Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 2022Division BenchAppeal partly allowed

Divisional Controller Maharashtra State Road Transport Corporation v. Kalawati Pandurang Fulzele

Case / Petition Number:
Civil Appeal No. 463 of 2022
Neutral Citation:[2022] 1 S.C.R. 399

Case Synopsis & Summary

Divisional Controller Maharashtra State Road Transport Corporation v. Kalawati Pandurang Fulzele deals with retrenchment of a workman in a contractual appointment. Kalawati Fulzele was employed as a sweeper by MSRTC at a consolidated honorarium of Rs 500 per month, with increments bringing it to Rs 550. She worked for about four years from 1989/1991 until her termination on 01.08.1994. The Labour Court found that the termination breached Sections 25F and 25G of the Industrial Disputes Act, and directed reinstatement with back wages. The Industrial Court in revision set aside that award, and the High Court, on writ petition, restored reinstatement with back wages. The Division Bench of the Bombay High Court then affirmed reinstatement and back wages. The Supreme Court reversed, noting that her appointment was contractual and on a fixed salary, with termination “till further orders.” There were no specific allegations of unfair labour practices; there was no evidence of ongoing service beyond the contractual term. Given the peculiar facts and the purely contractual basis, the Court held that reinstatement with back wages was not warranted under Sections 25-F and 25-G. Instead, a lumpsum compensation of Rs 3,00,000 was awarded in lieu of reinstatement and back wages, to meet the ends of justice. The appeal was partly allowed, with the modification, and the matter disposed accordingly.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • M. R. Shah
  • B. V. Nagarathna
Judgment Date
2022-01-31
Court Decision / Holding
Appeal partly allowed. The Division Bench’s order reinstating the respondent with back wages is modified. In lieu of reinstatement and back wages, the appellant is directed to pay a lumpsum compensation of Rs. 3,00,000 to the respondent within four weeks; no order as to costs.
Final Disposition
Appeal partly allowed

Parties to the Case

Appellants / Petitioners

  • Divisional Controller, Maharashtra State Road Transport Corporation (MSRTC)

Respondents

  • Kalawati Pandurang Fulzele

Legal Representation & Advocates

Counsels for Petitioners

  • • Ms. Mayuri Raghuvanshi
  • • Vyom Raghuvanshi
  • • Ms. Purvat Wali

Counsels for Respondents

  • • Subhasish Bhowmick
  • • Ms. Manisha Pandey
  • • Harsh Gupta
  • • John Thomas Hrakal

Provisions of Law Cited

Industrial Disputes Act, 1947 — ss. 25F and 25GIndustrial Disputes Act (Bombay) Rules, 1957 — r. 81Industrial Disputes Act, 1947 — s. 2(oo)(bb)Maharashtra Recognition of Trade Unions & Prevention of Unfair Labour Practices Act, 1971 — s. 28 r/w Schedule IV, Item (1)Section 28, Schedule IV, Maharashtra Recognition of Trade Unions & Prevention of Unfair Labour Practices Act, 1971

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant MSRTC submitted that the respondent’s appointment was contractual for a fixed term at a consolidated salary of Rs 500 per month, with no demonstrable unfair labour practice. It contended that Section 2(oo)(bb) is not applicable to a purely contractual or fixed-term arrangement and that reinstatement with back wages was unwarranted given the contractual nature of the employment; the appropriate remedy is a lump-sum compensation.

Contentions of Respondents

The respondent-workman argued that multiple concurrent findings showed breach of Sections 25-F and 25-G of the Industrial Disputes Act, justifying reinstatement with back wages; she had continuous service and termination without proper retrenchment compensation or notice; the Labour Court’s award should be upheld and back wages awarded.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,126 words•~10 min read

In The Court Record

Divisional Controller Maharashtra State Road Transport Corporation v. Kalawati Pandurang Fulzele

