DWARIKESH SUGAR INDUSTRIES LTD. v. PREM HEAVY ENGINEERING WORKS (P) LTD.

Case / Petition Number:
Civil Appeal No. 3376 of 1997

Case Synopsis & Summary

DWARIKESH SUGAR INDUSTRIES LTD. v PREM HEAVY ENGINEERING WORKS (P) LTD concerns the encashment of two unconditional bank guarantees issued by State Bank of India in favour of the appellant under a 1994 contract for boiling house equipment. The appellant invoked the guarantees after Prem Heavy Engg. failed to supply equipment on time and to replace defective items, leading to adverse effects on the project. The bank did not pay despite invocation; the respondent sought injunctions to restrain encashment. The Civil Judge vacated the ex parte injunctions; the Allahabad High Court stayed encashment and remanded for fresh decision, but with injunction continuing. The Supreme Court held that courts should be slow to grant injunctions restraining encashment of unconditional bank guarantees, recognizing only two exceptions: (i) established fraud vitiating the foundation of the guarantee, and (ii) irretrievable harm or injustice making it impossible for the guarantor to reimburse itself if it succeeds. The Court emphasized that the bank's refusal to honor in the present case was improper, and that the principle of unjust enrichment does not apply to encashment claims. It criticized lower courts for not referring to settled law and for failing to examine the guarantee terms and invocation letters. Citing UP Sugar Corp and other decisions, the Court allowed the appeal, set aside the High Court order, and restored the trial court's dismissal of the injunction applications, with costs to the appellant.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • I.K.S. Paripoornan
  • K. Venkat Swamy
  • B.N. Kirpal
Judgment Date
1997-05-07
Court Decision / Holding
Appeal allowed. The Allahabad High Court’s judgment dated 10 September 1996 in revision petition No. 257 of 1996 is set aside, and the trial court’s order dated 20 August 1996 dismissing the injunction application is restored. The appellant is entitled to costs of Rs. 20,000.
Final Disposition
Appeal allowed; High Court order set aside; Trial court order restored; Appellant entitled to costs.

Parties to the Case

Appellants / Petitioners

  • Dwarikesh Sugar Industries Ltd.

Respondents

  • Prem Heavy Engineering Works (P) Ltd.
  • State Bank of India

Legal Representation & Advocates

Counsels for Petitioners

  • • Harish N. Salve
  • • Krishan Mahajan
  • • P.H. Parekh
  • • Indu Verma

Counsels for Respondents

  • • Sudhir Chandra
  • • Manmohan
  • • Sanjay Raghuvanshi
  • • R. Sasiprabhu

Provisions of Law Cited

Code of Civil Procedure, 1908: Order 39 Rule JConstitution of India, 1950: Article 141Indian Arbitration Act, 1940: Section 20

Legal Doctrines & Maxims

  • Doctrine of Unjust Enrichment
  • Fraud must be established (established fraud) for exceptional injunctions

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contended that the bank guarantees were unconditional and encashable on demand; invocation letters were in conformity with the guarantees, and there was no established fraud. They argued that the banks ought to honor the guarantees, and that interim injunctions were improper since the law on encashment of guarantees is well settled with only two exceptions, none of which were proven here; the High Court failed to refer to jurisprudence and did not assess the guarantees and invocation letters. They emphasized the need to avoid judicial adventurism and undue enrichment against the contract’s terms.

Contentions of Respondents

The respondents argued for maintaining injunctions to restrain encashment pending disputes, emphasizing that guarantees secure performance and advances; they asserted possible breach and invoked fraud allegations; they argued against encashment until disputes are resolved, and critiqued the failing of appellate review to follow established authorities.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
U.P. State Sugar Corporation v. Sumac International Ltd.(1997) 1 SCC 568PositiveCited as the well-settled general principle on invocation of bank guarantees and the two exceptions (fraud and irretrievable harm).
Svenska Handelsbanken v. M/s. Indian Charge Chrome & Ors.(1994) 1 SCC 502PositiveListed as a recent pronouncement reinforcing the principle on encashment of bank guarantees.
Larsen & Toubro Ltd. v. Maharashtra State Electricity Board & Ors.(1995) 6 SCC 68DistinguishedDistinguished on facts: plant operations and guarantee terms differed; not applicable to the present case.
Hindustan Steel Works Construction Ltd. v. G.S. Atwal & Co. (Engineers) Pvt. Ltd.(1995) 6 SCC 76PositiveCited as part of recent pronouncements underpinning the governing principle.
U.P. Cooperative Federation Ltd. v. Singh Consultants and Engineers (P) Ltd.(1988) 1 SCC 174PositiveCited for the rule that the right to encashment is generally upheld unless exceptional grounds exist.
Bolivinter Oil SA v. Chase Manhattan Bank(1984) 1 All ER 351PositiveCited for the fraud exception and need for clear evidence of fraud against the bank guarantee.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•6,908 words•~32 min read

In The Court Record

DWARIKESH SUGAR INDUSTRIES LTD. v. PREM HEAVY ENGINEERING WORKS (P) LTD.

