Delhi Development Authority v. Rajan Sood & Ors.

Case / Petition Number:
CIVIL APPEAL NO. 1927 OF 2022; CIVIL APPEAL NO. 1928 OF 2022

Case Synopsis & Summary

The Delhi Development Authority (DDA) along with the Government of NCT of Delhi challenged a Delhi High Court ruling dated 30.08.2016 that declared the Land Acquisition proceedings under the Land Acquisition Act, 1894 in respect of certain lands to be deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The High Court’s decision turned on the petitioners’ case that possession of the land had already been taken and compensation not paid, so lapse should be deemed despite subsequent actions. The Supreme Court undertook a detailed analysis of the statutory framework and prior case law, noting that Pune Municipal Corporation v. Harakchand Misirimal Solanki (2014) 3 SCC 183 had been overruled by Indore Development Authority and related opinions, and that the controlling doctrine in Indore Development Authority requires careful consideration of possession and payment timelines, interim orders, and the fact that payment in court is not the same as tendering to landowners. The Court emphasized that interim stay orders and the five-year window under Section 24(2) must be interpreted in light of Indore, and that non-deposit in court does not automatically trigger lapse if possession was taken. It ultimately allowed the appeals, quashing the High Court’s deeming-lapse finding and restoring the authorities’ rights to proceed.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • M. R. Shah
  • B. V. Nagarathna
Judgment Date
2022-03-29
Court Decision / Holding
The present appeals are allowed. The impugned judgment and order of the High Court in Writ Petition (C) No. 1043/2015 declaring that the land acquisition proceedings under the Act, 1894 with respect to the land in question are deemed to have lapsed under Section 24(2) of the Act, 2013, is quashed and set aside. There shall be no order as to costs.
Final Disposition
Appeals allowed; High Court judgment declaring lapse under Section 24(2) of the 2013 Act is quashed and set aside; no order as to costs.

Parties to the Case

Appellants / Petitioners

  • Delhi Development Authority

Respondents

  • Rajan Sood & Ors.

Legal Representation & Advocates

Counsels for Respondents

  • • Ms. Pinky Anand

Provisions of Law Cited

Land Acquisition Act, 1894Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013Section 24(2) of the 2013 ActSection 24(1)(a) of the 2013 ActSection 24(1)(b) of the 2013 ActProviso to Section 24(2) of the 2013 ActSection 4 of the Lands Acquisition Act, 1894Section 16 of the Lands Acquisition Act, 1894Section 31 of the Lands Acquisition Act, 1894Section 34 of the Lands Acquisition Act, 1894Section 12(2) of the Lands Acquisition Act, 1894Section 48 of the Lands Acquisition Act, 1894

Legal Doctrines & Maxims

  • Deemed lapse under Section 24(2) of the 2013 Act is limited by five years of inaction prior to 1-1-2014; lapse requires absence of both possession and payment for five years.
  • The words 'or' between possession and compensation in Section 24(2) are to be read as 'nor' or 'and' depending on context, with lapse arising only where both possession has not been taken and compensation has not been paid for the statutory window.
  • Pune Municipal Corporation v. Harakchand Misirimal Solanki (2014) 3 SCC 183 is overruled by Indore Development Authority (2018/2020) on the interpretation of Section 24(2).
  • Indore Development Authority v. Shailendra (2018) 3 SCC 412; (2018) 2 SCC (Civ) 426 clarifies the 24(2) regime and the exclusion of interim-order periods from five-year calculations.
  • Indore Development Authority v. Manoharlal (2020) 8 SCC 129 reinforces the Indore approach to 24(2) in pending proceedings as of 1-1-2014.

Submissions & Arguments

Contentions of Appellants / Petitioners

Counsel for the DDA contended that possession of the land was taken on 23 September 1986, with a punchnama; compensation was tendered to the owner Shiv Kumar though not accepted; Rs. 2 crore was deposited with the Land and Building Department. The petitioners claim continued possession and lack of actual payment/tendering of compensation—thus lapse cannot be inferred. They argued that the High Court erred by relying on Pune Municipal Corporation, a line of authority overruled by Indore Development Authority. They relied on Indore to exclude time under interim orders and to interpret Section 24(2) consistently with possession having already been taken or compensation paid, so as not to deem lapse under the 2013 Act. In alternative, even if possession remained, stay orders from 2011 should be excluded per Indore. They urged allowing the appeals to restore the DDA’s case.