399 [2022] 1 S.C.R. 399 ## DIVISIONAL CONTROLLER MAHARASHTRA STATE ROAD A TRANSPORT CORPORATION v. ## KALAWATI PANDURANG FULZELE (Civil Appeal No. 463 of 2022) B JANUARY 31, 2022 ## **[M. R. SHAH AND B. V. NAGARATHNA, JJ.]** _Industrial Disputes Act, 1947:ss. 25F and 25G – Retrenchment of workman – On facts, terminationof workman set aside by courts belowexcept Industrial Court and ordered reinstatement with back wages – Correctness of – Held: Appointment of the workman was on contractual basis at a fixed honorarium, she worked for approximately for four years and there were no allegations on any unfair labour practice – Only finding recorded by the labour court was termination in breach of ss. 25F and 25G – Thus, order of reinstatement and back wages not warranted and instead lumpsum compensation is awarded, modifying the order passed by the labour court – s. 2(oo)(bb) – Industrial Disputes Act (Bombay) Rules, 1957 – r. 81._ C D E ## **Partly allowing the appeal, the Court** **HELD: 1.1 It is true that as such all the three courts below (except the Industrial Court) held the termination of the respondent-workman in breach of Sections 25-F and 25-G of the Industrial Disputes Act and, therefore, the Labour Court ordered reinstatement with back wages. However, it is required to be noted that even as per the appointment order produced by the respondent herself, her appointment was on contractual basis at a fixed salary/honorarium of Rs. 500/- per month. Though, it is a case on behalf of the appellant that her appointment was a fixed term appointment, however, considering the appointment order, the appointment was till further orders. It also cannot be disputed that she worked approximately for four years as a sweeper. As such there were no specific averments/allegations in the complaint on any unfair labour practice. Even there was no specific** F G H 399 400 SUPREME COURT REPORTS [2022] 1 S.C.R. - A **finding recorded by the Labour Court that there was any unfair labour practice adopted by the MSRTC. The only finding recorded by the Labour Court was that the termination was in breach of Sections 25-F and 25-G of the Industrial Disputes Act. In the peculiar facts and circumstances of the case, when the appointment was purely on contractual basis and on a fixed salary/** - B **honorarium of Rs.500/- per month, the order of reinstatement with back wages was not warranted and instead if the lumpsum compensation of Rs. Three lakhs only is awarded in lieu of reinstatement and back wages, it would meet the ends of justice.In view thereof, the impugned judgment and order passed** - C **by the Division Bench of the High Court and the judgment and award passed by the Labour Court ordering reinstatement with back wages is hereby modified and the appellant is directed to pay a lumpsum compensation of Rs.3,00,000/- (Rupees Three Lakhs only) to the respondent, within the stipulated period. [Paras 6-8][403-D-G; 404-A-D]** D CIVIL APPELLATE JURISDICTION: Civil Appeal No. 463 of 2022. From the Judgment and Order dated 30.01.2020 of the High Court of Judicature at Bombay, Nagpur Bench, Nagpur in Letters Patent Appeal E No.37 of 2008 in Writ Petition No.3819 of 2003. Ms. Mayuri Raghuvanshi, Vyom Raghuvanshi, Ms. Purvat Wali, Advs. for the Appellant. Subhasish Bhowmick, Ms. Manisha Pandey, Harsh Gupta, John Thomas Hrakal, Advs. for the Respondent. F The Judgment of the Court was delivered by ## **M. R. SHAH, J.** 1. Feeling aggrieved and dissatisfied with the impugned judgment and order dated 30.01.2020 passed by the High Court of Judicature at G Bombay at Nagpur in LPA No. 37 of 2008 by which the Division Bench of the High Court has dismissed the said appeal and has confirmed the judgment and order passed by the learned Single Judge quashing and setting aside the judgment and order passed by the Industrial Tribunal and restoring the award passed by the Labour Court directing the appellant H > DIVISIONAL CONTROLLER MAHARASHTRA STATE ROAD TRANSPORT 401 CORP. v. KALAWATI PANDURANG FULZELE [M. R. SHAH, J.] to reinstate the respondent with back wages, the employer – Maharashtra State Road Transport Corporation (hereinafter referred to MSRTC”) has preferred the present appeal. 2. That the respondent herein was appointed as sweeper firstly, by written order of appointment dated 08.06.1989 and by another order dated 01.04.1991 on a consolidated honorarium of Rs.500/- per month. That there was an increase of Rs.50/- per month in her consolidated honorarium. She continuously worked as sweeper till she was lastly terminated on 01.08.1994. It appears that her husband was working as a coolie in MSRTC, Chandrapur Depot and suddenly he became blind and his family thus abruptly went in a state of penury. Therefore, she was employed as a sweeper on contractual basis. She filed a complaint under Section 28 read with item (1) of Schedule IV of the Maharashtra Recognition of Trade Unions & Prevention of Unfair Labour Practices Act, 1971 before the Labour Court, Chandrapur against the appellant – MSRTC. In the complaint basically she challenged her termination. It was her case in the complaint that she worked without any break and while terminating her services she was neither paid any retrenchment compensation nor notice of one month or wages in lieu thereof were given to her. No seniority list was either prepared or published and there was violation of Section 25-G and Rule 81 of the Industrial Disputes Act (Bombay) Rules, 1957. 2.1 The Labour Court vide judgment and award dated 20.06.2002 directed the appellant to reinstate her with back wages on the ground that termination was in breach of Sections 25-F and 25-G of the Industrial Disputes Act. The Labour Court also held that the provision of Section 2(oo)(bb) of the Industrial Disputes Act shall be applicable. 2.2 Feeling aggrieved and dissatisfied with the order passed by the Labour Court of reinstatement and back wages, the MSRTC preferred revision petition before the Industrial Court and by judgment and order dated 01.07.2003, the Industrial Court allowed the said Revision Application No.339 of 2002 and set aside the judgment and award passed by the Labour Court dated 20.06.2002 in Complaint (ULPA) No. 135 of 1994. 