DLF Homes Panchkula Pvt. Ltd v. D.S. Dhanda, ETC. ETC.

Case / Petition Number:
Civil Appeal Nos. 4910-4941 of 2019; Civil Appeal Nos. 4942-4945 of 2019 (SLP(C) Nos. 3623-3654 of 2019; 4363-4366 of 2019)
Neutral Citation:[2019] 7 SCR 1061

Case Synopsis & Summary

DLF Homes Panchkula Pvt. Ltd. (the appellant) challenged orders of the State Consumer Disputes Redressal Commission (SCDRC) and the National Consumer Disputes Redressal Commission (NCDRC) directing possession, damages, and interest for delay in delivery of flats in the DLF Valley project in Panchkula, Haryana. The Buyer’s Agreements contemplated possession within 24 months from the filing date, with a Rs. 10 per sq. ft. per month delay charge. The builder’s stay during 2012, occasioned by a Supreme Court order, allegedly delayed completion; the appellant obtained consent from complainants to extend possession to about 36 months, with possession expected around February 2014. The SCDRC initially ordered possession and compensation; the NCDRC partly modified. The Court’s approach emphasizes that compensation must be just and commensurate with loss, not arbitrary or “by rule of thumb,” and that punitive damages should not be awarded for delays beyond the builder’s control. The judgment consolidates two strands: (i) delay in possession and consequent compensation, including interest, and (ii) refunds in separate appeals, with a uniform framework based on consent orders granting 9% interest per annum rather than higher rates. It directs the builder to issue occupation certificates, engage a maintenance agency, complete maintenance within two months, and pays Rs.50,000 per complaint for mental agony and litigation expenses, with interest capped at 9% for the delay period. The appeals are disposed of with modifications to the earlier awards, aligning with consent-based settlements.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Dr. Dhananjaya Y. Chandrachud
  • Hemant Gupta
Judgment Date
2019-05-10
Court Decision / Holding
The Court held that compensation cannot be arbitrary or punitive and cannot rely on a mere rule-of-thumb approach. It acknowledged the extended 36-month period granted by consent and directed the builder to implement a settlement framework, including issuing occupation certificates, engaging a maintenance agency, completing maintenance within two months, and paying interest at 9% per annum for the two months following offer of possession; consolidated mental agony and litigation cost of Rs. 50,000 per complaint; and, in the case of transfers, interest at 9% from the expiry of three years or from the transfer date, whichever is later. For refunds in the separate appeals, the Court reduced interest to 9% per annum from the date of deposit to refund, and maintained Rs. 35,000 as costs. The overall disposition was to dispose of the appeals with modifications that align with consent-based settlements rather than open-ended damages.
Final Disposition
Appeals disposed of with directions reflecting consent-based settlements; modification of awards to 9% interest on deposits/refunds and other specified terms.

Parties to the Case

Appellants / Petitioners

  • DLF Homes Panchkula Pvt. Ltd.

Respondents

  • D.S. Dhanda
  • Others

Legal Representation & Advocates

Counsels for Petitioners

  • • C. U. Singh
  • • Ruby Singh Ahuja
  • • Seema Sundd
  • • Prabhat Ranjan
  • • Alabhya Dhamija
  • • Shreyansi Goel
  • • Pravin Bahadur
  • • Nakul Gandhi
  • • Saurabh Kumar
  • • Sanjeet Ranjan
  • • Sahil Monga
  • • Sonali Jain

Counsels for Respondents

  • • Ramachandran
  • • Isha Aggarwal
  • • Sachin Jain
  • • Dr. Rau P.S. Girwar
  • • Archana Arora
  • • Shashi Kiran
  • • Arjun Sain
  • • Manoj Jain

Provisions of Law Cited

Consumer Protection Act, 1986

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant builder argued that construction could not be completed within the original two-year period due to a stay on construction ordered by the Supreme Court, spanning roughly eight months in 2012. It obtained consent from respondents to extend the possession deadline to about 36 months (around February 2014). It maintained that the flats were completed and occupation certificates were obtained for completed units. The appellate argument emphasized that compensation should be based on the agreed consequence of delay in the buyer’s agreement (Rs. 10 per sq ft per month) and that the consumer forums cannot award damages under multiple heads or on a rule-of-thumb basis. It relied on prior consent orders granting interest at 9% per annum and urged a harmonized, settlement-based approach, with possession delivered and maintenance addressed via a real estate maintenance agency. It also challenged awards of punitive damages as not warranted by the circumstances and urged limits based on consent and the contract.

