Unauthorized construction in Friends Colony, Cuttack, exceeded the sanctioned four-storey plan, with a fifth floor and unauthorized projections across every floor. The builder’s deviations triggered demolition proceedings under Section 92 of the Orissa Development Authorities Act, while the Authority offered compounding on some deviations. A local residents’ society, the Friends Colony Development Committee, intervened in the proceedings arguing that planning enforcement is essential to protect public health, safety, ecology, and infrastructure, and that any regularization must be exceptional and carefully supervised to deter repeats by professional builders. The High Court of Orissa disposed of the writ petitions by directing reconsideration of revised plans, a course that the Supreme Court found insufficient and proceeded to examine the broader issues of regularization, accountability, and public interest. The Supreme Court held that deviations from sanctioned plans are admissible only as exceptions, and that compounding should be reserved for bona fide deviations or misunderstandings where the benefit of demolition would be outweighed by the harm caused by displacement. It emphasized that professional builders are more likely to commit deliberate deviations and should face stern action, while also suggesting penalties and a welfare fund for affected buyers. The Court directed that all compounding decisions be taken at a high level by a multi-member High Powered Committee and remitted the matter to the High Court with directions for joint hearing and detailed evaluation of regularizable vs. non-regularizable portions.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • R. C. Lahoti
  • Ashok Bhan
Judgment Date
2004-11-01
Court Decision / Holding
Appeal allowed; High Court's judgment set aside; writ petitions restored on the High Court’s file to be heard along with the builder’s writ petition; directions to determine the extent of regularizable deviations and the terms for regularization, including the amount of compounding, with reliance on pre-2001 CDA Regulations; the High Court may suo motu register public interest litigation if warranted; builder to deposit compounding fee; case to be heard in the High Court with joint hearing of related petitions.
Final Disposition
Appeal allowed

Parties to the Case

Appellants / Petitioners

  • Friends Colony Development Committee

Respondents

  • M/s Modern Mechatech Housing Ltd.
  • Pratap Kumar Biswal
  • State of Orissa
  • Cuttack Development Authority

Legal Representation & Advocates

Counsels for Petitioners

  • • Vinoo Bhagat

Counsels for Respondents

  • • Raj Kumar Mehta
  • • Bikash Mohanty
  • • Jana Kalyan Das

Provisions of Law Cited

Orissa Development Authorities ActOrissa Development Authorities Act, Section 92Cuttack Development Authority (Planning and Building Standard) Regulation, 2001Cuttack Development Authority Regulations, 1994 (draft)Societies Registration Act, 1860

Submissions & Arguments

Contentions of Appellants / Petitioners

The Friends Colony Development Committee argued that the enforcement of planning laws is essential for public health, safety, and the orderly development of the city, and that regularization of deviations must be treated as an exception and subject to strict conditions to deter misuse by builders; urged that proceedings be heard in a holistic manner with related writ petitions, and that accountability be fixed on builders and any conniving officials; emphasized the need for public interest and adequate remedies for occupants, including rehabilitation where necessary.

Contentions of Respondents

The builder and respondents contended that some deviations are minor and amenable to compounding or regularization, and urged consideration of revised plans under existing regulations; argued for a balanced approach that protects public interest yet recognizes developers’ needs, while relying on updated regulations (including the 2001 CDA Regulation) to determine what can be regularized and under what terms; sought expeditious adjudication and deterrence against non-compliance.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•6,045 words•~28 min read

