amounts. The High Court upheld the arbitration referral. On appeal, the Court held that the critical issue was whether the 6 June 2003 document constitutes a genuine full and final settlement; given the lack of acceptance by the respondent, the matter should be adjudicated by an arbitrator, not dismissed outright. The Court ultimately dismissed the appeal, and directed the arbitrator to conclude proceedings expeditiously.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Surinder Singh Nijjar
  • Ranjana Prakash Desai
Judgment Date
2013-11-28
Court Decision / Holding
Appeal dismissed. The Supreme Court held that the question whether the 6 June 2003 letter constitutes a full and final settlement must be determined on proper appreciation of the evidence. Because the respondent did not accept the settlement, the issue was left to the Arbitrator to adjudicate. The Court also directed the Arbitrator to conclude the proceedings expeditiously.
Final Disposition
Appeal dismissed.

Parties to the Case

Appellants / Petitioners

  • Gayatri Project Ltd.

Respondents

  • Sai Krishna Construction

Legal Representation & Advocates

Counsels for Petitioners

  • • Arun Kathpalia
  • • Angad Mehta
  • • Sayooj Mohandas M.
  • • Sanooja M.
  • • Abhijit Sengupta

Counsels for Respondents

  • • K. Swami
  • • Prabha Swami
  • • Nikhil Swami

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 - s. 11(5) and (6)

Legal Doctrines & Maxims

  • Sanctity of contract
  • Accord and satisfaction / Full and final settlement
  • Settlement can be challenged in proper proceedings
  • Arbitration clause operates notwithstanding disputes settled by accord (Damodar Valley Corporation line of reasoning)

Submissions & Arguments

Contentions of Appellants / Petitioners

The 29 January 2001 agreement contains an arbitration clause and the matter of disputes arising under it is to be resolved through arbitration. The respondent’s claim relies on a 6 June 2003 “full and final settlement.” The appellant argues that this settlement supersedes the 2001 contract only if duly accepted by both parties. Since the respondent did not accept it, there remains an arbitrable dispute. The respondent’s assertions of reconciliation and a final settlement are unilaterally motivated and cannot bar a reference to arbitration. If the settlement is challenged, it must be done in proper proceedings; the respondent’s acceptance is lacking, and the time-bar/estoppel arguments do not negate arbitrability. The High Court erred in mandating arbitration; the present appeal should be decided with regard to the absence of mutual acceptance.

Contentions of Respondents

There was a genuine, negotiated full and final settlement on 6 June 2003, signed by the respondent’s manager, acknowledging payments and setting forth remaining balances. The respondent’s later claims are part of the post-settlement disputes arising out of the contract. The settlement extinguishes arbitrable disputes; to force arbitration would circumvent the sanctity of a concluded settlement. The appellant received substantial payments from the Government, and the respondent’s claims of further amounts are baseless and inequitable. The reliance on Nathani Steels and related cases is misplaced; Nat. Insurance Co. and Boghara Polyfab support the sanctity of valid settlements and discharge of contracts.”},

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
Nathani Steels Ltd. v. Associated Constructions1995 Supp (3) SCC 324Mentioned OnlyCited to illustrate the principle of accord and satisfaction, but its ratio is not applied where acceptance of settlement by both parties is not shown.
Nav Bharat Builders—Mentioned OnlyMentioned in the discussion of settlements and arbitrability as part of the evolving jurisprudence; not a controlling ruling in this case.
P. K. Ramaiah—Mentioned OnlyCited in historical context regarding voluntary accord and discharge; not the central controlling authority here.
National Insurance Co. Ltd. v. Boghara Polyfab Pvt. Ltd.2009 (1) SCC 267Positiveendorsement of the ratio that once there is a voluntary accord and satisfaction or discharge, arbitrable disputes may be extinguished; used as a controlling principle in the decision.
Damodar Valley Corporation—Mentioned OnlyCited to illustrate the contrasting view that mere claim of accord and satisfaction may not terminate arbitration; used for contextual balance.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,036 words•~19 min read

