Delhi Development Authority v. Nem Chand Sharma and Ors.

Case / Petition Number:
Civil Appeal No. 395 of 2023 (SLP(C) No. 1586 of 2023)

Case Synopsis & Summary

This is a Civil Appeal preferred by the Delhi Development Authority (DDA) challenging a Delhi High Court writ petition judgment which held that the acquisition of land under the Land Acquisition Act, 1894, was deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (2013 Act). The High Court had accepted the petitioners’ case that failure to clarify compensation and to satisfy Sections 30 and 31 of the 1894 Act rendered the acquisition lapsed. The Supreme Court traces the jurisprudence, noting that Pune Municipal Corporation v. Harakchand Misirimal Solanki (2014) has been overruled by the Constitution Bench in Indore Development Authority v. Manoharlal and Ors. (2020), which laid down twin conditions for lapse under Section 24(2): (i) non-takeover of possession and (ii) non-payment of compensation. In this matter, possession was already taken in 1990 and subsequently in 2007; the Constitution Bench clarified that if possession has been taken or compensation paid (or tendered), lapse does not arise. The Court also held that non-deposit of compensation in court does not automatically cause lapse under the proviso. Applying Indore Development Authority, the impugned High Court judgment is quashed and the appeal is allowed. No costs."

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • M. R. Shah, J.
  • C. T. Ravikumar, J.
Judgment Date
2023-01-20
Court Decision / Holding
Appeal allowed. The Supreme Court quashes the Delhi High Court’s judgment, holds that Indore Development Authority governs the interpretation of Section 24(2), and finds that there is no lapse in the acquisition proceedings. No costs. Pending applications, if any, are disposed of.
Final Disposition
Appeal Allowed; High Court’s judgment quashed and set aside; No costs; pending applications disposed.

Parties to the Case

Appellants / Petitioners

  • Delhi Development Authority

Respondents

  • Nem Chand Sharma and Ors.

Provisions of Law Cited

Section 24(2) of the Right to Fair Compensation and Transparency in land Acquisition, Rehabilitation and Resettlement Act, 2013Section 24(1)(a) of the 2013 ActSection 24(1)(b) of the 2013 ActProviso to Section 24(2) of the 2013 ActSection 4 of the Land Acquisition Act, 1894Section 16 of the Land Acquisition Act, 1894Section 30 of the Land Acquisition Act, 1894Section 31 of the Land Acquisition Act, 1894Section 34 of the Land Acquisition Act, 1894Section 31(1) of the Land Acquisition Act, 1894

Legal Doctrines & Maxims

  • Twin conditions for deemed lapse under Section 24(2) of the 2013 Act (non-possession and non-payment of compensation)
  • The word 'or' in Section 24(2) read as 'nor' or 'and' per Indore Development Authority (supra)
  • Non-deposit of compensation in court does not by itself cause lapse under Section 24(2) of the 2013 Act; proviso considerations apply
  • Indore Development Authority v. Manoharlal and Ors. lays down the controlling framework for Section 24(2) interpretation

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the High Court erred in relying on Pune Municipal Corporation v. Harakchand Misirimal Solanki (2014) 3 SCC 183, a decision later overruled by the Constitution Bench in Indore Development Authority v. Manoharlal and Ors. (2020) 8 SCC 129. The twin conditions for deeming lapse under Section 24(2) require either non-possession and non-payment, or if possession has been taken and compensation tendered/deposited, there is no lapse. In the present case, possession of the land was taken in 1990 and 2007; compensation payments/tenders (and satisfaction of Sections 30-31 of the 1894 Act) have been part of the record. The 2013 Act’s 24(2) is not intended to revive concluded proceedings or to reopen modes of possession or deposit. Moreover, non-deposit of compensation in court does not itself trigger lapse under the proviso to 24(2). Applying the Indore framework, the appeal should be allowed, and the High Court’s lapsed-acquisition finding set aside; the acquisition remains valid and the State retains control of the land.