A # DWARIKESH SUGAR INDUSTRIES LTD. # _v._ PREM HEAVY ENGINEERING WORKS (P) LTD. ## MAY 7, 1997 B ## IK.S. PARIPOORNAN, K. VENKATASWAMY AND B.N. KIRPAL, JJ.] _Code of Civil Procedure, 1908 : Order 39 Rule J._ C _Bank Guarantee-Encashment of unconditional bank guarantee-Injunction restraining-No allegation of fraud or i"etrievable ham1 or injustice made in the injunction application-Held : Only in exceptional case of established fraud which would vitiate the very foundation of the bank guarantee or its encashment resulting in i"etrievable hann or injustice which would make it impossible for the guarantor to reimburse himself, if it ultimately_ D _succeeded, cowt should nonnally not grant injunction-Principle of undue enrichment not applicable to encashme11t of bank guarantee-In the cir-_ - _cwnstances of the case, High Coult emd in granting the injunction without referring to the decisions of the Supreme Coult-Bank also not shown professional efficiency and acted in a paltisan manner in not honouring its com-_ E _mitmellts even when there was no restraint order of any coult._ _Bank guarantee---£ncashment of-Injunction restraining-Held : Injunction of cowt ought not to be an i11strnme11t which is used in nullifying the temis of a co/llract, agreement or u11de1taki11g which_ is _lawfully enforc2able._ F ## _Constitution of India, 1950: A1ticle 141._ _Precedelll-Wlzen law is well settled as a result of judicial pronouncemellls of Supreme Cowt it would amount to judicial impropriety and judicial adventurism for the mbordinate cowts including the High Coult to ignore the_ G _same and pass contrwy_ orde~Such _practice strongly deprecated._ ## _Doctrines :_ _"Doctrine of Unjust EnrichmeJZt''-Applicability of_ H The appellant and respondent No. I had entered into an agreement 184 DWARJKESH SUGAR IND. LTD. _v._ PREM HEAVY ENGG. WORKS LlD. 185 whereby respondent No. 1 was to supply boiling house equipment to the A appellant within a fixed time schedule. Respondent No. 1 furnished two bank guarantees in favour of the appellant. One of the bank guarantees was issued to ensure timely delivery of equipment and supply by respondent No. 1. The other bank guarantee was issued for securing the advance given by the appellant. The terms of the bank guarantees were similar. B The respondent on the very next day obtained an _ex parte_ injunction from the civil court restraining the appellant from encashing the bank guarantee. Hence, the bank made no payment. Subsequently, respondent No. 1 obtained another _ex parte_ injunction in respect of the second bank guarantee. c After the appellant became aware of the filing of the suit and the injunction application it entered appearance in court although no notice had been served on it. The Civil Judge vacated the _ex parte_ injunctions and dismissed the injunction applications relying on a number of decisions of this Court. D The appellant again approached the bank for the encashment of the guarantees, but without success. Respondent No. 1 then filed a revision petition before the High Court challenging the order of the trial court. The Single Judge of the High Court remanded the matter back to the trial' E Court for a fresh decision but, at the same time, directed that till the disposal of the injunction application the bank guarantees in question would not be invoked or encashed. Due to the dilatory tactics adopted by respondent No. 1 the said injunction application had not yet been disposed of by the trial court with F the result that the injunction gr,mted by the Single Judge continued. Being aggrieved, the appellant preferred the present appeal. ## Allowing the appeal, this Court G HELD : I.I. Courts should be slow in granting an injunction to restrain the realisation of the bank guarantee. The courts have carved out only two exceptions : (l) II' there is a fraud in connection with the bank guarantee which would vitiate the very foundation of such a bank guarantee and the beneficiary seeks to take advantage of it, then he can be restrained from doing so. But for that the fraud has to be an established H 186 ## SUPREME COURT REPORTS [1997] SUPP. 1 S.C.R. A fraud. (2) Where allowing the encashment of an unconditional bank guarantee would result in irretrievable harm or injustice to one of the, _/_ . parties concerned. The resulting of irretrievable injury has to be such a circumstance, which would make it impossible for the guarantor to reimburse himself, if he ultimately succeeds. This will have to be decisively B established and it must be proved to the satisfaction of the Court that there would be no possibility whatsoever of the recovery of the amount from the beneficiary, by way of restitution. (195-D-F; 196-D-E] _U.P. State Sugar Corporation_ v. _Sumac International Ltd.,_ (1997) 1 SCC 568; _Svenska Handeisbanken_ v. _M/s. Indian Charge Chrome & Ors.,_ C (1994) 1 SCC 502; _Larsen & Toubro Ltd._ v. _Maharashtra State Electricity Board & Ors.,_ (1995) 6 SCC 68; _Hindustan Steel Works Constrnction Ltd._ v. G.S. _Atwal & Co. (Engi.neers) Pvt. Ltd.,_ (1995) 6 SCC 76 and _U.P. Cooperative Federation Ltd._ v. _Singh Consultants and Engineers (P) Ltd.,_ (1988) 1 sec 174, relied on. ## D _Bolivi11ter Oil SA_ v. _Chase Manhattan Bank,_ (1984) 1 All ER 351, referred to. 1.2. If the bank could not in law avoid the payment, as the demand had been made in terms of the bank guarantee, as has been done in the E present case, then the court ought not to have issued an injunction which had the effect of restraining the bank from fulfilling its contractual obligation in terms of the bank guarantee. An injunction of the court ought not to be an instrument, which is used in nullifying the terms of a contract, agreement or undertaking, which is lawfully enforceable. [197-C] F F 1.3. It is an admitted fact that in the plaint itself, there was no such allegation. It was initially only in the first application for the grant of injunction that in a paragraph it has been mentioned that the appellant had invoked the bank guarantee arbitrarily. This application contains no facts or particulars in support of the allegation of fraud. A similar bald G averment alleging fraud is also contained in the second application for injunction. This is not a case where respondent No. l had at any time alleged fraud prior to the filing of the injunction application. The main contract pursuant to which the bank guarantees were issued, was not sought to be· avoided by alleging fraud, nor was it at any point of time alleged that the bank guarantee was issued because any fraud had been H played by the appellant. The bald assertion of fraud had been made solely DWARIKESHSUGARIND.LID. _v._ PREMHEAVYENGG.WORKSLID. 