In The Court Record

Gayatri Project Ltd. v. Sai Krishna Construction

## [2013] 14 S.C.R. 1138 A ## M/S. GAYATRI PROJECT LTD. _v._ MIS. SAi KRISHNA CONSTRUCTION (Civil Appeal No. 1854 of 2007) B ## NOVEMBER 28, 2013 ## **[SURINDER SINGH NIJJAR AND RANJANA PRAKASH DESAI, JJ.]** _Arbitration and Conciliation Act, 1996_ - _s. 11 (5) and (6)_ - - C - _Application under Maintainability Civil works relating to_ - _irrigation structures Granted to appellant by the State Government of Andhra Pradesh_ - _Appellant_ was _the main contractor and respondent_ was _the sub-contractor working_ - _under the appellant Agreement dated 29-01-2001 entered_ D _between the two parties contained an arbitration clause_ - _Claim of respondent that it had executed work to the satisfaction of the appellant and the State Government; but appellant having received all the amounts from the State Government failed to make corresponding payments to the_ E _respondent after deducting commission as stipulated under_ - _the agreement Counter claim of appellant that the accounts had been reconciled and that the parties had signed a full and_ - _final settlement document on 6. 6. 2003 Full and final_ - _settlement dated 6. 6. 2003 not accepted by respondent_ F _Dispute not resolved_ - _Respondent moved application ul_ s. _11 (5) and (6) for appointment of Arbitrator_ - _Plea of appellant that the application was liable to be dismissed inasmuch_ as _agreement dated 29.1.2001 which contains the arbitration clause had been superseded by the full and final_ G _settlement agreement dated 6. 6. 2003; and respondent having received the entire amount in terms of the "full and final settlement" dated 6-6-2003 was estopped from filing the application u/s. 11 (5) and (6)_ - _According to appellant, since the entire dispute had been settled, no reference could be_ H 1138 GAYATRI PROJECT LTD. _v._ SAi KRISHNA 1139 CONSTRUCTION _made to arbitration_ - _High Court, however, allowed the_ A _application u/s. 11 (5) and (6)_ - . _On appeal, held: The question as to whether letter dated 6-6-2003 would constitute_ a _"full and final settlement" would have to be determined on proper appreciation of the evidence led by the parties_ - _It is open to two interpretations_ - _Which of the two interpretations is_ B _ultimately accepted will have to be decided by the appropriate forum_ - _Appellant is relying on the alleged settlement by way of defence_ - _Respondent has not accepted the same_ - _Nor has the respondent denied the execution of the document_ - _Respondent has also not claimed that the fulr and final_ c _settlement was signed under coercion, undue influence, fraud, misrepresentation or mistake_ - _Furthermore, appellant did not make any claim on the basis of the settlement_ - _It would have been different, if the appellant had made a claim on the basis of settlement which was denied by the respondent by one or_ D _more of the defences_ - _In such circumstances, it would have to be held that the settlement can only be challenged in "proper proceedings"_ ..:. _However, in the instant case, since there is no acceptance of the full and final settlement by the respondent which has been relied upon by the appellant, the issue clearly had to be left to the Arbitrator to be adjudicated._ E _Nathani Steels Ltd. vs. Associated Constructions_ 1995 Supp (3) SCC 324; _National Insurance Company Limited vs. Boghara Polyfab Private Limited_ (2009) 1 SCC 267: 2008 (13) SCR 638 - referred to. F ## Case Law Reference: 1995 Supp (3) SCC 324 referred to Para 10 2008 (13) SCR 638 referred to Para 11 G CIVIL APPELLATE JURISDICTION : Civil Appeal No. 1854 of 2007. From the Judgment & Order dated 20.12.2006 of the High Court of Judicature of Andhra Pradesh at Hyderabad in H 1140 SUPREME COURT REPORTS [2013] 14 S.C.R. ## A Arbitration Application 55 of 2006. Arun Kathpalia, Angad Mehta, Sayooj Mohandas M., Sanooja M., Abhijit Sengupta for the Appellant. K. Swami, Prabha Swami, Nikhil Swami for the 8 Respondent. The following Order of the Court was delivered ## **ORDER** c D 1. This appeal is filed against the order passed by the High Court in an application under Section 11 (5) and (6) of the Arbitration and Conciliation Act, 1996 (for short the 'Act') directing that the matter be referred to arbitration by a former Judge of the Andhra Pradesh High Court. 