Delhi Development Authority v. Jagan Singh & Ors.

Case / Petition Number:Civil Appeal No.943 of 2023
Neutral Citation:[2023] 2 S.C.R. 411

Case Details & Bench

Court
High Court
Hon'ble Judges
  • M. R. Shah
  • C. T. Ravikumar
  • Sanjay Karol
Judgment Date
2023-02-17
Court Decision / Holding
Present appeal is allowed. The impugned judgment and order of the Delhi High Court declaring that the acquisition is deemed to have lapsed under Section 24(2) is quashed and set aside. The writ petition is dismissed; the acquisition shall continue under the 2013 Act in accordance with Indore Development Authority.
Final Disposition
Appeal allowed; impugned High Court order quashed; writ petition dismissed.

Parties to the Case

Appellants / Petitioners

  • Delhi Development Authority

Respondents

  • Jagan Singh and others

Legal Representation & Advocates

Counsels for Petitioners

  • • Ms. Manika Tripathy
  • • Mr. Ashutosh Kaushik
  • • Mr. Manish Vashist

Case Synopsis & Summary

Feeling aggrieved by the Delhi High Court's 24 January 2017 order, the Delhi Development Authority appeals, contending that the acquisition should not be deemed to have lapsed under Section 24(2) of the 2013 Act. The High Court had allowed the petition and held the acquisition to be lapsed since compensation had not been paid, even though possession had been taken on 16 July 2007. The Court notes that the Pune Municipal Corporation v. Harakchand Misirimal Solanki decision (2014) 3 SCC 183 relied upon by the High Court has been specifically overruled by the Constitution Bench in Indore Development Authority v. Manoharlal (2020) 8 SCC 129, which held that once possession is taken there shall not be deemed lapse under Section 24(2). The Supreme Court then extracts several propositions: (i) under Section 24(1)(a), if the award is not made by 1 January 2014, there is no lapse and compensation must be determined under the 2013 Act; (ii) if the award is within the five-year window excluding interim orders, the proceedings continue under Section 24(1)(b) as if the 1894 Act had not been repealed; (iii) the word “or” in Section 24(2) must be read as “nor” or “and”; (iv) deposit of compensation in court is not the same as “paid” for purposes of lapse; (v) the proviso to Section 24(2) is part of the section; (vi) possession under the 1894 Act vests land in the State; there is no lapse where possession is taken. Following Indore (supra), the impugned judgment is quashed and the appeal is allowed.

Provisions of Law Cited

Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 – s.24(2)Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 – s.24(1)(a)Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 – s.24(1)(b)Land Acquisition Act, 1894 – Section 4Land Acquisition Act, 1894 – Section 16Land Acquisition Act, 1894 – Section 31Land Acquisition Act, 1894 – Section 34Proviso to Section 24(2)

Submissions & Arguments

Contentions of Appellants / Petitioners

The Delhi Development Authority contends that once possession is taken under the 1894 Act, Section 24(2) of the 2013 Act cannot deem a lapse; the Constitution Bench in Indore Development Authority v. Manoharlal (2020) 8 SCC 129 holds that possession precludes lapse under Section 24(2). It argues that non-deposit of compensation in court does not cause lapse and that the five-year inaction period contemplated under Section 24(2) applies to proceedings pending as on 1-1-2014, with interim orders excluded. The High Court’s reliance on Pune Municipal Corporation (2014) 3 SCC 183 is misplaced after overrulement of that decision.

Contentions of Respondents

The respondents argued that non-payment of compensation triggers deemed lapse under Section 24(2) and that the High Court correctly applied the Pune standard; they contend the remedy is to treat the matter as lapse to ensure payment to landowners under the 2013 Act.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
Pune Municipal Corporation and Anr. v. Harakchand Misirimal Solanki and Ors.(2014) 3 SCC 183OverruledConstitution Bench in Indore Development Authority v. Manoharlal overruled Pune Municipal Corporation; holds that once possession is taken, Section 24(2) cannot deem lapse.
Indore Development Authority v. Manoharlal and Ors.(2020) 8 SCC 129PositiveDecision followed; holds that lapse does not occur if possession has been taken under the 1894 Act.
Sree Balaji Nagar Residential Assn. v. State of Tamil Nadu(2015) 3 SCC 353OverruledConstitution Bench overruled; cannot be good law.
Indore Development Authority v. Shailendra B.(2018) 3 SCC 412OverruledCannot prevail in light of the present judgment's discussion.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Delhi Development Authority v. Jagan Singh & Ors. and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

