Dharnidhar Mishra (D) & Anr. v. State of Bihar & Ors.

Case / Petition Number:
Civil Appeal No 6351 of 2024

Case Synopsis & Summary

This is an appeal under the Civil Appellate jurisdiction arising from a land acquisition for a State Highway in Bihar. In 1977, the State acquired the appellant’s land under Section 4 of the Land Acquisition Act but allegedly did not pay any compensation or pass an award. The appellant actively sought compensation, repeatedly approaching authorities for payment, but a writ petition before the Patna High Court was dismissed in 2019 on the ground of delay and lack of substantiating papers. The Division Bench later directed the appellant to file an application before the concerned authority for disbursement of Rs 4,68,099 (the value of the land as assessed). The Supreme Court found two critical deficiencies: (i) the basis for Rs 4,68,099 was not explained, and no speaking order explained how this figure was derived; (ii) the High Court’s order was non-speaking and did not scrutinize the 1977 award or the State’s non‑compliance with due process. The Court reaffirmed that property rights are protected by Article 300-A and that compensation for eminent domain must be just and fair, while emphasizing that delay cannot thwart a continuing constitutional remedy. Consequently, the matter was remitted to the High Court for fresh consideration with directions to decide within two months, restoring the Letters Patent Appeal. The appeal is thus allowed and remitted with these observations.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • J. B. Pardiwala
  • Manoj Misra
Judgment Date
2024-05-13
Court Decision / Holding
The appeal is allowed. The impugned order of the High Court is set aside and the matter is remitted to the High Court for fresh consideration. The High Court shall hear both sides and pass an appropriate order in accordance with the observations of this Court, preferably within two months. Pending applications, if any, are disposed of. Letters Patent Appeal No. 997 of 2019 is restored to its original file.
Final Disposition
Appeal allowed; remitted to High Court for fresh consideration; LP Appeal No. 997 of 2019 restored; matter to be decided within two months.

Parties to the Case

Appellants / Petitioners

  • Dharnidhar Mishra (D) & Anr.

Respondents

  • State of Bihar and Others

Legal Representation & Advocates

Counsels for Petitioners

  • • Mr. Dharnidhar Jha, Sr. Adv.
  • • Mr. Jayesh Gaurav, Adv.
  • • Ms. Diksha Ojha, Adv.
  • • Mr. Ishwar Chandra Roy, Adv.
  • • Mr. Ranjan Nikhil Dharnidhar, AOR

Counsels for Respondents

  • • Mr. Anshul Narayan, Adv.
  • • Mr. Prem Prakash, AOR

Provisions of Law Cited

Land Acquisition Act, Section 4Constitution of India, Article 31Constitution of India, Article 300-AConstitution (Forty-Fourth Amendment) Act, 1978

Legal Doctrines & Maxims

  • Property must be secured else liberty cannot subsist
  • No person shall be deprived of his property save by authority of law
  • Eminent domain requires public purpose and just and fair compensation
  • Right to property is a fundamental/human right under the Constitution
  • State must comply with the procedure laid down for acquisition or requisition, or any other permissible statutory mode
  • Delay and laches cannot defeat a continuing cause of action in constitutional remedies
  • Strict construction of Article 300-A to protect property rights

Submissions & Arguments

Contentions of Appellants / Petitioners

Appellants contend that the State admitted to acquiring the land and using it for the public purpose, but failed to pass an award or pay compensation for decades. They argue the 42-year delay cannot justify denial of a just remedy, and the High Court’s order- disposing of the writ petition on delay and directing the appellant to approach authorities for disbursement of Rs 4,68,099 - was non-speaking and unexplained in its basis. They emphasise constitutional protections (Articles 31/300-A) recognizing property rights and the State’s obligation to provide just compensation and due process; the award and calculation of compensation require transparent adjudication rather than a mechanical disbursement. They urge fresh consideration by the High Court with due process and a proper basis for the compensation figure.