Contentions of Respondents

The respondents contended that the High Court found the petitioners in continued possession and that neither possession nor compensation was properly paid, tendered, or deposited. The interim order in 2011 prevented coercive action and extended into the period after 2014; thereby the five-year clock under Section 24(2) of the 2013 Act had accrued, rendering lapse. They relied on the statutory language of Section 24(2) as well as the reliance on Pune’s decision prior to its overruling, arguing that the petitioners’ title is tainted by fraud and would be protected only if the lapse were recognized. They asserted that the 2013 Act’s transitional provisions apply to pending proceedings at 1 January 2014. They urged upholding the High Court’s conclusion that lapse had occurred and rejecting the DDA’s appeal.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
Pune Municipal Corporation v. Harakchand Misirimal Solanki(2014) 3 SCC 183OverruledOverruled by Indore Development Authority in para 365-366; Pune line of authority rejected.
Sree Balaji Nagar Residential Assn. v. State of Tamil Nadu(2015) 3 SCC 353OverruledOverruled by later Indore Development Authority decision.
Indore Development Authority v. Shailendra(2018) 3 SCC 412PositiveCited as controlling precedent clarifying Section 24(2) interpretation and exclusion of interim-order period.
Indore Development Authority v. Shailendra(2018) 2 SCC (Civ) 426PositiveAlternative citation reinforcing Indore’s interpretation of 24(2).
Indore Development Authority v. Manoharlal(2020) 8 SCC 129PositiveSubsequent Indore decision cited to support conclusions on 24(2).
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,433 words•~16 min read

In The Court Record

Delhi Development Authority v. Rajan Sood & Ors.