Contentions of Respondents

Respondents contended that delays caused substantial financial and emotional harm, and sought compensation for loss of use, mental agony, and litigation expenses, in addition to interest on deposits. They argued that SCDRC and NCDRC independently awarded compensation on multiple heads for the same default, effectively granting punitive damages. They pressed for interest at higher rates and for enforcement of the original terms and extension of possession rights. They relied on the extended construction period but asserted that the developer’s conduct and the delay caused by the stay should be reflected in the compensation. They supported the need for interest on the deposited amounts from the promised date, as a measure of the loss of use of funds, and sought maintenance and other ancillary costs as part of the relief, with appropriate timelines for possession and registration.”},

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (3)

Case NameCitationTreatmentExplanation
Secretary, Irrigation Department, Government of Orissa & Others v. G.C. Roy(1992) 1 SCC 508PositiveUsed to justify that compensation may include interest for deprivation of use of money when legitimately entitled.
DLF Homes Panchkula Pvt. Ltd. and Another Etc. v. Himanshu Arora and Another, Etc.[2019] 7 SCALE 678PositiveEarlier consent-based ruling granting 9% interest; relied upon for determining the applicable rate of interest.
DLF Homes Panchkula (P.) Ltd. v. Sushila Devi and Another[2019] 2 SCR 739Mentioned OnlyReferred to in the judgment but not a core controlling authority for the decision.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•5,615 words•~26 min read

In The Court Record

DLF Homes Panchkula Pvt. Ltd v. D.S. Dhanda, ETC. ETC.

