Case Synopsis & Summary

Following tender notices issued in 1995, the Department of Telecommunication granted licences to various cellular operators on terms that required licence fees to be paid in advance, with late-payment interest. The New Telecom Policy (NTP) 1999 introduced a migration package that notionally extended the effective date of payment by about six months for the licence fee, while the dispute arose over whether interest charged for the period before the actual payment should also be adjusted accordingly. The Cellular Operators Association challenged the DoT’s demands before the Telecom Disputes Settlement and Appellate Tribunal (TDSAT), which allowed the appeal and directed the authorities to modify the demands, refunding interest charged for the extended period or adjusting it against future dues. The DoT appealed to the Supreme Court. The Court held that the licence fee becomes due and payable from the effective date, and when that date is postponed by six months, it is the date from which the licence fee must be reckoned for both fee and interest. It rejected the notion that interest can accrue independently of the fee and endorsed the Tribunal’s mandate to modify excess charges, with refunds or set-offs for any overpaid amount. The appeal was dismissed subject to the specified modifications. The decision clarifies the application of the migration package’s extended date to both licence fee and interest, and directs proportional refunds/adjustments where excess charges were made.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • S. Rajendra Babu
  • Dr. AR. Lakshmanan
Judgment Date
2003-03-04
Court Decision / Holding
The licence fee becomes due and payable from the effective date; with the six-month extension the date for reckoning the licence fee, and hence interest, is adjusted accordingly. Interest is dependent on the licence fee becoming due and cannot accrue prior to that date. The Court upheld the Tribunal’s core direction but modified it: the appellants must modify the demands to the extent that they charge higher licence fee or interest, and the excess should be refunded or adjusted towards outstanding or future dues, with any remaining amount refunded at bank rates. The appeal is dismissed.
Final Disposition
Appeal dismissed; modified directions issued; excess amounts to be refunded or adjusted; refunds at bank rates.

Parties to the Case

Appellants / Petitioners

  • Department of Telecommunication and Anr.

Respondents

  • Cellular Operators Association of India
  • Others (licensees)

Legal Representation & Advocates

Counsels for Petitioners

  • • Mukul Rohtagi
  • • Navin Chawla

Counsels for Respondents

  • • P. Chidambaram
  • • C.S. Vadiyanathan
  • • Manjul Bajpai
  • • Ms. Bina Gupta
  • • Praveen Thomas
  • • Ms. Divya Roy
  • • Ms. Shaily Yogi
  • • Ms. Garima Dewan
  • • R.K. Sharma

Provisions of Law Cited

Clause 1(j) Schedule B (Effective Date)Migration Package (NTP 1999)Clause ix (ix) of Migration Package: calculation of outstanding licence fee

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioners argued that under the Migration Package of the New Telecom Policy 1999, the effective date for payment of licence fees was extended by six months, but not for interest that had already accrued, and that interest should not be charged based on the old effective date. They contended that interest is contingent on the licence fee becoming due and that the liability should be calculated from the extended date, with refunds or adjustments for any excess.

Contentions of Respondents

The respondents argued that the six-month extension under the migration package applies to the calculation of outstanding licence fee and interest, and that interest should be calculated from the extended date; they maintained that the Tribunal’s directions to modify the demands were proper and that any excess charged amounts should be refunded or adjusted toward outstanding/future dues.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,078 words•~10 min read

In The Court Record

Department of Telecommunication and Anr. v. Cellular Operators Association of India and Ors.

