High Court of KeralaDivision BenchAppeal dismissed

CPG CONSULTANTS INDIA PVT. LTD. v. MFAR REALTORS PVT. LTD.

Case / Petition Number:ARB.A NO. 69 OF 2017

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • P.B. SURESH KUMAR
  • C.S. SUDHA
Judgment Date
2021-11-17
Court Decision / Holding
The Arbitration Appeal No.69 of 2017 is dismissed. The award stands as rendered by the Arbitrator, with the lower court’s decision upheld.
Final Disposition
Appeal dismissed

Parties to the Case

Appellants / Petitioners

  • CPG CONSULTANTS INDIA PVT. LTD.

Respondents

  • MFAR REALTORS PVT. LTD.

Legal Representation & Advocates

Counsels for Petitioners

  • • Lal K. Joseph
  • • Joseph Kurian Vallamattam
  • • V. S. Shiraz Bava
  • • Zakir Hussain

Counsels for Respondents

  • • M. Gopikrishnan Nambiar
  • • P. Gopinath
  • • K. John Mathai
  • • Joson Manvalan
  • • Kuryan Thomas
  • • Pauloose C. Abraham
  • • T. K. Vipindas (Government Pleader)

Case Synopsis & Summary

CPG Consultants India Pvt. Ltd. (the appellant) and MFAR Realtors Pvt. Ltd. (the respondent) entered into a contract for design services relating to a development project, with disputes to be resolved by arbitration. The disputes were referred to an Arbitrator, who heard the claims and counter-claims. The respondent pursued a claim for Rs. 43,68,000/-, representing the balance on invoices, while the appellant counter-claimed for Rs. 81,61,137/-, including Rs. 37,93,137/- as ‘additional compensation’ computed at 1% per month on the overdue amount. The Arbitrator allowed the balance on invoices but rejected the counter-claim for the additional compensation and thus dismissed the claim for interest. The appellant challenged the award under Section 34 of the Arbitration and Conciliation Act, arguing that the contract contemplated interest and liquidated damages for late payment and that the Arbitrator had misconstrued the agreement. The court found that the Arbitrator’s rejection of the additional compensation was based on a finding that the appellant had waived the claim, a pure question of fact not amenable to correction under Section 34. It relied on ONGC Ltd. v. Saw Pipes Ltd. to discuss the principle that deviations from contract terms can render awards patently illegal, distinguishing the present facts and upholding the lower court’s dismissal of the petition. The appeal is dismissed.

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 - Section 37Arbitration and Conciliation Act, 1996 - Section 34Arbitration and Conciliation Act, 1996 - Section 28(3)

Legal Doctrines & Maxims

  • Fundamental policy of Indian law
  • Waiver
  • Patently illegal (as a doctrinal standard, per ONGC)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant submitted that Clause 5.2 contemplates compensation for non-payment within 30 days, with liquidated damages at 1% per month on the overdue sum. The term ‘Agreed Compensation’ was argued to pertain to the design services, while the ‘additional compensation’ for delay represented time-value of money. The appellant contended the counter-claim for Rs. 37,93,137/- should have been allowed along with the dues, and that the Arbitrator’s finding of waiver of this claim was a misapplication of law, not a valid ground to dismiss under Section 34. It relied on ONGC v. Saw Pipes Ltd. to support correction of awards that conflict with contract terms and argued the award should reflect the contract’s true terms. The appellant urged that the Court corrects the award to give effect to the contract and its clauses, and that the waiver finding does not extinguish contractual rights under Clause 5.2.