1061 # [2019] 7 S.C.R. 1061 DLF HOMES PANCHKULA PVT. LTD A v. D.S. DHANDA, ETC. ETC. (Civil Appeal Nos. 4910-4941 of 2019) MAY 10, 2019 B ## **[DR. DHANANJAYA Y CHANDRACHUD AND** ## **HEMANT GUPTA, JJ.]** _Consumer Protection Act, 1986 – Respondents-Complainants booked built up flats for purchase in one of the project of the_ C _appellant – Buyer’s Agreements executed– Possession of the unit was to be delivered within 24 months from the date of execution of the agreement, failing which the appellant was liable to pay Rs. 10/ - per sq. ft. per month for the period of delay – Complaints filed before State Consumer Dispute Redressal Commission (SCDRC)_ D _alleging delay in delivery of possession – Appellant_ inter alia _pleaded that construction could not be completed because of the stay on construction granted by Supreme Court which opearted for about 8 months – SCDRC directed the appellant to hand over the physical possession of the units allotted to the respondents, complete in all respects within four months – National Consumer Dispute Redressal_ E _Commission (NCDRC) partially modified the order – On appeal, held: There is no surviving dispute in respect of extended period of handing over possession available to the appellant i.e 36 months, in view of the consent it obtained from the respondents to extend the period of handing over possession further by one year– It is_ F _categorical stand of the appellant that the flats have been completed and occupation certificate has also been obtained – SCDRC and NCDRC awarded compensation under multiple heads on account of singular default of not handing over possession–For delay in handing over possession, the consumer is entitled to the consequences agreed at the time of executing buyer’s agreement –_ G _Though the 1986 Act empowers the authorities to award compensation for any loss or injury including building damages but the order of NCDRC or SCDRC awarding compensation is by rule of thumb, without any foundation on judicially recognised principles – Complainant entitled to interest as offered, for not_ D G H 1061 1062 SUPREME COURT REPORTS [2019] 7 S.C.R. A _handing over possession, but present is not a case to award special punitive damages as one of the causes for late delivery of possession was beyond the control of the appellant – In view of the settlement proposal submitted by the appellant in earlier two set of appeals before Supreme Court in respect of the same project and to settle any further controversy, directions issued to the appellant._ - B _Consumer Protection Act, 1986 – Respondents-Complainants booked built up flats for purchase in one of the project of the appellant – Amount deposited by the respondents – Delay in delivery of possession of the flats – Award of interest – Held: Amount of interest is the compensation to the beneficiary deprived of the use of the investment made by the complainant – Therefore, such interest will take into its ambit, the consequences of delay in not handing over possession._ C _Words & Phrases – “Interest” – Meaning of – Discussed._ ## D **Disposing of the appeals, the Court** **HELD: 1.1 The similar dispute in respect of same project came up for decision before Supreme Court in** _**DLF Homes Panchkula Pvt. Ltd. and Another Etc. v. Himanshu Arora and Another, Etc..**_ **The said set of appeals were decided on consent** E **granting interest at the rate of 9 per cent per annum. Subsequently, another set of appeals, Civil Appeal Nos. 2285-2330 of 2019 titled** _**DLF Homes Panchkula (P.) Ltd. vs. Sushila Devi and Another**_ **came up for decision before Supreme Court including appeals filed by the Appellants as well as by the Complainants. Such appeals were also decided by consent. [Paras 6, 7] [1070-C-E]** ## F **1.2 The appellant offered for built up 1775 flats in its project the DLF Valley in Sector 3, Kalka-Pinjore Urban Complex, Panchkula, Haryana. Some of the disputes settled in earlier two rounds of appeals, whereas, many complaints are still pending before different fora. There is no surviving dispute in respect of** G **extended period of handing over possession available to the Appellant i.e. 36 months. By virtue of such extended period, the possession was required to be handed over on or about 11.02.2014. It is categorical stand of the Appellant that the flats have been completed and occupation certificate obtained from** H DLF HOMES PANCHKULA PVT. LTD v. D.S. DHANDA, ETC. ETC. 1063 **the Office of Director, Town and Country Planning Department** A **of State of Haryana. The NCDRC rightly held that compensation for loss, mental agony, litigation expenses and hardship, uncertainty and helplessness can neither be meagre nor exorbitant but has to be just and commensurate with the loss and injury. [Paras 12-14] [1072-B-D]** B **1.3 The District Forum under the Consumer Protection Act, 1986 is empowered** _**inter-alia**_ **to order the opposite party to pay such amount as may be awarded as compensation to the consumer for any loss or injury suffered by the consumer due to the negligence of the opposite party including to grant punitive damages. But the forums under the Act cannot award interest and/or compensation by applying rule of thumb. The order to grant interest at the maximum of rate of interest charged by nationalised bank for advancing home loan is arbitrary and no nexus with the default committed. The appellant has agreed to deliver constructed flats. For delay in handing over possession, the consumer is entitled to the consequences agreed at the time of executing buyer’s agreement. There cannot be multiple heads to grant of damages and interest when the parties have agreed for payment of damages at the rate of Rs.10/- per sq. ft. per month. Once the parties agreed for a particular consequence of delay in handing over of possession then, there has to be exceptional and strong reasons for the SCDRC/NCDRC to award compensation at more than the agreed rate. Though the 1986 Act empowers the authorities to award compensation for any loss or injury including building damages but the order of NCDRC or that of SCDRC of awarding compensation is without any foundation being laid down by the complainant on judicially recognised principles and is by rule of thumb. Therefore, grant of compensation under various heads granted by the NCDRC cannot be sustained. The amount of the interest is the compensation to the beneficiary deprived of the use of the investment made by the complainant. Therefore, such interest will take into its ambit, the consequences of delay in not handing over his possession. The SCDRC as well as NCDRC awarded