+ '~ DEPARTMENT OF TELECOMMUNICATION AND ANR. A _v._ CELLULAR OPERATORS ASSOCIATION OF INDIA AND ORS. MARCH 4, 2003 [S. RAJENDRA BABU AND DR. AR. LAKSHMANAN, JJ.] B _New Telecom Policy, 1999:_ > _Licence granted to Cellular Operators on terms and conditions-_ c _Charging of interest on late payment of advance licence fee-Postponement of ejfer;tive date-Demand of interest by the Authority for extended periodChallenge to-Tribunal allowed the appeal directing the Autilority to modify demands-On appeal, held, since licence fee becoming due from a particular date and interest is depending on ·the licence fee, the interest on licence fee would not accrue from a date prior to the effective date of payment of fee-_ D _Authority to modify demands by adjusting excess amount of interest towards outstanding/future dues-Directions issued._ Appellant-Authority had granted licence to respondents-Cellular Operators on certain terms and conditions. The licensees were required to pay licence fee in advance by the due date/effective date and in case of failure to make payment of fee on due date, interest thereon would be charged. E Appellant had introduced the New Telecom Policy, 1999 whereby effective date of payment of fee was extended by certain period. However, appellant had raised demand of interest from the prior effective date which[F ] was challenged by the respondents before the Telecom Disputes Settlement and Appellate Tribunal. Tribunal allowed the appeal with certain directions on refund of interest charged for the extended period. Hence the present appeal. G ## Disposing of the appeal, the Court HELD: I. I. The licence fee becomes due and payable from the effective date. When the effective date stood postponed by a period of six months then that is the date from which the licence fee will have to be 547 H 548 ~- SUPREME COURT REPORTS [2003] 2 S.C.R. - A reckoned and appropriate calculation made both for purposes of licence fee and interest. Unless the licence fee becomes due the question of payment of interest will not arise. 1551-D-EI 1.2. The payment of interest is dependent upon the licence fee becoming due. Interest is not independent of the licence fee and when the B licence fee had to be paid from a par!icular date, the interest would not accrue from a date prior to the licence fee becoming due for payment. 1551-F-GJ 1.3. The appellants should modify the demand issued to the - C respondents to the extent it is found to charge higher amount of licence fee or interest on the principles set out in this order. The excess amount which is liable to be refunded to the respondents shall be adjusted towards outstanding or future dues and if still any amount becomres due to them the same shall be refunded at the relevant bank rates. (551-H; 552-AJ - D CIVIL APPELLATE JURISDICTION : Civil Appeal No. 5050 of 2002. From the Judgment and Order dated 9.4.2002 of the Telecom Disputes Settlement & Appellate Tribunal, New Delhi in P.No. 10 of 2001. E Mukul Rohtagi, Additional Solicitor General and Navin Chawla for the Appellants. P. Chidambaram and C.S. Vadiyanathan, Manjul Bajpai, Ms. Bina Gupta, Praveen Thomas, Ms. Divya Roy, Ms. Shaily Yogi, Ms. Garima Dewan and R.K. Sharma for the Respondents. ## F - ·The Judgment of the Court was delivered by RAJENDRA BABU, J. Pursuant to a tender notice issued on 16.1.1995 the appellants granted licences to various cellular operators on terms and conditions mentioned therein. The Licence Agreement provided that the G licencee has to pay the prescribed fee in advance in terms of Schedule B thereof and the period of licence was initially for 10 years. The licencee was obliged to install and run the system within 12 months of the effective date which is defined in the licence. The Agreement also provided that in case of failure to pay the licence fee within the prescribed time interest shall be H charged on the amount due at certain rate. + _)_ DEPT. OF TELECOMMUNICATION 1·. CELLULAR OP. ASSON. OF INDIA [S. RAJENDRA BABU.).] 549 The New Telecom Policy (1999] NTP 99 was introduced thereafter A which was known as 'migration package' and was offered to various licencees as set out in their letter dated 22.7.1999 which was accepted unconditionally by the members of respondent No.I and other licencees on 26.7.1999. In the NTP, under the migration package it was stated that the effective date is postponed by about six months for payment of licence fee. Demands were B raised on the basis that modified effective date is applicable only to licence fee and n?t to interest that had already accrued. The amounts were also paid by the cellular operators as demanded. Thereafter several representations were made stating that the charging of interest is not permissible as license fee had not become due in view of the notional extension of the effective date. However, the appellants having stuck to their stand as set out in their C demand, the respondent filed a petition on 26.6.200 I before the Telecom Disputes Settlement & Appellate Tribunal [hereinafter referred to as 'the Tribunal'] challenging, _inter a/ia_ the demand of interest without making any adjustment on account of notional extension of the effective date by six months. The Tribunal accepted the stand of the cellular operators and directed the appellants to modify their demand subject to certain other incidental D directions. This order is in challenge before us. Schedule B to the License Agreement provides for definition, interpretation and transitional provisions relating to the conditions. Clause l(j) defines 'effective da!e' as under: E "Effective date" is the date by which the licensing agreement comes into effect and the "effective date" is reckoned with effect from the date the license agreement is signed after payment of appropriate component of licence fee. F .In the present case, the effective date is 12.12.1995 which stood extended to 12.6.1996. The licence fee is due to be paid in a lump sum prior to signing of the License Agreement for the first year and for the subsequent years it was payable in quarterly instalments in advance. In