This Supreme Court case concerns mining in the State of Odisha and the legality of renewals of mining leases under the Mines and Minerals (Development and Regulation) Act, 1957 and related rules. The Court, acting on a preliminary point, formed the Central Empowered Committee (CEC) to inspect leases for environmental and forest clearances as well as Mining Plans and Consent to Operate under the Environment (Protection) Act, 1986 and the Forest Conservation Act, 1980. The CEC reported that 102 leases lacked requisite clearances, 29 leases had been determined or rejected or lapsed, and 56 leases were presently operating (some with forest or non-forest land issues). The judgment acknowledges that 16 leases have executed deeds and 14 leases are under first renewal while 26 leases operate under second or subsequent deemed renewals under Rule 24A(6) of the 1960 Rules, without express orders under Section 8(3). The Court reiterates that deemed renewals cannot be used for second/subsequent renewals and directs express renewal orders under Section 8(3) after reasons are recorded, with priority to captive mining and raw-material leases. It further directs that renewal applications be disposed of within six months and that leases lacking clearances remain suspended until compliant. The interim order aims to ensure mineral supply while enforcing environmental laws, and the matter is disposed of with interim directions.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • A. K. Patnaik
  • Surinder Singh Nijjar
  • Mohamed Ibrahim Kalifulla
Judgment Date
2014-05-16
Court Decision / Holding
Interim directions directing that 26 leases operating as second/subsequent renewals without express renewal orders under Section 8(3) shall not operate until express orders are passed; all renewal applications under Section 8(3) to be considered and disposed of within six months; priority to renewal applications for leases granted for captive mining or raw material supply; 16 leases with valid deeds may operate; 14 leases under first renewal may operate; 26 second/subsequent renewals to be handled after express orders; interim matter disposed of.
Final Disposition
Writ Petition disposed of.

Parties to the Case

Appellants / Petitioners

  • Common Cause

Respondents

  • Union of India
  • Ors

Provisions of Law Cited

Mines and Minerals (Development and Regulation) Act, 1957 — s. 8(2), s. 8(3)Mineral Concession Rules, 1960 — r. 24A(6)Environment (Protection) Act, 1986Forest Conservation Act, 1980Constitution of India — Article 32

Submissions & Arguments

Contentions of Appellants / Petitioners

Common Cause contended that mining operations in Odisha were continuing without essential environmental clearances and without renewal by the government, and that interim measures were necessary to enforce compliance with the law. It urged suspension of non-compliant leases, preservation of ecological safeguards under the Environment and Forest laws, and a time-bound process to resolve renewal applications under Section 8(3), prioritizing leases for captive mining or raw-material supply. The Court’s reliance on the CEC’s findings aimed to harmonize law enforcement with mineral production needs.

Contentions of Respondents

The respondents argued for a measured, time-bound renewal process under Section 8(3) to balance mineral development with environmental safeguards, highlighting the national need for iron ore and the role of captive mining in steel production. They contended that the deemed renewal provision under Rule 24A(6) cannot justify second or subsequent renewals without express orders and reasons recorded by the State Government, and urged expeditious processing of renewals, backed by a Special High-Level Committee to complete renewals within six months.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Goa Foundation v. Union of IndiaWrit Petition (C) No. 435 of 2012PositiveThe Court notes it had previously held in Goa Foundation v. Union of India (21.04.2014) that the deemed renewal provision under Rule 24A(6) is not applicable to second and subsequent renewals under Section 8(3), and follows that reasoning in the present judgment.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,491 words•~12 min read