In The Court Record

FRIENDS COLONY DEVELOPMENT COMMITTEE v. STATE OF ORISSA

A # FRIENDS COLONY DEVELOPMENT COMMITTEE _v._ # ST A TE OF ORIS SA AND ORS. ## NOVEMBER l, 2004 ## B [R.C. LAHOTI, CJ. AND ASHOK BHAN, J.] ## _Urban Development:_ _Unauthorised construction-Order for demolition of-Plea for_ C _regularization by compounding-Held: Deviations from sanctioned plan permissible only as exception-Condonation and compounding of the deviations is permissible only when it is_ bona fide _or are attributable to some misunderstanding and where the benefit gained by the demolition would be far less than the disadvantage suffered-Deliberate deviations not_ D _compoundable-Deviations by professional builders can be assumed to be deliberate-Compounding of deviations made by the builders should be dealt with at a higher level by multi-membered High Powered CommitteeStaff strength to be suitably increased to keep constant and vigilant watch on illegal and unauthorized construction-Orissa Development Authorities Act._ E Respondent Nos. 2 and 3, (a company engaged in building activities and its Managing Director) applied for construction of a multi-storeyed building to the Development Authority. The Authority sanctioned construction of a four storeyed building in accordance with the sanctioned building plans. The building was constructed in excess of the sanctioned plan on all the floors F and even a fifth floor was constructed. Authority initiated proceeding u/s 92 ofOrissa Development Authorities Act, against the builder for demolition of the offending portions. Builder pleaded for compounding for the deviations. Appellant, a society whose object was to oversee the development of residential area in question made representation to the Authority, Municipality, Pollution G Control Board and the State Government complaining of the offending construction. Authority directed demolition of the fifth floor and the unauthorized projections on each r.aor. It permitted compounding in respect of certain deviations on payment of certain amourit by the builder. Builder filed an appeal before Appellate Authority which granted _interim_ stay of 818 H -.., 819 FRIENDS COLONY DEVELOPMENT COMMITTEE _v._ STA TE OF ORISSA. demolition but on condition of stopping further construction. The builder A proceeded with building activity defying the condition. Appellant filed writ Petition before High Court. It also sought its impleadment in the appeal filed by the builder. Impleadment was allowed. Appellate Authority dismissed the appeal of the builder and the builder challenged it by filing Writ Petition, but without impleading the appellant. Appellant's application for impleadment in B the Writ Petition filed by the builder was rejected by High Court It disposed of the Writ Petition by directing that if the builder made a fresh application and/or submitted a revised plan for approval in respect of construction already undertaken by it, the Authority should deal with the same in accordance with law. Hence the appeal. Allowing the appeal, and remitting the matter to High Court for hearing C alongwith the Writ Petition filed by the appellant in the High Court, the Court HELD: 1. In the facts and circumstances of the present case the controversy should not have been brought to an end by the High Court merely by directing reconsideration of the application of revised building plans D submitted by the respondent builder. The matter needs a further probe and hearing in public interest. (830-D] 2. Though the municipal laws permit deviations from sanctioned constructions being regularized by compounding but that is by way of exception. Unfortunately, the exception, with the lapse of time and frequent exercise of the discretionary power conferred by such exception, has become E the rule. Only such deviations deserve to be condoned. as are _bona fide_ or are attributable to some mis-understanding or are such deviations as where the benefit gained by demolition would be far less than the disadvantage suffered. Other than these, deliberate deviations do not deserve to be condoned and compounded. Compounding of deviations ought to be kept at a bare minimum. F The cases of professional builders stand on a different footing from an individual constructing his own building. A professional builder is supposed to understand the laws better and deviations by such builders can safely be assumed to be deliberate and done with the intention of earning profits and hence deserve to be dealt with sternly so as to act as a deterrent for future. It is common knowledge that the builders enter into under hand dealings. Be G that as it may, the State Governments should think of levying heavy penalties on such builders and therefrom develop a welfare fund which can be utilised for compensating and rehabilitating such innocent or unwary buyers who are displaced on account of demolition of illegal constructions. [829-F-H; 830-A-B) H SUPREME COURT REPORTS [2004] SUPP. _5_ S.C.R. 820 A 3. The application for compounding the deviations made by the builders should always be dealt with at a higher level by multi•membered High Powered Committee so that the builders cannot 11}.anipulate. The officials who have connived at unauthorized or illegal constructions should not be spared. In developing cities the strength of staff which is supposed to keep a watch on building activities should be suitably increased in the interest of constant and B vigilant watch on illegal or unauthorized constructions. (830-B-C) CVIL APPELLATE JURISDICTION: Civil Appeal No. 12984of1999. From the Judgment and Order dated 16.4.96 of the Orissa High Court in O.J.C. No. 4995 of 1995. c Vinoo Bhagat for the Appellant. Shiv Sagar Tiwari (NP) for Intervenor. D Raj Kumar Mehta and Bikash Mohanty for the Respondent Nos 2-3. Jana Kalyan Das for the Respondent Nos. 5-6. The Judgment of the Court was delivered by R.C. LAHOTI, CJ. The Friends Colony Development Committee, the E appellant before us, is a society registered in the year 1982 under the Societies Registration Act, 1860. One of its objects is to over-see development of the residential