NTP-99, the migration package G provided that the licencee will be.required to be paid (I) one time entry fee and (2) licence fee as a percentage share of gross revenue under the licence. The entry fee chargeable will be the license fee dues payable by the existing licencees upto 31.7.1999 duly adjusted consequent upon notional extension of effective date as per the conditions of the existing licence. The licence fee H 550 [2003] 2 S.C.R. ## SUPREME COURT REPORTS - A as a percentage of gross revenue under the licence shall be payable with effect from 1.8.1999. - The dispute between the parties is in relation to payment of interest. - While the stand of the appellants is that the relevant clause providing for the effective date which has been extended notionally for a period of six months - B is only for the purpose of payment of licence fee and not in respect of the interest which had accrued upon the licence fee which was to be paid under the original licence while it is the stand of the cellular operators that inasmuch as the effective. date for calculation of the outstanding licence fee has been extended by a period of six monthS the interest will have to be calculated not - C from the original date but from the extended date and unless licence fee became due the question of payment of interest would not arise. The relevant provision of the migration package as set out in the letter dated 22. 7 .1999 are as follows. - D "(iv) A total of at least 35% of outstanding dues including interest payable as on 31. 7. 99 and LO charge in full will have to be paid on or before 15.8.1999. The amount paid, if any, against the earlier demand send under letter dated 25 .1.1999 for paying 20% or more of the outstanding dues, may be adjusted at licensee's option. The balance dues will have to be paid on or before - E 31.1.2000 alongwith interest calculated upto the actual date of payment. - (ix) For the purpose of calculation of outstanding licence fee upto 31.7.1999, the effective date of all the licenses of Cellular Telecom - F Circle and Basic Telephone Services will be notionally extended by a period of six months. This date does not apply to metro cellular licences. This is with the further condition that where extension of effective date has been given earlier due to whatever circumstances, further extension will be given after deducting the period of extension already given subject to the total extension - G period not exceeding six months. In cases where extension of period of more than six months has already been given there will be no further change. - (x) The liquidated damages as per the existing licence agreement shall be paid latest by 15.8.99. - H + DEPT. OF TELECOMMUNICATION 1·. CELLULAR OP. ASSON. OF INDIA IS. RAJENDRABABU, l.] 55] _.)_ - (xi) The period of licence shall be 20 years starting from the effective A date of the existing license agreement." The learned counsel qn either side have adverted to several decisions but in our ·view none of these decisions have a bearing on the issues to be decided in the present case as they turn upon the language of the License Agreement and its provisions. B It is no doubt true, as contended for appellants that the effective date is defined under the original licence under clause l(j) which is to be reckoned from the date the License Agreement is signed after payment of appropriate component of licence fee. By reason of NTP-99 and the migration package the effective date stood extended by a period of six months. That means the C effective date becomes a date which is after six months thereof thus, there is a substitution of the date of reckoning the licence fee. Whether it results in reduction of any licence fee payable or not is not for us to examine in the present proceeding. All that we are concerned in the present case is whether cellular operators are liable to pay interest without reference to the extended D effective date as demanded by the appellants. The Department's stand is that the expression "for the purpose of calculation of outstanding licence fee" used in clause (ix) will only cover licence fee as such and not outstanding interest. But this argument baffles all logic. The licence fee becomes due and payable from the effective date. When the effectjve date stood postponed by a period of six months then that is the date from which the licence fee will E have to be reckoned and appropriate calculation made both for purposes of licence fee and interest. Unless the licence fee becomes due the question of payment of interest will not arise. However, the learned Additional Solicitior General submitted that there are two components, namely, the licence fee and interest which was payable. In respect of one component the effective date p was extended but not in respect of the other. But payment of interest is dependent upon the licence fee becoming due. Interest is not independent of the licence fee and when the licence fee had to be paid from a particular date, the interest would not accrue from a date prior to the licence fee becoming due for payment. In that view of the matter, we think the view taken by the Tribunal is correct and no interference is called for. However, in regard to the G relief granted by the Tribunal we think the direction should be modified. The direction to the authorities will now read as follows: We direct the appellants to modify the demand issued to the respondents to the extent it is found to charge higher amount of licence fee or interest on H + 552 _!_ - SUPREME COURT REPORTS [2003] 2 S.C.R. - A the principles set out by us in this order. The excess amount which is liable to be refunded to the respondents shall be adjusted towards outstanding or future dues and if still any amount becomes due to them the same shall be refunded at the ~elevant bank rates. In other respects the direction given by the Tribunal stands maintained. B The appeal is thus dismissed subject to the modification made in the course of this order. S.K.S Appeal dismissi~d.
End of Judgment Record
Browse All Supreme Court of India (2003) Decisions
2003-09-22