Contentions of Respondents

The respondent argued that the counter-claim for additional compensation was not legally sustainable and that the Arbitrator provided cogent reasons to decline it. They asserted that no demand for compensation under Clause 5.2 or interest beyond the balance due had been properly raised within the relevant proceedings, and that the waiver finding is a pure factual determination not subject to correction under Section 34. They maintained that the award, including the rejection of the additional compensation, was consistent with the contract and the evidence, and that there is no contradiction with the fundamental policy of Indian law. Therefore, the appeal should be dismissed.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
ONGC Ltd. v. Saw Pipes Ltd.(2003) 5 SCC 705DistinguishedThe present case involves a factual finding about waiver. The court distinguished ONGC’s proposition that an award can be corrected for contracting terms violations and held it inapplicable to the present facts, which do not involve a direct contravention of contract terms by the award.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against CPG CONSULTANTS INDIA PVT. LTD. v. MFAR REALTORS PVT. LTD. and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

# **`IN THE HIGH COURT OF KERALA AT ERNAKULAM`** # **`PRESENT`** ``` THE HONOURABLE MR. JUSTICE P.B.SURESH KUMAR ``` ``` & ``` ``` THE HONOURABLE MRS. JUSTICE C.S. SUDHA ``` ``` WEDNESDAY, THE 17[TH] DAY OF NOVEMBER 2021 / 26TH KARTHIKA, 1943 ARB.A NO. 69 OF 2017 ``` ``` AGAINST THE ORDER/JUDGMENT IN OPARB 85/2016 OF II ADDITIONAL DISTRICT COURT,ERNAKULAM, ERNAKULAM ``` ``` APPELLANT/PETITIONER IN OP(ARB.)NO.85/2016/CLAIMANT: ``` ``` CPG CONSULTANTS INDIA PVT. LTD. 21/30 PRESTIGE CRAIG PARK LAYOUT, MAHATMA GANDHI ROAD, BANGALORE, REPRESENTED MR. SATINDER SINGH, POWER OF ATTORNEY HOLDER. ``` ``` BY ADVS. SRI.LAL K.JOSEPH SRI.JOSEPH KURIAN VALLAMATTAM SRI.V.S.SHIRAZ BAVA SRI.ZAKIR HUSSAIN ``` ## **`RESPONDENT/RESPONDENT IN OP(ARB)NO.85/2016/CLAIMANT:`** ``` MFAR REALTORS PVT. LTD. THROUGH ITS MANAGING DIRECTOR,NH 47 BY PASS, KUNDANNUR JN,COCHIN-682304. ``` ``` BY ADVS. SRI.M.GOPIKRISHNAN NAMBIAR SRI.M.GOPIKRISHNAN NAMBIAR SRI.P.GOPINATH SRI.K.JOHN MATHAI SRI.JOSON MANAVALAN SRI.KURYAN THOMAS SRI.PAULOSE C. ABRAHAM BY SR.GOVERNMENT PLEADER SRI. T.K.VIPINDAS ``` ## **`OTHER PRESENT:`** ``` adv.zakir hussain for petitioner ``` ``` THIS ARBITRATION APPEALS HAVING COME UP FOR ADMISSION ON 17.11.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING: ``` Arbitration Appeal No.69 of 2017 ..2.. ## **P.B.SURESH KUMAR & C.S.SUDHA, JJ.** **----------------------------------------------Arbitration Appeal No.69 of 2017 ----------------------------------------------Dated this the 17[th] day of November, 2021** ## **JUDGMENT** ## **P.B.Suresh Kumar, J.** This appeal under Section 37 of the Arbitration and Conciliation Act 1996 (the Act) is directed against the order dated 17.07.2017 in O.P.(Arbitration) No.85 of 2016 on the files of the court of the Second Additional District Judge, Ernakulam. The appellant is the petitioner in the said original petition. 2. The appellant, a company engaged in the business of providing design services for master planning, infrastructure planning etc., have entered into an agreement with the respondent, a company engaged in the business of development of lands, for rendering design services in respect of one of the projects of the respondent. Disputes arose between the parties in the course of execution of the project. The agreement entered into between the parties provided for resolution of disputes by recourse to arbitration. The disputes were accordingly referred to the Arbitrator for resolution at the instance of the respondent. Before the Arbitrator, Arbitration Appeal No.69 of 2017 ..3.. the respondent raised a claim against the appellant and the appellant, in turn, raised a counter claim against the respondent. The counter claim raised by the appellant against the respondent in the proceedings was for an award for Rs.81,61,137/-, which comprises of Rs.43,68,000/- towards the balance amount payable to them by the respondent covered by three invoices and Rs.37,93,137/- towards compensation at the rate of one percent per month worked out on Rs.43,68,000/- from the due date. The Arbitrator rejected the claim of the respondent and allowed the counter claim of the appellant in part permitting them to realise only the balance amount covered by the invoices, namely Rs.43,68,000/-. 3. Aggrieved by the award, to the extent it declined compensation at the rate of one percent per month worked out on Rs.43,68,000/- from the due date, the appellant instituted the original petition referred to above invoking Section 34 of the Act. The court below found that the award of the Arbitrator is not one which warrants any correction in terms of Section 34 and consequently, dismissed the original petition. The appellant is aggrieved by the said order and hence this appeal. 