## **REPORTABLE** ## IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION ## **CIVIL APPEAL NO. 1927 OF 2022** Delhi Development Authority ..Appellant (S) Versus Rajan Sood & Ors. ..Respondent (S) ## With ## **CIVIL APPEAL NO. 1928 OF 2022** ## **J U D G M E N T** ## **M. R. Shah, J.** 1. Feeling aggrieved and dissatisfied with the impugned judgment and order dated 30.08.2016 passed by the High Court of Delhi at New Delhi in Writ Petition (C) No. 1034/2015, by which the High Court has allowed the said writ petition preferred by the private respondents herein – original writ petitioners and has declared that the Signature Not Verified Digitally signed by R Natarajan initiated under the Land Date: 2022.03.29 acquisition proceedings 16:40:40 IST Reason: Acquisition Act, 1894 (hereinafter referred to as the Act, 1 1894) in respect of the subject lands are deemed to have lapsed under sub­section (2) of section 24 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as the Act, 2013), Delhi Development Authority (DDA) and Government of NCT of Delhi have preferred the present appeals. 2. Private respondent No.1 and 2 herein ­ original writ petitioners filed the writ petition before the High Court for a declaration that the acquisition proceedings initiated under the Act, 1894 in respect of the subject lands are deemed to have lapsed under sub­section (2) of section 24 of the Act, 2013. It was the case on behalf of the original writ petitioners before the High Court that as the possession of the land in question is with them and no compensation has been paid, the land acquisition proceedings are deemed to have lapsed. Heavy reliance was placed on the decision of this Court in the case of **Pune Municipal Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors, (2014) 3 SCC 183** . 2 - 2.1 The petition was opposed by the appellants herein and others. It was the specific case on behalf of the DDA that as such the compensation was tendered to one Shiv Kumar S/o Devi Chand. Relying upon the decision of this Court in the case of **Pune Municipal Corporation** (supra), the High Court, by the impugned judgment and order has allowed the said writ petition and has declared that the acquisition proceedings initiated under the Act, 1894 in respect of the subject lands are deemed to have lapsed under sub­section (2) of section 24 of the Act, 2013. - 2.2 Feeling aggrieved and dissatisfied with the impugned judgment and order passed by the High Court, DDA and Government of NCT of Delhi have preferred the present appeals. 3. Learned counsel appearing on behalf of the DDA has vehemently submitted that in the facts and circumstances of the case the High Court has materially erred in declaring that the acquisition proceedings have lapsed under sub­section (2) of section 24 of the Act, 2013. 3 - 3.1 It is submitted on behalf of the DDA that in the present case as such the possession was already taken over by the Authority on 23.09.1986 after following the due procedure as required and even a punchnama was also drawn, which was the requirement while taking over possession. - 3.2 It is urged that even the compensation was tendered to the recorded owner ­ Shri Shiv Kumar through notice under section 12(2) of the Act, 1894 but recorded owner never came forward to accept the same. It is submitted that therefore, the original writ petitioners cannot be permitted to take the benefit under sub­section (2) of section 24 of the Act, 2013. - 3.3 It is further submitted that even the amount of compensation of Rs.2.00 crores was deposited by the DDA with the Land and Building Department towards compensation. Therefore, the original writ petitioners are not entitled to the benefit of deemed lapse. - 3.4 It is further contended by learned counsel appearing on behalf of the DDA and the Government of NCT of Delhi 4 that as such the original writ petitioners were not having any locus to file the writ petition as their title to the property is shrouded with fraud and investigation is pending with the Anti­Corruption Branch. It is submitted that as the possession of the land in question was already taken over as far as back on 23.09.1986 and even compensation of Rs.2.00 crores was deposited with the Land and Building Department, in view of the subsequent decision in the case of **Indore Development Authority Vs. Manoharlal and Ors., (2020) 8 SCC 129** , it cannot be said the acquisition proceedings have lapsed under sub­ section (2) of section 24 of the Act, 2013. 3.5 It is further submitted on behalf of the appellants that while passing the impugned judgment and order, the High Court has relied on the decision of this Court in the case of **Pune Municipal Corporation** (supra). That, the said decision has been subsequently overruled by the Constitution bench of this Court in the case of **Indore Development Authority** (supra). 5 3.6 In the alternative, it is submitted by the learned counsel appearing on behalf of the respective appellants that assuming, without admitting that the possession of the land in question remain with the original writ petitioners, in that case also, as there was an order of stay granted by the High Court in the year 2011, in the writ petition filed by the original writ petitioners and the High Court granted the interim order of taking no coercive action/order qua the land, therefore, in view of the decision of this Court in the case of **Indore Development Authority** (supra), the period under which the stay was operative is to be excluded. Reliance is placed on para 366.8 of the decision of this Court in the case of **Indore Development Authority** (supra). - 3.7 Making the above submission and relying upon the aforesaid decision, it is prayed to allow the present appeals. 