Contentions of Respondents

State of Bihar submits that there was a public purpose for acquisition and the onus lay on the petitioner to pursue a just compensation process. It maintains that the land had been acquired and the State was ready to compensate, and that the petitioner’s delay cannot override the State’s obligation to follow the legal procedure for award and disbursement. The High Court’s decision, it contends, is sound, as the matter concerns the entitlement to compensation and the proper mode of computation and disbursement.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (9)

Case NameCitationTreatmentExplanation
K.T. Plantation (P) Ltd. v. State of Karnataka(2011) 9 SCC 1PositiveCited to support that Article 300-A implies an obligation to pay compensation for property taken by the State; the right to property is protected by the Constitution.
Hindustan Petroleum Corpn. Ltd. v. Darius Shapur Chenai(2005) 7 SCC 627PositiveCited for the principle that eminent domain must be for public purpose with reasonable compensation.
N. Padmamma v. S. Ramakrishna Reddy(2008) 15 SCC 517PositiveSupports strict construction of Article 300-A to protect property rights.
Delhi Airtech Services (P) Ltd. v. State of U.P.(2011) 9 SCC 354PositiveAffirms property rights as a basic human right and protection under constitutional framework.
Jilubhai Nanbhai Khachar v. State of Gujarat1995 Supp (1) SCC 596PositiveArt. 300-A limits State powers in depriving property.
Tukaram Kana Joshi v. MIDC(2013) 1 SCC 353PositiveState must comply with the statutory procedures for acquisition or requisition.
State of Haryana v. Mukesh Kumar(2011) 10 SCC 404PositiveProperty rights are treated as human rights within constitutional framework.
Vidya Devi v. The State of Himachal Pradesh(2020) 2 SCC 569PositiveDelay cannot defeat a continuing cause of action, especially for fundamental rights.
P.S. Sadasivaswamy v. State of Tamil Nadu(1975) 1 SCC 152PositiveJudicial discretion to promote substantial justice in constitutional remedies.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,749 words•~13 min read

In The Court Record

Dharnidhar Mishra (D) & Anr. v. State of Bihar & Ors.