4. Heard the learned counsel for the appellant as also the learned counsel for the respondent. 5. The learned counsel for the appellant submitted that the agreement entered into between the parties, in terms of Arbitration Appeal No.69 of 2017 ..4.. which design services have been rendered by the appellant to the respondent, is a peculiar one in the sense that the consideration payable in terms of the same is styled therein as 'compensation', instead of fees. Referring to Clause 5.2 of the agreement, the learned counsel has also submitted that the agreement was to the effect that if the appellant does not receive the compensation within thirty days from the date of submission of the invoice, the respondent shall pay to the appellant the compensation covered by the invoice along with additional compensation for overdue payment at the rate of one percent per month calculated on the overdue sum from the due date for payment of the invoice till the actual date of payment. It was argued by the learned counsel that though the agreement uses the expression 'additional compensation', what was meant by the parties by that expression was the interest for the amount covered by the invoice. It was pointed out by the learned counsel that it was the said amount that was claimed by the appellant in the counter claim preferred before the Arbitrator in addition to the balance amount covered by the invoices raised by them against the respondent. It was argued by the learned counsel that the Arbitrator, in the circumstances, ought to have upheld the said claim of the appellant also. It was the contention of the appellant that grant of interest on default of payment is part of the fundamental policy of Indian law and the award, insofar as it Arbitration Appeal No.69 of 2017 ..5.. declined the additional compensation claimed by the appellant over and above the amount covered by the invoices is, therefore, liable to the corrected under Section 34(2) of the Act, being one in conflict with the fundamental policy of Indian law. It was also the contention of the learned counsel that the said part of the counter claim of the appellant was strictly in accordance with the terms of the agreement, and the award, insofar as it relates to the said part of the counter claim being one rendered contrary to the terms of the agreement, the same is liable to be corrected as patently illegal also. The learned counsel relied on paragraphs 15, 55 and 61 of the decision of the Apex Court in **ONGC Ltd. v. Saw Pipes Ltd.** , (2003) 5 SCC 705, in support of his arguments. It was pointed out by the learned counsel that the main ground stated by the Arbitrator for declining the additional compensation claimed by the appellant is that the appellant had not claimed the same in the various correspondence addressed to the respondent. It was argued by the learned counsel that the said finding of the Arbitrator is perverse as the Arbitrator himself has noted in paragraph 51 of the award that the appellant has claimed the additional compensation in one of their correspondence addressed to the respondent. 6. Per contra, the learned counsel for the respondent submitted that cogent and convincing reasons have been given by the arbitrator to decline the additional compensation claimed by the Arbitration Appeal No.69 of 2017 ..6.. appellant against the respondent and that part of the award cannot, therefore, be questioned under any of the grounds provided for in Section 34 of the Act. 7. We have examined the contentions raised by the learned counsel for the parties on either side. 8. There is no dispute between the parties to the fact that the total amount covered by the invoices raised by the appellant against the respondent as on 29.10.2009 was Rs.87,36,000/- and that the said amount has not been paid by the respondent on the due dates. The materials indicate that after various correspondence in between, the respondent has made a proposal that they will pay 50% of the outstanding amount namely, Rs.43,68,000/- and on receipt of the same, appropriate changes required by the respondent in the designs already provided to them shall be carried out by the appellant and that balance amount will be effected only thereafter. The materials also indicate that the said proposal of the respondent was accepted by the appellant and they have carried out the changes required in the designs after receiving Rs.43,68,000/- in terms of the above proposal. The materials further indicate that the respondent has not paid the balance amount covered by the proposal as agreed even after the appellant carrying out appropriate changes in the designs required by the respondent and the counter claim