area known as 'Friends Colony' in Cuttack city. _Mis_ Modem Mechatech Housing Ltd., the respondent No. 2, is a company incorporated under the Companies Act, and engaged in building activity. Pratap Kumar Biswal, respondent No. 3, is its Managing Director. The other parties impleaded F in this appeal are the State ofOrissa, through the Commissioner-cum-Secretary, Housing and Urban Development Department, and Cuttack Development Authority (hereinafter the 'Authority' for short). The property involved in this litigation is a six storeyed apartment situated in Friends Colony and known as 'Kalyani Apartment'. G The background facts leading to the present appeal are briefly stated hereinafter. The property l?elonged to one Abhiram Panda. He gave a power of attorney to the builder (respondent No. 2 and 3) for construction of a multistoreyed apartment on the said land. On an application made by the builder, the Authority accorded sanction on 3 .3 .1993 for construction of a four storeyed H building in accordance with the building plans sanctioned by the Authority. ## - FRIENDS COLONY DEVELOPMENT COMMITTEE _v._ STA TE OF ORISSA. [LAHOTI, CJ.] 821 The construction commenced and when the building came up it was found A to have been built up grossly in excess of the sanctioned plan on all the floors. Though the sanction accorded by the Authority permitted only four stories but even a fifth floor had also come up. On 7.2.1994, the Authority initiated proceedings under Section 92 of the Orissa Development Authorities Act (hereinafter referred to as 'the Act', for short) against the builder calling upon it to show cause why the offending portions .be not demolished. The B stand taken by the builder in its response was that the deviations were very minor ones calling for a sympathetic view and compounding of the deviations instead of being demolished. On 25.9.1994 the appellant made a representation to the Authority complaining of the offending construction and submitting that the deviations from the sanctioned plan damaged the environment and . C endangered life and safety of not only the occupants of the building, but also of other inhabitants of the locality. The representations by the appellant were made not only to the Authority, but also to the Cuttack Municipality, the Pollution Control Board and the State Government. By order dated 8.11.1994, the Authority directed 5th floor of the building D to be demolished as also the unauthorized projections of 605 sq. ft. on each floor to be demolished. In respect of certain deviations which were compoundable, the Authority permitted compounding on payment of Rs. 2.09 lakhs by the builder. A notice-cum-order for securing compliance of the order dated 8.l l.1994 of the Authority was issued on 30.l l.1994 to the builder. E On 2.12.1994 the builder filed an appeal before the appellate authority which granted _interim_ stay of demolition as directed by the Authority, but subject to the condition that the builder shall stop all further constructions. However, the builder proceeded with the building activity by defying the conditions incorporated in the order of the stay granted by the appellate p authority. The appellant's representations inviting attention of the Authority did not serve any purpose. On 5.12.1994 the appellant filed a writ petition in public interest in the High Court of Orissa which was registered as OJC No. 8128/94 laying challenge to the illegal, unauthorized and dangerous construction in the building and G seeking demolition to the extent necessary. The appellant also sought for its impleadment in the appeal filed by the builder which was pending before the appellate authority. The impleadment was allowed, though opposed by the builder. By order dated 28.6.1995 the appellate authority directed the builder's H SUPREME COURT REPORTS [2004] SUPP. 5 S.C.R. 822 A appeal to be dismissed. The appellate authority found _inter alia_ that the offending construction was a threat to the environment and, if not demolished, it would encourage other builders to make similar violations much to the detriment of the planned development of the city. Laying challenge to the order of the appellate authority, the builder filed a writ petition in the High Court which was registered as OJC No. 4995/95. Though the appellant was B a party before the appellate authority, it was not joined by the builder as a party in the writ petition filed by him. However, the appellant moved for its impleadment in the writ petition and filed a counter affidavit controverting several averments made and pleas raised by the builder. The appellant also prayed for the writ petition filed by it in public interest being taken up for C hearing along with the writ petition filed by the builder so that all the issues relating to the said building could be heard and decided together. However, the writ petition filed by the builder was taken up for hearing, while the writ petition filed in public interest by the appellant remained pending. By its judgment dated 16.4.1996 the Division Bench held that the appellant D had no right to participate in the "hearing; it was neither a necessary nor a proper party; it was not entitled to be heard in the writ petition filed by the builder, and the remedy, if any, of the appellant was to file a civil suit for protection and enforcement of its rights, if any. Having said so, the High Court proceeded to examine, on merits, the pleas urged by the builder in his E writ petition. > The plea of the builder was that in spite of the construction having come up, it could yet move a fresh application and submit revised plan for approval in respect of construction already undertaken and then it will be for the Authority to consider and approve or n9t to approve the same. It seems F to have been urged before the High Court by the learned counsel for the builder, as noted in the judgment of the High Court, that at different points of time the Planning Member and Vice-Chairman of the Authority had suggested certain courses of action which would obviate difficulties of the builder while not making any departure from