2. The respondent moved the aforesaid application on the basis that it is a partnership firm, carrying on business of civil works relating to irrigation structures. The Irrigation Department of Government of Andhra Pradesh had given the work to the E appellant herein. Thus, the appellant was the main contractor and respondent was the sub-contractor working under the appellant. The works involved earth work excavation and cohesive non-swelling soil filling in KC Canal including CC lining and structures form KMs 156.650 to KMs 170-00 of Package F ICB-10' in Kurnool District of Andhra Pradesh. The appellant identified the respondent as a suitable agency for execution of the work and entrusted the work to the respondent as a subcontractor. After due negotiations, an agreement dated 29.1.2001 was entered into between the parties. The G agreement inter alia provides various terms and conditions including the nature of work to be executed by the respondent, security deposits, penalties leviable, commission to which the appellant would be entitled to, method of payment for the work undertaken, taxes and Government levies. The agreement also contained an arbitration clause which reads as under:- H ## GAYATRI PROJECT LTD. _v._ SAi KRISHNA 1141 CONSTRUCTION "All disputes relating to the original contract shall be A properly referred and correspond by the work contractor. However, the settlement of disputes and consequential awards shall be to the account of principal contractor and work contractor. All disputes relating to the work contract under this agreement shall be mutually settled between the B work contractor and the principal contractor. In case of any differences, the same will be decided by a sole arbitrator appointed by the principal contractor and work contractor." 3. Clause 6 of the agreement provides that the measurements shall be taken for the work done once in a month. Payment shall be released as and when principal contractor received payment from the Department, duly deducting the commission and other recoveries as mentioned in Clause 6 above. Final payment shall be released after completion of the work satisfactorily. Clause 5 provided that the work contractor (sub-contractor) shall be paid the balance amount after deducting certain amounts from the gross amount of running account bills. Relevant part of clause 5 is as under:- C D "The work contractor shall be paid the balance amount after deducting the following from the gross amount of running account bills. E i. a. Earth work excavation in bed and slopes including sectioning and leveling @ 14% (Fourteen percent only) of Agreement rate. F b. Filling bed and slopes with CNS soils as directed and as per specifications @ 17% (Seventeen percent only) of Agreement rates. ii. Sales Tax/Turnover Tax G iii. Income Tax in the running account bills. iv. Value of materials etc., if any, supplied by the H 1142 SUPREME COURT REPORTS [2013) 14 S.C.R. A department or by the principal contractor and hire charges of machinery given. v. Any other recoveries affected by the department in the account bills. B 4. The agreement further provided that the final payment shall be released after completion of the work satisfactorily. 5. The respondent claims that it has executed the work to the satisfaction of the appellant and the State Government. The c appellant having received all the amounts from the Government of Andhra Pradesh failed to make corresponding payments to the respondent after deducting commission as stipulated under the agreement. The respondent, therefork, approached and tried to persuade the appellant to make the payment of the 0 outstanding amount after the completion of the entire work. However, the appellant failed to pay. Since the amounts were not paid by the appellant, the respondent served a Claim Notice. on 6.5.2004 demanding the payment of Rs.1,01,27,776/-. On 17.8.2004, the Appellant sent a reply to the aforesaid notice E not only disputing the various claims but also raising a counter claim in the amount of Rs.32, 12,950/-. The appellant claimed that the accounts had been reconciled. The parties had signed a full and final settlement document on 6.6.2003, under which the respondent acknowledged the receipt of certain amounts. The balance of Rs.17,32,843/- was to be paid in two or three F instalments before 30.6.2003. After receiving the entire payment, the respondent was falsely claiming further amounts with mala fide intentions. On receipt of the reply with the counter-claim, the respondent sent a further reply reiterating its claim and also disputing the counter claim of the appellant as G being frivolous and false. The responrJent in the aforesaid reply also stated that unless the entire claim is satisfied, it will seek the remedy by way of arbitration. In spite of the above, the appellant still made efforts to settle the entire dispute but without any useful results. H GAYATRI PROJECT LTD. _v._ SAi KRISHNA 1143 CONSTRUCTION 6. Instead of accepting the full and fincil settlement dated A 6.6.2003, the respondent, in fact, raised a further claim for the amount of Rs.25,50,048/- towards the value of HSD oil supply and exemption of excise duties and sales tax which had been availed by the appellant. A claim in this regard was sent to the appellant on 30-5-2006. According to the respondent, the total B