187 with a view to obtain an order of injunction. In the absence of established fraud and not a mere allegation of fraud and that also having been made only in the injunction application, the court could not, in the present case, have granted an injunction to the encashment of the bank guarantees. [198-G-H; 199-A-B] 2. The High Court erred in not considering it necessary to refer to B various judicial pronouncements of this Court in which the principles, which have to be followed, while examining an application for grant of interim relief have been clearly laid down. The observation of the High Court that reference to judicial decisions will not be of much importance was clearly a method adopted by it in avoiding to follow and apply the law C as laid down by this Court. Yet another serious error which was committed by the High Court, in the present case, was not to examine the terms of the bank guarantee and consider the letter of invocation which had been written by the appellant. There is no justification for the High Court in invoking the alleged principle of unjust enrichment to the facts of the present case and then deny the appellant the right to encash the bank guarantees. In D encashment of bank guarantee the principle of unjust enrichment has no application. [199-C-F] 3. When a position in law, is well settled as a result of jndicial pronouncement of this Court, it would amount to judicial impropriety to E_ say the least, for the subordinate courts including the High Courts to ignore the settled decisions and then to pass a judicial order is clearly contrary to the settled legal position. Such judicial adventurism cannot be permitted and the tendency of the subordinate courts in not applying the settled principles and in passing whimsical orders which necessarily has the effect of granting wrongful and unwarranted relief to one of the parties F is strongly deprecated. It is time that this tendency stops. [200-8) . 4. Moreover, the bank, which has chosen not to be represented in this case, has not shown professional efficiency, to say the least, and has acted in a partisan manner with a view to help and assist respondent No. G 1. At the time when there was no restraint order from any Court, the bank was under a legal and moral obligation to honour its commitments. It, however, failed to do so. It appears that the bank deliberately dragged its feet so as to enable respondent No. 1 to secure favourable order of injunction from the Court. Such conduct of a bank is difficult to appreciate. [200-D] H 188 SUPREME COURT REPORTS (1997] SUPP. 1 S.C.R. • . A CIVIL APPELLATE JURISDICTION : Civil Appeal No. 3376 of 1997. From the Judgment and Order dated 10.9.96 of the Allahabad High Court in C.R. No. 257 of 1996. **B** Harish N. Salve, Krishan Mahajan, P.H. Parekh and Indu Verma for the appellant. Sudhir Chandra, Manmohan, Sanjay Raghuvanshi and R. Sasiprabhu for the Respondents. c The Judgment of the Court was delivered by **KIRPAL, J.** Special leave granted. - Having been thwarted by orders of the court below in its attempt to - **D** get encashment of the bank guarantees, issued by the State Bank of India, Meerut Cantt. Branch (respondent No. 2) respondent No. 1 has led to the - " filing of this appeal by the aggrieved beneficiaries. The appellant and respondent No. 1 had entered into an agreement on 27th July, 1994 whereby respondent No. 1 was to supply boiling house E equipment the cost of which was Rs. 5.23 crores. The supply of equipment and material was to start from 15th September, 1994 and the same was to be completed by 10th August, 1995, as per the schedule of the supply agreed to by the parties. According to one of the clauses of the aforesaid agreement responF dent no. 1 had agreed to furnish bank guarantees in favour of the appellant. Out of the above six, only four bank guarantees were furnished including bank guarantee no. 40/51 dated 1st December, 1994 for a sum of Rs. 26,15,000 and bank guarantee no. 40/47 dated 24th November, 1994 for a sum of Rs. 35 lacs. These are the bank guarantees with which we are G concerned in the present case. Bank guarantee no. 40/51 was issued to ensure timely delivery of equipment and supply by respondent no. 1. The relevant clauses of the said bank guarantee no. 40/51 are as follows : **H** "In consideration of the premises the Guarantor hereby uncon- DWARIKESHSUGAR IND. LTD. _v._ PREMHEA VY ENGG. WORKS LTD. [KIRPAI.,J.) 189 ditionally and irrevocably undertakes to pay to the Purchaser on A their first written demand and without demur such a sum not exceeding Rs. 26,15,000 (Twenty six lacs fifteen thousand only) as the purchaser may demand representing 5% (five per cent) of the contract price, and if the guarantor fails to pay the sum on demand the guarantor shall also pay on the sum demanded interest at the B bank lending rates then prevailing reckoned from the date of demand till the date of payment. 2. The guarantor shall pay to the purchaser on demand the sum under clause 1 above without demur and requiring the purchasers to invoke any legal remedy that may be available to them, it being C understood and agreed firstly that the purchasers shall be the sole judge of and as to whether the sellers have committed breach( es) of any of the terms and conditions of the said agreement and secondly that the right of _the purchasers to recover from the guarantor any amount due to the purchasers shall not be affected D or suspended by reasons of the fact that any dispute or disputes have been raised by the sellers with regard to their liability or that proceedings are pending before any Tribunal, arbitrator( s) or Court with regard to or in connection therewith, and thirdly that the guarantor shall immediately pay the aforesaid guaranteed amount on demand and it shall not be open to the guarantor to E know the reasons of or to investigate or to go into the merits of the demand or to question or to challenge the demand or to know any facts affecting the demand, and lastly that it shall not be open to the guarantor to require the proof of the liability of the seller to pay the amount before paying the aforesaid guaranteed amount F to the purchasers. The other bank guarantee no. 40/47 was originally issued for a sum of Rs. 51,70,000 for securing advance payment. The agreement contemplated the liability being gradually reduced and on 28th August, 1995 this bank guarantee was reduced for a diminished amount of Rs. 33 lacs. G The relevant clause of this bank guarantee is as follows : "In consideration of the premises the guarantor hereby unconditionally and irrevocably undertakes to pay to the purchaser on their first written demand and without demur such a sum not H . SUPREME COURT REPORTS [1997] SUPP.1 S.C.R. 