compensation under different heads on account of singular default of not handing over possession. Such award under various heads in respect of the same default is not** C D E F G H 1064 SUPREME COURT REPORTS [2019] 7 S.C.R. - A **sustainable. Thus, the complainant is entitled to interest from the Appellant for not handing over possession as projected as is offered by it but it is not a case to award special punitive damages as the one of the causes for late delivery of possession was beyond the control of the Appellant. Therefore, in view of the settlement proposal submitted by the Appellant in earlier two set of appeals** - B **in respect of same project, and to settle any further controversy, the Appellant is directed as follows: i) To send a copy of the occupation certificate to the Complainants along with offer of possession. The Appellant shall also direct the Jones Lang LaSalle- the real estate maintenance agency, engaged by the** - C **Appellant to undertake such maintenance works as is necessary on account of damage due to non-occupation of the flats after construction etc. ii) It shall be open to the Complainants to seek the assistance of the maintenance agency to attend to the maintenance work which may arise on account of non-occupation or on account of natural vagaries. iii) Such maintenance work** - D **shall be completed by the Appellant within two months of the offer of possession but the payment of interest at the rate of 9 per cent per annum will be for a period of two months from the date of offer of possession in all situations. iv) Since the Complainants have been forced to invoke jurisdiction of the** - E **consumer forums, they shall be entitled to consolidated amount of Rs. 50,000/- in each complaint on all accounts such as mental agony and litigation expenses etc. The complainant shall not be entitled to any other amount over and above the amount mentioned above. v) In case, the original allottee has transferred the flat, the transferee shall be entitled to interest at the rate of 9** - F **per cent per annum from the date of expiry of three years from the agreement or from the date of transfer, whichever is later. [Paras 16-19] [1072-H; 1073-A-H; 1074-A-G]** **CIVIL APPEAL NOS.4942-4945 OF 2019** - G **(@SLP (C) Nos. 4363-4366 of 2019)** **1.4 The grant of interest at the rate of 15% by SCDRC is highly excessive. Since in other two set of appeals decided earlier, Supreme Court had awarded interest at the rate of 9% per annum on the amount of refund, therefore, the order of SCDRC stand** H DLF HOMES PANCHKULA PVT. LTD v. D.S. DHANDA, ETC. ETC. 1065 **modified so as to pay interest at the rate of 9% per annum from** A **the date of deposit till the date of refund. However, in case any transfer of the flat, such interest will be payable from the date of expiry of three years from the date of agreement or from the date of transfer whichever is later. The Costs of Rs. 35,000/imposed by the SCDRC is maintained. The amount of refund be** B **paid to the Complainants within two months along with the costs. [Paras 23-27] [1075-E-G]** _Secretary, Irrigation Department, Government of Orissa & Others vs. G.C. Roy_ **(1992) 1 SCC 508 : [1991] 3 Suppl. SCR 417 – relied on.** C _DLF Homes Panchkula Pvt. Ltd. And Another Etc. v. Himanshu Arora and Another, Etc._ **[2019] 7 SCALE 678 ;** _DLF Homes Panchkula (P.) Ltd. v. Sushila Devi and Another_ **[2019] 2 SCR 739 – referred to.** ## **Case Law Reference** |||||||| |---|---|---|---|---|---|---| ||||**Case**|**Law Reference**||D| |**[2019]**|**7**|**SCALE 678**||**referred to**|**Para 6**|| |**[2019]**|**2**|**SCR 739**||**referred to**|**Para 7**|| |**[1991]**|**3**|**Suppl. SCR**|**417**|**relied on**|**Para 18**|| CIVIL APPELLATE JURISDICTION : Civil Appeal Nos. 49104941 of 2019. E From the Judgment and Orders dated 24.10.2018 and 12.12.2018 of the National Consumer Disputes Redressal Commission, New Delhi in First Appeal Nos. 853, 1144, 1237, 1239, 1240, 1306, 1307, 1308, 1309, 1310, 1311, 1312, 1314, 1356, 854 and 855 of 2016. F With C.A. Nos. 4942-4945 of 2019. C. U. Singh, Sr. Adv., Ms. Ruby Singh Ahuja, Ms. Seema Sundd, Prabhat Ranjan, Alabhya Dhamija, Ms. Shreyansi Goel, Pravin Bahadur, Nakul Gandhi, Saurabh Kumar, Sanjeet Ranjan, Sahil Monga, Ms. Sonali Jain (for M/S. Karanjawala & Co.), Advs. for the Appellant. G Amarjeet Singh, Narender Yadav, Savinder Singh, Anant Agarwal, Ms. Sweta Rani, Rajesh Sharda, Akshay Sharma, Nikilesh H 1066 SUPREME COURT REPORTS [2019] 7 S.C.R. - A Ramachandran, Ms. Isha Aggarwal, Sachin Jain, Dr. Rau PS Girwar, Ms. Archana Arora, Ms. Shashi Kiran, Arjun Sain, Manoj Jain, Advs. for the Respondents. The Judgment of the Court was delivered by ## **HEMANT GUPTA, J.** - B CIVIL APPEAL NOS.4910-4941 OF 2019 (@ SLP(C) Nos. 3623-3654 OF 2019) 1. Leave granted. 2. The present appeals are directed against orders dated C 24.10.2018 & 12.12.2018 passed by the National Consumer Disputes Redressal Commission[1] disposing 16 First Appeals wherein the appeals filed by the Appellant were decided by partially modifying the order passed by the State Consumer Disputes Redressal Commission[2] on 02.06.2016 wherein SCDRC directed the Appellant to hand over the D physical possession of the units allotted to the respondents (Complainants), complete in all respects within a period of four months. However, for facility of reference, facts are taken from the complaint filed by Shri D.S. Dhanda. The SCDRC issued the following directions: - “Consumer Complaint bearing No. 94 of 2016, titled as D.S. - E Dhanda Vs DLF Homes Panchkula Private Limited and anr. The opposite parties are jointly and severally directed as under:- 1. To hand over physical possession of the unit, allotted in favour of the complainant, complete in all respects, as per the terms and conditions of the Agreement, to the complainant, within a F period of four months, from the date of receipt of a certified copy of this order, on payment of the amount, legally due against him. 2. To execute and get registered the sale deed, in respect of the unit, in question, within one month from the date of handling G over possession, as indicated in Clause (i) above, on payment of registration charges and stamp duty, by the complainant, directly to the Registering Authorities concerned. - 1 NCDRC - H 2 SCDRC DLF HOMES PANCHKULA PVT. LTD v. D.S. DHANDA, ETC. 1067 ETC. [HEMANT GUPTA, J.] 3. To pay compensation, by way of interest @ 12% p.a., on the A deposited amount, to the complainant, from 10.02.2014 (promised date in view of the extension sought vide letter dated 05.06.2013 i.e. 12 months after the stipulated date as per Agreement i.e. from 10.02.2013) to 31.05.2016, within 2 months, from the date of receipt of a certified copy of this B order, failing which, the said amount shall carry penal interest @ 15% p.a. instead of 12% p.a., till realization. 