Delhi Development Authority v. Surender Singh & Ors.

Case / Petition Number:
Civil Appeal No. 1548 of 2023

Case Synopsis & Summary

Delhi Development Authority v. Surender Singh & Ors., along with connected Civil Appeals, concerns the validity of land acquisitions under the Land Acquisition Act, 1894, in light of the 2013 Act's Section 24(2). Notifications under Section 4 and 6 were issued for planned development projects in Delhi, with awards announced in the 1990s–2000s and compensation deposited with the Land Acquisition Collector. A series of writ petitions challenged the lapsing of the acquisitions under Section 24(2) of the 2013 Act on the ground that possession had not been taken or compensation paid to landowners, while the State argued that possession had indeed been taken and the land handed over to the Delhi Development Authority for development. The High Court relied on Pune Municipal Corporation’s decision (2014) and held that the acquisitions had lapsed due to non-payment or disputed title. The Constitution Bench, however, in Indore Development Authority v. Manoharlal and Others (2020) overruled Pune and held that satisfaction of either possession or payment suffices to prevent lapse, and that the word 'or' in Section 24(2) should be read as either 'nor' or 'and' depending on context. It also clarified that deposit of compensation in court does not constitute payment; the proviso to Section 24(2) forms part of the Section. Applying these principles to the present facts, it was found that possession was taken and handed over to the DDA, satisfying one condition. Therefore, the High Court's lapsing findings were set aside, and the appeals were allowed with writ petitions dismissed.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Abhay S. Oka
  • Rajesh Bindal
Judgment Date
2023-04-11
Court Decision / Holding
The appeals are allowed. The writ petitions filed by the respondents before the High Court are ordered to be dismissed.
Final Disposition
Appeals allowed; writ petitions dismissed.

Parties to the Case

Appellants / Petitioners

  • Delhi Development Authority

Respondents

  • Surender Singh and others
  • Ram Singh and others
  • Gyan Chand and others
  • Veena Jain and others

Provisions of Law Cited

Land Acquisition Act, 1894: Section 4Land Acquisition Act, 1894: Section 6Land Acquisition Act, 1894: Section 11Land Acquisition Act, 1894: Section 16Land Acquisition Act, 1894: Section 31(1)Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013: Section 24(2)Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013: Section 24(1)(a)Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013: Section 24(1)(b)Proviso to Section 24(2) (2013 Act)

Legal Doctrines & Maxims

  • Satisfaction of either possession or payment suffices to save the acquisition from lapse under Section 24(2) of the 2013 Act (Indore Development Authority)
  • The word 'or' in Section 24(2) read as 'nor' or 'and' (366.3)
  • Non-deposit of compensation in court does not by itself cause lapse; proviso applies to majority holdings (366.4–366.5)
  • Mode of taking possession under the 1894 Act and Section 24(2) is by inquest/memorandum; once possession is taken, there is no lapse (366.7)
  • Proviso to Section 24(2) of the 2013 Act treated as part of Section 24(2) (366.6)
  • Section 24(2) applies to proceedings pending on 1-1-2014; it does not revive concluded proceedings (366.9)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contended that, following the Constitution Bench decision in Indore Development Authority v. Manoharlal and Others (2020) 8 SCC 129, which overruled Pune Municipal Corporation’s decision, the High Court’s orders should be set aside. They argued that possession or payment suffices to avoid lapse under Section 24(2) of the 2013 Act and that the possession in these cases was taken before a final vesting or payment, thus the acquisitions could not lapse; they further argued that Manav Dharma Trust and subsequent decisions were overruled by Indore Dev. Authority's decision. They asserted the title issues were not to be reopened and that the writ petitions challenge should be decided in light of the updated legal position.

Contentions of Respondents

The respondents argued that the 2013 Act’s Section 24(2) requires either possession or payment to have been completed; as compensation had not been paid or deposit made in court in several cases, the acquisitions should be deemed lapsed. They relied on prior decisions and the High Court's reliance on Pune Municipal and Manav Dharma Trust, while noting that possession had been taken but not necessarily compensated; they argued that the 2013 Act does not revive stale actions and that the High Court’s order was based on existing law.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
Indore Development Authority v. Manoharlal and Others2020 (8) SCC 129PositiveConstitution Bench decision laying down that satisfaction of either possession or payment saves acquisition; used as controlling authority.
Pune Municipal Corporation & Anr. v. Harakchand Misirimal Solanki & Ors.2014 (3) SCC 183OverruledOverruled by Indore Development Authority (2020) per the Constitution Bench.
Govt. of NCT of Delhi v. Manav Dharma Trust and Another2017 (6) SCC 751Mentioned OnlyCited as a precedent for locus; not controlling in light of Indore bench.
Manav Dharma Trust and Another’s Case2017 (6) SCC 751OverruledOverruled by Shiv Kumar v Union of India (2019) 10 SCC 229.
Shiv Kumar v Union of India2019 (10) SCC 229Mentioned OnlyCited to support that Manav Dharma Trust’s position has been overruled.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,588 words•~12 min read

In The Court Record

Delhi Development Authority v. Surender Singh & Ors.