190 A B exceeding Rs. 51,70,000 (Rupees fifty one lacs seventy thousand only) as the purchasers may demand representing 10% (Ten per cent) of the contract price, and if the guarantor fails to pay the sum on demand the guarantor shall also pay on the sum demanded interest at the bank lending rates then prevailing reckoned from the date of demand till the date of payment. Provided that liability of the guarantor hereunder shall reduce to the extent of the advance adjusted under clause 13 of the said agreement. c D E F The guarantor shall pay to the purchaser on demand the sum under clause 1 above without demur and requiring the purchasers to invoke any legal remedy that may be available to them, it being understood and agreed firstly that the purchaser shall be the sole judge of and as to whether the sellers have .committed any breach( es) of any of the terms and conditions of th~ said agreement and secondly that the right of the purchasers to recover from the guarantor any amount due to the purchasers shall not be affected or suspended by reasons of the fact that any dispute or disputes have been raised by the sellers with regard to their liability or that proceedings are pending before any Tribunal, arbitrator(s) or court with regard thereto or in connection therewith, and thirdly that the guarantor shall immediately pay the aforesaid guaranteed amount on demand and it shall not be open to the guarantor to know the reasons of or to the investigate or to go into the merits of the demand or to question or to challenge the demand or to know any facts affecting the demand, and lastly that it shall not be open to the guarantor to require the proof of the liability of the seller to pay the amount before paying the aforesaid guaranteed amount to the purchasers". According to the appellant respondent no. 1 did not supply the equipment at site, within the time allowed, nor replaced any of the defective items which, according to the appellant, had resulted in the late G commencement of the trial crushing in the mill. It is further the case of the appellant that it had to make direct purchases of many parts from other sources as the respondent no. 1 had failed to supply the equipment. Ultimately by letter dated 21st November, 1995 written to respondent no. 2; the appellant invoked the bank guarantee. The material portion of this H letter was as follows : DWARIKESHSUGARIND. LTD. _v._ PREMHEAVYENGG. WORKSLTD.iKIRPAL,J.] 191 "We wish to inform you that M/s. Prem Heavy Engineering A Works (P) Ltd. Rani Mill, Delhi Road, Meerut have failed to fulfil the conditions of our agreement dated 27.7.1994 in so far as timely supply of the machinery and equipment under order with them. In view of their failure, we hereby invoke the bank guarantee in terms of clause 1, 2 and 3 of the aforesaid guarantee and hereby B demand payment of Rs. 26,15,000 (Rupees twenty six lakhs fifteen thousand only). You are, therefore, required to issue a demand draft drawn in favour of our company payable at Najibabad for Rs. 26,15,000 (Rupees twenty six lakhs fifteen thousand only). The original guarantee is enclosed which may please be acknowledged." C Respondent bank did not make the payment, notwithstanding the receipt of the aforesaid letter dated 21st November, 1995 but the effect which this letter had was that, on 23rd November, 1995, respondent no. 1 filed original suit No. 1182of1995 before the Court of Civil Judge, Meerut, under Section 20 of the Indian Arbitration Act, 1940. In the said suit the D appellant herein was impleaded as defendant no. 1 while the State Bank of India was impleaded as defendant no. 2. The only relief claimed ieithis suit \\'.as that the dispute between the parties should be referred to an arbitrator. Along with this suit respondent no. 1 also field an application for the grant of injunction restraining the appellant herein from encashing E the aforesaid bank guarantee no. 40/51 which had been issued for a sum of Rs. 26,15,000. It appears that there was some discussion between the representatives of the appellant and respondent no. 1 in connection with the encashment of the said bank guarantee no. 40/51. Pursuant thereto letter F dated 24th November, 1995 was written by respondent no. 1 to the appellant which was to the following effect : · As discussed with your managing director Sh. G.R. Mararka today at your Delhi guest house, we are confirm that we shall G despatch balance parts except lime elevator direct from our works by 26.11.1995 and shall arrange despatch of balance fright oil after payment except air compressor by 27.11.1995. We shall ensure commissioning of the two shall of cooling towers o( one complete shall of twin crystalizer and F.M. Piping by 30.111995 and F.M. I Tonor with rouling in 10.12.1995. We request you to kindly keep H SUPREME COURT REPORTS [1997] SUPP. 1 S.C.R. 192 A the invocation of the above guarantee in abeyance till 10.12.1995. According to the appellant it was not aware that original suit No. 1182 of 1995, along with an application for injunction had already been filed by respondent no. 1 a day earlier to the respondent's letter dated 24th B November, 1995. Acting on the basis of the aforesaid letter of the respondent no. 1 the appellant wrote a letter dated 27th November, 1995 to the Manager, State Bank of India, Meerut Cantt. After expressing its regret that the proceeds of the guarantee had not been paid to the appellant, it was stated in this letter that respondent no. 1 had assured to make a complete supply of the ordered plant and machinery within next three or C four days. In view of this it wthdrew its letter of invocation dated 21st November, 1995 but it was added that "it may, however, be noted that demand payment is being withdrawn without prejudice to our right of invocation under the guarantee". D Apparently having succeeded in pursuading the appellant to write the aforesaid letter dated 27th November, 1995 withdrawing the letter of invocation, respondent no. 1 on the very next day, i.e., 28th November, 1995 obtafried an et _parte_ injunction from the Court of Civil Judge, Meerut, . restraining the appellant from encashing the aforesaid bank guarantee no. 40/51. E According to the appellant, respondent no. 1 did not make the requisite supplies with the result that vide letter dated 9th January, 1996, written to the Assistant General Manager, State Bank of India, Meerut, it invoked bank guarantee no. 40/51 by, _inter alia,_ stating as follows : F "As per clause 14 of the supply agreement M/s. Prem Heavy Engineering Works (P) Ltd., Meerut has failed to deliver the equipments and its commissioning within the scheduled time frame. G H Now we hereby invoke the aforesaid guarantee for Rs. 26,15,000 (Rupees twenty six lacs fifteen thousand only) being 5% of the contract value and enclose herewith the original guarantee for your record. Kindly hand over the Demand Draft in our favour payable at Najibabad, Distt. Bijnor, Uttar Pradesh towards the invocation amount." DWARIKFSHSUGARIND.LTD. _v._ PREMHEAVYENGG. WORKSLID.