4. Both these appeals are vehemently opposed by Ms. Pinky Anand, learned Senior Advocate appearing on behalf of 6 the original writ petitioners. Counter affidavits have been filed on behalf of private respondent No.1 and 2 – original writ petitioners opposing the present appeals. - 4.1 It is vehemently submitted by Ms. Anand, learned Senior Advocate appearing on behalf of the original writ petitioners that as such there are specific findings recorded by the High Court that the original writ petitioners continue to be in physical possession and therefore, as neither the actual possession of land in question was taken over nor any compensation was paid and/or even tendered to the original writ petitioners. It is rightly held that acquisition proceedings have lapsed. - 4.2 It is urged that in fact in the earlier order passed by the High Court on 09.11.2011 in writ petition No.7714/2011, the Division Bench directed the authority to consider their application under section 48 of the Act, 1894 and to decide it on merits. That as per section 48 of the Act, 1894 only in a case where possession of the land is not taken over by the acquiring authority, then only, the application under section 48 of the Act, 1894 would be 7 maintainable. It is submitted therefore, when the Division Bench directed the authority to consider the application of the petitioners under section 48 of the Act, 1894 on merits, it is to be presumed that only original writ petitioners continue to remain possession. It is contended that the authority might have taken ex­parte possession on paper as alleged on 23.09.1986, however, the original writ petitioners remained in possession actually. It is further submitted by learned Senior Advocate appearing on behalf of the original writ petitioners that there is also a specific finding recorded by the High Court that the authorities have failed to prove that any amount of compensation was paid and/or tendered to the original writ petitioners or even deposited with the treasury. It is submitted that when the original writ petitioners remain in possession and neither the compensation was tendered nor it was paid, the twin conditions to declare the acquisition proceedings as having lapsed under sub­ section (2) of section 24 of the Act, 2013 have been satisfied. It is therefore submitted that the High Court has not committed any error in declaring that the 8 acquisition proceedings in respect of the subject lands are deemed to have lapsed under sub­section (2) of section 24 of the Act, 2013 5. We have heard learned counsel appearing on behalf of the respective parties at length. 6. By the impugned judgment and order the High Court has held and declared that the land acquisition proceedings in respect of the land in question are deemed to have lapsed under sub­section (2) of section 24 of the Act, 2013. While holding and declaring so the High Court has relied upon decision of this Court in the case of **Pune Municipal Corporation** (supra). However, the said decision of this Court has been subsequently overruled by the decision of this Court in the case of **Indore Development Authority** (supra). In paragraph 365 to 366, this Court in the case of **Indore Development Authority** (supra) has observed and held as under: ­ **“365.** Resultantly, the decision rendered in _Pune Municipal Corpn._ [ _Pune Municipal Corpn._ v. _Harakchand Misirimal Solanki_ , (2014) 3 SCC 183 : (2014) 2 SCC (Civ) 274] is hereby overruled and all other decisions in which _Pune Municipal_ 9 _Corpn._ [ _Pune Municipal Corpn._ v. _Harakchand Misirimal Solanki_ , (2014) 3 SCC 183 : (2014) 2 SCC (Civ) 274] has been followed, are also overruled. The decision in _Sree Balaji Nagar Residential Assn._ [ _Sree Balaji Nagar Residential Assn._ v. _State of T.N._ , (2015) 3 SCC 353 : (2015) 2 SCC (Civ) 298] cannot be said to be laying down good law, is overruled and other decisions following the same are also overruled. In _Indore Development Authority_ v. _Shailendra_ [ _Indore Development Authority_ v. _Shailendra_ , (2018) 3 SCC 412 : (2018) 2 SCC (Civ) 426] , the aspect with respect to the proviso to Section 24(2) and whether “or” has to be read as “nor” or as “and” was not placed for consideration. Therefore, that decision too cannot prevail, in the light of the discussion in the present judgment. **366.** In view of the aforesaid discussion, we answer the questions as under: **366.1.** Under the provisions of Section 24(1)( _a_ ) in case the award is not made as on 1­1­2014, the date of commencement of the 2013 Act, there is no lapse of proceedings. Compensation has to be determined under the provisions of the 2013 Act. **366.2.** In case the award has been passed within the window period of five years excluding the period covered by an interim order of the court, then proceedings shall continue as provided under Section 24(1)( _b_ ) of the 2013 Act under the 1894 Act as if it has not been repealed. **366.3.** The word “or” used in Section 24(2) between possession and compensation has to be read as “nor” or as “and”. The deemed lapse of land acquisition proceedings under Section 24(2) of the 2013 Act takes place where due to inaction of authorities for five years or more prior to commencement of the said Act, the possession of land has not been taken nor compensation has been paid. In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly, if compensation has been paid, possession has not been taken then there is no lapse. 10 **366.4.** The expression “paid” in the main part of Section 24(2) of the 2013 Act does not include a deposit of compensation in court. The consequence of non­deposit is provided in the proviso to Section 24(2) in case it has not been deposited with respect to majority of landholdings then all beneficiaries (landowners) as on the date of notification for land acquisition under Section 4 of the 1894 Act shall be entitled to compensation in accordance with the provisions of the 2013 Act. In case the obligation under Section 31 of the Land Acquisition Act, 1894 has not been fulfilled, interest under Section 34 of the said Act can be granted. Non­deposit of compensation (in court) does not result in the lapse of land acquisition proceedings. In case of non­deposit with respect to the majority of holdings for five years or more, compensation under the 2013 Act has to be paid to the “landowners” as on the date of notification for land acquisition under Section 4 of the 1894 Act. **366.5.** In case a person has been tendered the compensation as provided under Section 31(1) of the 1894 Act, it is not open to him to claim that acquisition has lapsed under Section 24(2) due to non­ payment or non­deposit of compensation in court. The obligation to pay is complete by tendering the amount under Section 31(1). The landowners who had refused to accept compensation or who sought reference for higher compensation, cannot claim that the acquisition proceedings had lapsed under Section 24(2) of the 2013 Act. **366.6.** The proviso to Section 24(2) of the 2013 Act is to be treated as part of Section 24(2), not part of Section 24(1)( _b_ ). **366.7.** The mode of taking possession under the 1894 Act and as contemplated under Section 24(2) is by drawing of inquest report/memorandum. Once award has been passed on taking possession under Section 16 of the 1894 Act, the land vests in State there is no divesting provided under Section 24(2) of the 2013 Act, as once possession has been taken there is no lapse under Section 24(2). **366.8.