was for realisation of the said balance amount Arbitration Appeal No.69 of 2017 ..7.. covered by the invoices together with the additional compensation at the rate of one percent per month worked out on Rs.43,68,000/for the delayed period. ## 9. Clause 5.2 of the agreement reads thus: “If the consultant does not receive payment within thirty days(30) Days from the date of submission of invoice, the client shall pay the consultant the Agreed Compensation along with additional compensation for overdue payment at the rate of one percent(1%) per month calculated on the overdue sum from the due date for payment of the invoice till the actual date of payment. Notwithstanding the above, nothing provided in this clause 5.2 shall affect the rights of the consultant stated in clause 12.3.” As discernible from the extracted clause in the agreement what is provided for in the clause aforesaid is that in the event of non payment of the compensation covered by the invoice within 30 days from the date of submission of the invoice, the respondent is liable to pay the said amount to the appellant together with the amount worked out at one percent per month on the overdue sum from the due date for payment of the invoice till the actual date of payment by way of liquidated damages. The learned counsel for the appellant is right in contending that insofar it is found that the balance amount covered by the invoices has not been paid by the respondent, the appellant is entitled to the said amount. The question however is as to whether the decision of the Arbitrator in declining the said relief to the appellant is one which could be Arbitration Appeal No.69 of 2017 ..8.. corrected in a proceedings under Section 34 of the Act. 10. Paragraphs 58 to 61 of the Award of the Arbitrator dealing with the claim of the appellant for additional compensation read thus: “58. As regards the counter claim raised for compensation for delay in payment of Rs.43,68,000/-, as per clause 5(2) of Ex.C1 agreement; I am of the considered opinion that it is not sustainable in law in the special facts and circumstances of the case. 59. The balance amount due as per invoices 1 to 3 was pending from 29.10.2009. Thereafter repeated attempts were made by the respondent for collecting the outstanding amount through M/s GCS Management Solutions India Pvt. Ltd. The averments in Para 9 to 12 of the defense statement and the contents of email Ex R17 dated 13.6.2011 would show that there was a proposal made by the claimant at the time when the total amount due was Rs.87,36,000/- that the claimant will pay 50% of the outstanding amount namely Rs.43,68,000/ immediately to the respondent on acceptance of the proposal to effect some revision/modification to the plan and designs already submitted and the balance amount will also be paid on resubmission of the plans and designs after revision/modification. Even at the risk of repetition I may state that the proposal was considered in detail taking considerable time and was accepted by Ex R17 email dated 13.6.2011 which was to the following effect. "Dear Mr. Abdul Basheer, Arbitration Appeal No.69 of 2017 ..9.. Please find the trail of mails that elaborates the approval and acceptance of the proposal by CPG." The email was one Issued by Satinder of GCS to Abdul Basheer of the claimant company. 60. The trail mails would clearly show that the proposal was to pay 50% of the outstanding amount on the condition that respondent will agree to carry out necessary revision/modification to the plans and designs already submitted and that on resubmission the remaining 50% of the balance amount will also be paid in full. Even though the making of the above proposal and acceptance of the same by the respondent were made about two years after 29.10.2009 no claim for compensation was made by the respondent during that time. Similarly during the second attempt made by the claimant to revive the relationship between the parties on the basis of Ex R18 email dated 14.6.2011 also, no claim for payment of compensation for delay in payment of Rs.43,68,000/- was raised by the respondent. Neither during the joint meetings held for discussing and considering the proposal for revision/modification nor while finalizing the terms to be included in the proposed amendment agreement, no demand is seen made by the respondent to claim compensation for delay on the above amount from the claimant. In fact the respondent through out its correspondence and joint meetings with the claimant was only pressing for the outstanding amount of Rs.87,36,000/-and no demand was ever made for payment of any compensation as provided in clause 5.2 or by way of interest at the rate of 1% per month or at any other rate. Even in Ex R29 A, R29 B, R30 and R31 Arbitration Appeal No.69 of 2017 ..10.. the respondent has not made any claim specifically for the payment of compensation as per clause 5.2 or for interest at any other rate in addition to the outstanding amount of Rs.43,68,000/-. As such taking note of the entire facts and circumstances of the case especially the attitude of the respondent taken consistently during the several attempts made to recover the outstanding amount as evidenced by the various documents produced in the case, I find that it is a totally unjust and unfair counter claim which is only to be rejected. As such I reject the claim for compensation under clause 5.2 of Ex C1 agreement. 