(KIRPAI,J.] 193 As on 28th November, 1995 respondent no. 1 h!ld already obtained A an er _parte_ injunction restraining the encashment of bank guarantee, no payment was made to the appellant by the bank. - Respondent no. 1 then filed another injunction application dated 12th January, 1996 with regard to the second bank guarantee dated 24th November, 1994 which was for a sum of Rs. 33 lacs. It obtained an er _par._ B injunction in respect thereto on the same day. Being ignorant of this the appellant wrote a letter dated 16th January, 1996 to the respondent bank invoking the said bank guarantee no. 40/47. In the said letter it was stated that respondent no. 1 had failed to deliver the equipment as per the terms of the agreement and that the appellant had J>rought equipment from C various markets due to which the advance amount which had been paid to respondent no. 1, in respect of which this bank guarantee had been issued, remained unadjusted. The bank was accordingly required to pay the said amount of Rs. 33 lacs. -According to the appellant it is only after 16th January, 1996 that it D became aware of the filing of the aforesaid suit and the injunction application and it entered appearance in Court on 18th January, 1996 even though no notice had been served on it. As per the appellant, there was delay in the disposal of the injunction application, consequently it approached the High Court for appropriate directions and the Allahabad High Court vide E order dated 10th May, 1996 directed the Civil Judge, Meerut Cantt, to dispose of the suit within the time fixed by it. By a detailed order dated 20th August, 1996, the Second Civil Judge (Sr. Division), Meerut vacated the er _parte_ injunctions which had been granted and dismissed the injunction applications. In arriving at this con·. F clusion it observed that respondent no. 1 had not stated that the work had been completed and nor was there any allegation of cheating or fraud contained in the plaint which had been filed. The trial court referred to a number of decisions of this Court and came to the conclusion that there was no basis, in law, for the grant of any interim prolubitory order. G The appellant on 22nd August, 1996 again approached the respondent bank for the encashment of the bank guarantees, but without success. Respondent no. 1 then filed revision petition No. 257 of 1996 on 10th September, 1996 before the Allahabad High Court challenging the order H SUPREME COURT REPORTS [1997] SUPP. 1 S.C.R. 194 - A dated 20th August, 1996 of the trial court. Single judge of the Allahabad High Court took up the revision petition and disposed it of on the same day and, after setting aside the order dated 20th August, 1996 it remanded the matter back to the trial court for a fresh decision but, at the same time, directed that till the disposal of injunction application the bank guarantees B[in question shall not ][be ][invoked or encashed. The trial court ][was ][directed ] to hear the parties within fifteen days of the receipt of the order and to dispose of the injunction application with fifteen days thereafter. Needless to state, due to dilatory tactics adopted by respondent no. 1, which is evident from the documents available on the record of this case, the said injunction applications have not been disposed of till date with the result C that the injunction granted by the single judge of the High Court vide order dated 10th September, 1996 still continues. While· allowing the civil revision the single judge in his judgment did not think it necessary to refer to the judicial decision which were cited D before him. The court observed that reference to the same was not necessary because the trial court, who had observed that the plaint did not •• contain any allegation with regard to fraud, had not noticed that allegation of fraud was contained in the injunction application. The learned judge noticed that the liability of bank under the guarantee was absolute and that ' it was not supposed to question the authority of the beneficiary to encash E the bank guarantee but observed that the same "could not be the guideline for allowing the defendant to encash the bank guarantee unless there was a finding that the defendant was having undue enrichment thereby". The aforesaid decision of the High Court has been assailed by Sh. F Harish N. Salve, learned senior counsel for the appellant, who has contended that the High Court fell in serious error in ignoring and not in even referring to the decisions of this Court where the principles regarding the grant of injunction in matters relating to encashment of bank guarantees have been clearly spelt out. Had this been done, the learned counsel submits, the High Court could not, in law, have continued with the temG porary injunction. Numerous decisions of this Court rendered over a span of nearly two decades have laid down and reiterated the principles which the Courts must apply while considering the question whether to grant an injunction H which has the effect of restraining the encashment of a bank guarantee. We ## DWARIKESH SUGAR IND. LTD. _v._ PREMHFA VY ENGG. WORKS LTD. (KIRPAI.,J.] 195 - do not think it necessary to burden this judgment by referring to all of A them. Some of the more recent pronouncements on this point where the earlier decisions have been considered and reiterated are _Svenska Handelsbanken_ v. _Mis. Indian Charge Chrome and Ors.,_ [1994] l SCC 502; _Larsen & Toubro Ltd._ v. _Maharashtra State Electricity Board and Ors.,_ [1995] 6 SCC 68; _Hindustan Steel Works Constrnction Ltd._ v. _G.S. Atwal & Co (Engineers)_ B _Pvt. Ltd.,_ [1995] 6 SCC 76 and _U.P. State Sugar Cotporation_ v. _Sumac International Ltd.,_ [1997] 1 SCC 568. The general principle which has been laid down by this Court has been summarised in the case of _U.P. Sugar Cotporation 's_ case as follows : "The law relating to invocation of such bank guarantees is by C now well settled. When in the course of commercial dealings an unconditional bank guarantee is given or accepted, the beneficiary is entitled to realize such a bank guarantee in terms thereof irrespective of any pending disputes. The bank giving such a guarantee is bound to honour, it as per its terms irrespective of D any dispute raised by its customer. The very purpose of giving such a bank guarantee would otherwise be defeated. The courts should therefore, be