Contentions of Respondents

The respondents argued that the 2013 Act’s Section 24(2) deems lapse where there has been delay in taking possession and/or paying compensation, with the five-year clock and interim court orders affecting computation. They contended that the disposal of compensation under the 1894 Act’s provisions (Sections 30, 31, and 34) and the absence of clear payment in the 2013 framework led to a deemed lapse. The High Court relied on Pune Municipal (overruled) and found that the lack of clarity about compensation and procedural compliance effectively nullified the acquisition. They rely on statutory non-fulfilment and inaction by authorities prior to 1-1-2014 to argue lapse and deem the proceedings closed. They seek to uphold the High Court’s view that the acquisition lapsed under Section 24(2) and that the ownership and compensation issues should not be revived.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
Pune Municipal Corporation v. Harakchand Misirimal Solanki(2014) 3 SCC 183OverruledConstitution Bench in Indore Development Authority overruled Pune Municipal's approach to 24(2).
Indore Development Authority v. Manoharlal and Ors.(2020) 8 SCC 129PositiveConstitution Bench decision controlling the interpretation of Section 24(2) and the twin conditions for lapse; overruled earlier precedents.
Sree Balaji Nagar Residential Assn. v. State of Tamil Nadu(2015) 3 SCC 353OverruledCannot be said to be good law per Indore Development Authority.
Indore Development Authority v. Shailendra[(2018) 3 SCC 412]OverruledCannot prevail in light of Indore and the present judgment.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,516 words•~7 min read

In The Court Record

Delhi Development Authority v. Nem Chand Sharma and Ors.