Civil Appeal No. 1548 of 2023, Etc. # **REPORTABLE** # **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** # **CIVIL APPEAL NO. 1548 OF 2023** # **DELHI DEVELOPMENT AUTHORITY …APPELLANT(S)** # **VERSUS** **SURENDER SINGH & ORS. …RESPONDENT(S)** **WITH CIVIL APPEAL NO. 1572 OF 2023** **WITH CIVIL APPEAL NO. 1549 OF 2023** **WITH CIVIL APPEAL NO. 1547 OF 2023** **J U D G M E N T** ## **Rajesh Bindal, J.** 1. This order will dispose of a bunch of appeals as common questions of law and fact are involved. The facts of the cases have been noticed separately. ## **FACTS:** Signature Not Verified **CIVIL APPEAL NO. 1548 OF 2023** Digitally signed by Indu Marwah **(DELHI DEVELOPMENT AUTHORITY VS. SURENDER SINGH** Date: 2023.04.11 17:38:57 IST Reason: **& ORS)** Page 1 of 13 Civil Appeal No. 1548 of 2023, Etc. 2. As pleaded, notification under Section 4 of the Land Acquisition Act, 1894 (for short, “the Act") was issued on 21.03.2003 seeking to acquire land for Rohini Residential Scheme at Delhi. On 19.3.2004, Notification under Section 6 of the Act was issued. The Land Acquisition Collector announced the award under Section 11 of the Act assessing compensation for the acquired land on 12.7.2005. The compensation amount of **₹** 80,40,76,004/- for the acquisition of the land was deposited by the State with the Land Acquisition Collector. 3. A writ petition was filed in the High Court invoking Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (for short “ 2013 Act”) claiming that the acquisition in question has lapsed since neither possession has been taken nor the compensation therefor has been paid. The definite stand of the State before the High Court was that the possession of the land was taken on 31.08.2005 and handed over to the Delhi Development Authority for planned development of Delhi. The title of the writ petitioners was in dispute. Hence, the compensation could not be paid to them. It was deposited with the Land Acquisition Collector. The High Page 2 of 13 Civil Appeal No. 1548 of 2023, Etc. Court after relying upon the judgment of this Court in **Govt. of NCT of Delhi vs. Manav Dharma Trust and another’s** (2017) 6 SCC 751 held that petitioner therein had locus to file the writ petition though not being the recorded owner. It further relied upon the judgment of this Court in **Pune Municipal Corporation & another v. Harakchand Misirimal Solanki & Ors.** (2014) 3 SCC 183 and held that the acquisition has lapsed as the compensation had not been paid to the land owners. Though, the issue of title of the land was left open. ## **CIVIL APPEAL NO. 1572 OF 2023 (DELHI DEVELOPMENT AUTHORITY VS. RAM SINGH & ORS.)** **4.** From the facts as are available on record, it is evident that notification under Section 4 of the Act was issued on 23.09.1989 proposing to acquire the land situated in the revenue estate of village Ghonda Gujran Khadar, Shahdra, Delhi, for the purpose of planned development of Delhi. under Section 6 of the Act was issued on Notification 20.06.1990 and award bearing no. 8/92-93 was announced by the Land Acquisition Collector on 19.06.1992. Page 3 of 13 Civil Appeal No. 1548 of 2023, Etc. **5.** A writ petition was filed in the High Court invoking Section 24(2) of the 2013 Act claiming that the acquisition in question has lapsed as neither possession has been taken nor the compensation therefor has been paid. The appellant’s stand before the High Court was that the possession of the land was taken on 21.03.2007 and handed over to the Delhi Development Authority for planned development of Delhi. The compensation could not be paid to the land owners as they never claimed the same. 6. The High Court relying upon the judgment of this Court in **Pune Municipal Corporation’s** case (supra) held that the acquisition has lapsed as the compensation was not paid to the land owners. ## **CIVIL APPEAL NO. 1549 OF 2023** ## **(GOVT. OF NCT DELHI & ANR. VS. GYAN CHAND & ORS.)** 7. From the facts as are available on record, it is evident that notification under Section 4 of Act seeking to acquire the land situated in revenue estate of villages Tughlakabad, Delhi, was issued on 25.01.1965. The same was followed by notification issued under Section 6 of the Act on 13.02.1969. Page 4 of 13 Civil Appeal No. 1548 of 2023, Etc. The award bearing No. 50-A/1969-70 for the same was announced by the Land Acquisition Collector on 04.11.1981. 8. A writ petition was filed in the High Court invoking Section 24(2) of the 2013 Act claiming that the acquisition in question has lapsed since neither the possession has been taken nor the compensation therefor has been paid. The appellant’s stand before the High Court was that the possession of the land was taken on 23.11.1981 and handed over to the Delhi Development Authority for planned development of Delhi. The compensation could not be paid to the land owners as they never claimed the same. It was further submitted that the entire record pertaining to the compensation was not traceable being old. 9. The High Court relying upon the judgment of this Court in **Pune Municipal Corporation’s** case (supra) held that the acquisition has lapsed as the compensation was not paid to the land owners. ## **CIVIL APPEAL NO. 1547 OF 2023 (DELHI DEVELOPMENT AUTHORITY VS. VEENA JAIN & ORS.)