** The provisions of Section 24(2) providing for a deemed lapse of proceedings are applicable in case 11 authorities have failed due to their inaction to take possession and pay compensation for five years or more before the 2013 Act came into force, in a proceeding for land acquisition pending with the authority concerned as on 1­1­2014. The period of subsistence of interim orders passed by court has to be excluded in the computation of five years. **366.9.** Section 24(2) of the 2013 Act does not give rise to new cause of action to question the legality of concluded proceedings of land acquisition. Section 24 applies to a proceeding pending on the date of enforcement of the 2013 Act i.e. 1­1­2014. It does not revive stale and time­barred claims and does not reopen concluded proceedings nor allow landowners to question the legality of mode of taking possession to reopen proceedings or mode of deposit of compensation in the treasury instead of court to invalidate acquisition.” 7. The High Court while passing the impugned judgment and order has observed that the possession of the land in question continued with the original writ petitioners and that the compensation was neither paid nor even tendered to the original writ petitioners. However, by holding that the original writ petitioners have continued to remain in possession, the High Court has relied upon the earlier order dated 09.11.2011 passed in writ petition No.7714/2011, by which the High Court directed the authority to consider their application under section 48 of the Act, 1894 on merits. However, it was the specific case 12 on behalf of the authority before the learned Single Judge that the possession of the land in question was already taken over on 23.09.1986 and even the compensation amount of Rs.2.00 crores was deposited with the land and building department. - 7.1 It is the case on behalf of the original writ petitioners that a purported letter dated 23.09.1986 allegedly taking symbolic possession was never disclosed by appellants in the proceedings conducted before the High Court on two separate occasions and the same has been filed for the first time in the present proceedings. The aforesaid is not correct. Even in the impugned order itself in paragraph 2, the High Court has noted the submissions on behalf of the appellants to the effect that the possession was taken over on 23.09.1986. Therefore, it cannot be said such a plea is taken for the first time before this Court. It is the case on behalf of the original writ petitioners, relying upon the earlier order passed by the High Court dated 09.11.2011 in writ petition No.7714/2011 that, the original writ petitioners continue to be in possession and 13 the actual possession has never been taken over. However, it is required to be noted that even in the order dated 09.11.2011, there was no specific finding given by the High Court that the original writ petitioners are in possession of the land in question. On the contrary, it is observed that the authority to consider the application under section 48 of the Act, 1894 on merits on the assumption of the possession being with the original writ petitioners. Therefore, while passing the order dated 09.11.2011 also, the High Court assumed the original writ petitioners are in possession hence as such no specific finding was given to the effect that the original writ petitioners are in possession. 7.2 It is next contented on behalf of the original writ petitioners that the alleged possession on 23.09.1986 is illegal and it was a paper possession. However, it is submitted on behalf of the appellants that possession of land in question was taken over by drawing the punchnama which can be said to be sufficient compliance of the requirement while taking possession. 14 The High Court has also doubted the compensation being tendered as contended on behalf of the appellant. - 7.3 Be that as it may. Assuming for the sake of argument that the original writ petitioners are found to be in possession and the compensation was not tendered, in that case also as can be seen from the order passed by the High Court on 09.11.2011 in writ petition No.7714/2011, the authority was restrained from taking any coercive action in respect of the land in question. Therefore, in view of the subsequent decision of this Court in the case of **Indore Development Authority** (supra ­ paragraph 366.8), the period, during which the interim order is/was operative, has to be excluded in the computation of five years’ period. In the present case even, it is the contention on behalf of the original writ petitioners that the order of no coercive action was directed to be continued till the application under section 48 of the Act, 1894 was decided. It is the specific case on behalf of the original writ petitioners before this Court and even so stated in the written submissions that till 15 date no decision is taken on the application under section 48 of the Act, 1894. Meaning thereby the direction/stay granted by the High Court while passing the order dated 09.11.2011 in writ petition No.7714/2011 continued when the Act, 2013 came into force. - 7.4 In that view of the matter and considering the decision of this Court in case of **Indore Development Authority** (supra), it cannot be said that the land acquisition proceedings are deemed to have lapsed under sub­section (2) of section 24 of the Act, 2013. 8. Applying the law laid down by this Court in the case of **Indore Development Authority** (supra), more particularly, paragraph 366, it cannot be said that the land acquisition proceedings are deemed to have lapsed. 9. In view of the above and for the reasons stated above and on the aforesaid ground alone that at the time when the Act, 2013 came into force there was a stay granted by the High Court vide order dated 09.11.2011 in writ petition No.7714/2011 restraining the authority taking any 16 coercive action in respect of the land in question, the impugned judgment and order passed by the High Court declaring that the land acquisition proceedings are deemed to have lapsed under sub­section (2) of section 24 of the Act, 2013, is unsustainable. 10. In view of the above and for the reasons stated above, the present appeals are allowed. The impugned judgment and order passed by the High Court in Writ Petition (C) No.1043/2015 declaring that the land acquisition proceedings under the Act, 1894 with respect to the land in question are deemed to have lapsed under sub­section (2) of section 24 of the Act, 2013, is hereby quashed and set aside. The present appeals are allowed to the aforesaid extent, accordingly. There shall be no order as to costs. …………………………………J. - **(M. R. SHAH)** …………………………………J. ## **(B.V. NAGARATHNA)** New Delhi, March 29, 2022. 17
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.