2.3 Feeling aggrieved and dissatisfied with the judgment and order passed by the Industrial Court, the respondent-workman preferred writ petition before the High Court being Writ Petition No. 3819 of 2003. By judgment and order dated 04.06.2007, the learned Single Judge of the A B C D E F G H 402 SUPREME COURT REPORTS [2022] 1 S.C.R. - A High Court allowed the said writ petition and set aside the judgment and order passed by the Industrial Court and restored the award passed by the Labour Court of reinstatement and back wages. 2.4 Feeling aggrieved and dissatisfied with the judgment and order passed by the learned Single Judge restoring the award passed by the B Labour Court of reinstatement and back wages and holding the termination of the respondent in breach of Sections 25-F and 25-G of the Industrial Disputes Act, the MSRTC preferred the Letters Patent Appeal before the Division Bench of the High Court and by the impugned judgment and order, the Division Bench of the High Court has dismissed the said appeal, hence the MSRTC has preferred the present appeal. C 3. Ms. Mayuri Raghuvanshi, learned counsel appearing on behalf of the appellant has vehemently submitted that in the facts and circumstances of the case, the High Court has committed a grave error in ordering reinstatement of the respondent with back wages. It is submitted that the High Court has materially erred in observing and/or D confirming the order passed by the Labour Court holding that there was a breach of Sections 25-F and 25-G of the Industrial Disputes Act. It is submitted that the appointment of the respondent was on purely contractual basis and for a particular period and on completion of the contractual period, her services were put to end. It is therefore submitted E that when she was serving as a part-timer on contractual basis, Section 2(oo)(bb) of the Industrial Disputes Act shall not be applicable and therefore there is no question of breach of Sections 25-F and 25-G of the Industrial Disputes Act as held by the Labour Court and confirmed by the High Court. F 3.1 Making above submissions, it is prayed to allow the present appeal. 4. Present appeal is vehemently opposed by Shri Subhasish Bhowmick, learned counsel appearing on behalf of the respondent – workman. G H 4.1 It is submitted that as such there are concurrent findings recorded by the three courts below that the termination of the respondent was in breach of Sections 25-F and 25-G of the Industrial Disputes Act. It is submitted that once it is found that the termination was in breach of Sections 25-F and 25-G of the Industrial Disputes Act, the Labour Court rightly ordered reinstatement with back wages. > DIVISIONAL CONTROLLER MAHARASHTRA STATE ROAD TRANSPORT 403 CORP. v. KALAWATI PANDURANG FULZELE [M. R. SHAH, J.] 4.2 It is further submitted by Shri Subhasish Bhowmick, learned counsel appearing on behalf of the respondent- workman that as such the complaint was made by the respondent alleging unfair labour practices. It is submitted that the respondent was appointed in place of her husband, who was serving as a coolie in the MSRTC, however, unfortunately, he became blind and, in his place, the respondent was appointed. It is submitted that as she continuously worked till her services were terminated and there was no break in service, the termination is rightly held to be in violation of Sections 25-F and 25-G of the Industrial Disputes Act. 4.3 Making above submissions, it is prayed to dismiss the present appeal. A B C 5. We have heard the learned counsel appearing for the respective parties at length. 6. It is true that as such all the three courts below (except the Industrial Court) held the termination of the respondent – workman in breach of Sections 25-F and 25-G of the Industrial Disputes Act and, therefore, the Labour Court ordered reinstatement with back wages. However, it is required to be noted that even as per the appointment order produced by the respondent herself, her appointment was on contractual basis at a fixed salary/honorarium of Rs. 500/- per month. Though, it is a case on behalf of the appellant that her appointment was a fixed term appointment, however, considering the appointment order, the appointment was till further orders. Be that it may, the fact remains that her appointment was on contractual basis and on a fixed salary/ honorarium of Rs.500/- per month. It also cannot be disputed that she worked approximately for four years as a sweeper. As such there were no specific averments/allegations in the complaint on any unfair labour practice. Even there was no specific finding recorded by the Labour Court that there was any unfair labour practice adopted by the MSRTC. The only finding recorded by the Labour Court was that the termination was in breach of Sections 25-F and 25-G of the Industrial Disputes Act. D E F G 7. Having heard the learned counsel for the respective parties and considering the nature of appointment of the respondent namely as contractual appointment on a fixed salary/honorarium of Rs.500/- per month and she worked for approximately four years, we are of the opinion that in lieu of reinstatement and back wages, if a lumpsum compensation H 404 SUPREME COURT REPORTS [2022] 1 S.C.R. - A of Rs.3,00,000/- (Rupees Three Lakhs only) is awarded, it will meet the ends of justice. In the peculiar facts and circumstances of the case, when the appointment was purely on contractual basis and on a fixed salary/honorarium of Rs.500/- per month, the order of reinstatement with back wages was not warranted and instead if the lumpsum compensation is awarded in lieu of reinstatement and back wages as - B observed hereinabove, it will meet the ends of justice. 8. In view of the above and for the reasons stated above, present appeal succeeds in part. The impugned judgment and order passed by the Division Bench of the High Court and the judgment and award passed by the Labour Court ordering reinstatement with back wages is hereby C modified and in lieu of reinstatement and back wages, the appellant is directed to pay a lumpsum compensation of Rs.3,00,000/- (Rupees Three Lakhs only) to the respondent, to be paid within a period of four weeks from today. - Present appeal is partly allowed to the aforesaid extent. In the - D facts and circumstances of the case, there shall be no order as to costs. Pending application(s), if any, also stand disposed of. Nidhi Jain Appeal partly allowed. E F G H
End of Judgment Record
Browse All Supreme Court of India (2022) Decisions
2022-12-09