slow in granting an injunction to restrain the realization of such a bank guarantee. The courts have carved out only two exceptions. A fraud in connection with such a bank guarantee would vitiate the very foundation of such a bank guarantee. Hence E if there is such a fraud of which the beneficiary seeks to take the advantage, he can be restrained from doing so. The second exception relates to cases where allowing the encashment of an unconditional bank guarantee would result in irretrievable harm or injustice to one of the parties concerned. Since in most cases F payment of money under such a bank guarantee would adversely affect the bank and its customer at whose instance the guarantee is given, the harm or injustice contemplated under this head must be of such an exceptional and irretrievable nature as would override the terms of the guarantee and the adverse effect of such an injunction on commercial dealings in the country." G Dealing with the question of fraud it has been held that fraud has to be an ,, established fraud. The following observations of Sir John Donaldson, M.R. in _Bolivinter Oil SA_ v. _Chase Manhattan Bank,_ (1984) 1 All ER 351, are apposite : H 196 SUPREME COURT REPORTS (1997] SUPP. lS.C.R. A B "The wholly exceptional case where an injunction may be granted is where it is proved that the bank knows that anY demand for payment already made or which may thereafter be made will clearly be fraudulent. But the evidence must be clear both as to the fact of fraud and as to the bank's knowledge. _It would certainly not nonnally be sufficient that this rests on the uncorroborated statement of the customer,_ for irreparable damage can be done to a bank's credit in the relatively brief time which must elapse between the granting of such an injunction and an application by the bank to have it charged." ## c (emphasis supplied) The aforesaid passage was approved and followed by this Court in _U.P. Cooperative Federation Ltd._ v. _Singh Consultants and Engineers (P) Ltd.,_ (1988] 1 sec 174. D The second exception to the rule of granting injunction, i.e., the resulting of irretrievable injury, has to be such a circumstance whic.li would make it impossible for the guarantor to reimburse himself, if he ultimately succeeds. This will have to be decisively established and it must be proved to the satisfaction of the Court that there would be no possibility whatE soever of the recovery of the amount from the beneficiary, by way of restitution. In the instant case, as has been already noticed there were two types of bank guarantees which were issued. Bank Guarantee no. 40/51 for Rs. 26,15,000 was issued to ensure timely performance of the agreement by F respondent no. 1. The relevant terms of this guarantee firstly makes it clear that the bank has unconditionally and irrevocably undertaken to pay to the appellant, on written demand and without demand, the amount demanded by it. Secondly, Clause II of the said guarantee clarifies that the payment shall be made without demand and on the undertaking that the appellant is to be sole judge whether the seller has committed any breach. ConseG quently the right of the appellant to recover the guaranteed amount is not to be effected or suspended by reason of any dispute which can be raised or pending bef~re the courts tribunals or arbitrator, Thirdly the guarantor had no right to know the reasons of or to investigate the merits of the demand or to question or to challenge the demand or to know any facts H affecting the demand and lastly it was not open to the bank to require the ... DWARIKESHSUGAR IND. LTD. _v._ PREMHFAVY ENGG. WORKS LTD. [KIRPAI.,J.] 197 proof of the liability of respondent no. 1 to pay the amount before paying A the aforesaid guaranteed amount to the appellant. The letter of invocation issued by the appellant demanding the payment of Rs. 26,15000 was in accordance with the terms of bank guarantee no. 40/51 and the bank was, therefore, under an obligation to honour B its undertaking and to make •the payment. It, however, chose not to fulfil its obligation. If the bank could not ·in law avoid the payment, as the demand had been made in terms of the bank guarantee, as has been done in the present case, then the court ought not to have i.Ssued an injunction which had the effect of restraining the bank from fulfilling its contractual obligation in terms of the bank guarantee. An injunction of the court ought C not to be an instrument which is used in nullifying the terms of a contract, agreement or undertaking which is lawfully enforceable. In its aforesaid letter dated 24th November, 1995 respondent no. 1 had clearly admitted that entire supply had not been made. In view of this also the High. Court was not justified in granting an injunction. D Bank guarantee no. 40/97 dated 24th November 1994, which had been issued to secure the advance of Rs. 129.24 lacs which had been given by the appellant, was also similar in terms to the earlier bank guarantee no. 40/51. The main contract between the parties contemplated that the amount of bank guarantee shall stand reduced on adjustment being made. E It is contended by Shri Sudhir Chandra, learned counsel for the respondents that the full amount which was given had been adjusted and no amount remained outstanding and therefore, the bank guarantee no. 40/47 could no longer be regarded as alive. In support of this contention, the learned counsel relied on the observations of this Court in _Larson & Tubro_ F _Ltd._ v. _Maharashtra State ElectJicity Board and Ors.,_ [1995) 6 SCC 68 where an injunction was granted where the bank guarantee which was issued was to be kept alive till the successful completion of trial operations. In our opinion, this decision can be of no assistance to respondent no. 1 because in _Larson & Turbo's_ case (supra) this Court found that the guarantee which had been given by the bank was to ensure only till the successful completion G of the trial operations and the taking over of the plant. The documents revealed that the contractual term in this regard has been complied with and after successful completion of the trial operation, the plant had admittedly been taken over. In view of this, it was held by this Court that the terms of the bank guarantee did not permit its invocatil;m once the trial H ' 198 SUPREME COURT REPORTS [1997] SUPP. 1 S.C.R. •· A operations have been successfully completed. In the present case clause 3 of bank guarantee no. 40/47 relating to adjustment of the advance stipulated as follows : B c D "The guarantee shall come into force from the date thereof and shall remain valid till the full advance amount is adjusted under Clause 13 of the said agreement which according to