4. To pay compensation by way of interest @12% p.a. on the deposited amount, due to the complainant w.e.f. 01.06.2016, onwards (per month) by the 10[th] of the following month, failing which, the same shall also carry penal interest @ 15% p.a., instead of 12% p.a., from the date of default, till the delivery of possession. 5. To pay compensation by way of interest @12% p.a. on the deposited amount, due to the complainant w.e.f. 01.06.2016, onwards (per month) by the 10[th] of the following month, failing which, the same shall also carry penal interest @ 15% p.a., instead of 12% p.a., from the date of default, till the delivery of possession. 6. To pay cost of litigation, to the tune of Rs. 50,000/-, to the complainant, within two months from the date of receipt of a certified copy of this order, failing which, the same shall also carry interest @12% p.a., from the date of filing the complaint till realization.” 3. The Appellant preferred appeal against such order passed by SCDRC before the NCDRC. The NCDRC issued inter-alia the following directions: C D E F “(C) Compensation: The compensation for loss and injury, for mental agony and physical harassment, hardship and difficulty, uncertainty and helplessness, can be neither meagre nor exorbitant, but has to be just and equitable, commensurate with the loss and injury (note: it could be less than or more than what the complainant asked for or what the State Commission determined, at the considered wisdom of G H 1068 SUPREME COURT REPORTS [2019] 7 S.C.R. A B C D E F G the adjudicating authority/court in the facts and specificities of the case). And it is always desirable and preferable, to the extent feasible and appropriate in the facts and specificities of a case, that some objective logical criteria be identified and adopted to determine the compensation. The compensation cannot be arbitrary or whimsical, some reasonable and acceptable rational has to be evident subjectivity has to be minimized. We note that the State Commission has given compensation in two parts, one, by way of interest on the deposited amount from the ‘promised’/ assured date after taking in view the extension sought vide letter dated 05.06.2013 i.e. 12 months after the 24 months’ conveyed and understood time period for completing construction and handling over possession, and, two, a lumpsum amount. If compensation comprises of two parts, (i) by way of interest on the deposited amount from the assured date (milestone date) of completing construction and handling over possession to the actual date of handling over possession, and, (ii) lumpsum amount, we find nothing wrong in it. We do not agree with the builder co.’s contentions that interest on the deposited amount should not be provided since it is not a case of refund but a case of delay in possession. The interest on the deposited amount has to be viewed in the light of the purpose for which it is intended. It is but a way of computing compensation for delay in possession that is commensurate with the amount deposited by the complainant, and here it has been computed after adopting a milestone date as per the builder co.’s own (unfair and deceptive) letter of 05.06.2013. There can be and is no question of not agreeing to an endorsing the award of interest from the said milestone date. Here we may however add that the rate of interest also cannot be arbitrary or whimsical, some reasonable and acceptable rationale has to be evident, subjectivity has to be minimized, a logical correlation has to be established. Albeit detailed arithmetic or algebra is not required. Logical (to the extent feasible) objective H DLF HOMES PANCHKULA PVT. LTD v. D.S. DHANDA, ETC. 1069 ETC. [HEMANT GUPTA, J.] parameters should be adopted. Rounding off simplification etc. to make the computation doable could be adopted. We feel it appropriate that, considering that the subject units in question are dwelling units, in a residential housing project, the rate of interest for house building loan for the corresponding period in a scheduled nationalized bank (take, State Bank of India) would be appropriate and logical, and , if ‘floating’/ varying/different rates of interest were/ are prescribed, the higher rate of interest should be taken for this instant computation. We also feet it appropriate and logical that the lumpsum amount awarded should be commensurate with the period for which there has been delay in possession beyond the milestone date, and be objectively and logically computed so. In our considered view, a sum of Rs. 1 lakh per year from the assured date of handing over possession to the actual date of possession (pro-rata to the nearest whole month, with part month to be taken as one month) would be objective, logical, just and equitable in the facts and specificities of the case. A B C D ## (D) Cost of litigation: In respect of cost of litigation, too, just and equitable cost is necessary (this, by its very nature needs no elaboration). E In our considered view, cost of litigation of Rs. 1 lakh is just and appropriate in the facts and specificities of the case.” 4. The Complainant book a built up flat for purchase in pursuance of a brochure on 30.03.2010 in a project known as “DLF Valley” in Sector 3, Kalka-Pinjore Urban Complex, Panchkula, Haryana. The Buyer’s Agreement was executed on 11.02.2011. The possession of the unit was contemplated to be delivered within 24 months from the date of execution of the agreement i.e. up to 10.2.2013 failing which the Appellant was liable to pay Rs. 10/- per sq. ft. per month for the period of delay. The complaints were filed before the SCDRC alleging delay in delivery of possession of the escalation free flats and compensation on account of delay in handing over possession including mental agony and litigation expenses etc. F G H 1070 SUPREME COURT REPORTS [2019] 7 S.C.R. A 5. In the return, the stand of the Appellant was, construction could not be completed on account of stay granted on construction activities by this Court which operated from 19.04.2012 to 12.12.2012. Thereafter, the Appellant sought consent from the Complainant to extend the period of handing over possession by one year vide letter dated 05.06.2013. In the alternative, option was given to get back the money deposited by the B Complainant along with simple interest at the rate of 9 per cent per annum. It is also pointed out that on the day reply was filed, construction of 258 independent floors was complete and another 1517 built-up units were near completion. Even occupation certificate has been received for the units for which construction was complete. C 6. The similar dispute in respect of same project came up for decision before this Court in **DLF Homes Panchkula Pvt. Ltd. and Another Etc. v. Himanshu Arora and Another, Etc.