Tenetowl LogoTenetowl
Landmark CasesDivision BenchAppeals dismissed; no costs.

CLP India Pvt. Ltd. vs Gujarat Urja Vikas Nigam Ltd. & Anr. (Civil Appeal Nos. 2793 of 2010 and 2969 of 2010)

Case / Petition Number:
CA 2793/2010; CA 2969/2010

Case Synopsis & Summary

This Supreme Court judgment disposes of two Civil Appeals filed under Section 125 of the Electricity Act, 2003, challenging an Appellate Tribunal for Electricity order on recovery of deemed generation incentive and related interest. The core dispute arises from a 1994 power purchase agreement between the erstwhile Gujarat State Electricity Board (now Gujarat Urja Vikas Nigam Ltd., GUVNL) and CLP, concerning the supply of 635 MW for 20 years and tariff normalization under notifications issued under Section 43A of the Electricity (Supply) Act, 1948. After amendments to the tariff framework—most notably the 1995 amendment (Note 2) to the 1992 notification, restricting deemed generation incentives—the parties continued payments for incentives for a period, followed by disputes and a petition before the Gujarat Electricity Regulatory Commission (GERC) in 2006. The central question was whether incentive payments (and related deemed loan/own capital arrangements) and interest on certain capital components could be claimed beyond certain periods, and whether amendments to the tariff regime bound the parties. The Supreme Court held that the amended notification Note 2 applied and that relief could be granted only for a three-year window prior to the filing of the petition, dismissing the appeals and upholding the concurrent findings of the GERC and APTEL. The decision emphasizes that statutory tariff notifications bind contractual terms and that change-in-law provisions within PPAs cannot override statutory norms when determining tariff.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • S. Ravindra Bhhat, J.
  • Arun Mishra, J.
  • Vineet Saran, J.
Judgment Date
2020-05-06
Court Decision / Holding
Both appeals fail; the judgments of the GERC and APTEL are upheld and the appeals are dismissed with no order as to costs.
Final Disposition
Appeals dismissed; no costs.

Parties to the Case

Appellants / Petitioners

  • CLP (India) Pvt. Ltd.
  • Gujarat Urja Vikas Nigam Ltd.

Respondents

  • Gujarat Urja Vikas Nigam Ltd. (GUVNL) & Anr.
  • CLP Limited

Legal Representation & Advocates

Counsels for Petitioners

  • • Mr. Sajan Poovayya (Senior Counsel)

Counsels for Respondents

  • • Mr. C.A. Sundaram (Senior Counsel)

Provisions of Law Cited

Section 125 of the Electricity Act, 2003Section 43A of the Electricity (Supply) Act, 1948Section 86(1)(f) of the Electricity Act, 2003Limitation Act, Section 18Tariff Regulations: CERC Tariff Regulations, 2001 and 2004Notification No. SO 251(E) dated 30-03-1992 (as amended)Note(2) to the 06-11-1995 amendment to the 1992 notificationTariff terms under PPA Schedule VII (Clause 7.1, 7.4, 7.5.10)Clause 6.5 (Change in Law) of the PPA09.06.1998 Union Ministry notification for incentive norms

Legal Doctrines & Maxims

  • Estoppel
  • Change in Law (Tariff) principle
  • Expressio unius est exclusio alterius (implied)

Submissions & Arguments

Contentions of Appellants / Petitioners

CLP contends that the 1995 amendmentNote(2) to the 1992 notification applied prospectively and did not apply to its gas-based plant, which used naphtha only as a supplementary/fallback fuel. It argues that the PPA terms, including the incentive for generation above normative PLF, reflect a negotiated tariff framework; the amendment could not retroactively nullify obligations and that the issue of deemed loan interest should be determined by the agreement’s terms and applicable tariff regulations, including the 2001 and 2004 Tariff Regulations. CLP also asserts that an estoppel/equitable claim cannot bar a legitimate pre-existing dispute; it seeks recovery for the past periods unless barred by limitation.—(Concise summary of CLP’s stance.)

