High CourtDivision BenchDisposal with liberty to pursue compensation an...

E. JEEVANANDAM v. N. KOTESWARA RAO & ORS.

Case / Petition Number:Special Leave Petition (C) No.27337 of 2017; Special Leave Petition (C) No.35197 of 2017
Neutral Citation:[2023] 1 S.C.R. 1099

Case Details & Bench

Court
High Court
Hon'ble Judges
  • Dr. Dhananjaya Y. Chandrachud
  • V. Ramasesubramanian
  • J. B. Pardiwala
Judgment Date
2023-01-23
Court Decision / Holding
Special Leave Petitions disposed of; petitioner granted liberty to pursue compensation and to establish title to the land in a competent court; the work of laying the sewer line was completed in the absence of a stay; PIL and related orders stand disposed; pending applications, if any, stand disposed.
Final Disposition
Disposal with liberty to pursue compensation and to establish title; no order setting aside the earlier Division Bench directions; work completed; proceedings accordingly

Parties to the Case

Appellants / Petitioners

  • E. Jeevanandam

Respondents

  • N. Koteswara Rao & ORS

Legal Representation & Advocates

Counsels for Petitioners

  • • Ms. Kiran Suri, Sr. Adv.

Counsels for Respondents

  • • Mr Jaideep Gupta, Senior Counsel
  • • Vivek Singh
  • • C. P. Rajwar
  • • Rohan Chandra
  • • Ms. Somi Sharma
  • • Chandra Prakash
  • • Ms. Rakhi Ray
  • • D. Kumanan
  • • Ms. Sujeeta Srivastava
  • • Vinodh Kanna B.

Case Synopsis & Summary

E. Jeevanandam v. N. Koteswara Rao & ORS concerns sewerage facilities in the Chennai metropolitan area, where the local body had resolved to provide sewerage facilities to the area including Ward No. 147 of Rukmani Nagar Road. A scheme was sanctioned in 2009 and the sewerage main was laid for most of its length, except for about 110 meters on the petitioner’s land, which he purchased in 2011. Civil disputes exist regarding title to the land, and the petitioner urged that the realignment of the sewer line would minimize damage to his property and protect his rights. The Single Judge dismissed the writ petition, noting the road’s public status and the petitioner’s knowledge of the project when purchasing the land. The petitioner appealed; the Division Bench directed the State to select a better option to minimize damage caused by laying the sewer main in the petitioner’s land. A Public Interest Litigation in the Madras High Court sought completion of underground drainage for residents. The Division Bench directed completion within three months, and subsequent orders challenged the Division Bench’s directions. The Supreme Court held that, in the absence of a stay, the work had been completed and public amenity had been created; it granted the petitioner liberty to pursue compensation and to establish title in a competent court, while disposing of the petitions.

Provisions of Law Cited

Chennai Metropolitan Water Supply & Sewerage Act, 1978, Section 67(3)Constitution of India, Article 136

Legal Doctrines & Maxims

  • Status quo ante

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends that while sewerage facilities were largely laid, about 110 meters on his land remains; he seeks an alternate route to minimize damage and protect his land rights, arguing the road is public and used for decades. He asserts that title to the land is disputed in civil proceedings and that completion of underground drainage would affect his relief rights; he seeks liberty to pursue compensation and to establish his title in a competent court. The petition also challenges the Division Bench's directives given the ongoing civil disputes, and insists that due process be observed, including adequate opportunity to be heard before any final order.

Contentions of Respondents

The Board/State respondents contend that the sewer main and underground drainage have been partially laid and that the public utility is already functioning; further realignment would cause delay and deprive residents of sewerage. They argue that the petitioner’s land-title dispute should be resolved in court and that compensation would be addressed only after due process and any final adjudication.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against E. JEEVANANDAM v. N. KOTESWARA RAO & ORS. and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