In The Court Record

Common Cause v. Union of India

. ' A # [2°'14) 7 S.C.R. 561 # COMMON CAUSE _v._ # UNION OF INDIA & ORS (Writ Petition (Civil) No. 114 of 2014) MAY 16, 2014. 8 # **[A;K. PATNAlK, SURINDER SINGH NIJJAR,** FAKKI~ . ' **MOHAMED IBRAHIM KALIFULLA, JJ.]** ## _Mines and minerals:_ c _Mines and Minerals (Development and Regulation) Act, 1957_ - _s. 8(3)_ - _Mineral Concession Rules, 1960_ - _r. 24A(6)_ - _Illegal mining in State of Odisha_ - _Writ petition_ - _Several_ ... _lessees operating without clearances under the 1986 Act and_ 0 . _the 1980 Act, and without renewal by the Government- Interim order- Pursuant thereto, examination of the matter by Central Empowered Committee (CEC)_ - _Submission of report by CEG as regards the mining leases which are operational, which were not having requisite environmental .:;f.9arances,_ E _which are suspended, rejected or lapsed, and those under first_ - _renewal and deemed renewal provision Out of these 26 iron ore/manganese leases being operated as second and subsequent deemed renewals u/r. 24A(6) of the 1960 Rules without any express orders of renewal passed by the State_ F _Government_ - _Held: Directions issued that the 26 leases_ . _operating as second and subsequent renewals without any express orders of renewal passed by the State Government would not be allowed to operate by State Government until express orders are passed in terms of s.8(3) of the 1957 Act_ G - _State Government directed to consider· all renewal applications and dispose them of within_ six _months from today_ - _State Government further directed to consider first the_ H 561 • 562 SUPREME COURT REPORTS [2014] 7 S.C.R. A _renewal applications in respect of leases granted for captive mining for providing iron or manganese ore as raw material for industries and thereafter, the renewal applications in_ - _respect of the other leases Environment (Protection) Act,_ - _1986 Forest Conservation Act, 1980._ B Goa _Foundation Vs .. Union of India_ Writ Petition (C) No. 435 of 2012 dated 21.4.2014-referred to . . CIVIL ORIGINAL JURISDICTION : Writ Petition (Civil) No. 0[114 ][of ][2014. ] Under Article 32 of the Constitution of India. K. V. Vishwanathan, Rakesh Kumar Khanna, ASG., Dr. Abhishek Man Singhvi, Mukul Rohtagi, Pinaki Mishra, F. S. D Nariman,Gopal Jain, Gopal Subramanium, Ashok Parija, K. K. Venugopal, Manas Mahapatra, P.P. Rao, Ajit Kumar Sinha, Anil B. Dewan, Raj Panjawani, Prashant Bhushan, Ramesh K. Mishra, Shyam Singh Chauhan, Ramesh Singh, R.M. Patnaik, E Kedar Nath Tripathi, Sunil K. Jain, Madhur Jain, Jagmohan Sharma, Rajat Jeriwal, Aakash Bajaj, Sanjeev Kumar, R.N. Karanjawala, Manik Karanjawala, Nandini Gore, Devina Sehgal; Tahira Karanjawala, Neha Khandelwal (for Karanjawal & Co.,) Anand Varma, ·P. M. Patnaik, Shiv Mangal Sharma, F :Nishit Agrawal, Shrey K.aRoor (For AURA & Co.,) D. L. Chidananda, Seema Rao, Mohit Nagar, Syed Tanweer Ahmad, Sudarshan Singh Rawat, D.S. Mahta, Tanveer Ahmad, Sukhbeer Kaur Bajwa, Kirlt Renu Mishra, Apurva Upmanyu, Dheeraj Nair for the Appearing Parties. G. The Order of the Court was delivered by A. K. PATNAIK, J. 1. This writ petition relates to mining in the State of Odisha. When the writ petition was heard on the preliminary point on 21.04.2014, we found from the averments H COMMON CAUSE _v._ UNION OF INDIA [A.K. PATNAIK, J.] 563 in paragraph 14 of the writ petition that several le;;sees were operating without clearances under the Environment (Protection) Act, 1986 and the Forest (Conservation) Act, 1980, and without renewal by .the Government and we were of the opinion that an. interim order needs to be passed in respect of the lessees who are operatin!J the leases in violation of the law. On 21.04.2014, therefore, while issuing notice in the writ petition, we directed that the matter be listed on ~8.04.2014 for consideration of the Interim order that should be passed in the writ petitioh. On 21.04.2014, we also directed that the CEC, . in the meanwhile, will make out a iist of such lessee.s who are operating the leases in violation of the law and granted liberty to the parties to produce t.heir papers before the CEC and directed that the State of Odisha and the Union of India will . cooperate with the CEC to prepare the list. A B C D 2. Pursuant to the order passed on 21.04.2014, the cec . examined the matter during a meeting held on 24.04,2014 with ·the Chief Secretary, the Commissioner-cum-Secretary (Mines), the Principal Secretary (Forest), the Principal Chief Conservator of Forests and other senior officers of the Government of E Odisha as well as Dr. V.P. Upadhyay, Director IA(Non-Coal Mining) and Mrs. Bharati, Director (AOHQ), of the Ministry of Environment and Forests and the Secretary General, Federation of Indian Mining Industries (FIMI) and also examined· F th.e representations received by the CEC on behalf of the lease holders, and has submitted a report dated 25.4.2014. E 3. We have considered the report dated 25.4.2014 of the CEC, and the submissions made by learned counsel appearing . for- ~ifferent parties, and we find that 102 mining leases'do not have requisite environmental clearances, approvals under the Forest (Conservation) Act, 1980, approved Mining Plan and/ or Consent to Operate. A list of these 102 mining leases is annexed to the report of the CEC as Annexure R-2. The CEC G H 564 SUPREME COURT REPORTS [2014] 7 S.C.R. A has, however, stated in the report that mining operations in these 102 mining leases have been suspended and these 102 mining leases have been classified as non-working leases. We direct that mining operations in these 102 mining leases listed in Annexure R-2 of th,e report of the CEC shall remain B suspended, but it will be open to such lessees to move the concerned authorities for environmental clearances, approval under the Forest (Conservation) Act, 1980, approval of Mining Plan or Consent to Operate and as and when the mining lessees are able to obtain all the clearances/approval/consent, c they may move this Court for modification of this interim order in relation to their cases. 4. We further find that 29 mining leases listed in Annexure R-3 to the report of the CEC have been determined or have o been rejected or have lapsed. We direct that mining operations in these 29 mining leasei> will also remain suspended, but it will be open for the lessees of these 29 mining leases to move the concerned authorities or the Court or the Tribunal for necessary relief and as and when they get appropriate relief E from the concerned authorities or the Court or the Tribunal, they may move this Court for modification of this interim order in relation to their cases. 5. We also find that 53 iron ore/manganese mining leases F listed in Annexure R-4 to the report of the CEC are operating and all of them are having approvals under the Forest .