Deputy Executive Engineer v. Kuberbhai Kanjibhai
Case Synopsis & Summary
This Supreme Court Civil Appeal arises from a 2007 Labour Court award directing reinstatement of a respondent daily-wage worker in the State R&B Department, Surendranagar, after termination. The appellant-State challenged the Labour Court’s order, arguing that the respondent’s service of only two years (1979–1981) over a long span and intermittent work did not justify reinstatement or back wages. The Gujarat High Court dismissed the writ petition and upheld the Labour Court’s award. In allowing the appeal in part, the Supreme Court relied on Bharat Sanchar Nigam Limited v. Bhurumal (2014) 7 SCC 177 and District Development Officer and Anr. v. Satish Kantilal Amerelia (2018) 12 SCC 298, to hold that the automatic grant of reinstatement with back wages is not universal for daily-wage workers whose termination is found illegal due to procedural defects under Section 25-F of the Industrial Disputes Act, 1947. The Court held that monetary compensation can meet ends of justice, invoking Section 11A of the IDA and awarding Rs.1,00,000 in lieu of reinstatement and back wages. It also noted a caveat that reinstatement may be appropriate in exceptional cases where illegal termination involves unfair labour practices or last-come, first-go considerations. The High Court’s order was set aside to the extent of this modification, with the payment to be made within three months.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- Abhay Manohar Sapre
- Indu Malhotra
- Judgment Date
- 2019-01-07
- Court Decision / Holding
- The appeal is allowed in part; the Labour Court’s award is modified to award a lump-sum monetary compensation of Rs.1,00,000 under Section 11A of the IDA in lieu of reinstatement and back wages, to be paid within three months; the High Court’s order is set aside to the extent of this modification.
- Final Disposition
- Appeal allowed in part; relief modified to monetary compensation in lieu of reinstatement and back wages
Parties to the Case
Appellants / Petitioners
- Deputy Executive Engineer (R&B) Surendranagar / State of Gujarat
Respondents
- Kuberbhai Kanjibhai
Legal Representation & Advocates
Counsels for Petitioners
- • Ms. Jesal Wahi
Counsels for Respondents
- • Mr. A.P. Mayee
Provisions of Law Cited
Legal Doctrines & Maxims
- Last come first go
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellant-State contends that the respondent was a daily-wage employee with intermittent service from 1979–1981, and therefore is not entitled to reinstatement or back wages; reinstatement should not be automatic given the lack of regular service and due process issues under Section 25-F.
Contentions of Respondents
The respondent worker asserts illegal termination without due process; seeks reinstatement with back wages; Labour Court granted reinstatement, which the High Court affirmed. The appellant challenges these remedies on the grounds of the employee’s classification and the adequacy of procedural compliance.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (2)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Bharat Sanchar Nigam Limited vs Bhurumal | (2014) 7 SCC 177 | Positive | The Court relied on BSNL to support the proposition that reinstatement with back wages is not automatic for daily-wage workers where termination is illegal for procedural defects; monetary compensation may meet ends of justice. |
| District Development Officer and Anr. vs. Satish Kantilal Amerelia | (2018) 12 SCC 298 | Positive | Cited as supportive authority clarifying the approach to compensation in lieu of reinstatement in similar contexts, reinforcing the exception to automatic reinstatement. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Deputy Executive Engineer v. Kuberbhai Kanjibhai
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.