claim finally comes to Rs.1,26, 77 ,824/- with interest accrued thereon at 18% per annum from 6-5-2004. The appellant on 24.6.2004 denied the aforesaid claim. The dispute not having oeen resolved, the respondent served a legal notice on the appellant dated 19.6.2006. The appellant again denied the c claim. The respondent thereafter moved the application under Section 11 (5) and (6) of the Arbitration Act. The appellant filed a reply to the application disputing and denying the claims of the appellant. The appellant stated that the application for appointment of Arbitrator is liable to be dismissed. It was 0 pleaded that Agreement dated, 29.1.2001 which contains the arbitration clause has been superseded by the full and final settlement agreement dated 6.6.2003. It was further the case of the appellant that the respondent having received the entire amount in terms of the "full and final settlement" dated 6-6-2003 E is estopped from filing the application under Section 11 (5) and (6) of the Arbitration Act. According to the Appellant, since the entire dispute had been settled, no reference could be made to arbitration. The appellant had also pleaded that the respondent had failed to disclose that the parties had entered F into a full and final settlement on 6-6-2003. The plea was also raised to the effect that invocation of the arbitration on 9-6-2006 is time barred as the cause of action for filing the application arose on 6-6-2003 when the "full and final settlement" was entered into between the parties. G 7. It was also the case of the appellant that the works executed by the respondent not being of the required standard and specifications, were (ejected by the Government. Consequently, the appellant had to rectify the defects and incur extra expenses. These were liable to the deducted from the H 1144 SUPREME COURT REPORTS (2013) 14 S.C.R. A amount claimed by the respondent. It is also the claim of the appellant that since the works had not been satisfactorily completed, the agreement itself was terminated on 16-11-2001. The appellant had also pleaded that pursuant to the Settlement dated 6-6-2003, the respondent had received a sum of Rs.16 B lakhs. Therefore, there is no arbitrable dispute which can be referred to arbitration. It is also the case of the appellant that he has actually suffered a loss as it has incurred an expenditure of Rs.32, 13,950/- in rectification of the works which were unsatisfactorily performed by the respondent. The appellant also c claims that in order to maint~in cordial relations, it had entered into a "full and final settlement" with the respondent with regard to the entire claims of the sub-contractor. 8. Upon examination of the entire factual as well as the 0[legal position, the High Court has allowed the application under ] Section 11 (5) and (6) of the Act. This Appeal has been filed against the aforesaid Judgment of the High Court. 9. We have heard learned Counsel for the parties. E 10. Mr. Arun Kathpalia, learned Advocate appearing for the appellant relied heavily on the "full and final settlement" and submitted that the settlement has been duly signed by a representative of the respondent. Therefore, the respondent cannot now be permitted to submit that there was no "full and F final settlement". He further submitted that once there was "full and final settlement", no arbitrable dispute remains which could have been referred to the Arbitrator. To make good his submissions, Mr. Kathpalia submitted that the respondent had been negligent in the performance of the works which were G entrusted to the sub-contractor. This had ultimately led to the termination of the Agreement on 16-11-2001. In fact, the appellant had incurred huge amount of expenses in rectifying the defects in the works executed by the respondent. Mr. Kathpalia relied on clauses 5 and 6 of the Agreement and submitted that the appellant was entitled to be compensated H GAYATRI PROJECT LTD. _v._ SAi KRISHNA 1145 CONSTRUCTION for the rectification work which had to be performed to the A satisfaction of the Andhra Pradesh Government. Learned counsel also submitted that the respondent would be entitled to the final payment only upon satisfactory completion of the work entrusted to the sub-contractor. In order to settle the dispute between the parties and to maintain a cordial B relationship, the parties have entered into a voluntary settlement on 6-6-2003 which is evidenced by the signatures appended on the same by the Manager of the respondent sub-contractor. In such circumstances, learned counsel submitted that there was no arbitrable dispute which could have been left to the c Arbitrator and, therefore, the judgment of the High Court allowing the application under Section 11 (5) and (6) of the Act is erroneous. He further submitted that in case the respondent intend to challenge the validity of the binding nature of the settlement, the dispute cannot be left to the Arbitrator. The 0 settlement would form an independent contract which can only be nullified in appropriate proceedings being taken by the respondent. 