(Conservation) Act, 1980, Consent to Operate granted by the Odisha State Pollution Control Board and approved Mining Plans and 3 more mining leases listed in Annexure R-5 are G located in forest as well as in non-forest land and those located In non-forest area do not have approval under the Forest (Conservation) Act, 1980. Hence, a total of 56 iron ore/ manganese mining leases are presently operating in the State <;>f Odisha, but out of these 56 operating mining leases, lease H COMMON' CAUSE _v._ UNION OF INDIA [A.K. PATNAIK, J.] 565 ' deeds in respeet of 16 mining leases listed in Annexure R-6 to the report of the CEC have been executed and the balance 140 mining leases are operating under the deemed renewal 1provision in Rule 24A(6) of the Mineral Cohcession Rules, 1[1960. Out of these 40 mining leases, 14 leases are operating ] 1 as first renewal and 26 leases are "operating a. s second and 1 subsequent renewals and the renewal applications are at 1 various stages of examination and in some cases 'in principle' decision to grant the renewals have been taken and the follow up actions are under process. A B c 6. The 16 mining leases listed in Annexure R-6 to the report of the CEC in respect of which the lease deeds for grant or the renewal 'of mining leases have been executed may be allowed to be operated for the time being as they have valid lease deeds in their favour. Out of the remaining 40 mining D leases, 14 leases are under the first renewal. As the lessees have a right of first renewal for a period not exceeding 20 years under Section 8(2) of the Mines and Minerals (Development and Regulation) Act, 1957 and as under Rule 24A(6) of the Mineral Concession Rules, 1960, the leases are deemed to E have been extended by a further period till the State Goveroment passes orders thereon, these 14 leases under the first renewal I may be allowed to be operated. The 'remaining 26 leases are being operated as second and subsequent deemed renewals F under Rule 24A(6} of the Min.era! Concession Rules, 1960 without any express orders of renewal passed by the State Government. We have 'already taken a view in our judgment dated 21.4.2014 in Writ Petition (C) No. 435 of 2012 (Goa _Foundation Vs. Union of India)_ that the provision of deemed G renewal in Rule 24A(6) of the Mineral Concession Rule, 1. 960 is not available for the second and subsequent renewals of a mining lease considering the language of Section 8 (3) of the ·Mining and Minerals (Development and Regulation) Act, 1957. 'Hence, these 26 leases cannot be allowed to be operated until H D F G H [2014] 7 S.C.R. ## 566 SUPREME COUl~T REPORTS A the State Government passes express orders in terms of Section 8(3) of the Mines and Minerals (Development and Regulation) Act, 1957 after it forms an opinion that in the interests of mineral development it is necessary to renew the leases and after it records reasons for renewal of the leases B in respect of the minerals. 7. Learned counsel for the lessees, however, submitted that the lessees are not at fault inasmuch as they have submitted their applications for renewal in tim~ and it was for c the State Government to consider their applications and pass orders in terms of Section 8(3) of the Mines and Minerals (Development and Regulation) Act, 1957 and, therefore, the lessees should not be allowed to suffer closure of their mines for the fault of the State Government. We cannot accept this D submission of learned -counsel for the lessees because under Section 8(2) of the Mines and Minerals (Development and Regulation) Act, 1957 the lessees have a statutory right of a first renewal for a maximum period of 20 years, but after the expiry of the first renewal they have right only to apply for further E renewal of the leases under Section 8(3) of the Mines and Minerals (Development and Regulation) Act, 1957 and the State Government has the power to renew for a further period only if it is of the opinion that in the interest of mineral F development it is necessary so to do and only if reasons are recorded by the State Government for such renewal of the leases and in the case of the 26 lessees who are operating under the second and subse!quent renewals, this opinion has not been formed and the reasons have not been recorded by G th~ State Government in te'rms of Section 8(3) of the Mines and Minerals (Development and Regulation) Act, 1957. 8. Mr. K.V. Viswanathan, learned Additional Solicitor General, referred to the application for intervention filed on H COMMON CAUSE _v._ UNION OF INDIA 567 [A.K. PATNAIK, J.] behalf of Ministry of Steel, Government of India, supported by A , the affidavit of Shri KB. Nair, Under Secretary, Ministry of Steel, Government of India, and submitted that more than 50% of the requirement of iron ore of the country is met from the State of Odisha and a large number of iron ore leases in the State are B granted for captive mining and the ore from the mines is being utilized for the manufacturing of the steel in the plants of the lessees. He further submitted that commercial miners are also ,. providing raw material to iron and steel industries not only in the State but also in the whole country. He submitted that while ·c . there is a need to impose time limits by various authorities, · closure of mining operations due to delay in decisions by the State Government on mining lease renewal applications, may adversely affect the availability of critical raw materials like iron _ore_ for domestic value addition industry, including the steel 0 sector and,, therefore, where t~e application for renewals have . been mede within the time prescribed under the statute, _l_ th~ · State Government which has to take the decision should ·be directed to decide the applications in a time bound manner so that the industry is not penalized~ E B 0[. ] E 9. We find from the report of the C.EC that the Chief Secretary,_ Odisha, has stated before the CEC that a special drive has been undertaken to complete the process of renewal of the mining leases and for this purpose a High Level Committee under the Cha•rmanship of th~ Additional Chief Secretary has been constituted and this Committee has met five.times and'in a number _qf_ cases 'in principle' decisions have been taken and efforts are on to ensure that the process of renewal_ of leases is completed within the next six months, F G . ,_ . ') .10. After considering the report of the CEC as weH as the submissions on behalf of the parties! we .. direct as an interim · measure that these 26 leases operating as second and. subsequent renewals without any express orders of re.newal H ~ . [201~] 7 S.C.R. ## 568 SUPREME COURT REPORTS A passed by the State Government will not be allowed to operate by the State Government until express orders are passed in terms of Section 8(3) of the Mines arid Minerals (Development and Regulation) Act, 195,7 and we . also direct . that . all renewal applications under Section 8(3) of the Mines and Minerals B (Development and Regulation) Act, 1957 will be considered and ' disposed of by the State Government within six months from today. We furthet direct that the ~tate Government will-consider first the renewal applications in respect of leases which were C granted for captive mining for providing iron or manganese or~ as raw material for industries and only thereafter consider the renewal applications in respec~ of the other leases. In any ca1e. the State Government wi.11 ensure that the entire process of consideration and disposal of renewal applications under 0[Section ][8(3) ][of ][the ][Act ][is ][completed ][within ][six ][months ][from ] today. With the aforesaid interim directions, the interim matter stand disposed of. Nidhi Jain Writ Petition disposed of.
End of Judgment Record
Browse All Supreme Court of India (2014) Decisions
2014-07-01