the requirements of law and such suggestions were, by and large, accepted by the builder. However, from the G records we find that this was only an oral submission made, not supported by any documents, and the judgment of the High Court also does not make reference to any document or affidavit filed by or on behalf of the Authority or any of its officials in support of the plea urged by the builder. The High Court disposed of the writ petition by directing that if the builder made a fre.sh H application and/or submitted a revised plan for approval in respect of FRIENDS COLONY DEVELOPMENT COMMITTEE _v._ STATE OF ORISSA. [LAHOTI, CJ.] 823 construction already undertaken by it, the Authority should deal with the A same in accordance with law. The learned counsel for the builder undertook before the High Court to maintain _status quo_ and not to make any further construction till a decision was taken by the Authority on re-submission of the application accompanied by plans for sanction as permitted by the High Court. The High Court allowed one month's time from the date of its judgment for filing a written undertaking by the builder incorporating the oral undertaking B given before the High Court and also for filing the application and plan for sanction before the Authority. The High Court left the question of dc.viations already made open for consideration and to be dealt with in accordance with law after the Authority had taken decisions on such application. Feeling aggrieved by the judgment of the High Court this appeal has[c ] been filed by special leave. By order dated 7 .10.1996 leave was granted and, at the same time, this Court directed the operation of the impugned judgment of the High Court to remain stayed. 30 occupants of the apartment have sought for intervention D at the hearing in this Court. On 5.5.1997, in the presence of the parties, this Court directed the order of stay made on 7 .10.1997 to be confirmed and clarifiecl that no demolition of the construction already made would be done during the pendency of this appeal, but the unauthorized portion would not be permitted to be occupied and no third party interest would be created therein in the meantime. After 5.5.1997 the appeal came up for hearing before E this Court on 6.11.2003. Having noticed that it was a case of unauthorized constructions made by a builder in a multi-storeyed building and the High Court had permitted the possibility of regularization of unauthorized constructions to be explored afresh as per law, this Court made the following directions :- F (i) The respondents Nos. 5 and 6 shall have a plan of the existing structure prepared through their architects/engineers. The authority shall consider in accordance with the existing building bye-laws/ regulations as to how much of the unauthorized construction can be regularized and if so then subject to what terms and conditions. The G Plan showing in different colours, the sanctioned construction, the unauthorized construction and the construction to the extent to which it can be regularized shall be filed. (ii) The terms and conditions on which the regularization can take place shall also be filed. H 824 SUPREME COURT REPORTS [2004] SUPP. 5 S.C.R. A (iit) The status of the area which cannot be regularized shall be stated, i.e., whether it is occupied or unoccupied." The compliance by the Authority was directed to be reported within eight weeks along with. plans and statement as above being filed duly supported by affidavit. B On 14.1.2004 another two week's time was sought for by the Authority for reporting compliance with the order dated 6.11.2003. However, the learned counsel, who is appearing in this court for the builder, pointed out that his client, that is the builder, was not responding to his communications. The notices of hearing issued by the Registry of this Court to the builder company C and its Managing Director were returned with postal remarks 'refused'. Later, on I0.2.2004 the Managing Director of the builder company was present in Court on having been served and pointed out that during the pendency of these proceedings he has shifted his residence to Bangalore. D The Court directed him to remain present in person on all the dates of hearing unless otherwise permitted by this Court and also to keep his counsel and this Court informed of his address and his availability thereat. On behalf of the Authority affidavit in compliance with the order dated 6.11.2003 was filed. Shri S.M. Patnaik, the Planning Member in the Authority E was also present in person. The plan filed by the Authority showed the authorized and unauthorized constructions and also the extent of unauthorized constructions which could be regularized subject to tenns. This Court directed as under :- F G "The Cuttack Development Authority shall file an additional affidavit pointing out how much of the unauthorized construction though not available for regularization as per the existing law can still be tolerated without any loss of public interest and how much unauthorized construction must necessarily go in public interest. The Authority shall also state and suggest the terms on which the builder should be placed for the purpose of regularization of the permissible unauthorized construction and the terms on which the builder should be placed for tolerating the extent of unauthorized construction though not available for regularization. Compliance in six weeks." H The builder was also allowed the liberty of filing a statement on affidavit FRIENDS COLONY DEVELOPMENT COMMITTEE _v._ STATE OF ORISSA. [LAHOTI, CJ.] 825 incorporating such relevant facts and information as would enable the Court A to arrive at a just and equitable decision. That further affidavit has been filed. According to the Stability Report submitted by the Structural Analysis and Design Cell to the Planning Member of the Authority the following facts have been reported about the Kalyani Apartment :- B "Wis a framed structure building having partial parking area in the ground floor and five floors above it along with the access to the terrace with the load of overhead