411 [2023] 2 S.C.R. 411 ## DELHI DEVELOPMENT AUTHORITY A v. ## JAGAN SINGH & ORS. (Civil Appeal No.943 of 2023) FEBRUARY 17, 2023 B ## **[M. R. SHAH, C.T. RAVIKUMAR & SANJAY KAROL JJ.]** _Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 – s.24(2) – High Court relying on the decision of Supreme Court in_ Pune C Municipal Corporation and Anr. v. Harakchand Misirimal Solanki and Ors. _reported as declared that the acquisition proceeding initiated w.r.t the land in question is deemed to have lapsed u/s.24(2) – On appeal, held: Decision in_ Pune Municipal Corporation _case has been overruled by the Constitution Bench in_ Indore Development Authority v. Manoharlal and Ors. _reported as wherein it is held that once the_ D _possession is taken over there shall not be deemed lapse u/s.24(2)– In the present case,even as per the finding recorded by the High Court,the physical possession of the subject land was admittedly taken– Impugned judgment setaside._ _Indore Development Authority v. Manoharlal and Ors._ **(2020) 8 SCC 129 : [2020] 3 SCR 1** – followed. **==> picture [8 x 8] intentionally omitted <==** _Pune Municipal Corporation and Anr. vs. Harakchand Misirimal Solankiand Ors._ **(2014) 3 SCC 183 : [2014] 1 SCR 783–referred to.** ## **Case Law Reference** F **[2014] 1 SCR 783 referredto Para2 [2020] 3 SCR 1 followed Para 2.1** CIVIL APPELLATE JURISDICTION : Civil Appeal No.943 of 2023. G From the Judgment and Order dated 24.01.2017 of the High Court of Delhi at New Delhi in WP (C) No.3164 of 2015. Ms. Manika Tripathy, Ashutosh Kaushik, Manish Vashist, Advs. for the Appellant. H 411 412 SUPREME COURT REPORTS [2023] 2 S.C.R. A The Judgment of the Court was delivered by ## **M. R. SHAH, J.** 1. Feeling aggrieved and dissatisfied with the impugned judgment and order dated 24.01.2017 passed by the High Court of Delhi at New Delhi in Writ Petition (Civil) No. 3164 of 2015 by which the High Court B has allowed the said writ petition preferred by the respondent no.1 herein – original writ petitioner and has declared that the acquisition with respect to the land in question is deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as C ‘the Act 2013’), the Delhi Development Authority has preferred the present appeal. 2. From the impugned judgment and order passed by the High Court and even as per the finding recorded by the High Court in para 3, the physical possession of the subject land was admittedly taken on D 16.07.2007. However, thereafter relying upon the decision of this Court in the case of **Pune Municipal Corporation and Anr. Vs. Harakchand Misirimal Solanki and Ors.** reported in **(2014) 3 SCC 183** and on the ground that the compensation has not been paid to the original petitioner, the High Court has allowed the said writ petition and has declared that the acquisition with respect to the land in question is deemed E to have lapsed. 2.1 At this stage, it is required to be noted that the earlier decision of this Court in the case of **Pune Municipal Corporation and Anr. (supra)** , which has been relied upon by the High Court has been specifically over-ruled by the Constitution Bench of this Court in the F case of **Indore Development Authority versus Manoharlal and others** reported in **(2020) 8 SCC 129** . In the said decision it is specifically observed and held that once the possession was taken over there shall not be deemed to have lapsed under Section 24(2) of the 2013 Act. G In paragraphs 365 and 366, the Constitution Bench of this Court has observed and held as under:- H “ **365.** Resultantly, the decision rendered in Pune Municipal Corpn. [Pune Municipal Corpn. v. Harakchand Misirimal Solanki, (2014) 3 SCC 183] is hereby overruled and all other decisions in which Pune Municipal Corpn. [Pune Municipal Corpn. v. 413 DELHI DEVELOPMENT AUTHORITY v. JAGAN SINGH [M. R. SHAH, J.] Harakchand Misirimal Solanki, (2014) 3 SCC 183] has been A followed, are also overruled. The decision in Sree Balaji Nagar Residential Assn. [Sree Balaji Nagar Residential Assn. v. State of T.N., (2015) 3 SCC 353] cannot be said to be laying down good law, is overruled and other decisions following the same are also overruled. In Indore Development Authority v. Shailendra B [(2018) 3 SCC 412], the aspect with respect to the proviso to Section 24(2) and whether “or” has to be read as “nor” or as “and” was not placed for consideration. Therefore, that decision too cannot prevail, in the light of the discussion in the present judgment. **366.** In view of the aforesaid discussion, we answer the questions as under: **366.1.** Under the provisions of Section 24(1)(a) in case the award is not made as on 1-1-2014, the date of commencement of the 2013 Act, there is no lapse of proceedings. Compensation has to be determined under the provisions of the 2013 Act. **366.2.