Duryodhan Rout v. State of Orissa

These appeals challenge a common judgment convicting Duryodhan Rout of rape and murder of a 10-year-old girl, Subhasini Bhoi. The trial court convicted him under IPC sections 376(f), 302, and 201 and sentenced him to death; on reference, the High Court remitted the death sentence for the 302 offence to life imprisonment while keeping the other sentences unchanged. The prosecution's case rested solely on circumstantial evidence. PW-1 and PW-2 saw the accused with the victim on a bicycle around 4 p.m. and returning alone about an hour later; PW-5 (father) and PW-6 (mother) testified that the child was taken on the pretext of talking on the phone. In custody, the accused confessed before PW-3 and PW-4, and under Section 27 of the Evidence Act the recovery of the body and the underwear was recorded; the autopsy by PW-9 indicated throttling and injuries consistent with rape. The chain of circumstances — last-seen with the victim, recovery of the corpse in the jungle, and the forensic findings — formed a robust basis for conviction. The central legal issue was whether sentences for multiple offences should run consecutively. The Court held that life imprisonment is the remainder of a convict's natural life, and the proviso to Section 31(2) Cr.P.C. prevents aggregation beyond fourteen years, thus consecutive sentences cannot be imposed where life imprisonment is one of the terms. Consequently, all IPC sentences should run concurrently; the death sentence for the 302 offence was replaced by life imprisonment, and the appeal was allowed in part.