## **REPORTABLE** ## **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** **CIVIL APPEAL NO. 395 OF 2023 (@ SLP (C) NO. 1586 OF 2023) (@ DIARY NO. 32640 OF 2022)** **Delhi Development Authority …Appellant(s)** ## **Versus** **Nem Chand Sharma and Ors. …Respondent(s)** ## **J U D G M E N T** ## **M.R. SHAH, J.** 1. Feeling aggrieved and dissatisfied with the impugned judgment and order passed by the High Court of Delhi at New Delhi in Writ Petition (C) No. 3446 of 2015 by which the High Court has allowed the said writ petition preferred by the original writ petitioners – respondents herein and has declared that the acquisition proceedings initiated under the Signature Not Verified Land Acquisition Act, 1894 (hereinafter referred to as “Act, 1894”) with Digitally signed by Neetu Sachdeva Date: 2023.02.18 12:25:07 IST Reason: regard to the land in question is deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land 1 Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as “Act, 2013”), the Delhi Development Authority has preferred the present appeal. 2. We have heard the learned counsel appearing on behalf of the respective parties at length and perused the impugned judgment and order passed by the High Court. 2.1 From the impugned judgment and order passed by the High Court, it appears that though the High Court has observed and believed the case on behalf of the appellant and the Government of NCT of Delhi that the possession of the land in question was taken over, still, the High Court has allowed the writ petition and has declared that the acquisition with respect to the land in question is deemed to have lapsed under Section 24(2) of the Act, 2013 solely on the ground that it is not clear as to what compensation was paid and if so, who raised the dispute and whether the provisions of Sections 30 and 31 of the Act, 1894 were satisfied in accordance with the prevailing procedure. While passing the impugned judgment and order, the High Court has heavily relied upon the earlier decision of this Court in the case of **Pune Municipal Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors., (2014) 3 SCC 183** . However, it is required to be noted that the decision of this Court in the case of **Pune Municipal Corporation and Anr.** 2 **(supra)** has been subsequently overruled by the Constitution Bench decision of this Court in the case of **Indore Development Authority Vs. Manoharlal and Ors., (2020) 8 SCC 129** . 2.2 Apart from the above, even in the case of **Indore Development Authority (supra)** , the Constitution Bench of this Court has observed and held that for attracting the provisions of Section 24(2) of the Act, 2013, twin conditions of not taking over of possession and not tendering/paying the compensation are to be satisfied and if one of the conditions is not satisfied, there shall not be any deemed lapse of acquisition. In the present case, as observed hereinabove, the possession of the land in question was taken and handed over to the beneficiary department initially on 27.12.1990 and thereafter the remaining 1 bigha was taken and handed over to the beneficiary department on 09.02.2007. In the case of **Indore Development Authority (supra)** in paragraphs 365 and 366, the Constitution Bench of this Court has observed and held as under:- “ **365.** Resultantly, the decision rendered in Pune Municipal Corpn. [Pune Municipal Corpn. v. Harakchand Misirimal Solanki, (2014) 3 SCC 183] is hereby overruled and all other decisions in which Pune Municipal Corpn. [Pune Municipal Corpn. v. Harakchand Misirimal Solanki, (2014) 3 SCC 183] has been followed, are also overruled. The decision in Sree Balaji Nagar Residential Assn. [Sree Balaji Nagar Residential Assn. v. State of T.N., (2015) 3 SCC 353] cannot be said to be laying down good law, is overruled and other decisions following the same are also 3 overruled. In Indore Development Authority v. Shailendra [(2018) 3 SCC 412], the aspect with respect to the proviso to Section 24(2) and whether “or” has to be read as “nor” or as “and” was not placed for consideration. Therefore, that decision too cannot prevail, in the light of the discussion in the present judgment. **366.** In view of the aforesaid discussion, we answer the questions as under: **366.1.** Under the provisions of Section 24(1)(a) in case the award is not made as on 1-1-2014, the date of commencement of the 2013 Act, there is no lapse of proceedings. Compensation has to be determined under the provisions of the 2013 Act. **366.2.** In case the award has been passed within the window period of five years excluding the period covered by an interim order of the court, then proceedings shall continue as provided under Section 24(1)(b) of the 2013 Act under the 1894 Act as if it has not been repealed. **366.3.** The word “or” used in Section 24(2) between possession and compensation has to be read as “nor” or as “and”. The deemed lapse of land acquisition proceedings under Section 24(2) of the 2013 Act takes place where due to inaction of authorities for five years or more prior to commencement of the said Act, the possession of land has not been taken nor compensation has been paid. In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly, if compensation has been paid, possession has not been taken then there is no lapse. **366.4.** The expression “paid” in the main part of Section 24(2) of the 2013 Act does not include a deposit of compensation in court. The consequence of non-deposit is provided in the proviso to Section 24(2) in case it has not been deposited with respect to majority of landholdings then all beneficiaries (landowners) as on the date of 4 notification for land acquisition under Section 4 of the 1894 Act shall be entitled to compensation in accordance with the provisions of the 2013 Act. In case the obligation under Section 31 of the Land Acquisition Act, 1894 has not been fulfilled, interest under Section 34 of the said Act can be granted. Non-deposit of compensation (in court) does not result in the lapse of land acquisition proceedings. In case of non-deposit with respect to the majority of holdings for five years or more, compensation under the 2013 Act has to be paid to the “landowners” as on the date of notification for land acquisition under Section 4 of the 1894 Act. **366.5.** In case a person has been tendered the compensation as provided under Section 31(1) of the 1894 Act, it is not open to him to claim that acquisition has lapsed under Section 24(2) due to non-payment or nondeposit of compensation in court. The obligation to pay is complete by tendering the amount under Section 31(1). The landowners who had refused to accept compensation or who sought reference for higher compensation, cannot claim that the acquisition proceedings had lapsed under Section 24(2) of the 2013 Act. **366.6.** The proviso to Section 24(2) of the 2013 Act is to be treated as part of Section 24(2), not part of Section 24(1)(b). **366.7.** The mode of taking possession under the 1894 Act and as contemplated under Section 24(2) is by drawing of inquest report/memorandum. Once award has been passed on taking possession under Section 16 of the 1894 Act, the land vests in State there is no divesting provided under Section 24(2) of the 2013 Act, as once possession has been taken there is no lapse under Section 24(2). **366.8.** The provisions of Section 24(2) providing for a deemed lapse of proceedings are applicable in case authorities have failed due to their inaction to take possession and pay compensation for five years or more 5 before the 2013 Act came into force, in a proceeding for land acquisition pending with the authority concerned as on 1-1-2014. The period of subsistence of interim orders passed by court has to be excluded in the computation of five years. **366.9.** Section 24(2) of the 2013 Act does not give rise to new cause of action to question the legality of concluded proceedings of land acquisition. Section 24 applies to a proceeding pending on the date of enforcement of the 2013 Act i.e. 1-1-2014. It does not revive stale and time-barred claims and does not reopen concluded proceedings nor allow landowners to question the legality of mode of taking possession to reopen proceedings or mode of deposit of compensation in the treasury instead of court to invalidate acquisition.” 3. Applying the law laid down by this Court in the Constitution Bench decision in the case of **Indore Development Authority (supra)** , the impugned judgment and order passed by the High Court is unsustainable and the same deserves to be quashed and set aside and is accordingly quashed and set aside. Present appeal is accordingly allowed. No costs. Pending applications, if any, also stand disposed of. ………………………………….J. **[M.R. SHAH]** NEW DELHI; ………………………………….J. JANUARY 20, 2023. **[C.T. RAVIKUMAR]** 6
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.