State of Punjab v. Pohla Singh and Anr.

This is a Supreme Court of India decision (September 22, 2003) arising from Criminal Appeal No. 901 of 1996, where the State of Punjab challenges acquittal by the Punjab and Haryana High Court of two respondents for offences under Section 302 read with Section 34 IPC. The trial court had convicted Pohla Singh and Balkaur Singh for homicidal death of Mandip Singh around 5.30 a.m. on 11 June 1991; the other two accused were given the benefit of doubt. The High Court acquitted the two respondents on the ground of delay in lodging the FIR and questioned the time of occurrence, treating these as improbable factors that undermined the prosecution case. The State contends that there is no embargo on appellate review of acquittals and that the High Court’s reasoning rests on surmises and conjectures, ignoring the eye-witnesses’ detailed testimony and the trial court’s careful evaluation. The Supreme Court agrees to re-appreciate admissible evidence to prevent miscarriage of justice, noting that unexplained delay, standing alone, is the relevant factor, and that the prosecution need not answer every hypothetical question. It faulted the High Court’s approach, upheld the credibility of witnesses, reversed the acquittal, and restored the trial court’s verdict, directing the respondents to serve their sentences.

2003-05-01

Parwati Bai v. Radhika

This Supreme Court decision concerns eviction of a sub-tenant from municipal non-residential premises in Khargaon, Madhya Pradesh. The appellant (Parwati Bai) had leased the premises from the Municipal Council and sub-let to the respondent (Radhika). The ownership of the premises vested in the municipality, and the landlord sought eviction on the ground of non-payment of rent and need for self-occupation under the Transfer of Property Act, while contending that the Madhya Pradesh Accommodation Control Act, 1961 should not apply since the property is owned by a local authority used for non-residential purposes. The Trial Court and the First Appellate Court, and the High Court, held that the accommodation-control Act applied and dismissed the eviction suit for lack of proven grounds under Section 12. The Supreme Court held that the premises, being owned by a local authority, are immune from the Act itself, and between the landlord (appellant) and sub-tenant (respondent), the landlord-tenant relationship arises with the municipality as the landlord. The key issue is whether tenancy was terminated validly under Section 106 of the Transfer of Property Act; there is no infirmity in the notice. Consequently, the appeal is allowed: the suit for eviction is decreed, the respondent to vacate within six months (with undertaking), rent arrears to be determined by the Executing Court, and no order as to costs. The decision aligns with existing rulings on premiss-based immunity and the applicability of transfer-only remedies.

2003-03-31

T. Lakshmipathi v. P. Nithyananda Reddy

This Supreme Court judgment deals with an eviction challenge under the Andhra Pradesh Buildings (Lease, Rent and Eviction) Control Act, 1960, over a property in Chittoor whose ownership status arose from a partition among co-owners. Respondent No. 1, P. Nithyananda Reddy, remained a co-owner and landlord after partition, while several co-owners sold their interests. Tenants of the property temporarily yielded possession to transferees (appellants Nos. 3–5) and later to appellants Nos. 1–2 through sale deeds; eviction petitions were filed on grounds of bona fide need and rent arrears. The Rent Controller decreed eviction, confirmed by the Appellate Authority and High Court. The central issue was whether eviction could proceed when tenancy rights persisted despite transfers, and whether the doctrine of merger could terminate the tenancy. The Court held that merger requires complete coalescence of the lessee’s and lessor’s interests in the whole property at the same time in one person; because the appellants acquired only a portion of the co-owners’ interests, there was no merger, and tenancy rights remained. Demolition of the superstructure by tenants did not destroy the tenancy since the land continued. The judgment relies on several precedents concerning co-ownership, merger, and estoppel, reinforcing that partial acquisitions do not extinguish tenancy. Consequently, the appeal was dismissed and the eviction decree upheld with costs.

2003-11-17

Nair Service Society v. District Officer, Kerala Public Service Commission and Ors.

Nair Service Society (NSS) challenged a Kerala High Court order directing the Kerala Public Service Commission (KPSC) to advise candidates from the Muslim supplementary list against not-joining-duty vacancies (NJD) in the recruitment for Sub-Engineers for the Kerala State Electricity Board (KSEB). The case turns on the Kerala State and Subordinate Service Rules, 1958, particularly Rules 14–17, which provide a rotating chain of appointments between open competition (merit) and reserved categories (SC/ST/OBC) with a 50% aggregate ceiling for reservation in any recruitment year. KPSC had prepared a main rank list of 177 and a supplementary list of 62 to satisfy reservation requirements. After the main list exhausted, KPSC advised Muslims from the supplementary list for NJD vacancies, prompting NSS to file petitions. The High Court and Division Bench had held that the supplementary list could continue to operate, even after the main list expired, to fill NJD vacancies, thereby potentially breaching the 50% ceiling. The Supreme Court held that the supplementary list has no survival once the main list is exhausted and that advising from it would violate the 50:50 rule, as envisaged by Article 16(4) and related provisions. Nevertheless, appointments already made pursuant to the impugned judgment were not to be disturbed. The appeals were disposed of with no costs.