This is a Review Petition (C) arising out of a writ matter challenging the validity of the 2017 Environment Impact Assessment (EIA) Notification and the 2021 Office Memorandum (OM) issued by the Ministry of Environment, Forest and Climate Change (MoEF&CC) in the wake of National Green Tribunal directions. The majority judgment (B.R. Gavai CJI) held the ex post facto Environmental Clearances (ECs) under the 2017 Notification and 2021 OM to be illegal, striking down those instruments and directing their quashing while keeping already granted ECs intact. The CREDAI sought recall of the Vanashakti judgment (May 16, 2025) alleging non-disclosure of pertinent authorities and decisions and arguing that upholding JUR would cause massive economic disruption and environmental harm due to demolition of several completed/near-complete projects. A coordinate judgment by Justice U. Bhuyan concurred with recalling the JUR but another opinion by Justice K. Vinod Chandran disagreed, endorsing the review. The petition ultimately involves balancing environmental principles (precaution, polluter pays, non-regression) with development needs, and whether the court should revisit (recall) the prior stance to avoid disproportionate harm or retrograde environmental protections. The operative outcome in the document is a recall of the JUR and restoration of the writ petitions and civil appeals to their files for adjudication consistent with the review proceedings.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- B. R. Gavai, CJI
- Ujjal Bhuyan, J.
- K. Vinod Chandran, J.
- Judgment Date
- 2025-11-18
- Court Decision / Holding
- The review petition is recalled in part/fully by the majority, with writ petitions and civil appeals restored to file for fresh consideration in light of the recall; the matter is to be placed before the Chief Justice for administrative directions. A concurrent opinion notes divergence on recall, but the prevailing order in the document recalls the JUR and reopens the avenues for reconsideration consistent with the review process.
- Final Disposition
- Recall of the JUR; writ petitions and civil appeals restored to file; matter to be placed before the Chief Justice for administrative directions; no final substantive decision on environmental policy taken in this order.
Parties to the Case
Appellants / Petitioners
- Confederation of Real Estate Developers of India (CREDAI)
Respondents
- Vanashakti and Anr.
Legal Representation & Advocates
Counsels for Petitioners
- • Mukul Rohatgi (Senior Counsel)
Counsels for Respondents
- • Kapil Sibal (Senior Counsel)
- • Gopal Sankaranarayanan (Senior Counsel)
- • Sanjay Parikh
- • Raju Ramachandran
- • Anand Grover
- • Ms. Anitha Shenoy
Provisions of Law Cited
Legal Doctrines & Maxims
- Precautionary principle
- Polluter pays principle
- Non-regression
- Sustainable development
- Per incuriam (doctrine of precedent)
- Ratio decidendi
Submissions & Arguments
Contentions of Appellants / Petitioners
CREDAI pressed that the JUR’s recall was required for correct interpretation of precedents and to safeguard public funds and ongoing developments; they contended that the 2017 Notification and 2021 OM, though challenged, had been referenced without notice of other relevant judgments (notably D. Swamy and Pahwa Plastics), and that continuing with a wrong ruling would cause widespread destruction and economic loss; their argument rested on the need for consistent environmental jurisprudence and the principle that a higher court may correct its own errors in exercise of inherent jurisdiction.
Contentions of Respondents
Vanashakti and others argued that the JUR correctly struck down the ex post facto EC framework; recall would undermine environmental safeguards and precedent; they emphasized the illegality of ex post facto EC under EIA 1994/2006, the precautionary and polluter pays principles, and the need to deter violators; they also warned against destabilizing ongoing projects and the public funds already spent on compliant activities.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (5)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Common Cause v. Union of India and Others | (2017) 9 SCC 499 | Positive | Used to underpin the principle that ex post facto ECs are detrimental to the environment and ordinarily not permissible. |
| Alembic Pharmaceuticals Limited v. Rohit Prajapati and Others | (2020) 17 SCC 157 | Mentioned Only | Cited for discussion on ex post facto EC; however, later parts (paras 24–43) not noticed in JUR affected the weight of its ratio. |
| Electrosteel Steels Limited v. Union of India and Others | (2023) 6 SCC 615 | Positive | Cited to reinforce that ex post facto EC should not ordinarily be granted and that prior EC is non-negotiable, though exceptions can apply in exceptional circumstances. |
| D. Swamy v. Karnataka State Pollution Control Board and Others | (2023) 20 SCC 469 | Overruled | Notes that the JUR’s approach diverged from D. Swamy; the later decision is treated as per incuriam with respect to the JUR’s reasoning. |
| Pahwa Plastics Private Limited and Another v. Dastak NGO and Others | (2023) 12 SCC 774 | Overruled | Similar to D. Swamy, JUR perceives the later decision as per incuriam, thus not binding. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Confederation of Real Estate Developers of India (CREDAI) v. Vanashakti and Anr.
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.