11. In support of the submissions, the learned counsel relied on _Nathani Steels Ltd. vs. Associated Constructions[1 ] •_ Mr. Kathpalia relied on the observations made in paragraph 3 of the judgment. The learned Counsel submits that the judgment of the High Court is erroneous and has to be set aside. E 12. On the other hand, Mr. K. Swami, learned counsel appearing for the respondent submits that there is no "full and final settlement" of the amounts which were due to the respondent from the appellant. He further submits that the respondent had executed all the works which were entrusted to his client to the full satisfaction of the appellant. The claim and counter claim now made by the appellant is totally false and without any basis. The respondent is disputing each and every claim made by the appellant. Learned counsel further submitted that the alleged settlement dated 6-6-2003 is a unilateral F G H 1. 1995 Supp (3) sec 324. 1146 SUPREME COURT REPORTS [2013] 14 S.C.R. A document. There is no agreement between the parties for a final settlement. The document has been only received and the Manager has signed only to indicate that the letter has been received. There have been no negotiations between the parties prior to the issuance of letter dated 6-6-2003. He submits that B the judgment relied upon by Mr. Kathpalia is not applicable in the facts of this case. In fact, according to him, the matter is· squarely covered by the judgment of this Court in _National Insurance Company Limited vs. Boghara Polyfab Private Limited2._ Learned counsel has relied on paragraphs 33, 34 and c 35 of the judgment. It is pointed out that in paragraph 33, this Court has considered the ratio of the judgment in Nathani Steels (supra) and distinguished the same. Relying upon the aforesaid judgment, the learned counsel submits that the appeal deserves to be dismissed. D 13. Learned counsel further submitted that the receipt of a sum of Rs.16 lakhs subsequent to the letter dated 6-6-2003 does not signify the acceptance by the respondent of the aforesaid letter as a "full and final settlement". According to the learned counsel, in fact, the claim of the respondent was for E over Rs.10,00,000/- and, therefore, the amounts which were received by the respondent were only in part payment of the amount due. D 14. We have considered the submissions made by the F learned Counsel for the parties. 15. In our opinion, the question as to whether letter dated 6-6-2003 would constitute a "full and final settlement" would have to be determined on proper appreciation of the evidence led by the parties. It is, in our opinion, open to two G interpretations. Which of the two interpretations is ultimately accepted will have to be decided by the appropriate forum. We are also not inclined to accept the submissions of Mr. Kathpalia that if the alleged settlement is to be doubted, it cannot be H 2. (2009) 1 ~~sec~~ 2s1. ## GAYATRI PROJECT LTD. _v._ SAi KRISHNA 1147 CONSTRUCTION doubted before the Arbitrator. It must be remembered that the A appellant is relying on the alleged settlement by way of defence. The respondent has not accepted the same. Nor has the respondent denied the execution of the document. The respondent has also not claimed that the full and final settlement was signed under coercion, undue influence, fraud, B misrepresentation or mistake. Furthermore, the appellant had not made a claim on the basis of the settlement. It would have been different, if the appellant had made a claim on the basis of settlement which was denied by the respondent by one or more of the defences, as noticed above. In such c circumstances, following the judgment in _Nathani's_ case (supra), it would have to be _held that the settlement can only be challenged in "proper proceedings". But these observations would be applicable only if there was a clear cut acceptance by the parties that there was a "full and final settlement". 0 16. In fact, the matter would be squarely covered against the appellant by the ratio of the judgment _in National Insurance Company Limited_ (supra) wherein this Court has considered the cases which were earlier considered in _Nathani's Steel_ {supra) and observed as follows:- E "33. Nathani Steels related to a dispute on account of noncompletion of the con.tract. The Court found that the said dispute was settled by and between the parties as per deed dated -20.12.1980 signed by both parties. The deed referred to the prior discussions between the parties and recorded the amicable settlement of the disputes and differences between the parties in the presence of the Architect on the terms and conditions set out in clauses 1 to 8 thereof. In view of it, the Court rejected the contention of the contractor that the settlement was liable to be set aside on the ground of mistake. A three-Judge Bench of this Court, after referring to the decisions in P .K. Ramaiah and Nay Bharat Builders, held thus: (SCC p.326, para 3) F G "3 ........ that once the parties have arrived at a settlement H 1148 SUPREME COURT REPORTS [2013] 14 S.C.R. B c D E F G in respect of any dispute or difference arising under a contract and that dispute or the difference is amicable settled by way of a final settlement by and between the parties, unless that settlement is set aside in proper proceedings, it cannot lie in the mouth of one of the parties to the settlement to spurn it on the ground that it was a mistake and proceed to invoke the Arbitration clause. If this is permitted the sanctity of contract, the settlement also being a contract, would be wholly lost and it would be open to one party to take the benefit under the settlement and then to question the same on the ground of mistake without having the settlement set aside. In the circumstances, we think that in the instant case since the dispute or difference was finally settled and payments were made as per the settlement, it was not open to the respondent unilaterally to treat the settlement as non est and proceed to invoke the Arbitration clause." 34. What requires to be noticed is that in Nav Bharat Builders and Nathani Steels, this Court on examination of facts, was satisfied that there were negotiations and voluntary settlement of all pending disputes, and the contract was discharged by accord and satisfaction. In P.K. Ramaiah, the Court was satisfied that there was a voluntary acceptance of the measurements and full and final payment of the amount found due, resulting in discharge of the contract, leaving no outstanding claim or pending dispute. In those circumstances, this Court held that after such voluntary accord and satisfaction or discharge of the contract, there could be no arbitrable disputes. 36. In Damodar Valley Corporation, the question that arose for consideration of this Court was as follows: (SCC p. 144 para 4) "where one of the parties refers a dispute or disputes to arbitration and the other party takes a H ## GAYATRI PROJECT LTD. _v._ SAi KRISHNA 1149 CONSTRUCTION plea that there was a final settlement of all claims, is the Court, on an application under Sections 9(b) and 33 of the Act, entitled to enquire into the truth and validity of the averment as to whether there was or was not a final settlement on the ground that if that was proved it would bar a reference to the arbitration inasmuch as the arbitration clause itself would perish." In that case the question arose with reference to a claim by the supplier. The purchaser required the supplier to furnish a full and final receipt. But the supplier did not give such a receipt. Even though there was no discharge voucher, the purchaser contended that the payments made by it were in full and final settlement of the bills. This Court rejected that contention and held that the question whether there has been a settlement of all the claims arising in connection with the contract also postulates the existence of the contract which would mean that the arbitration clause operates. This Court held that the question whether there has been a full and final settlement of a claim under the contract is itself a dispute arising 'upon' or in relation to' or 'in connection with' the contract; and where there is an arbitration clause in a contract, notwithstanding the plea that there was a full and final settlement between the parties, that dispute can be referred to arbitration. It was also observed that mere claim of accord and satisfaction may not put an end to the arbitration clause. It is significant that neither P.K. Ramaiah nor Nathani Steels disagreed with the decision in Damodar Valley Corporation but only distinguished it on the ground that there was no full and final discharge voucher showing accord and satisfaction in that case." A B c D E F G 17. In our opinion, since there is no acceptance of the full and final settlement by the Respondent which has been relied H 1150 SUPREME COURT REPORTS # [2013] 14 S.C.R. A upon by the appellant, the issue clearly had to be left to the Arbitrator to be adjudicated. 18. In view of the above, we find no merit in the appeal and the same is accordingly dismissed. B 19. Before we part with this matter, we would request the learned Arbitrator to conclude the Arbitration Proceedings as expeditiously as possible since the matter was referred long back as this would be in the interest of justice. Bibhuti Bhushan Bose Appeal dismssed.
End of Judgment Record
Browse All Supreme Court of India (2013) Decisions
2013-12-06