CA 6351/2024 2024 INSC 415 **==> picture [72 x 72] intentionally omitted <==** ## **Reportable** ## **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** ## **Civil Appeal No 6351 of 2024** (Arising out of SLP (C) No 10492 of 2023) ## **Dharnidhar Mishra (D) and Another Appellants Versus State of Bihar and Others Respondents** ## **O R D E R** - 1 Application for substitution to bring on record the legal heirs of the first petitioner is allowed. Cause title be amended accordingly. - 2 Leave granted. - 3 This appeal arises from a order passed by the High Court of Judicature at Patna dated 7 February 2023 in the Letters Patent Appeal No 997 of 2019 in Civil Writ Jurisdiction Case No 8408 of 2019 by which the Division Bench of the High Court disposed of the Letters Patent Appeal by asking the appellant herein to file an appropriate application before the concerned authority for disbursement of the value of the land assessed at Rs 4,68,099. Signature Not Verified Digitally signed by CHETAN KUMAR Date: 2024.05.15 16:54:41 IST Reason: 1 CA 6351/2024 - 4 The facts giving rise to this appeal may be summarized as under: In the year 1976, a notification under Section 4 of the Land Acquisition Act was issued for the purpose of construction of State Highway as notified by the State of Bihar. The land owned by the appellant herein was included in Section 4 notification referred to above. Sometime in 1977, the land of the appellant was acquired. However, it is the case of the appellant that not a single penny was paid to him towards compensation. - 5 The appellant preferred an appropriate application addressed to the State Government immediately after his land came to be acquired and possession was taken over in the year 1977 for payment of compensation. It is the case of the appellant that State did not even pass any award of compensation and kept the matter in limbo. - 6 Years passed by and the appellant kept on requesting the authorities to pass an appropriate award and pay the amount towards compensation. - 7 As the respondents did not pay heed to the say of the appellant, he was left with no other option but to file a writ petition in the High Court of Patna. The writ petition was heard by a learned Single Judge and by order dated 19 July 2019 rejected the same only on the count that the petition had been filed after a period of forty-two years of the acquisition. While dismissing the writ petition, the learned Single Judge also observed that the appellant had failed to submit any paper or notification in connection with acquisition of his land 2 CA 6351/2024 for the purpose of payment of compensation. - 8 Being dissatisfied with the order passed by the learned Single Judge rejecting his writ petition, the appellant went in appeal. The appeal came to be disposed of by a Division Bench in the following terms: “A hard copy of the supplementary affidavit on behalf of the State has been filed across the Board. Let it be taken on record. In view of the categorical stand of the State that the land of the appellants had been consumed and that the State is ready to compensate the appellants, nothing remains in this appeal to be decided. The appellants have been informed about the value of the land has been assessed at Rs 4,68,099/- . All that the appellants have to do is to file an application before the concerned authority as to how the amount shall be apportioned between him and his son. It is expected that the decision in that regard by the State Authority shall be taken without any delay as already the matter has become five decades old. The appeal stands disposed of." - 9 Mr. Dharnidhar Jha, the learned senior counsel appearing for the appellant submitted that the State conceded to the fact that the land of the appellant had been acquired and was put to use for the purpose the same was acquired. He would submit that if the State thought fit to acquire the land of his client, then it was obligatory on the part of the State to pass an appropriate award determining the amount towards compensation. He would 3 CA 6351/2024 submit that it is not the case that the appellant herein was lethargic in asserting his rights, but rather kept on requesting the authorities concerned to determine the amount towards compensation and pay the same. - 10 On the other hand, the learned counsel appearing for the State of Bihar submitted that no error, not to speak of any error of law could be said to have been committed by the High Court in passing the impugned order. He would submit that it is not in dispute that the land of the appellant was acquired for a public purpose, but at the same time, it was the duty of the appellant to pursue the matter further for the purpose of getting appropriate compensation determined in accordance with law. - 11 Having heard the learned counsel appearing for the parties and having gone through the materials on record, the only question that falls for our consideration is whether the High Court committed any error in passing the impugned order. - 12 We take notice of the fact that the Single Judge of the High Court thought fit to reject the writ petition only on the ground of delay and in appeal, the appellate court disposed of the appeal asking the