This is a group of connected Civil Appeals heard together in the Supreme Court’s Civil Appellate Jurisdiction. The appellants are development authorities (Faizabad-Ayodhya Development Authority, Faizabad and Moradabad Development Authority) challenging High Court writ petitions filed by original landowners seeking compensation for land acquired under the 1894 Act. The writ petitions arose from acquisitions under notifications issued under Sections 4, 6 and 17 of the Land Acquisition Act, 1894, and relate to plots that were not the subject of initial awards due to pendency of writ petitions and interim stays. When the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (Act 2013) came into force on 01.01.2014, the High Court directed compensation to be paid under Section 24(1) of the 2013 Act, on the premise that no award under Section 11 of the 1894 Act had been made. The Supreme Court undertook a contextual interpretation of Section 24(1) and 24(2) of Act 2013, as well as the saving provisions in Section 24, relying on Indore Development Authority and other restitutionary authorities. The Court held that where no award under Section 11 of the 1894 Act was made by 01.01.2014 due to pendency or interim court orders, the landowners are not automatically entitled to compensation under Section 24(1) of Act 2013; instead, the acquisition proceedings must continue under the 1894 Act, with possible enhancement under that Act. The decision emphasizes restitutory principles to prevent litigants from obtaining undue advantage from court stays. The appeals are allowed; High Court judgments are set aside, and the authorities are to declare awards under the 1894 Act and determine compensation thereunder, with remedies for enhancement under the old Act available to aggrieved parties.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- M. R. SHAH
- Judgment Date
- 2022-05-20
- Court Decision / Holding
- Appeals allowed. The High Court judgments directing payment of compensation under Section 24(1) of the 2013 Act are set aside. The appropriate Authority(s) must declare the award under Section 11 of the Land Acquisition Act, 1894 (Act 1 of 1894) for the lands in question and determine the compensation under the provisions of Act 1894, taking into account Section 114 of the 2013 Act read with the General Clauses Act, 1897 where applicable. The original landowners shall be paid compensation under the 1894 Act. The court clarified that where no award under Section 11 of Act 1894 was made by 01.01.2014 owing to pendency or interim court orders, the 2013 Act’s Section 24(1) is not automatically triggered; the remedy lies under the 1894 Act with potential enhancement under that Act. The matter is remanded to the appropriate authorities to comply with these directions; costs none.
- Final Disposition
- Appeals allowed. High Court judgments set aside; awards to be determined under Act 1894 with applicability of Act 2013 provisions as per saving clauses; remedy to enhanced compensation under 1894 remains available.
Parties to the Case
Appellants / Petitioners
- Faizabad-Ayodhya Development Authority, Faizabad
- Moradabad Development Authority & Anr.
Respondents
- Dr. Rajesh Kumar Pandey & Ors.
- Babu & Ors.
- Horam Singh & Ors.
- Smt. Malka Begum & Ors.
Legal Representation & Advocates
Counsels for Petitioners
- • V.K. Shukla (Senior Advocate)
Counsels for Respondents
- • S.R. Singh (Senior Advocate)
Provisions of Law Cited
Legal Doctrines & Maxims
- Lex non cogit ad impossibilia
- Impotentia excusat legem
- Actus curiae neminem gravabit
- Commodum ex injuria sua nemo habere debet
- Nemo tenetur ad impossibilia
- Restitution (inherent jurisdiction of courts)
- Ex debito iustitiae
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellants argued that the High Court erred in directing payment of compensation under Section 24(1) of the 2013 Act where an award under Section 11 of the 1894 Act was not declared by 01.01.2014 due to pendency of writ petitions and interim orders. They relied on Indore Development Authority (supra) to contend that Section 24(1) of the 2013 Act is not automatically applicable to such cases and that the statutory framework requires determining compensation under the 1894 Act, with the 2013 Act applying only when no award under Section 11 was made and where there was no interim obstruction to progress. They emphasized restitution principles to ensure no litigant gains from court stays and argued that excluding time spent under interim orders is essential to avoid inequitable outcomes.