the terms and conditions of the said Agreement is stipulated to be adjusted proportionately from each bill of the Sellers against actual deliveries of the machinery and equipment at site but if the deliveries as aforesaid have not been completed by the Sellers within the said period for any reason whatsoever the Guarantor hereby undertakes that the Sellers shall furnish a fresh or renewed guarantee on the Purchaser's proforma for such further period as the purchaser's may intimate failing which the guarantor shall pay to the purchasers a sum not exceeding Rs. 51,70,000 (Rupees Fifty one lacs seventy thousand only) or the residual amount of balance unadjusted advance left after proportionate adjustment in accordance with clause I above as the purchaser may demand." ... No plea was taken before the courts below, and no document has E been shown to us by the respondents, which can _prim a f acie_ indicate that the full amount of advance had been adjusted under Clause 13 of the main contract between the appellant and the defendant no. 1. According to the appellant, the original guarantee was for Rs. 51,70,000 but the same, after adjustment of the advance, in terms of clause 13 of the main agreement, stood reduced to Rs. 33,00,000. This amount was still outstanding and, F therefore, the bank guarantee had not come to an end and was rightly invoked. Coming to the allegation of fraud, it is an admitted fact that in the plaint itself, there was no such allegation. It was initially only in the first application for the grant of injunction that in a paragraph it has been G mentioned that the appellant herein had invoked the bank guarantee arbitrarily. This application contains no facts or particulars in support of the allegation of fraud. A similar bald averment alleging fraud is also contained in the second application for injunction relating to bank guarantee no. 40/47. This is not a case where defendant no. 1 had at any time H alleged fraud prior to the filing of injunction application. The main con- DWARIKESHSUGAR!ND. LID; _v._ PREMHEAVYENGG. WORKSLID.[KIRPAl,J.] 199 tract, pursuant to which the bank guarantees were issued, was not sought A to be avoided by alleging fraud, nor was it at arty point of time alleged that the bank guarantee was issued because any fraud had been played by the appellant. We have no manner of doubt that the bald assertion of fraud had been made solely with a view to obtain an order of injunction. In the absence of established fraud and not a mere allegation of fraud and that B also having been made only in the injunction application, the cdurt could not, in the present case, have granted an injunction relating to the encashment of the bank guarantees. It is unfortunate that the High Court did not consider it necessary to refer to various judicial pronouncements of this Court in which the prinC ciples which have to be followed while examining an application for grant of interim relief have been clearly laid down. The observation of the High Court that reference to judicial decisions will not be of much importance was clearly a method adopted by it in avoiding to follow and apply the law as laid down by this Court. Yet another serious error which was committed D by the High Court, in the present case, was· not to examine the terms of the bank guarantee and consider the letters of invocation which had been written by the appellant. If the High Court had taken the trouble of examining the documents on record, which had been referred to by the trial court, in its order refusing to grant injunction, the court would not have granted the interim injunction. We also do not find any justification E for the High Court in invoking the alleged principle of unjust enrichment to the facts of the present case and then deny the appellant the right to encash the bank guarantee. If the High Court had taken the trouble to see the law on the point it would have been clear that in encashment of bank guarantee the applicability of the principle of undue enrichment has no F application. C We are constrained to make these observations with regard to the manner in which the High Court had dealt with this case because this is not an isolated case where the courts, while disobeying or not complying with the law laid down by this Court, have at time been liberal in granting G injunction restraining encashment of bank guarantees. It is unfortunate, that notwithstanding the authoritative pronouncements of this Court, the High Courts and the courts subordinate thereto, still seem intent on affording to this Court innumerable opportunities for H 200 SUPREME COURT REPORTS [1997] SUPP. 1 S.C.R. A dealing with this area of law, thought by this Court to be well settled. When a position, in law, is well settled as a result of judicial pronouncement of this Court, it would amount to judicial impropriety to say the least, for the subordinate courts including the High Courts to ignore the settled decisions and then to pass a judicial order which is clearly contrary B to the settled legal position. Such judicial adventurism cannot be permitted and we strongly deprecate the tendency of the subordinate courts in not applying the settled principles and in passing whimsical orders which necessarily has the effect of granting wrongful and unwarranted relief to one of the parties. It is time that this tendency stops. ## c Before concluding we think it appropriate to mention about the conduct of the respondent - bank which has chosen not to be represented in this case. From the facts stated hereinabove it appears to us that the respondent bank has n,ot shown professional efficiency, to say the least, and has acted in a partisan manner with a view to help and assist respondent D no. 1. At the time when there was no restraint order from any Court, the bank was under a legal and moral obligation to honour its commitments. It, however, failed to do so. It appears that the bank deliberately dragged its feet so as to enable respondent no. 1 to secure favourable order of injunction from the Court. Such conduct of a bank is difficult to appreciate. E We do not wish to say anything more lest it may feel that it will be prejudicial in the event of the appellant taking action against it. ,. For the aforesaid reasons this appeal is allowed. The judgment and order of the Allahabad High Court dated 10th September, 1996 in revision petition no. 257 of 1996 is set aside and the order of the trial court dated . p 20th August, 1996 dismissing the injunction application is restored. The appellant would be entitled to costs which are quantified at Rs. 20,000. v.s.s. Appeal allowed.
End of Judgment Record
Browse All Supreme Court of India (1997) Decisions
1997-12-17