MOHD. SABEER @ SHABIR HUSSAIN v. RM, U. P. STATE ROAD TRANSPORT CORP.

The appellant, Mohd. Sabeer (also known as Shabir Hussain), a scrap dealer, was a passenger in a UP State Road Transport Corporation bus when the driver rashly and negligently drove the vehicle, causing a collision near Ghaziabad in 2009. He sustained grave injuries including an amputation of the right lower limb and other bodily injuries. The Motor Accident Claims Tribunal (MACT) awarded Rs. 15,76,465 with interest; the High Court of Delhi enhanced the amount to Rs. 16,70,932. The Disability Certificate recorded 70% permanent disability. The High Court had treated the claimant’s functional disability as 35%, relying on post‑accident income reflected in IT returns, and erred in not adequately recognizing the impact on earning capacity of a self‑employed person who cannot drive. The Supreme Court held that the appellant’s functional disability should be treated as 60% for loss of future earning capacity and that permanent disablement warrants consideration of future prospects in addition to future income. It invoked National Insurance Co. v. Pranay Sethi to apply a 40% addition for future prospects, and directed compensation for prosthetic limb purchase and maintenance, as well as enhanced non‑pecuniary damages. The final award was increased to Rs. 38,70,120 with 9% interest from the date of application, and the appeals were allowed, emphasizing liberal, holistic justice to restore the claimant to his pre‑accident position in light of socio‑economic factors.

2022-01-25

Intercontinental Hotels Group (India) Pvt. Ltd. & ANR. v. Waterline Hotels Pvt. Ltd.

