Case Synopsis & Summary

This Supreme Court civil appeal arises from a challenge to a Delhi High Court order in Writ Petition (C) 6478 of 2017, where the High Court declared that the land acquisition proceedings for land acquired in 1964 under the Land Acquisition Act, 1894 had lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The High Court relied on Harbans Kaur and Pune decisions, holding that mere deposit of compensation with the Reference Court did not constitute payment to landowners and that actual possession had not been taken, leading to deemed lapse. The appellant, Delhi Development Authority (DDA), contends that possession was taken in 1967 (panchnama) and the compensation was deposited with the Reference Court in 1967; no landowners’ grievance on non-payment was pursued, and subsequent constitutional bench decisions require re-reading of Section 24(2). The judgment discusses Indore Development Authority v. Manoharlal (2020) which overruled Pune and related cases and clarifies the proper interpretation of Sections 24(1)(a), 24(1)(b), 24(2) of the 2013 Act, and the status of deposit versus payment. The Court holds that the 2013 Act’s deeming provisions apply to proceedings pending as of 1-1-2014 and that, given possession in 1967 and no challenge until 2017, there is no lapse. Consequently, the appeal is allowed and the High Court’s judgment is set aside with no costs."

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • M.R. Shah
Judgment Date
2023-01-20
Court Decision / Holding
Appeal allowed. The High Court’s judgment declaring that the acquisition had lapsed under Section 24(2) of the 2013 Act is quashed; the acquisition proceedings are not deemed to have lapsed; the decision reinforces that possession taken in 1967 and compensation deposited in court do not amount to lapse under the 2013 Act; no costs.
Final Disposition
The appeal is allowed; High Court’s judgment declaring lapse under Section 24(2) of the 2013 Act is quashed and set aside; acquisition proceedings are not deemed to have lapsed; no costs; pending applications disposed of.

Parties to the Case

Appellants / Petitioners

  • Delhi Development Authority

Respondents

  • Rajesh Dua and Ors.

Provisions of Law Cited

Land Acquisition Act, 1894 (Section 16, Section 4)Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (Section 24(2); Section 24(1)(a); Section 24(1)(b); Proviso to Section 24(2))Section 31 (1894 Act)Section 34 (1894 Act)

Legal Doctrines & Maxims

  • Deemed lapse under Section 24(2) of the 2013 Act when five years of inaction occur prior to commencement
  • Deposit in court is not payment to landowners (distinguished from actual payment)
  • Proviso to Section 24(2) to be treated as part of Section 24(2) (not part of Section 24(1)(b))
  • Posession taken under 1894 Act occurs by drawing an inquest report/memorandum; once possession is taken under Section 16, land vests in the State
  • Five-year computation excludes periods of interim orders; applies to proceedings pending on 1-1-2014
  • If a person has been tendered compensation under Section 31(1), no lapse can be claimed under 24(2)

Submissions & Arguments

Contentions of Appellants / Petitioners

The Delhi Development Authority contends that the land acquisition proceedings initiated under the Land Acquisition Act, 1894 for land acquired in 1964 were validly completed with possession taken in 1967 and compensation deposited with the Reference Court in 1967. Citing Indore Development Authority v. Manoharlal (2020) 8 SCC 129, the appellant submits that the Pune decision (Pune Municipal Corpn. v. Harakchand Misirimal Solanki, 2014) 3 SCC 183 and Sree Balaji Nagar Residential Assn. v. State of Tamil Nadu (2015) 3 SCC 353 were overruled or restricted, and that deposit of compensation in court does not constitute payment to landowners. The 2013 Act’s Section 24(2) deeming provision should be examined with reference to possession already effected and the five-year clock before 2014, thus negating any lapse. The appeal seeks to set aside the High Court’s deeming lapse, restore the acquisition as valid, and dismiss the writ petition’s finding that the proceedings lapsed.

Contentions of Respondents

The respondents contend that deposit of compensation with the Reference Court cannot be treated as payment to landowners; the High Court correctly held that the acquisition could lapse under Section 24(2) of the 2013 Act due to non-payment and non-possession, following the Pune and Harbans Kaur line of authority, until Indore Development Authority overruled those precedents. They argue the 2013 Act’s deeming provisions apply to pending proceedings as of 1-1-2014, and that non-deposit or non-payment of compensation would result in lapse unless the authorities timely acted; thus, the writ petition should be allowed and the lapse held valid.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
Pune Municipal Corpn. v. Harakchand Misirimal Solanki(2014) 3 SCC 183OverruledOverruled by Indore Development Authority v. Manoharlal (2020) 8 SCC 129; Pune’s reasoning formed the basis for the High Court’s view now rejected.
Smt. Harbans Kaur v. Govt. of NCT of Delhi and Ors.W.P.(C) 5358 of 2014Overruled relied on Pune; with Pune overruled and Indore clarifying the law, Harbans Kaur’s reasoning is not to be followed.
Sree Balaji Nagar Residential Assn. v. State of Tamil Nadu(2015) 3 SCC 353OverruledCannot be said to be laying down good law; overruled by Indore and subsequent discussion.
Indore Development Authority v. Shailendra(2018) 3 SCC 412DistinguishedIndore (2018) not placed for consideration in present judgment and cannot prevail in light of Indore (2020); distinguished.
Indore Development Authority v. Manoharlal and Ors.(2020) 8 SCC 129PositiveConstitution Bench decision relied upon to overrule Pune and Harbans Kaur and to interpret 24(2) and the 2013 Act.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,701 words•~8 min read