water tanks and headrooms. (2) There is a 5 feet width Cantilever used as living areas such as toilet, Kitchen and bedrooms projected to all sides in each floors. (3) The peripheral walls are of 10" width K.B. brick masonry wall and all internal walls are 5" width. (4) 1 "thick mosaic tiles are laid in all floors as flooring materials. (5) Average width of building is 41 '-8" feet and average height of D building is 58 feet. (6) Soil condition is sandy loamy type. (7) There was no sign of any sinking of foundation in the static load at present. E (8) There was no scope to check the actual foundation provided in the building. (9) Size of all existing column are 10" x 15" where as the size is 12" x 24" in the drawing approved in CDA. F (I 0) I have considered the column 'C 5' (Column Lay-out drawing is attached) for example, to calculate all the loads in it to check the stability of the said column. The detail calculation of the column 'C 5' is as follows." Calculations and analysis data and documents have been made available. In Calculations it is stated as under :- "As per the above Calculations and observations it is observed that this building is unsafe for the ground plus five floors along with cantilever in all sides because the section of column is not adequate. H 826 SUPREME COURT REPORTS [2004] SUPP. _5_ S.C.R. A It is also noticed that during the structural design of this building the wind load calculation has not taken into consideration. Also the seismic load consideration has not been included in it though this area comes under seismic zone-III. B c To make the building structurally stable the load in the building should be reduced. The load can be reduced by removing the fifth floor in total. The load can also be reduced by removing the cantilever portion in all sides of each floor. A strong impact load may affect the main building during the breaking of cantilevers but if we break the top floor no such impact load may not affect the structure in the lower floors." In the subsequent affidavits filed the builder has pointed out and relied on certain changes in the regulations framed by the Authority in support of his plea that all deviations in the building are compoundable. The builder has also sought to contend that there are several other buildings with more or less D similar deviations which have either been compounded or not proceeded against. On such averments the builder has sought for the deviations being condoned and regularized. On the other hand, the affidavit sworn in by Shri Gupteshwar Acharya, Law Officer of the Authority, filed on 2.2.2004 with the plan of the building E specifically and separately setting out the deviations-compoundable and non-compou.ndable, as also the calculation sheets have been filed. It is stated _inter a/ia:-_ F G {I) that the floorwise coverage and deviation are set out in detail in the chart annexed to the present affidavit. From a perusal of the said chart it is submitted that as per draft CDA regulations dated 29 .12.1994 the case was considered for regularization etc. After detailed examination it was found that the entire 5th floor which was constructed without prior permission covering the are_a 4009.5 sq. ft. was beyond the permissible norms for regularization _I_ compounding and hence the same has to be demolished. On account of operation of stay order from this Hon'ble Court the demolition work could not be carried out. H (2) that from the remaining unauthorized construction area a total area of 5735.5 sq. ft. could be compounded upon payment of Rs. 2,09,160 as per the then prevailing fee. It is relevant to mention that the said amount till date has not been deposited and therefore in the FRIENDS COLONY DEVELOPMENT COMMIITEE _v._ ST A TE OF ORISSA. [LAHOTI, CJ.] 82 7 absence of the said amount being deposited the said compounding A also has not been carried out and the area is liable for demolition. (3) that with effect from 13.12.2001 the Cuttack Development Authority (Planning and Building Standard) Regulation, 200 I has come into force. Under the said 200 I Regulation more stringent condition in respect of highrise building pertaining to setbacks etc. have been laid B down. Applying the standards laid down in the Regulation, 2001 the permissible compounding area of unauthorized construction would be far less than what was offered under the earlier draft regulation. (4) that since the offer for regularization _I_ compounding had already been made under the regulation then applicable the Authority can C consider compounding _I_ regularization of an area of 5735.5 sq. ft. subject to payment of Rs. 2,09, 160/- with interest as deemed fit and proper by this Hon'ble Court. (5) that upon site inspection and personal visit carried out by the Planning Member and the technical staff it is noticed that all the floors D are in occupation." The pleadings, documents and other material brought on record disclose a very sorry and sordid state of affairs prevailing in the matter of illegal and unauthorized constructions in the city of Cuttack. Builders violate with impunity the sanctioned building plans and indulge deviations much to the prejudice E of the planned development of the city and at the peril of the occupants of the premises constructed or of the inhabitants of the city at large. Serious threat is posed to ecology and environment and, at the same time, the infrastructure consisting of water supply, sewerage and traffic movement facilities suffer unbearable burden and are often thrown out of gear. Unwary F purchasers in search of roof over their heads and purchasing flats/apartments from builders, find themselves having fallen prey and become victims to the design of unscrupulous builders. The builder conveniently walks away having pocketed the money leaving behind the unfortunate occupants to face the music in the event of unauthorized constructions being detected or exposed and threatened with demolition. Though the local authorities have the staff G consisting of engineers and inspectors whose duty is to keep a watch on building activities and to promptly stop the illegal constructions or deviations coming up, they often fail in discharging their duty. Either they don't act or do not act promptly or do connive at such activities apparently for illegitimate considerations. If such activities are to stop, some stringent actions are H .... 