2014-12-16

Nand Kishore v. State of Madhya Pradesh

This is a criminal original jurisdiction writ petition under Article 32 challenging the continued incarceration of a convict under Section 302 IPC, with the petitioner contending entitlement to the Juvenile Justice (Care and Protection of Children) Act, 2000 (JJC Act) protections on the ground that he was a juvenile at the time of the offence (born 14 April 1980; incident on 18 June 1997). The Court scrutinized documentary and oral evidence from the Juvenile Justice Board indicating the petitioner’s true date of birth and concluded that on the date of occurrence he was 17 years 2 months 4 days old, thereby satisfying the juvenile criteria. The judgment clarifies a central legal question: whether the protections and benefits under the JJC Act, enacted in 2000, can be extended to those convicted before its coming into force if they were juveniles at the time of the offence. Relying on earlier decisions such as Hariram v. State of Rajasthan and Ajay Kumar v. State of Madhya Pradesh (and others), the Court held that a person who had not completed 18 years on the date of offence is entitled to the Act’s benefits as if the provisions had always existed, effectively retroactively applying the protective regime. The petition was allowed; the petitioner is to be released forthwith, with bail bonds and sureties discharged, reflecting the Court’s protective stance for juveniles in criminal proceedings.

2014-04-24

Vishal Goyal & Ors. v. State of Karnataka & Ors.

This batch of writ petitions under Article 32 concerns admissions to Post Graduate Medical and Dental courses in government medical/dental colleges and the state quota in private colleges in Karnataka for the 2014-2015 academic year. The petitioners, who completed MBBS/BDS in Karnataka, challenged sub-clause (a) of clause 2.1 of two National Board of Examinations Information Bulletins (PGET-2014) which defined “Karnataka Origin” to permit admission only to those who satisfy certain criteria, effectively excluding many who studied in Karnataka institutions. They argued this violates Article 14 (equality before law and equal protection of laws) and undermines merit-based selection for postgraduate courses. They invoked Dr. Pradeep Jain & Others v. Union of India (1984) to contend that institutional preference may be permissible but must conform to equality; Magan Mehrotra v. Union of India (2003), Saurabh Chaudhri v. Union of India (2003), and Nikhil Himthani v. State of Uttarakhand (2013) were cited to support the continuing emphasis on merit and equality. The State countered that Article 371J allows reservation for the Hyderabad-Karnataka region and argued that the Pradeep Jain framework applies only to government or state-instrumentality institutions and not to private colleges. The Court held sub-clause (a) ultra vires Article 14, directed fresh Information Bulletins, and ordered admissions in accordance with the law on the basis of existing entrance test results, with the general counselling schedule from Dr. Fraz Naseem & Ors. not applying for 2014-2015 Karnataka admissions.

2014-08-21

SINGH RAM (D) THR. L.Rs. v. SHEO RAM & ORS.

This is a Supreme Court of India decision on the limit of time within which a usufructuary mortgagee can seek relief, and the corresponding equity of redemption for the mortgagor. The appellants challenged the Punjab and Haryana High Court Full Bench’s view that there is no fixed time for redemption in a usufructuary mortgage and that the right to seek redemption arises on payment/deposit of mortgage money, irrespective of the mortgage date. The HP High Court’s decision was later reversed by a larger bench of this Court in the context of reconciling conflicting precedents such as Sampuran Singh, Prabhakaran and Jayasingh Dhyanu Mhoprekar, Parichhan Mistry and Harbans etc., emphasizing that Section 62 of the Transfer of Property Act confers a special right on the usufructuary mortgagor to recover possession, which begins only when the mortgage money is paid out of rents and profits or when paid/deposited by the mortgagor. Article 61 of the Limitation Act governs the period for redeeming or recovering possession (30 years from accrual of the right, unless restricted). The Court reaffirms the principle ‘once a mortgage, always redeemable’ and rejects a blanket 30-year extinguishment rule for usufructuary mortgages, upholding the Full Bench view of the Punjab and Haryana High Court and dismissing the appeals. The decision emphasizes equity, statutory recognition under Section 62, and the distinctive treatment of usufructuary mortgages.