Sharad Vasant Kotak and Ors. v. Ramniklal Mohanlal Chawda and Anr.

This Supreme Court judgment concerns the maintainability of a suit for dissolution of partnership and accounts under the Indian Partnership Act, 1932, as amended by the Maharashtra Amendment of 1984 (Section 69(2A)). The Paramount Builders partnership, registered in 1980 with seven partners (Kotak family and Chawda family), underwent changes after the death of partner Mohanlal Chawda in 1986, when his widow was inducted as a partner. A series of deeds (1986, 1992) reconstituted the firm without informing the Registrar of Firms, raising questions about registration and the applicability of Section 69(2A), which restricts suits to registered firms where the suing partner is shown in the Register of Firms. The Bombay High Court Division Bench held that reconstitution does not cancel registration and that amendments to pleadings were permissible; it concluded that Section 69(2A) does not bar the suit. The appellants argued that induction of a new partner dissolves the old firm and requires a fresh registration, while the respondents contended that dissolution and reconstitution are distinct concepts and that registration continues despite changes. The Supreme Court ultimately held that the firm was merely reconstituted, not dissolved; non‑compliance with registration provisions may attract penalties, but does not erase registration. The Special Leave Appeal was dismissed, with no costs.

1997-11-18

National Insurance Co. Ltd. v. Santro Devi and Ors.

National Insurance Co. Ltd. v. Santro Devi deals with a motor-accident compensation claim under the Motor Vehicles Act. A Tribunal found that the offending vehicle was driven by a person who held a valid driving licence, which had been renewed on the date of the accident, and the claimants were accordingly awarded compensation. The Punjab and Haryana High Court affirmed this finding on appeal but then referred the matter to a full Bench to decide a legal question: whether a forged or fake licence, if renewed, would be treated as a valid licence for purposes of liability. The full Bench answered that a forged licence would not become valid under the Motor Vehicles Act and that an insured, bonafide believing in the licence’s validity, would still incur liability toward third parties under the policy; several related conclusions regarding insurer liability were laid down. The Insurance Company challenged these High Court observations. The Supreme Court allowed the appeal in part, holding that the claimants were rightly granted compensation on the facts, and that the High Court’s observations on forged licences were obiter and not binding precedents since there was concurrent factual finding that the driver held a valid licence renewed on the date of the accident. The Court affirmed the substantive order and dismissed the related Special Leave Petition.

1997-02-03

JAIPUR DEVELOPMENT AUTHORITY v. SITA RAM AND ORS.

This appeal concerns the validity of notifications under Section 52 of the Rajasthan Urban Improvement Act, 1959, by which the Jaipur Development Authority sought to continue land acquisition even after the repeal of the 1959 Act, and after a fresh notification was issued in 1984 under the Jaipur Development Authority Act. The Rajasthan High Court had held that unless the master plan scheme under the JDA Act had been properly framed, the notification issued under Section 52 was not valid in law. The appellants challenge this proposition, contending that framing of a scheme is not a mandatory pre-condition for acquisition and that the 1984 notification cannot be quashed solely for lack of a sanctioned scheme. The matter traces several precedents: Pratap v. State of Rajasthan; State of Tamil Nadu v. Mohd. Yousef; Narain v. State of Rajasthan; and Urban Improvement Trust v. State of Rajasthan. The decision ultimately clarifies that framing of a scheme is not a required pre-condition for land acquisition; overruled or distinguished interpretations in earlier decisions, especially Tamil Nadu Yousef, Krishnan’s later formulation and Narain’s approach. The Court endorses the view that the notification for acquisition cannot be invalidated on account of non-framing of a scheme, and thus allows the appeals, setting aside the High Court’s judgment and dismissing the writ petitions, with no costs to either side.

1997-07-07

Delhi Administration (Now Govt. of N.C.T. Delhi) through the Chief Secretary, Delhi and Ors. v. Nand Lal Pant and Anr.

Delhi Administration v. Nand Lal Pant concerns the scope of promotion from the cadre of Trained Graduate Teachers (TGT) to Post-Graduate Teachers (Sanskrit) in the Delhi education cadre, and the remedy when a sanctioned channel does not exist. Pant, appointed as a TGT in 1974 and confirmed, was asked to officiate in the PGT (Sanskrit) post when it became vacant after the retirement of S.N. Sastri, a Sanskrit-qualified officer. He repeatedly sought promotion to the PGT position, which the Delhi High Court granted in 1996, directing promotion with effect from 1986 and ordering payment of consequential benefits. The Delhi Administration appealed on the ground that there was no direct promotional channel from TGT (General) to PGT (Sanskrit), and that the SC caste reservation for the post should be respected. The Supreme Court accepted that there is no direct channel, but noted Pant’s extended officiation in the PGT post since 1986. It held that justice required a workable remedy: creation of a supernumerary PGT (Sanskrit) post in any school or directorate, allowing Pant to continue there until retirement, with pay from the date of creation. The decision clarifies it as a discretionary remedy and not a general precedent, and it disposed of the appeal with no costs.