828 SUPREME COURT REPORTS [2004] SUPP. _5_ S.C.R. A required to be taken by ruthlessly demolishing the illegal constructions and non-compoundable deviations. The unwary purchasers who· shall be the sufferers must be adequately compensated by the builder. The arms of the law must stretch to catch hold of such unscrupulous builders. At the same time, in order to secure vigilant performance of duties, responsibility should be fixed on the officials whose duty it was to prevent unauthorized constructions, B but who failed in doing so either by negligence or by connivance. The conduct of the builder in the present case deserves to be noticed. He knew it fully well what was the permissible construction as per the sanctioned building plans and yet he not only constructed additional built up C area on each floor but also added an additional fifth floor on the building, and such a floor was totally unauthorized. In spite of the disputes and litigation pending he parted .with his interest in the property and inducted occupants on all the floors, including the additional one. Probably he was under the impression that h.e would be able to either,escape the clutches of the law or twist the arm of the law by some manipulation. This impression must prove D to be wrong. In all developed and developing countries there is emphasis on planned development of cities which is sought to be achieved by zoning, planning and regulating building construction activity. Such planning, though highly complex, is a matter based on scientific research, study and experience leading to E rationalization of laws by way of legislative enactments and rules and regulations framed thereunder. Zoning and planning do result in hardship to individual property owners as their freedom to use their property in the way they like, is subjected to regulation and control. The private owners are to some extent prevented from making the most profitable use of their property. p But for this reason alone the controlling regulations cannot be termed as arbitrary or unreasonable. The private interest stands subordinated to the public good. It can be stated in a way that power to plan development of city and to regulate the building activity therein flows from the police power of the state. The exercise of such governmental power is justified on account of its being reasonably necessary for the public health, safety, morals or G general welfare and ecological considerations; though an unnecessary or unreasonable inter-meddling with the private ownership of the property may not be justified. The municipal laws regulating the building construction activity may H provide for regulations as to floor area, the number of floors, the extent of FRIENDS COLONY DEVELOPMENT COMMITTEE _v._ STATE OF ORISSA. [LAHOTI, CJ.] 829 height rise and the nature of use to which a built-up property may be A subjected in any particular area. The individuals as property owners have to pay some price for securing peace, good order, dignity, protection and comfort and safety of the community. Not only filth, stench and unhealthy places have to be eliminated, but the layout helps in achieving family values, youth values, seclusion and clean air to make the locality a better place to live. Building regulations also help in reduction or elimination of fire hazards, the B avoidance of traffic dangers and the lessening of prevention of traffic congestion in the streets and roads. Zoning and building regulations are also legitimized from the point of view of the control of community development, the prevention of over-crowding of land, the furnishing of recreational facilities like parks and playgrounds and the availability of adequate water, sewerage C and other governmental or utility services. Structural and lot-area regulations authorize the municipal authorities to regulate and restrict the height, number of stories and other structures; the percentage of a plot that may be occupied; the size of yards, courts, and open spaces; the density of population; and the location and use of buildings and D structures. All these have in view and do achieve the larger purpose of the public health, safety or general welfare. So are front setback provisions, average alignments and structural alterations. Any violation of zoning and regulation laws takes the toll in terms of public welfare and convenience being sacrificed apart from the risk, inconvenience and hardship which is posed to E the occupants of the building. [For a detailed discussion reference may be had to the chapter on Zoning and Planning in American Jurisprudence, 2d, Vol. 82.] Though the municipal laws permit deviations from sanctioned constructions being regularized by compounding but that is by way of F exception. Unfortunately, the exception, with the lapse of time and frequent exercise of the discretionary power conferred by such exception, has become the rule. Only such deviations deserve to be condoned as are _bona_ fid~ or are attributable to some mis-understanding or are such deviations as where the benefit gained by demolition would be far less than the disadvantage suffered. Other than these, deliberate deviations do not deserve to be condoned G and compounded. Compounding of deviations ought to be kept at a bare minimum. The cases of professional builders stand on a different footing from .an individual constructing his own building. A professional builder is supposed to understand the laws better and deviations by such builders can safely be assumed to be deliberate and done with the intention of earning profits and lJ SUPREME COURT REPORTS [2004) SUPP. _5_ S.C.R. ## 830 A hence deserve to be dealt with sternly so as to act as a deterrent for future. It is common knowledge that the builders enter into under hand dealings. Be that as it may, the State Governments should think of levying heavy