1099 # [2023] 1 S.C.R. 1099 ## E. JEEVANANDAM A v. ## N. KOTESWARA RAO & ORS. (Special Leave Petition (C) No.27337 of 2017) ## JANUARY 23, 2023 B ## **[DR. DHANANJAYA Y. CHANDRACHUD, CJI, V. RAMASUBRAMANIAN AND J. B. PARDIWALA, JJ.]** _Public Amenity – Sewerage facilities to the area – Claim of petitioner over the land on which the proposed sewerage line was_ C _sought to be laid – A resolution was passed by the local body to provide sewerage facilities to the area enclosing a list of streets – The petitioner purchased the property in 2011, inclusive of the road over which the proposed sewerage line was sought to be laid – The sewerage main was laid down both upstream and downstream except_ D _to the extent of the 110 meters (land of petitioner) – After various rounds of the litigation, the Division Bench of the High Court directed the State Government to choose a better option so as to minimize the damage that could be caused to the petitioner by laying the sewer main and sewer pumping station in the land of the_ E _petitioner – PIL filed on behalf of the residents who sought a direction for the completion of the underground drainage work so as to enable them to have the benefit of a sewerage facility – Division Bench of the High Court disposed of the petition by directing the Board to lay the pipelines and complete the_ F _underground drainage – On appeal, held: In the absence of an order of stay, the work of laying the sewerage line was completed – The developmental work which was carried out by the Board is in the form of a public amenity to the residents of the area – The title_ G _of the petitioner is not free from doubt since it is the subject matter of a civil dispute – Setting aside the impugned order of the Division Bench would give rise to further complications – Ultimately, the claim of the petitioner at the highest would be for the payment of damages – Therefore, petitioner granted liberty to pursue his rights_ D G H 1099 1100 SUPREME COURT REPORTS [2023] 1 S.C.R. - A _and remedies for establishing a case of compensation and for the award of damages subject to his rights to the land being established in a competent court – Special Leave Petitions disposed of._ EXTRAORDINARY CIVIL JURISDICTION : Special Leave B Petition (C) No.27337 of 2017. From the Judgment and Order dated 03.10.2017 of the High Court of Judicature at Madras in Writ Petition No.25595 of 2017. With C Special Leave Petition (C) No.35197 of 2017 Ms. Kiran Suri, Sr. Adv., Vivek Singh, C. P. Rajwar, Rohan Chandra, Ms. Somi Sharma, Chandra Prakash, Ms. Rakhi Ray, D. Kumanan, Ms. Sujeeta Srivastava, Vinodh Kanna B., Advs. for the D appearing parties. ## **DR. DHANANJAYA Y CHANDRACHUD, CJI** 1. The petitioner was the Chairperson of the erstwhile Maduravoyal Town Panchayat. On 28 November 2001, during his tenure E as Chairperson, a resolution was passed by the local body to provide sewerage facilities to the area enclosing a list of streets in which ward No 147 of Rukmani Nagar Road, Chennai was included. A scheme was prepared in terms of the request made by the local body. F 2. On 3 June 2009, the Government accorded administrative sanction for spending an amount of Rs 57.45 crores. The scheme commenced on 18 August 2009. Sewerage facilities were laid since there was no objection except for an area covering 110 meters at Rukmani Nagar Road. The sewerage main was laid down both upstream and G downstream of Rukmani Nagar except to the extent of the 110 meters. The petitioner purchased the property in 2011, inclusive of the road over which the proposed sewerage line was sought to be laid. H 3. Certain civil disputes are pending before the civil court as regards the claim of the petitioner in regard to the ownership of the land. Notice 1101 E. JEEVANANDAM v. N. KOTESWARA RAO & ORS. [DR. DHANANJAYA Y CHANDRACHUD, CJI] was issued to the petitioner under Section 67(3) of the Chennai Metropolitan Water Supply & Sewerage Act, 1978[1] . The petitioner suggested that an alternative route should be taken for laying the sewerage line. On 19 June 2015, an order was passed invoking the provisions of Section 67(3) of the 1978 Act. This gave rise to a writ petition at the behest of the petitioner. 4. During the course of the hearing of the writ petition, the Single Judge was informed that almost the entire work was completed save and except to the extent of 110 meters along the Rukmani Nagar Road. The Single Judge held that the residents of three streets would be deprived of sewerage facilities if a realignment as sought by the petitioner were to be granted. The Single Judge observed as follows: “Residents of the three streets would be deprived of the facility if the realignment as sought for by the petitioner is undertaken. The road has been shown as a public road as stated in the counter affidavit filed, through various documents. In fact it has been shown as such. Even during the tenure of the chairmanship of the petitioner, the scheme was contemplated and proposed by the local body. The road has also been relaid by the local body on two occasions. It is only a link road between Ganga Nagar and Rukmani Nagar.” 