STATE OF RAJASTHAN v BASANT AGROTECH (INDIA) LTD.

This batch of appeals challenges Chapter VI I of the Rajasthan Finance Act, 2008, which imposes an environment and health cess on mineral rights, and the accompanying 2009 notification amending rates (notably Rock Phosphate to Rs.500 per tonne) with retrospective effect from 1.4.2008. The Rajasthan High Court held the levy within the legislative competence but struck down the 2009 notification’s retrospective operation. The State challenged this, contending that where a statute vests power in a state government, the power may be exercised “from time to time” and, by implication, retrospective action may be permissible under delegated powers under the main Act and General Clauses. The Court clarifies that fiscal statutes must be construed strictly and that subordinate legislation cannot ordinarily possess retrospective effect unless expressly or by necessary implication authorized by the parent statute. The majority emphasizes that the words “from time to time” have a futuristic tenor and do not automatically authorize retroactive rates, and that a notification can have prospective effect only. The judgment surveys a spectrum of precedents on taxation, the distinction between taxes/cess, and the constitutional framework regarding mineral development (MMDR Act) and the legislative scope of state versus central power. Ultimately, the appeals are dismissed with no costs, upholding the High Court’s view on retrospective validity of the notification and the need for precise statutory authorization for retrospective action.

2013-07-16

M/S. HOTEL QUEEN ROAD PVT. LTD. & ORS. v. MR. RAM PARSHOTAM MITTAL & ORS.

This Supreme Court judgment arises from Civil Appeal No. 5499 of 2013 in which M/S Hotel Queen Road Pvt. Ltd. and others challenged an order of the Delhi High Court that permitted withdrawal of FAO(OS) 349 of 2009 and extended interim relief beyond the date of withdrawal. The High Court had heard the matter on merits, allowed withdrawal to pursue an alternative remedy, and extended the interim relief up to 10 May 2010, with stated reasons. The appellants contended that such observations during withdrawal were improper and that upon final disposal the court would become functus officio; hence continuing interim relief beyond withdrawal was impermissible. The respondents argued that, in the interest of justice, the court retains inherent power to extend interim relief where the matter has been heard on merits and withdrawal is permitted to facilitate the remedy, and that the observations were prima facie and non-merits determinations. The Supreme Court, after examining the jurisprudence, held that the High Court’s observations were innocuous and did not decide the merits. It clarified that ordinarily a petition that is withdrawn should not receive continued interim relief, but where the matter has been heard on merits and withdrawal is permitted, interim relief can be extended for a limited period with reasons. The appeal and SLP were dismissed, and the interim relief stood vacated. The decision relies on authorities including State of Orissa v. Madan Gopal Rungta, Padam Sen, Ajay Mohan, and G.E. Power Controls (cited).

2013-02-07

Lakshmi alias Bhagyalakshmi and Anr. v. E. Jayaram (D) by LR.

This Supreme Court appeal arises from a Karnataka High Court decision in a suit for permanent injunction over the ownership and occupancy of the suit property. The plaintiffs claimed absolute ownership of the suit property purchased from defendant No.1, though the sale deed was not registered; the entire sale consideration was paid. Plaintiff No.2 asserted possession as a tenant of Plaintiff No.1, and the trial court granted ad-interim relief under Order 39 Rule 1 and 2 CPC restraining interference with possession. The defendants denied the purchase, contending that Plaintiff No.1 was a stranger and that Plaintiff No.2 was a tenant under Defendant No.1. The High Court, instead of testing the legality of the interim injunction, examined Section 53A of the Transfer of Property Act and Order 2 Rule 2 CPC and concluded that, since the suit complained only of injunction and not of specific performance, the incidental relief of injunction would be unavailable. The Supreme Court held that the High Court had completely misconstrued Order 39 and misconstrued the scope of Section 53A and Order 2 Rule 2, and that the trial court’s injunction could stand where interim protection was warranted. It allowed the appeal, set aside the High Court’s order, and directed the trial court to hear and dispose of the suit within four months from the date of receipt of copy of this order, treating the merits independently of appellate observations.

2013-06-18

Roop Singh v. State of Madhya Pradesh

Roop Singh v. State of Madhya Pradesh concerns a rape case arising from an incident in village Tighrapura in Morena district. The complainant (PW-5) alleged that at about 2 a.m. the appellant, her neighbour, forcibly committed intercourse with her while her sister‑in‑law (PW-4) slept nearby and her husband was away at the fields. A FIR was registered; the medical examination and FSL report supported the occurrence of sexual assault. The trial court convicted the appellant under Section 450, IPC (house trespass to commit an offence) and Section 376, IPC (rape) and sentenced him to three years’ RI for Section 450 and seven years’ RI for Section 376 with fines. The Madhya Pradesh High Court dismissed the appeal, upholding the convictions. In special leave proceedings before the Supreme Court, the appellant argued that the complainant had consented to the intercourse and that the case was false, allegedly due to a land dispute. The State countered that consent in rape requires voluntary participation after fully exercising the choice between resistance and assent, citing established authority on the meaning of consent (State of U.P. v. Chhotey Lal; Mango Ram) and that the evidence shows the complainant did not consent. The Court accepts the standard of consent and, after reviewing the testimonies of PW-4 and PW-5 and the medical evidence, holds that the complainant was not a willing participant. Consequently, the appeal is dismissed, and the convictions and sentences stand.