penalties on such builders and therefrom develop a welfare fund which can be utilized for compensating and rehabilitating such innocent or unwary buyers who are displaced on account of demolition of illegal constructions. ## B The application for compounding the deviations made by the builders should always be dealt with at a higher level by multi-membered High Powered Committee so that the builders cannot manipulate. The officials who have connived· at unauthorized or illegal constructions should not be spared. In C developing cities the strength of staff which is supposed to keep a watch on building activities should be suitably increased in the interest of constant and vigilant watch on illegal or unauthorized constructions. In the facts and circumstances of the present case, we are of the opinion that the controversy should not have been brought to an end by the D High Court merely by directing reconsideration of the application of revised building plans submitted by the respondent builder. The matter needs a further probe and hearing in public interest. The appeal is allowed. The impugned judgment of the High Court is set aside. The writ petition filed by respondents Nos. 2 and 3 herein shall stand E restored on the file of the High Court to be taken up for hearing along with the writ petition filed by the appellant. The present status of the writ petition filed by the Friends Colony Development Committee-the appellant before us, is not known as to whether it is pending or has been disposed of and, if so, with what result. Be that as it may, even if the writ petition filed by F the appellant has been disposed of, the hearing therein shall be reopened and the hearing in the two petitions shall proceed in the High Court in such manner as the High Court may deem fit but keeping in view the following directions: ## G (1) Both the petitions, that is, the writ petition filed by respondents No. 2 and 3 herein registered as OJC No. 4995 of 1995 and the writ petition filed by the appellant herein registered as OJC No. 8128 of 1994 shall be taken up for hearing together. H (2) The following documents which have come up on the record of. this Court during the course of hearing and pursuant to directions issued from time to time by this Court shall be sent to the High Court FRIENDS COLONY DEVELOPMENT COMMITTEE v. ST A TE OF ORISSA. [LAHOTI, CJ.] 831 > to be taken up in consideration at the hearing of the writ petitions :- A (i) Affidavit of compliance on behalf of Cuttack Development Authority and Planning Member dated 2.2.2004 along with enclosures. • (ii) Additional affidavit of compliance on behalf of the Planning Member, Cuttack Development Authority, respondent No. 6 herein B filed on 5.4.2004. (iii) Further affidavit on behalf of respondent Nos. 2 and 3 herein dated 25.3.2004 along with enclosures . > (iv) Copy of the report submitted by the Planning Member, Cuttack c Development Authority. (v) Reply to the further/additional affidavit dated 6.4.2003 filed on behalf of respondent Nos. 2 and 3 . (vi) Reply on behalf of respondent Nos. 2 and 3 to the additional affidavit dated 5.4.2004 filed on behalf of the Cuttack Development D Authority, respondent No. 6 herein with copy of the structural stability certificate, copies Qf photographs of the site, copy of sketch map showing the main storm water channel, copy of letter issued by the Project Engineer, Orissa Water Supply and Sewerage Board and copy of the order dated 17.4.2003 passed by the High Court, Orissa in Writ E Petition (c) No. 3310 of2003. (vii) The Stability Report submitted by the Structural Analysis and Design Cell to the Planning Member, Cuttack Development Authority on 18.3.2003. Photocopies of the documents transmitted to the High Court shall be F retained on the record of this Court. (3) The High Court shall find out and determine how much deviation can be regularized and subject to what terms. If any part of the construction found to be illegal has to be demolished and/or any of the occupants are liable to be displaced, the High Court shall take G appropriate steps for their rehabilitation and compensation at the cost of the builder. (4) Present address at which respondent No. 3 is available, as furnished by him to this Court, shall also be sent to the High Court. During the SUPREME COURT REPORTS (2004] SUPP. _5_ S.C.R. 832 ## A course of hearing respondent No. 3 shall remain personally present in the High Court unless exempted from personal appearance. (5) Any non-compliance of the orders of the Court by respondent Nos. 2 and 3 shall be construed as contempt of the orders of the Court and they shall be liable for the legal consequences. B c D E (6) The builder must deposit the compounding fee of Rs. 2,09,160/within such time as the High Court may allow in this behalf. This deposit shall be treated as a provisional payment of compounding fee subject to adjustment against such amount as the High Court may ultimately arrive at. During the pendency of these proceedings, we are told that new Regulations of the year 200 I-more stringent in nature, have come into force replacing the preceding Regulations. We do not propose to decide the general question-whether in the matter of determining and compounding deviations it is the law as on the date . of such decision which would apply or the one as was prevailing on the date of commission of the illegal act would apply. Leaving that question open, in the facts and circumstances of the present case, we direct that the present case shall be determined by reference to the regulations as were prevailing prior to the coming into force of the Cuttack Development Authority (Planning and Building Standard) Regulations, 200 I. (7) The High Court, if it feels that illegal/unauthorized building activities in Cuttack are so rampant as to be noticed judicially, may _suo motu_ register a public interest litigation and commence monitoring the same by issuing directions so as to curb such tendency and fixing liability and accountability. ...... F K.K.T. Appeal allowed.
End of Judgment Record
Browse All Supreme Court of India (2004) Decisions
2004-05-26