61. Before concluding the discussion under issues nos. 3&4, I would record a finding that having rejected the counter claim for compensation for delay In paying the amount of Rs 43,68,000/-, it is only just, legal and necessary to allow interest at a reasonable rate of 12% on the said amount and to recover such amount also from the claimant if the claimant fails to pay the said amount to the respondent within three months from the date of the award. In that event respondent will be entitled to recover interest on the amount at the above rate from the date of the award till the date of recovery.” A close reading of the extracted paragraphs would show that on an appraisal of the evidence on record, especially the various correspondence addressed to each other by the parties, the Arbitrator found that the relationship between the parties broke sometime during October, 2009 and was revived only in terms of the proposal made by the respondent during the year 2011 which Arbitration Appeal No.69 of 2017 ..11.. was accepted by the appellant in their e-mail dated 13.06.2011. The Arbitrator also found from the materials on record that even though the amount agreed in terms of the proposal has been paid by the respondent to the appellant, there were still disputes between the parties and there had been several correspondence and joint meetings between them to resolve the disputes by modifying the terms of the agreement. The Arbitrator also found that the appellant had not raised the claim for additional compensation in any of those meetings or correspondence. The learned counsel for the appellant is right in pointing out that the Arbitrator has noted in paragraph 51 of the award that in Ext.C10 notice, the respondent claimed not only the balance outstanding due but also the additional compensation. But, it is seen that the Arbitrator was referring to the various correspondence and meetings took place between the parties thereafter. It is all the more so since the Arbitrator has specifically referred to the correspondence addressed by the appellant to the respondent which were marked in the proceedings as Exts.R29A, R29B, R30 and R31. Those are correspondence addressed by the appellant to the respondent between 14.09.2012 to 27.09.2012. In the light of the said findings, it is seen that the Arbitrator was of the view that the claim for additional compensation raised by the appellant against the respondent is one that was waived by the appellant, though the Arbitration Appeal No.69 of 2017 ..12.. Arbitrator does not use the expression 'waiver' in the award. The said stand of the Arbitrator and the findings rendered by the Arbitrator to arrive at the said stand, may or may not be correct on facts, but the question is whether the said findings could be corrected in a proceedings under Section 34 of the Act. The question whether the appellant has waived a particular claim against the respondent is a pure and simple question of fact to be rendered on an appraisal of the evidence on record. A finding to that effect even if it is rendered on an erroneous application of law, cannot be corrected in a proceedings under Section 34 of the Act. If the view aforesaid cannot be interfered with in a proceedings under Section 34, it has to be accepted as correct and if that be so, it cannot be said that the award of the Arbitrator is in conflict with the fundamental policy of the Indian law or that the same is patently illegal, being contrary to the terms of the contract. 11. In **ONGC Ltd.** , the Apex Court has held that if an award is contrary to the terms of the contract, it would be patently illegal and could be corrected under Section 34 of the Act. There cannot be any doubt to the said proposition especially in the light of the provisions contained in Section 28(3) of the Act. According to us, the said judgment will not have any application to the facts of the present case, for the view taken by the Arbitrator is that there was a conscious abandonment of a term of the contract by one of Arbitration Appeal No.69 of 2017 ..13.. the parties to the contract. In the said view of the matter, we do not find any merit in the appeal and the same is, accordingly, dismissed. **Sd/P.B.SURESH KUMAR, JUDGE.** **Sd/C.S.SUDHA, JUDGE.** ds 09.11.2021