appellant herein to file an application before the concerned authority for disbursement of the amount of compensation. - 13 We take notice of two things: First, the High Court in its impugned order has stated that the appellant herein has been informed about the value of the 4 CA 6351/2024 land assessed at Rs 4,68,099. We fail to understand on what basis this figure has been arrived at; at what point of time this amount came to be assessed; and the basis for the assessment of such amount. Secondly, the order of the High Court could be said to be a non-speaking order. Although at this stage, the learned counsel appearing for the State of Bihar submitted that it was an order obtained with the consent of the parties, yet there is nothing to indicate that any consent was given by the appellant herein to pass such an order. - 14 The first thing that the High Court should have enquired with the State is as to why in the year 1977 itself, that is the year in which the land came to be acquired, the award for compensation was not passed. The High Court should have enquired why it took forty-two years for the State to determine the figure of Rs 4,68,099. The High Court should also have asked the State the basis of the determination of the amount towards compensation. It is a well settled position of law that after the award towards compensation is passed, if the owner of the land is not satisfied with the quantum, he can even file an appeal for the enhancement of the same. The High Court proceeded on the footing that the amount of Rs 4,68,099 has been assessed and it is now for the appellant to file an appropriate application and get the amount disbursed in his favour. - 15 We are not convinced but rather disappointed with the approach of the High Court while disposing of the appeal. 5 CA 6351/2024 - 16 There are many issues arising in this litigation and the High Court should have taken little pains to ask the State why it made the appellant run from pillar to post. It is sad to note that the appellant passed away fighting for his right to receive compensation. Now the legal heirs of the appellant are pursuing this litigation. - 17 In 1976, when the land of the appellant came to be acquired the right to property was a fundamental right guaranteed by Article 31 in Part III of the Constitution. Article 31 guaranteed the right to private property, which could not be deprived without due process of law and upon just and fair compensation. - 18 The right to property ceased to be a fundamental right by the Constitution (Forty-Fourth Amendment) Act, 1978, however, it continued to be a human right in a welfare State, and a constitutional right under Article 300-A of the Constitution. Article 300-A provides that no person shall be deprived of his property save by authority of law. The State cannot dispossess a citizen of his property except in accordance with the procedure established by law. The obligation to pay compensation, though not expressly included in Article 300A, can be inferred in that Article. [See: _K.T. Plantation (P) Ltd._ v. _State of Karnataka_ , (2011) 9 SCC 1] - 19 In _Hindustan Petroleum Corpn. Ltd._ v. _Darius Shapur Chenai_ reported in (2005) 7 SCC 627, this Court held that: 6 CA 6351/2024 “ _6_ . … Having regard to the provisions contained in Article 300A of the Constitution, the State in exercise of its power of “eminent domain” may interfere with the right of property of a person by acquiring the same but the same must be for a public purpose and _reasonable compensation therefor must be paid_ .” (Emphasis supplied) - 20 In _N. Padmamma_ v. _S. Ramakrishna Reddy_ reported in (2008) 15 SCC 517, this Court held that: “ _21_ . _If the right of property is a human right as also a constitutional right, the same cannot be taken away except in accordance with law_ . Article 300-A of the Constitution protects such right. The provisions of the Act seeking to divest such right, keeping in view of _the provisions of Article 300-A of the_ ” _Constitution of India, must be strictly construed_ . (Emphasis supplied) - 21 In _Delhi Airtech Services (P) Ltd._ v. _State of U.P._ reported in (2011) 9 SCC 354, this Court recognised the right to property as a basic human right in the following words: “ _30_ . _It is accepted in every jurisprudence and by diferent political thinkers that some amount of property right is an indispensable safeguard against tyranny and economic oppression of the Government_ . Jefferson was of the view that liberty cannot long subsist without the support of property. “Property must be secured, else liberty cannot subsist” was the opinion of John Adams. Indeed the view that _property itself is the seed-bed which must be conserved if other constitutional values are to fourish, is the consensus among political thinkers and jurists_ .” (Emphasis supplied) - 22 In _Jilubhai Nanbhai Khachar_ v. _State of Gujarat_ reported in 1995 Supp (1) SCC 596, this Court held as follows: 7 CA 6351/2024 “ _48_ . … In other words, Article 300-A only limits the powers of the State that no person shall be deprived of his property save by authority of law. _There has to be no deprivation without any sanction of law. Deprivation by any other mode is not acquisition