[3]** . The said set of appeals were decided on consent granting interest at the rate of 9 per cent per annum. D 7. Subsequently, another set of appeals, Civil Appeal Nos. 22852330 of 2019 titled **DLF Homes Panchkula (P.) Ltd. vs. Sushila Devi and Another** came up for decision before this Court including appeals filed by the Appellants as well as by the Complainants. Such appeals were also decided by consent. The agreed terms are as under: E “(a) In all Refund cases, the award of interest @ 9% would be payable in respect of deposits from the day they were made till the date of refund. (b) In cases where, upon transfer, a subsequent purchaser had stepped into the shoes of the original allottee and had prayed for F Refund, the reckoning date for computing the interest be from the date of his transfer in respect of all the amounts that were deposited by the original allottee and if any subsequent deposits were made by the transferee, from the dates of such deposits; (c) In cases where Possession was sought, the period available to G the Developer under the agreement being three years (that is to say original period of two years which was extendable, at the option of the Developer, by further period of one year) ought not to be computed while calculating compensation in the form of 3 C.A No. 11097/2018 with C.A. Nos. 11098-11138 of 2018 decided on 19.11.2018 H DLF HOMES PANCHKULA PVT. LTD v. D.S. DHANDA, ETC. 1071 ETC. [HEMANT GUPTA, J.] interest. Therefore, the period to be reckoned shall be after expiry A of three years from the date of agreement and in respect of such period the compensation shall be at the same rate of 9%. (d) In Possession cases, if there was any transfer and the transferee had stepped into the shoes of the original allottee, the compensation shall be paid from the date of expiry of three years from the agreement as aforesaid or from the date of transfer, whichever is later.” 8. Learned Senior Counsel for the Appellant submitted that in terms of the consent orders passed by this Court, the consumer complaints be decided in terms of the Court orders passed in two sets of appeals that is the cases of delay in handing over possession as well the cases, where the complainants have sought refund of the amount deposited. However, it is contended that certain allottees are not taking possession so as to earn interest at the rate of 9 per cent per annum which is more than a contractual compensation of Rs.10/- per sq. ft. per month for the delayed possession as well as the loss of rent per month pleaded by the allottees such as D.S. Dhanda (F.A. No. 853/2016), Sandeep Malik (F.A. No. 1312/2016), Bijender Singh Sangwan (F.A. No. 1314/2016), Kanwal Mohan (F.A. No. 1356/2016). 9. It is contended that since the rental value is not more than the compensation awarded by this Court in the consent order referred to above, therefore, some of the allottees are intentionally not taking possession so as to continue to earn interest under the guise that it is the Appellant who is not handing over the possession. It is contended that in terms of the chart produced in **Sushila Devi’s case (supra)** , 9 per cent interest is payable till two months after offer of possession though such clause does not find specifically mentioned in the order passed by this Court. 10. It is argued that the Appellant will hand over possession only after obtaining occupancy certificate from the Town and Country Planning Department of the State of Haryana and after ensuring that the maintenance works are taken care of by Jones Lang LaSalle - the international real estate maintenance agency. B C D E F G 11. On the other hand, learned counsel for the allottees argued that the possession is being offered of incomplete building and that allottees H 1072 SUPREME COURT REPORTS [2019] 7 S.C.R. - A are entitled to compensation on account of the mental agony and litigation expenses awarded by SCDRC and as modified by NCDRC. 12. We have heard learned counsel for the parties and find that the appellant offered for built up 1775 flats in its project the DLF Valley in Sector 3, Kalka-Pinjore Urban Complex, Panchkula, Haryana. Some B of the disputes settled in earlier two rounds of appeals, whereas, many complaints are still pending before different fora. 13. There is no surviving dispute in respect of extended period of handing over possession available to the Appellant i.e. 36 months. By virtue of such extended period, the possession was required to be handed C over on or about 11.02.2014. The present set of appeals relates to the Complainants claiming possession of the flats allotted to them in the DLF Valley. It is categorical stand of the Appellant that the flats have been completed and occupation certificate obtained from the Office of Director, Town and Country Planning Department of State of Haryana. D 14. The learned NCDRC rightly held that compensation for loss, mental agony, litigation expenses and hardship, uncertainty and helplessness can neither be meagre nor exorbitant but has to be just and commensurate with the loss and injury. After holding so, the learned NCDRC found that the Complainants are not entitled to stipulated amount on account of delay in handing over possession but damages on the E amount deposited apart from interest on the amount so deposited. D 15. A perusal of the order passed by NCDRC shows that it approved the directions of the SCDRC granting interest on the amount deposited from the assured date and a lumpsum compensation on the deposited amount from the assured date of completing construction and F handing over possession to the actual date of handing over possession. The NCDRC thereafter awarded interest on the amount deposited by the complainants at the maximum rate of interest on which the House Building Loans are granted by nationalized Bank such as the State Bank of India; awarded a sum of Rs. 1,00,000/- per year from the assured G date of handing over possession to the actual date of compensation and another sum of Rs. 1,00,000/- as cost of litigation. 