Intercontinental Hotels Group (India) Pvt. Ltd. & Anr. v Waterline Hotels Pvt. Ltd. is a Supreme Court decision addressing appointment of a sole arbitrator under Section 11(6) read with Section 11(12)(a) of the Arbitration and Conciliation Act, 1996, in a dispute arising from a Hotel Management Agreement (HMA) for renovating the Holiday Inn & Suites Bengaluru, Whitefield. The petitioners allege breach by Waterline Hotels, including non-payment of incentive management fee and related charges, culminating in Waterline’s email termination of the HMA on 12 October 2018 after rebranding the hotel as Miraya. The petitioners invoked arbitration; Waterline challenged the enforceability of the arbitration clause on the ground that the HMA is an unstamped instrument under the Karnataka Stamp Act. A Karnataka High Court ad‑interim relief was granted in 2018, but the Supreme Court’s judgment focuses on the scope of judicial interference at the pre‑appointment stage. The Court reiterates a pro‑arbitration stance, noting that arbitrability/validity are generally matters for the arbitrators, with a narrow exception to cut deadwood or to refer for authoritative settlement where necessary, invoking Vidya Drolia. It also analyzes stamp duty, observing that stamp duty has been paid (albeit disputed) and that the question of the correct stamp duty may be resolved later, not as a precondition to appointing an arbitrator. Consequently, the Court appoints Justice A. V. Chandrashekara as a sole arbitrator, directs SIAC to proceed under its rules, and allows the petition in terms stated, while leaving stamp duty issues for arbitration to determine later.

2022-02-01

The State of Sikkim v. Jasbir Singh & ANR

This appeal by the State of Sikkim challenges a High Court judgment upholding a Sessions Judge’s order directing a written notice to the Army’s commanding officer to transfer the case to a court-martial. The case concerns concurrent jurisdiction between a court-martial and an ordinary criminal court under the Army Act for an offence allegedly committed by Lance Naik Jasbir Singh during active service in Sikkim, with the FIR under IPC 302 and related charges. The High Court held that the procedure under Sections 125/126 Army Act, the 1978 Rules (Rules 3-5) and CrPC Rule 475 had not been observed and that the Army authorities had exercised their discretion to prefer a court-martial; thus, the court-martial alone would have jurisdiction. The Supreme Court, however, held that the offence falls into a category with concurrent jurisdiction under Sections 69 and 70 of the Army Act, and that where there is concurrent jurisdiction, the first instance discretion to choose the forum lies with the designated officer under Section 125. In the present case there was no decision by the designated officer to institute proceedings before a court-martial, and the sequence of events showed significant cooperation with the CrPC process. Consequently, the Sessions Judge’s competence to proceed in the criminal court was not in error, the High Court’s order is set aside, and the respondent-accused is to be transferred to civil custody to face trial in the criminal court. The appeal is allowed.

2022-07-22

Hemant Kumar Verma & Ors. v. Employees State Insurance Corporation & Ors.

This writ petition concerns whether junior resident doctors in ESIC-run medical colleges should be eligible for the 50% in-service reservation for postgraduate medical courses, a benefit presently available to Insurance Medical Officers Grade-II (IMO-II) recruited through competitive selection. ESIC recruits IMO-II and provides a 50% in-service quota for PG seats; however junior residents, who complete MBBS under bond and serve as part of ESIC's residency scheme, are not deemed in-service doctors. The petitioners argued parity with IMO-II because their qualifications, duties, and work environment are similar, and urged the Court to treat them as in-service to extend the 50% reservation to their batch. ESIC contends that junior residents are contractual, bond-based appointees governed by the ESIC Residency Scheme; IMO-II is a permanent post governed by the ESIC Staff and Condition of Service Regulations 1959; the bond reduction in 2020 and the 2018/2020 memoranda cannot convert junior residents into in-service doctors. The Court relies on precedents establishing institutional preference in PG admissions—Saurabh Chaudri v. Union of India, Yatin Kuma Jasubahi v. State of Gujarat, and Pradeep Jain v. Union of India — to acknowledge the legitimacy of institutional preference, but ultimately holds that junior residents and regular ESIC doctors are distinct categories and the in-service quota cannot be equitably extended to junior residents. The petition is dismissed.