State of West Bengal v. Haresh C. Banerjee and Ors.

This appeal concerns the constitutional validity of Rule 10(1) of the West Bengal Services (Death-cum-Retirement Benefit) Rules. The Calcutta High Court had previously held the rule ultra vires the Constitution and had struck down the power to conduct a departmental inquiry against a retired employee. The Supreme Court granted special leave and noted that even if the appeal were to succeed, the benefit already due to respondent No. 1 in the High Court’s order would not be recalled; arrears would be paid by the State within the time prescribed. The sole question before the Court is the validity of Rule 10(1) and its relation to the West Bengal (Classification, Control and Operation) Rules, 1971, including sub-rule (1) of Rule 10, which governs classification and control of service. The Court observed that the issue raises a larger question of operation that could affect a large number of employees, and therefore it is appropriate to refer the matter to a larger Bench for authoritative adjudication. The matter is thus directed to be placed before a larger Bench, and the judgment does not finally decide the vires of Rule 10(1). In short, the Court stayed further adjudication on the matter of validity and opted for an expeditious reference to a larger judicial forum. The background also includes the Court’s directive in leave proceedings that arrears, if any, would be payable according to the High Court’s order, not recalled pending appellate resolution.

2004-05-05

Commissioner of Customs & Central Excise & Ors. v Charminar Nonwovens Ltd.

The case concerns the proper classification and duty liability of Floor G Coverings and Filter Fabrics under the Central Excises and Salt Act, 1944, specifically whether these goods fall under Tariff sub-headings 5703.90 (30% ad valorem) or 5703.20 (5% ad valorem). The respondent, Charminar Nonwovens Ltd., received a detention memo and a show-cause notice challenging the classification and the related duty. An appellate authority had previously upheld the assessee's classification on a similar adjudication, and the Andhra Pradesh High Court later quashed the show-cause notice on the ground that the appellate order had become final. The petitioners challenged this, arguing that classification must be decided on facts arising in each case and that new facts or changes in law may warrant re‑examination, not interference by the High Court at the show-cause stage. The Supreme Court held that classification and the determination of duty are case-specific, and even if a decision was taken earlier, further investigation can reveal new facts or a change in law requiring re‑examination. The High Court's interference at the show-cause stage was improper. The Court then set aside the High Court order and remitted the matter to the Adjudicating Authority for fresh adjudication, with similar directions to related appeals. The overarching principle is that revenue classifications are not frozen by earlier judgments and must be reconsidered as facts or law evolve.

2004-08-16

G. B. LAHOTI v. S. J. CHOURASIYA

This Supreme Court decision concerns substitution of legal heirs in a pending appeal arising from a land-lord–tenant dispute. The landlord sued for possession; the trial court decreed possession due to unlawful sub-letting. The tenant’s successor-deceased Ganesh Prasad Lahoti’s heirs sought substitution under Order XXII Rule 11 after the defendant’s death; the first substitution application Exh. 22 was rejected on a technical ground, and three further applications followed (for setting aside abatement, for condonation of delay, and for interim relief). The appellate court dismissed these on merits and on the ground of res judicata, and the High Court dismissed revisions. The Court held that the doctrine of res judicata does not bar such subsequent applications where, as in this case, there was no inaction or negligence by the heirs and the delay was explained by the circumstances—knowledge of pendency arose only after a letter from the advocate confirming hearing. The Supreme Court allowed the appeal, set aside the lower orders, and directed the lower appellate court to hear the appeal on merits in accordance with law, with an award of costs (Rs. 10,000) within three months, and a fresh deadline for a merits decision by Aug. 31, 2005. The decision clarifies substitution rights in the context of pending appeals and limits of res judicata in substitution petitions.

2004-05-05

SHAKUNTALA BAI v. NARAYAN DAS

This Supreme Court decision arises from a long-drawn eviction suit under the Madhya Pradesh Accommodation Control Act, 1961, filed for bona fide landlord’s need to carry on business in a non-residential premises. The trial court decreed eviction; during appeal, the landlord died and his heirs sought to amend the plaint to plead their own bona fide need. The tenant urged amendment of his pleadings to claim that, after the landlord’s death, the personal need ceased. The High Court dismissed the suit on the ground that after the landlord’s death the personal need could not be pursued by heirs. The Supreme Court, allowing the appeals, held that the bona fide need of the landlord must be examined as on the date of institution of proceedings, and if a decree for eviction is passed, the death of the landlord during pendency of the appeal does not invalidate the Plaintiffs’ right to defend the estate. It clarified the law: the bar under s.12(1) prevents filing the suit except on listed grounds; the need may be tested with amended pleadings after remand; the object of the Act is expeditious disposal and not perpetual litigation. Citing earlier decisions, the Court ultimately restored the trial court’s decree, set aside the High Court’s dismissal, and granted four months for eviction with an undertaking. The decision reaffirms that heirs may defend the estate where a valid eviction decree has been issued.