16. The District Forum under the Consumer Protection Act, 1986[4] is empowered _inter-alia_ to order the opposite party to pay such amount as may be awarded as compensation to the consumer for any loss or H 4 1986 Act DLF HOMES PANCHKULA PVT. LTD v. D.S. DHANDA, ETC. 1073 ETC. [HEMANT GUPTA, J.] injury suffered by the consumer due to the negligence of the opposite party including to grant punitive damages. But the forums under the Act cannot award interest and/or compensation by applying rule of thumb. The order to grant interest at the maximum of rate of interest charged by nationalised bank for advancing home loan is arbitrary and no nexus with the default committed. The appellant has agreed to deliver constructed flats. For delay in handing over possession, the consumer is entitled to the consequences agreed at the time of executing buyer’s agreement. There cannot be multiple heads to grant of damages and interest when the parties have agreed for payment of damages at the rate of Rs.10/- per sq. ft. per month. Once the parties agreed for a particular consequence of delay in handing over of possession then, there has to be exceptional and strong reasons for the SCDRC/NCDRC to award compensation at more than the agreed rate. 17. Though the 1986 Act empowers the authorities to award compensation for any loss or injury including building damages but the order of NCDRC or that of SCDRC of awarding compensation is without any foundation being laid down by the complainant on judicially recognised principles and is by rule of thumb. Therefore, we find that grant of compensation under various heads granted by the NCDRC cannot be sustained. 18. This Court in a judgment reported as **Secretary, Irrigation Department, Government of Orissa & Others vs. G.C. Roy[5]** examined the question as to whether an arbitrator has the power to award interest pendente lite. It was held that a person deprived of use of money to which he is legitimately entitled has a right to be compensated for the deprivation which may be called interest, compensation or damages. Thus, keeping in view the said principle laid down in the aforesaid judgment, the amount of the interest is the compensation to the beneficiary deprived of the use of the investment made by the complainant. Therefore, such interest will take into its ambit, the consequences of delay in not handing over his possession. In fact, we find that the learned SCDRC as well as NCDRC has awarded compensation under different heads on account of singular default of not handing over possession. Such award under various heads in respect of the same default is not sustainable. A B C D E F G > 5 (1992) 1 SCC 508 H 1074 SUPREME COURT REPORTS [2019] 7 S.C.R. A B C D 19. Thus, we find that the complainant is entitled to interest from the Appellant for not handing over possession as projected as is offered by it but it is not a case to award special punitive damages as the one of the causes for late delivery of possession was beyond the control of the Appellant. Therefore, in view of the settlement proposal submitted by the Appellant in earlier two set of appeals in respect of same project, and to settle any further controversy, the Appellant is directed as follows: i) To send a copy of the occupation certificate to the Complainants along with offer of possession. The Appellant shall also direct the Jones Lang LaSalle - the real estate maintenance agency, engaged by the Appellant to undertake such maintenance works as is necessary on account of damage due to non-occupation of the flats after construction etc. ii) It shall be open to the Complainants to seek the assistance of the maintenance agency to attend to the maintenance work which may arise on account of non-occupation or on account of natural vagaries. iii) Such maintenance work shall be completed by the Appellant within two months of the offer of possession but the payment of interest at the rate of 9 per cent per annum will be for a period of two months from the date of offer of possession in all situations. E F v) Since the Complainants have been forced to invoke jurisdiction of the consumer forums, they shall be entitled to consolidated amount of Rs. 50,000/- in each complaint on all accounts such as mental agony and litigation expenses etc. The complainant shall not be entitled to any other amount over and above the amount mentioned above. vi) In case, the original allottee has transferred the flat, the transferee shall be entitled to interest at the rate of 9 per cent per annum from the date of expiry of three years from the agreement or from the date of transfer, whichever is later. - G CIVIL APPEAL NOS.4942-4945 OF 2019 (@SLP (C) Nos. 4363-4366 of 2019) 20. Leave granted. H DLF HOMES PANCHKULA PVT. LTD v. D.S. DHANDA, ETC. 1075 ETC. [HEMANT GUPTA, J.] 21. The Complainant in these cases have sought refund of the A amount deposited by them with the Appellant. The learned SCDRC passed an order on 04.08.2017 directing the Appellant as under:- “i. To refund the amounts of Rs. 49,25,461/- alongwith simple interest @ 15% per annum, to the complainant, from the respective dates of deposits, till realization, within 45 days, from the date of receipt of a certified copy of this order, failing which, the Opposite Parties shall pay the aforesaid amounts alongwith simple interest @ 18% per annum, instead of 15% per annum, from the date of default till actual payments; ii. To pay an amount of Rs. 35,000/- as litigation costs, to the complainant, within a period of 45 days from the date of receipt of a certified copy of the order, failing which, the Opposite Parties shall pay the aforesaid amount alongwith simple interest @ 15% per annum from the date of filing the complaint till actual payment.” 22. The appeal filed by the Appellant before NCDRC was dismissed for non-compliance of an order in an application of condonation of delay. Still aggrieved, the Appellants are before this Court. 23. We find that the grant of interest at the rate of 15% by SCDRC is highly excessive. Since in other two set of appeals decided earlier, this Court has awarded interest at the rate of 9% per annum on the amount of refund, therefore, the order of SCDRC stand modified so as to pay interest at the rate of 9% per annum from the date of deposit till the date of refund. 24. However, in case any transfer of the flat, such interest will be payable from the date of expiry of three years from the date of agreement or from the date of transfer whichever is later. B C D E F 25. The Costs of Rs. 35,000/- imposed by the SCDRC is maintained. 26. The amount of refund be paid to the Complainants within two months along with the costs. G Divya Pandey Appeals disposed of. H
End of Judgment Record
Browse All Supreme Court of India (2019) Decisions
2019-09-03