5. After noting that the petitioner was himself a party to the resolution in 2001 in- spite of which he had purchased the property in 2011, the Single Judge dismissed the petition. The Single Judge observed that _prima facie_ it appeared that there was a public road which was being used for the last few decades and the petitioner who had dealt with the issue in a different capacity in 2001 could not be stated to be unaware of the laying of the sewer line, having purchased the property subsequently in 2011. A B C D E F G 6. The petitioner instituted an appeal against the order of the Single Judge. On 27 April 2017, a Division Bench of the High Court disposed of the appeal by directing the State government to choose a better option so as to minimize the damage that could be caused to the petitioner by > 1 “1978 Act” H 1102 SUPREME COURT REPORTS [2023] 1 S.C.R. - A laying the sewer main and sewer pumping station in the land of the petitioner. 7. In the meantime, a Pubic Interest Litigation[2] was instituted before the High Court of Judicature at Madras. The petitioner was impleaded as sixth respondent to the writ petition. The PIL was instituted B on behalf of the residents of Ward No. 147 who sought a direction for the completion of the underground drainage work so as to enable them to have the benefit of a sewerage facility. The residents submitted that 15,000 families were affected because of the failure to lay pipelines along the stretch of the 110 meters connecting the underground drainage C to the pumping station. 8. The Division Bench in its judgment dated 3 October 2017, adverted to the writ petition instituted by the petitioner which was dismissed by the Single Judge of 4 April 2017. The Division Bench also noted that D there was an appellate order of 27 April 2017. After having noticed the provisions of the statute, the Division Bench disposed of the writ petition by directing the Board to lay the pipelines and complete the underground drainage within three months. The last paragraph of the order indicates that the petitioner was directed to be impleaded as the sixth respondent, together with the final order disposing of the petition. - E 9. The challenge in the first Special Leave Petition is to the order of the Division Bench dated 3 October 2017 by which the authorities have been directed to complete the laying of the drainage line. The companion Special Leave Petition has been instituted by the Chennai F Metropolitan Water Supply & Sewerage Board for challenging the order dated 27 April 2017 of the Division Bench. 10. As regards the first of the two Special Leave Petitions under Article 136 of the Constitution, the petitioner does have a legitimate grievance that an order was passed in the PIL directly affecting the G rights of the petitioner without furnishing an adequate opportunity of being heard. As noted earlier, the order for the impleadment of the petitioner was passed when the PIL was disposed of finally on 3 October 2017. H 2 “PIL” 1103 ## E. JEEVANANDAM v. N. KOTESWARA RAO & ORS. [DR. DHANANJAYA Y CHANDRACHUD, CJI] 11. Ordinarily, we would have been inclined to set aside the impugned order of the High Court and to remit the proceedings back for fresh consideration. That however would not resolve the substance of the controversy. When the Special Leave Petition arising from the order of the Division Bench dated 3 October 2017 was entertained by this Court on 27 October 2017, while issuing notice, the Court observed that if the petitioner succeeds, he shall be entitled to compensation in accordance with law. In the absence of an order of stay, the work of laying the sewerage line has been completed. The developmental work which has been carried out by the Board is in the form of a public amenity to the residents of the area. The title of the petitioner is by no means free from doubt since it is the subject matter of a civil dispute. 12. In this backdrop, setting aside the impugned order of the Division Bench would give rise to further complications since at this stage it would be difficult to restore the _status quo_ ante by directing the removal of the sewerage line. Ultimately, the claim of the petitioner at the highest would be for the payment of damages and for compensation for the laying of the sewerage line subject to the rights of the petitioner to the property being established in accordance with law. 13. For the above reasons, having heard Ms Kiran Suri, senior counsel appearing on behalf of the petitioner and Mr Jaideep Gupta, senior counsel appearing on behalf of the Board, we are of the considered view that the relief which should be granted to the petitioner would be to allow him the liberty to pursue his rights and remedies in accordance with law for establishing a case of compensation and for the award of damages subject to his rights to the land being established in a competent court. 14. The challenge by the Board to the order of the Division Bench dated 27 April 2017 does not require to be enquired into at this stage in view of the subsequent developments; the work of laying the sewer line having been duly completed. 15. Both the Special Leave Petitions shall accordingly stand disposed of subject to the above observations by which the Court has A B C D E F G H 1104 SUPREME COURT REPORTS [2023] 1 S.C.R. - A granted liberty to the petitioner in the first Special Leave Petition to pursue his claim for compensation in accordance with law and for establishing his title to the land on which the sewerage line has been laid. 16. Pending applications, if any, stand disposed of. B Ankit Gyan SLPs disposed of. C D E F G H