Gajubha Jadeja Jesar v Union of India & Ors
Case Synopsis & Summary
This judgment disposes of two Civil Appeals arising from the National Green Tribunal order dated 12 February 2020. The Project Proponent sought Consent to Establish/Operate for a Cold Rolled Stainless Steel unit in Gujarat, arguing that the unit was erected with only CTE/CTO and that the relevant EIA notification (2006) required prior environmental clearance (EC) for a category 3(a) metallurgical industry. The Tribunal, after a joint committee and expert reports, granted a grace period of at least one year to fall under the EC regime, following the Expert Appraisal Committee’s recommendation. The applicant contended that the Tribunal had no jurisdiction to grant time for EC and that the EIA notification mandates prior EC; a closure notice was issued on 25.06.2021. The Government introduced a new notification on 20.07.2022 authorizing a window for standalone re-rolling units to apply for EC/ToR and to obtain EC within one year. The Court, while noting nationwide ambiguity (some 1689 units across India, with 403 in Gujarat) in the 2006 notification, upheld the Tribunal’s direction to provide time to comply with EC and quashed the closure notice, emphasizing the evolving interpretation and the need to avoid abrupt shutdowns impacting livelihoods. The appeal is dismissed; closure notice is set aside under the new regulatory framework.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- Hemant Gupta
- Vikram Nath
- Judgment Date
- 2022-08-10
- Court Decision / Holding
- Civil Appeal No. 3116 of 2020 is dismissed. I.A. No. 81563 of 2021 in Civil Appeal No. 3576 of 2020 challenging the closure notice dated 25.06.2021 is allowed and the closure notice is quashed. Civil Appeal No. 3576 of 2020 stands disposed of in the above terms.
- Final Disposition
- Civil Appeal Nos. 3116 of 2020 and 3576 of 2020: The former is dismissed; the latter is disposed of with closure notice quashed and a path for EC under the amended regime opened. The I.A. challenging the closure is allowed in terms described above and the unit may pursue EC within the one-year window introduced by the 2022 notification.
Parties to the Case
Appellants / Petitioners
- Gajubha Jadeja Jesar
- Project Proponent
Respondents
- Union of India
- Ministry of Environment, Forest and Climate Change
- Gujarat State Pollution Control Board
Legal Representation & Advocates
Counsels for Petitioners
- • Ms. Anitha Shenoy
- • Mr. Shyam Divan
Provisions of Law Cited
Legal Doctrines & Maxims
- Sustainable development
- Environmental justice / environmental equity
- Polluter pays principle
- Ex post facto environmental clearance should not ordinarily be granted (with exceptions)
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellants contended that the NGT had no jurisdiction to grant a period to obtain EC as the EIA notification mandates prior EC. Since the unit was set up in violation of the notification, a one-year extension would undermine statutory requirements. They argued that Section 21 of the NGT Act contemplates adjudication and redressal, not time-bound relaxations for EC, and that the ongoing closure process should stand. They urged that the 2022 amendment clarifies the position, but could not justify retroactive exemptions to units established earlier.
Contentions of Respondents
The respondents argued that the Tribunal’s order was within its remit to ensure sustainable development under Section 21 of the NGT Act. Given the ambiguity in the EIA notification 2006 and the EAC’s recommendation, the Tribunal could grant time for moderation to bring units within the EC regime. The MoEFCC’s affidavit and the high-level committee report supported regulatory clarifications, ultimately culminating in the 2022 amendment allowing a one-year window for ToR/EC to be sought.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (6)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Common Cause v. Union of India & Ors. | (2017) 9 SCC 499 | Mentioned Only | Cited by counsel to argue mandatory EC but the Court found it not helpful to support the arguments in this case. |
| Hanuman Laxman Aroskar v. Union of India | (2019) 15 SCC 401 | Positive | Cited and used by the Court to underscore the evolving and sustainable framework of environmental norms under the EIA notification. |
| Alembic Pharmaceuticals Limited v. Rohit Prajapati & Ors. | (2020) 17 SCC 157 | Distinguished | Not applicable to the present facts due to the amended EIA notification resolving the ambiguity; the Court distinguishes it. |
| Municipal Corporation of Greater Mumbai v. Ankita Sinha & Ors. | (2021) SCC OnLine SC 897 | Positive | Cited to discuss NGT’s jurisdiction and the broader scope of its remedial powers in environmental matters. |
| Pahwa Plastics Pvt. Ltd. & Anr. v. Dastak NGO & Ors. | (2021) SCC OnLine SC 897 | Positive | Cited to illustrate ex post facto EC can be granted in exceptional circumstances and not merely denied on technical grounds. |
| Electrosteel Steels Limited (supra) | Not explicitly provided in text | Positive | Used to frame the general rule that ex post facto EC should not be granted routinely, while recognizing exceptional circumstances. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Gajubha Jadeja Jesar v Union of India & Ors
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.