** 10. From the facts of the case as are available on record, it is evident that vide notification dated 23.06.1989 issued Page 5 of 13 Civil Appeal No. 1548 of 2023, Etc. under Section 4 of the Act large chunk of the land including the land of petitioner comprised in Khasra No.490, measuring 1 bigha 1 biswa situated in revenue estate of village Madan Pur Khadar, New Delhi was sought to be acquired for planned development of Delhi. It was followed by the notification issued under Section 6 read with Section 17 of the Act. The Award bearing No.20/92-93 was announced by the Land Acquisition Collector / Collection (DS) on 19.06.1992. 11. A writ petition was filed in the High Court invoking Section 24(2) of the 2013 Act claiming that the acquisition in question has lapsed as neither the possession has been taken nor the compensation therefor has been paid. The appellant’s stand before the High Court was that the possession of the land was taken on 03.12.2012 and handed over to the Delhi Development Authority for planned development of Delhi. The compensation was sent to the Reference Court under Section 30-31 of the Act on account of dispute of apportionment amongst different owners. 12. The High Court relying upon the judgment of this Court in **Manav Dharma Trust and another’s** case (supra) held that the petitioner has locus to file the writ petition though Page 6 of 13 Civil Appeal No. 1548 of 2023, Etc. not being the recorded owner. The High Court further relied upon the judgment of this Court in **Pune Municipal Corporation’s** case (supra) and held that the acquisition has lapsed as the compensation was not paid to the land owners. The question of title of subject land was left open to be decided by the appropriate forum. ## **ARGUMENTS RAISED BY THE COUNSELS:** 13. The arguments raised by learned counsels appearing for the appellants are that in view of the Constitution Bench judgment of this Court in **Indore Development Authority vs. Manoharlal and Others** (2020) 8 SCC 129 whereby earlier judgment of this Court in **Pune Municipal Corporation & Anr.’s** case (supra) was overruled, the orders passed by the High Court, in aforesaid Civil Appeals are liable to be set aside. It was opined by the Constitution Bench that compliance of either of the two conditions i.e. taking over of possession of the land or payment of compensation, is good enough to sustain the acquisition. From the undisputed facts available on record it is evident that in all cases, the possession of land in dispute Page 7 of 13 Civil Appeal No. 1548 of 2023, Etc. was taken after the acquisition was complete and awards were announced. 14. Additional arguments raised in Civil Appeal Nos. 1547 & 1548 of 2023 Civil Appeal No. 1547/2023 are that the judgment in **Manav Dharma Trust and another’s** case (supra) was overruled by this Court in subsequent judgment in **Shiv Kumar vs. Union of India,** (2019) 10 SCC 229 and the aforesaid Civil Appeals are not maintainable. 15. On the other hand, the arguments raised by learned counsel for the respondents are that the writ petitions having been decided on the basis of law as existing on the date of decision by the High Court cannot be set aside on the basis of the subsequent judgment of this Court. The High Court has held that compensation having not been paid, as per the interpretation of Section 24(2) of the 2013 Act by this Court in **Pune Municipal Corporation’s** case (supra), the acquisition proceedings lapsed. It is a matter of fact which has been noticed in the order passed by the High Court that the possession of the land had already been taken by the authority concerned. Page 8 of 13 Civil Appeal No. 1548 of 2023, Etc. 16. Heard learned counsel appearing for the parties and perused the records. ## **OBSERVATIONS:** 17. The Constitution Bench of this Court in **Indore Development Authority's** case (supra) had opined that satisfaction of either of the conditions namely either taking possession of the acquired land or payment of compensation to the landowners would be sufficient to save the acquisition from being lapsed in terms of Section 24(2) of the 2013 Act. Various questions posed before the Constitution Bench of this Court were also answered. Relevant para-Nos. 362 and 366 are extracted below: “362. Resultantly, the decision rendered in Pune Municipal Corporation & Anr. (supra) is hereby overruled and all other decisions in which Pune Municipal Corporation (supra) has been followed, are also overruled. … ... …. 