** In case the award has been passed within the window period of five years excluding the period covered by an interim order of the court, then proceedings shall continue as provided under Section 24(1)(b) of the 2013 Act under the 1894 Act as if it has not been repealed. **366.3.** The word “or” used in Section 24(2) between possession and compensation has to be read as “nor” or as “and”. The deemed lapse of land acquisition proceedings under Section 24(2) of the 2013 Act takes place where due to inaction of authorities for five years or more prior to commencement of the said Act, the possession of land has not been taken nor compensation has been paid. In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly, if compensation has been paid, possession has not been taken then there is no lapse. **366.4.** The expression “paid” in the main part of Section 24(2) of the 2013 Act does not include a deposit of compensation in court. The consequence of non-deposit is provided in the proviso to Section 24(2) in case it has not been deposited with respect to majority of landholdings then all beneficiaries C D E F G H 414 SUPREME COURT REPORTS [2023] 2 S.C.R. A B C D E F G (landowners) as on the date of notification for land acquisition under Section 4 of the 1894 Act shall be entitled to compensation in accordance with the provisions of the 2013 Act. In case the obligation under Section 31 of the Land Acquisition Act, 1894 has not been fulfilled, interest under Section 34 of the said Act can be granted. Non-deposit of compensation (in court) does not result in the lapse of land acquisition proceedings. In case of non- deposit with respect to the majority of holdings for five years or more, compensation under the 2013 Act has to be paid to the “landowners” as on the date of notification for land acquisition under Section 4 of the 1894 Act. **366.5.** In case a person has been tendered the compensation as provided under Section 31(1) of the 1894 Act, it is not open to him to claim that acquisition has lapsed under Section 24(2) due to non-payment or non-deposit of compensation in court. The obligation to pay is complete by tendering the amount under Section 31(1). The landowners who had refused to accept compensation or who sought reference for higher compensation, cannot claim that the acquisition proceedings had lapsed under Section 24(2) of the 2013 Act. **366.6.** The proviso to Section 24(2) of the 2013 Act is to be treated as part of Section 24(2), not part of Section 24(1)(b). **366.7.** The mode of taking possession under the 1894 Act and as contemplated under Section 24(2) is by drawing of inquest report/memorandum. Once award has been passed on taking possession under Section 16 of the 1894 Act, the land vests in State there is no divesting provided under Section 24(2) of the 2013 Act, as once possession has been taken there is no lapse under Section 24(2). **366.8.** The provisions of Section 24(2) providing for a deemed lapse of proceedings are applicable in case authorities have failed due to their inaction to take possession and pay compensation for five years or more before the 2013 Act came into force, in a proceeding for land acquisition pending with the authority concerned as on 1-1-2014. The period of subsistence of interim orders passed by court has to be excluded in the computation of five years. H 415 DELHI DEVELOPMENT AUTHORITY v. JAGAN SINGH [M. R. SHAH, J.] **366.9.** Section 24(2) of the 2013 Act does not give rise to A new cause of action to question the legality of concluded proceedings of land acquisition. Section 24 applies to a proceeding pending on the date of enforcement of the 2013 Act i.e. 1-1-2014. It does not revive stale and time- barred claims and does not reopen concluded proceedings nor allow landowners B to question the legality of mode of taking possession to reopen proceedings or mode of deposit of compensation in the treasury instead of court to invalidate acquisition.” 3. In view of the law laid down by this Court in the case of **Indore Development Authority (supra)** and applying the same to the facts in the case on hand the impugned judgment and order passed by the High Court declaring that the acquisition with respect to the land in question is deemed to have lapsed is unsustainable. Consequently, the impugned judgment and order passed by the High Court deserves to be quashed and set aside. 3.1 In view of the above and for the reasons stated above, the impugned judgment and order passed by the High Court declaring that the acquisition with respect to the land in question is deemed to have lapsed is hereby quashed and set aside. The original writ petition preferred by the respondent – original writ petitioner filed before the High Court stands dismissed. C D E Present appeal is allowed. No costs. Divya Pandey (Assisted by : Abhishek Pratap Singh, LCRA) Appeal allowed. F G H