In The Court Record

Delhi Development Authority v. Rajesh Dua and Ors.

## **REPORTABLE** ## **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** **CIVIL APPEAL NO. 363 OF 2023 (@ SLP (C) NO. 1500 OF 2023) (@ DIARY NO. 6078 OF 2022)** ## **Delhi Development Authority** ## **…Appellant(s)** ## **Versus** ## **Rajesh Dua and Ors.** **…Respondent(s)** ## **J U D G M E N T** ## **M.R. SHAH, J.** 1. Feeling aggrieved and dissatisfied with the impugned judgment and order passed by the High Court of Delhi at New Delhi in Writ Petition (C) No. 6478 of 2017 by which the High Court has allowed the said writ petition preferred by the respondent Nos. 1 and 2 herein and has declared that the acquisition proceedings initiated under the Land Signature Not Verified Acquisition Act, 1894 (hereinafter referred to as “Act, 1894”) with regard Digitally signed by Neetu Sachdeva Date: 2023.01.20 16:12:12 IST Reason: to the land in question is deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, 1 Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as “Act, 2013”), the Delhi Development Authority (DDA) has preferred the present appeal. 2. In the present case, the land in question was acquired in the year 1964 and the award was declared in the year 1967. According to the Land Acquisition Collector (LAC) and so stated in the counter affidavit filed before the High Court, the possession of the land in question was taken over in the year 1967 by drawing the panchnama. The compensation with respect to the land in question was duly deposited with the Reference Court in the year 1967 itself. That thereafter the respondent Nos. 1 and 2 herein – original writ petitioners filed the writ petition before the High Court in the year 2017 and prayed to declare that the acquisition with respect to the land in question is deemed to have lapsed under Section 24(2) of the Act, 2013 as the compensation was not actually tendered/paid to the landowners. Relying upon its earlier decision in the case of **Smt. Harbans Kaur Vs. Govt. of NCT of Delhi and Ors.** [W.P.(C) 5358 of 2014, decided on 02.02.2015], in which after relying upon the decision of this Court in the case of **Pune Municipal Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors., (2014) 3 SCC 183** , it was held that the depositing of the amount of compensation with the Reference Court cannot be regarded as compensation having been paid to the landowners and the High 2 Court by the impugned judgment and order has allowed the writ petition and has declared that the acquisition with respect to the land in question is deemed to have lapsed as actual physical possession of the subject land has not been taken over by the land acquiring agency. Feeling aggrieved and dissatisfied with the impugned judgment and order, the Delhi Development Authority has preferred the present appeal. 3. We have heard the learned counsel appearing on behalf of the respective parties at length. 4. At the outset, it is required to be noted that according to the LAC, the amount of compensation was deposited with the Reference Court in the year 1967. Even the possession of the land in question was taken over by drawing the panchnama, which is a permissible mode as observed and held by this Court in the Constitution Bench decision in the case of **Indore Development Authority Vs. Manoharlal and Ors., (2020) 8 SCC 129.** 4.1 Even otherwise, it is required to be noted that while deciding the case of **Smt. Harbans Kaur (supra)** , the High Court has relied upon the earlier decision of this Court in the case of **Pune Municipal Corporation and Anr (supra).** However, the decision of this Court in the case of **Pune Municipal Corporation and Anr. (supra)** has been specifically overruled by the Constitution Bench of this Court in the case of **Indore** 3 ## **Development Authority Vs. Manoharlal and Ors., (2020) 8 SCC 129** . In paragraphs 365 and 366, the Constitution Bench of this Court has observed and held as under:- “ **365.** Resultantly, the decision rendered in Pune Municipal Corpn. [Pune Municipal Corpn. v. Harakchand Misirimal Solanki, (2014) 3 SCC 183] is hereby overruled and all other decisions in which Pune Municipal Corpn. [Pune Municipal Corpn. v. Harakchand Misirimal Solanki, (2014) 3 SCC 183] has been followed, are also overruled. The decision in Sree Balaji Nagar Residential Assn. [Sree Balaji Nagar Residential Assn. v. State of T.N., (2015) 3 SCC 353] cannot be said to be laying down good law, is overruled and other decisions following the same are also overruled. In Indore Development Authority v. Shailendra [(2018) 3 SCC 412], the aspect with respect to the proviso to Section 24(2) and whether “or” has to be read as “nor” or as “and” was not placed for consideration. Therefore, that decision too cannot prevail, in the light of the discussion in the present judgment. **366.** In view of the aforesaid discussion, we answer the questions as under: **366.1.