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors.

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors. concerns allegations that Uber, in its ride‑hailing network, abused a dominant position under the Competition Act, 2002. The case arose on appeals challenging the Competition Appellate Tribunal’s order in Appeal No. 31 of 2016, which upheld the Director General’s inquiry into whether Uber’s pricing and incentive practices violated Section 4. The Supreme Court analysed whether the information before it sufficed to constitute a prima facie case under Section 26(1) and whether there was abuse of a dominant position in the National Capital Region. It focused on the two ingredients for abuse: the existence of a dominant position and its misuse. The court considered, based on a statement summarizing driver incentives and a period when Uber reportedly paid high incentives to fleet owners, that Uber may have pursued a pricing strategy that would affect its competitors. Under Section 4(2)(a), abuse includes an unfair price, including predatory pricing. The Court accepted that there is a prima facie case for infringement, yet did not itself interfere with the Appellate Tribunal’s order and dismissed the appeals. It directed the Director General to complete the investigation within six months from today.

2019-07-19

STATE OF BIHAR & ORS. v. DR. CHAITRAYA KUMAR SINGH & ORS.

This civil appeal concerns the reorganization of the erstwhile Bihar into Bihar and Jharkhand in 2000 and the post-allocation transfer of an employee. The first respondent, Dr. Chaitraya Kumar Singh, was initially allocated to Jharkhand in 2007 as an Ayurvedic Medical Officer and, following Union guidelines permitting transfer after final allocations, was re-allocated to Bihar on 6 September 2010 with mutual consent of both States. Bihar issued formal orders, and the respondent joined Jharkhand in 2007; however, he remained in Jharkhand and continued to work there until his retirement on 30 April 2017. A few days before retirement, he filed a writ petition in Jharkhand seeking relief to join Bihar and to be relieved by Jharkhand so that Bihar could accept joining. The Jharkhand High Court confirmed a Single Judge’s order directing Bihar to absorb him. The appellants contend that after the 2010 allocation there was no vacancy, the respondent did not pursue available remedies promptly, and seven years of service in Jharkhand after allocation render absorption in Bihar inappropriate. The Court agrees, noting the allocation to Bihar continued to hold and the petitioner failed to pursue remedies in time; his superannuation in Jharkhand eliminates the basis for absorption. The relieving order issued post-retirement is irrelevant. The appeal is allowed, the High Court’s order set aside, and there shall be no costs; pending applications are disposed.

2019-01-07

PUNJAB FINANCIAL CORPORATION v. M/S PAULBRO LEATHERS PVT. LTD.

Punjab Financial Corporation (lender) filed against Paulbro Leathers Pvt. Ltd. after Paulbro defaulted on a loan. The dispute was settled under the Corporation’s One Time Settlement (OTS) policy on 01.04.2003, and a court-ordered reference to a Chartered Accountant (CA) was made to determine the remaining outstanding balance. After the CA submitted his report, a new dispute arose about the precise liability and how much had been paid, prompting the Corporation to issue a demand for Rs. 49,86,713 which Paulbro disputed in a writ petition before the Punjab and Haryana High Court. The High Court allowed the petition on the ground that the entire exercise had been carried out with consent and no objection had been raised, effectively barring re-opening of the settlement. The appellant challenged these rulings in this Court. The Supreme Court held that the settlement created a fresh dispute arising out of its terms and that the matter must be decided on its merits under the law. It emphasized that the High Court should record how and on what basis Paulbro satisfied the settlement and discharged liability, and if needed, refer the report to another CA. The Court remanded the case to the High Court to decide the writ petition afresh on merits, with a directions to decide expeditiously (preferably within six months).

2019-12-06

RAJESH KUMAR DWIVEDI v. STATE OF U.P. & ANR.

Rajesh Kumar Dwivedi challenges the rejection of his candidature for the post of Instructor in Fitter at Government Industrial Training Institutes in Uttar Pradesh. An advertisement of 17 March 2008 required candidates to possess a certificate in the respective trade from the NCVT, in addition to experience. Dwivedi possessed three National Trade Certificates from Model Industrial Training Institute, Haldwani (one-year basic training in Mechanical, six-month Fitter General module, six-month Metrology and Engineering Inspection), but did not hold a two-year NCVT certificate. The High Court had dismissed his writ petition, holding that three separate courses could not be treated as equivalent to the NCVT qualification. Dwivedi relied on (i) the 16 December 1983 circular clarifying equivalence between the Restructured and Conventional patterns of the Craftsmen Training Scheme, and (ii) 1988 and 1992 UP circulars recognizing MITI, Haldwani training as equivalent to NCVT, including a two-year Fitter trade certificate. The State argued that the amended UP ITI Rules require NCVT certification and that the reliance on circulars cannot override the Rules. The Supreme Court held that the eligibility condition is to have a certificate in the respective trade from NCVT, and that if the State had earlier treated certain qualifications as equivalent through its circulars, such equivalence cannot be disregarded. Consequently, the appellant’s candidature could not be validly rejected, and the State was directed to appoint him within two months. The decision underscores how State-issued equivalence can complement or override rigid Rule-based qualifications when consistently recognized.