or taking possession under Article 300-A_ . In other words, if there is no law, there is no deprivation.” (Emphasis supplied) - 23 In _Tukaram Kana Joshi_ v. _MIDC_ reported in (2013) 1 SCC 353, this Court held that the State must comply with the procedure for acquisition, requisition, or any other permissible statutory mode. The State being a welfare State governed by the rule of law cannot arrogate to itself a status beyond what is provided by the Constitution. - 24 This Court in _State of Haryana_ v. _Mukesh Kumar_ reported in (2011) 10 SCC 404 held that the right to property is now considered to be not only a constitutional or statutory right, but also a human right. Human rights have been considered in the realm of individual rights such as right to shelter, livelihood, health, employment, etc. Human rights have gained a multifaceted dimension. - 25 We regret to state that the learned Single Judge of the High Court did not deem fit even to enquire with the State whether just and fair compensation was paid to the appellant or not. The learned Single Judge rejected the writ petition only on the ground of delay. As held by this court in _Vidya Devi v. The State of Himachal Pradesh & Ors._ reported in (2020) 2 SCC 569, delay and laches cannot be raised in a case of a continuing cause of action or if the circumstances shock the judicial conscience of the court. The condition of 8 CA 6351/2024 delay is a matter of judicial discretion, which must be exercised judiciously and reasonably in the facts and circumstances of the case. As held by this Court, it would depend upon the breach of fundamental rights, and the remedy claimed, and when and how the delay arose. There is no period of limitation prescribed for the courts to exercise their constitutional jurisdiction to do substantial justice. - 26 In a case where the demand for justice is so compelling, a constitutional court would exercise its jurisdiction with a view to promote justice, and not defeat it. [See: _P.S. Sadasivaswamy_ v. _State of T.N._ , (1975) 1 SCC 152] - 27 In _Tukaram Kana Joshi_ v. _MIDC_ reported in (2013) 1 SCC 353, this Court while dealing with a similar fact situation, held as follows: “11. There are authorities which state that delay and laches extinguish the right to put forth a claim. Most of these authorities pertain to service jurisprudence, grant of compensation for a wrong done to them decades ago, recovery of statutory dues, claim for educational facilities and other categories of similar cases, etc. Though, it is true that there are a few authorities that lay down that delay and laches debar a citizen from seeking remedy, even if his fundamental right has been violated, under Article 32 or 226 of the Constitution, the case at hand deals with a different scenario altogether. _The functionaries of the State took over possession of the land belonging to the appellants without any sanction of law_ . The appellants had asked repeatedly for grant of the benefit of compensation. _The State must either comply with the procedure laid down for acquisition, or requisition, or any other permissible statutory mode_ .” (Emphasis supplied) 9 CA 6351/2024 - 28 In such circumstances referred to above, we are of the view that we should set aside the impugned order passed by the High Court and remit the matter for fresh consideration. - 29 In the result, this appeal succeeds and is hereby allowed. The impugned order passed by the High Court is set aside and the matter is remitted to the High Court for fresh consideration. Letters Patent Appeal No 997 of 2019 is restored to its original file. The High Court shall hear both the sides and pass an appropriate order in accordance with what has been observed by this Court in this order. We request the High Court to decide the matter within a period of two months from today. - 30 Pending applications, if any, stand disposed of. **..…....…........……………….…........J. [J B Pardiwala]** **..…....…........……………….…........J. [Manoj Misra]** New Delhi; May 13, 2024 CKB 10 CA 6351/2024 **ITEM NO.61 COURT NO.17 SECTION XVI** **S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS** ## **Civil Appeal No.6351/2024** **DHARNIDHAR MISHRA (D) & ANR. Appellant(s)** **VERSUS** **THE STATE OF BIHAR & ORS. Respondent(s)** **(With IA No.88293/2024 - APPLICATION FOR SUBSTITUTION and IA No.102966/2023 - EXEMPTION FROM FILING O.T.)** **Date : 13-05-2024 These matters were called on for hearing today.** ## **CORAM :** **HON'BLE MR. JUSTICE J.B. PARDIWALA HON'BLE MR. JUSTICE MANOJ MISRA** **For Appellant(s) Mr. Dharnidhar Jha, Sr. Adv.** **Mr. Ranjan Nikhil Dharnidhar, AOR** **For Respondent(s) Mr. Anshul Narayan, Adv. Mr. Prem Prakash, AOR** **UPON hearing the counsel the Court made the following O R D E R** 1 Application for substitution to bring on record the legal heirs of the first petitioner is allowed. Cause title be amended accordingly. 11 CA 6351/2024 - 2 Leave granted. - 3 The appeal is allowed in terms of the signed reportable order. - 4 Pending applications, if any, stand disposed of. **(CHETAN KUMAR) (RAM SUBHAG SINGH) A.R.-cum-P.S. Court Master (Signed Reportable Order is placed on the file)** 12
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.