** Under the provisions of Section 24(1)(a) in case the award is not made as on 1-1-2014, the date of commencement of the 2013 Act, there is no lapse of proceedings. Compensation has to be determined under the provisions of the 2013 Act. **366.2.** In case the award has been passed within the window period of five years excluding the period covered by an interim order of the court, then proceedings shall continue as provided under Section 24(1)(b) of the 2013 Act under the 1894 Act as if it has not been repealed. 4 **366.3.** The word “or” used in Section 24(2) between possession and compensation has to be read as “nor” or as “and”. The deemed lapse of land acquisition proceedings under Section 24(2) of the 2013 Act takes place where due to inaction of authorities for five years or more prior to commencement of the said Act, the possession of land has not been taken nor compensation has been paid. In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly, if compensation has been paid, possession has not been taken then there is no lapse. **366.4.** The expression “paid” in the main part of Section 24(2) of the 2013 Act does not include a deposit of compensation in court. The consequence of non-deposit is provided in the proviso to Section 24(2) in case it has not been deposited with respect to majority of landholdings then all beneficiaries (landowners) as on the date of notification for land acquisition under Section 4 of the 1894 Act shall be entitled to compensation in accordance with the provisions of the 2013 Act. In case the obligation under Section 31 of the Land Acquisition Act, 1894 has not been fulfilled, interest under Section 34 of the said Act can be granted. Non-deposit of compensation (in court) does not result in the lapse of land acquisition proceedings. In case of non-deposit with respect to the majority of holdings for five years or more, compensation under the 2013 Act has to be paid to the “landowners” as on the date of notification for land acquisition under Section 4 of the 1894 Act. **366.5.** In case a person has been tendered the compensation as provided under Section 31(1) of the 1894 Act, it is not open to him to claim that acquisition has lapsed under Section 24(2) due to non-payment or nondeposit of compensation in court. The obligation to pay is complete by tendering the amount under Section 31(1). The landowners who had refused to accept compensation or who sought reference for higher compensation, cannot 5 claim that the acquisition proceedings had lapsed under Section 24(2) of the 2013 Act. **366.6.** The proviso to Section 24(2) of the 2013 Act is to be treated as part of Section 24(2), not part of Section 24(1)(b). **366.7.** The mode of taking possession under the 1894 Act and as contemplated under Section 24(2) is by drawing of inquest report/memorandum. Once award has been passed on taking possession under Section 16 of the 1894 Act, the land vests in State there is no divesting provided under Section 24(2) of the 2013 Act, as once possession has been taken there is no lapse under Section 24(2). **366.8.** The provisions of Section 24(2) providing for a deemed lapse of proceedings are applicable in case authorities have failed due to their inaction to take possession and pay compensation for five years or more before the 2013 Act came into force, in a proceeding for land acquisition pending with the authority concerned as on 1-1-2014. The period of subsistence of interim orders passed by court has to be excluded in the computation of five years. **366.9.** Section 24(2) of the 2013 Act does not give rise to new cause of action to question the legality of concluded proceedings of land acquisition. Section 24 applies to a proceeding pending on the date of enforcement of the 2013 Act i.e. 1-1-2014. It does not revive stale and time-barred claims and does not reopen concluded proceedings nor allow landowners to question the legality of mode of taking possession to reopen proceedings or mode of deposit of compensation in the treasury instead of court to invalidate acquisition.” 6 5. Applying the law laid down by this Court in the case of **Indore Development Authority (supra)** , and considering the fact that the compensation with respect to the land in question was deposited in the Reference Court in the year 1967 and that between 1967 and 2017, nothing is on record to show that the writ petitioners were praying and/or a grievance was made by the original landowners with respect to nonpayment of compensation and that the possession of the land in question was stated to be taken in the year 1967 by drawing the panchnama, the impugned judgment and order passed by the High Court is unsustainable and the same deserves to be quashed and set aside and is accordingly quashed and set aside. Present appeal is accordingly allowed. No costs. Pending application, if any, also stands disposed of. ………………………………….J. **[M.R. SHAH]** NEW DELHI; ………………………………….J. JANUARY 20, 2023. **[C.T. RAVIKUMAR]** 7
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.