366. In view of the aforesaid discussion, we answer the questions as under: 366.1. Under the provisions of Section 24(1) (a) in case the award is not made as on 1-12014, the date of commencement of the 2013 Act, there is no lapse of proceedings. Page 9 of 13 Civil Appeal No. 1548 of 2023, Etc. Compensation has to be determined under the provisions of the 2013 Act. 366.2. In case the award has been passed within the window period of five years excluding the period covered by an interim order of the court, then proceedings shall continue as provided under Section 24(1)(b) of the 2013 Act under the 1894 Act as if it has not been repealed. 366.3. The word “or” used in Section 24(2) between possession and compensation has to be read as “nor” or as “and”. The deemed lapse of land acquisition proceedings under Section 24(2) of the 2013 Act takes place where due to inaction of authorities for five years or more prior to commencement of the said Act, the possession of land has not been taken nor compensation has been paid. In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly, if compensation has been paid, possession has not been taken then there is no lapse. **(Emphasis supplied)** 366.4. The expression “paid” in the main part of Section 24(2) of the 2013 Act does not include a deposit of compensation in court. The consequence of non- deposit is provided in the proviso to Section 24(2) in case it has not been deposited with respect to majority of landholdings then all beneficiaries (landowners) as on the date of notification for land acquisition Page 10 of 13 Civil Appeal No. 1548 of 2023, Etc. under Section 4 of the 1894 Act shall be entitled to compensation in accordance with the provisions of the 2013 Act. In case the obligation under Section 31 of the Land Acquisition Act, 1894 has not been fulfilled, interest under Section 34 of the said Act can be granted. Nondeposit of compensation (in court) does not result in the lapse of land acquisition proceedings. In case of non-deposit with respect to the majority of holdings for five years or more, compensation under the 2013 Act has to be paid to the “landowners” as on the date of notification for land acquisition under Section 4 of the 1894 Act. 366.5. In case a person has been tendered the compensation as provided under Section 31(1) of the 1894 Act, it is not open to him to claim that acquisition has lapsed under Section 24(2) due to non-payment or non- deposit of compensation in court. The obligation to pay is complete by tendering the amount under Section 31(1). The landowners who had refused to accept compensation or who sought reference for higher compensation, cannot claim that the acquisition proceedings had lapsed under Section 24(2) of the 2013 Act. 366.6. The proviso to Section 24(2) of the 2013 Act is to be treated as part of Section 24(2), not part of Section 24(1)(b). Page 11 of 13 Civil Appeal No. 1548 of 2023, Etc. 366.7. The mode of taking possession under the 1894 Act and as contemplated under Section 24(2) is by drawing of inquest report/memorandum. Once award has been passed on taking possession under Section 16 of the 1894 Act, the land vests in State there is no divesting provided under Section 24(2) of the 2013 Act, as once possession has been taken there is no lapse under Section 24(2). 366.8. The provisions of Section 24(2) providing for a deemed lapse of proceedings are applicable in case authorities have failed due to their inaction to take possession and pay compensation for five years or more before the 2013 Act came into force, in a proceeding for land acquisition pending with the authority concerned as on 1-1-2014. The period of subsistence of interim orders passed by court has to be excluded in the computation of five years. 366.9. Section 24(2) of the 2013 Act does not give rise to new cause of action to question the legality of concluded proceedings of land acquisition. Section 24 applies to a proceeding pending on the date of enforcement of the 2013 Act i.e. 1-1-2014. It does not revive stale and time-barred claims and does not reopen concluded proceedings nor allow landowners to Page 12 of 13 Civil Appeal No. 1548 of 2023, Etc. question the legality of mode of taking possession to reopen proceedings or mode of deposit of compensation in the treasury instead of court to invalidate acquisition.” 18. It is the undisputed fact on the record, as has been noticed in the impugned orders passed by the High Court in the aforesaid Civil Appeals, the possession of the land was taken over by the Land Acquisition Collector and handed over to Delhi Development Authority. Hence, one of the conditions being satisfied, we need not examine any other argument. 19. Keeping in view the aforesaid fact and the law laid down by the Constitution Bench of this Court in **Indore Development Authority’s** case (supra), in our opinion the orders passed by the High Court cannot be legally sustained and the same are accordingly set aside. The appeals are allowed. The writ petitions filed by the respondents before the High Court are ordered to be dismissed. **……………………J.** **[Abhay S. Oka]** **……….……………J. [Rajesh Bindal]** **New Delhi 11.04.2023.** Page 13 of 13
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.