Contentions of Respondents
The respondents argued that, as no award under Section 11 of the 1894 Act had been made by the enforcement date of the 2013 Act due to stay orders, Section 24(1) of the 2013 Act should apply, with compensation determined under the 2013 Act. They contended that the 2013 Act was enacted to protect landowners and ensure fair compensation, and that the High Court’s direction to compute under Section 24(1) was consistent with the saving provisions. They also argued that the legislature did not intend to discriminate among landowners under the same notification and that interim orders should be treated as part of the litigation framework rather than a reason to deny the 2013 Act’s benefits.”},
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (20)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Indore Development Authority v. Manoharlal & Ors. | (2020) 8 SCC 129 | Positive | Applied as the controlling precedent to interpret Section 24 of the 2013 Act, especially excluding the period of interim stay from counting towards the five-year limit and endorsing restitutionary principles. |
| Sree Balaji Nagar Residential Assn. v. State of Tamil Nadu | (2015) 3 SCC 353 | Positive | Cited for interpretation of Section 24(2) and the approach to interim stays and five-year computation; supports the restitution framework. |
| Yogesh Neema v. State of M.P. | (2016) 6 SCC 387 | Partly Overruled / Limited | Doubted and referred to a larger Bench; not treated as binding authority here. |
| Union of India v. Modi Rubber Ltd. | (1986) 4 SCC 66 | Positive | Cited for interpretational aspects relating to stay and obligations under statutory schemes. |
| DDA v. Sukhbir Singh | (2016) 16 SCC 258 | Positive | Cited to support exclusion of interim-order period in computing five-year limit under 24(2). |
| Ram Krishna Verma v. State of U.P. | (1992) 2 SCC 620 | Positive | Restitutionary principle; helps justify neutralising the advantage gained due to interim orders. |
| Grindlays Bank Ltd. v. CIT | (1980) 2 SCC 191 | Positive | Restitution principle; court should neutralise undue advantage from litigation delays. |
| GTC Industries Ltd. v. Union of India | (1998) 3 SCC 376 | Positive | Delay accounting and equity reasoning in restitution context. |
| Jaipur Municipal Corpn. v. C.L. Mishra | (2005) 8 SCC 423 | Positive | Interim orders merge in final orders; interim carve-outs are not autonomous. |
| A.R. Antulay v. R.S. Nayak | (1988) 2 SCC 602 | Positive | Maxim that the act of the court should prejudice no one; restitutionary framework. |
| South Eastern Coalfields Ltd. v. State of M.P. | (2003) 8 SCC 648 | Positive | Restitution principles; unjust enrichment concerns in litigation. |
| Padmawati v. Harijan Sewak Sangh | (2012) 6 SCC 460 | Positive | Restitutionary reasoning and costs to deter frivolous litigation; balance equities. |
| Marshall Sons & Co. (India) Ltd. v. Sahi Oretrans (P) Ltd. | (1999) 2 SCC 325 | Positive | Restitutionary jurisdiction; courts may order restitution to undo wrongs from interim orders. |
| Ouseph Mathai v. M. Abdul Khadir | (2002) 1 SCC 319 | Positive | Stay by court does not confer a perpetuating right; remedy at first opportunity. |
| Om Parkash v. Union of India | (2010) 4 SCC 17 | Positive | Interim stay can impede declaration under Section 6; restitution principles apply. |
| Kavita Trehan v. Balsara Hygiene Products Ltd. | (1994) 5 SCC 380 | Positive | Restitutionary jurisdiction inherent in courts to neutralise litigation gains. |
| Karnataka Rare Earth v. Deptt. of Mines & Geology | (2004) 2 SCC 783 | Positive | Restitution and revise-equity approach; delay must be offset. |
| Kalabharati Advertising v. Hemant Vimalnath Narichania | (2010) 9 SCC 437 | Positive | Restitutionary considerations; caution against unjust enrichment due to interim orders. |
| Sambasiva Chari v. Ramasami Reddi | (ILR 1899) 22 Mad 179 | Positive | Maxim on impossibility and court acts not prejudicing litigants; supports equitable relief. |
| Padma Sundara Rao v. State of Tamil Nadu | (2002) 3 SCC 533 | Positive | Casus omissus and restitution principles in procedural context. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Faizabad-Ayodhya Development Authority, Faizabad v. Dr. Rajesh Kumar Pandey & Ors.; Moradabad Development Authority & Anr. v. Babu & Ors.; Moradabad Development Authority & Anr. v. Horam Singh & Ors.; Moradabad Development Authority v. Smt. Malka Begum & Ors.
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.