Contentions of Respondents

Gujarat Urja's position is that the 1995 amendment Note(2) is binding; generation incentives were legally restricted and not payable to CLP for periods beyond the amendment; the GERC and APTEL correctly held that incentives payable under the older regime were not admissible; the deviation from the amended tariff cannot be justified by earlier correspondence or negotiations. Gujarat Urja also upholds the prospective effect of the amendment and the change-in-law clause; it emphasizes that statutory tariff norms govern the PWAs and any overpayments must be recovered within the time-bar limits (three-year window) as determined by the tribunal and the regulator. The Respondent stresses that the law governing tariff takes precedence over private contract terms when a statutory notification alters incentives.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (9)

Case NameCitationTreatmentExplanation
India Thermal Power Ltd. v. State of M.P. & Ors.(2000) 3 SCC 379PositiveAuthority for the proposition that PPAs can contain terms agreed by the parties, but tariffs must be in accordance with Section 43A.
Binani Zinc Ltd. v. Kerala State Electricity Board(2009) 11 SCCPositiveSupports the view that PPAs can be statutory to the extent they contain tariff provisions under Section 43A.
Tata Power Co. Ltd. v. Adani Electricity Mumbai Ltd. & Ors.(2009) 11 SCC 244PositiveCited as aligning with the approach that tariff regulations govern the determination of tariff despite terms of a PPA.
Hari Shankar Singhania v. Gaur Hari Singhania(2006?) SCCMentioned OnlyCited in context of limitation and estoppel, but not adopted as controlling doctrine here.
Sri Ram Mills Ltd. v. Utility Premises Ltd.(2007) 4 SCC 599Mentioned OnlyCited in discussion on limitation and time-bar; not adopted as binding in this decision.
Uttar Haryana Bijli Vitran Nigam Ltd. & Ors. v. Adani Power Ltd. & Ors.(2019) 5 SCC 325PositiveUsed to illustrate the treatment of debt-equity and its implications on tariff/incentive issues.
National Thermal Power Corp. Ltd. v. MP State Electricity Board(2011) 15 SCC 580PositiveSupports principles related to changes in law and tariff adjustments.
South Eastern Coalfields Ltd. v. Union of India(2003) 8 SCC 648PositiveCited in relation to damages/interest under statutory provisions and tariff regimes.
Damodar Valley Corporation v. Central Electricity Regulatory Commission & Ors.(2018) SCALE 451PositiveUsed to explain capital structure and interest on normative debt within tariff regulations.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•6,897 words•~32 min read

In The Court Record

CLP India Pvt. Ltd. vs Gujarat Urja Vikas Nigam Ltd. & Anr. (Civil Appeal Nos. 2793 of 2010 and 2969 of 2010)

1 ## **REPORTABLE** ## **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 2793 OF 2010** ## **CLP INDIA PVT. LTD.** **...APPELLANT(S)** **VERSUS** **GUJARAT URJA VIKAS NIGAM LTD. & ANR. ...RESPONDENT(S)** **WITH** **CIVIL APPEAL NO. 2969 OF 2010** ## **JUDGMENT** ## **S. RAVINDRA BHAT, J.** **1.** The present judgment will dispose of two appeals preferred under Section 125 of the Electricity Act, 2003. One appeal (CA 2969/2010) has been preferred by the Gujarat Urja Vikas Nigam Ltd. (hereafter,"Gujarat Urja"or "GUVN”) `;` the second (CA 2793/2010) has been preferred by CLP (India) Pvt. Ltd. (formerly, Gujarat Torrent Energy Corporation Ltd; later, Gujarat Paguthan Energy Corporation Ltd, a generating company, hereafter collectively "CLP”). Both appeals challenge a common order of the Appellate Tribunal for Electricity `(` “APTEL” hereafter). **2.** The erstwhile Gujarat Electricity Board (GEB) (now “Gujarat Urja”) entered into a power purchase agreement (“PPA” `)` with CLP on 03.02.1994. In terms of the Signature Not Verified Digitally signed by DEEPAK SINGH Date: 2021.07.17 PPA, Gujarat Urja was under an obligation to purchase - and CLP was under 17:50:07 IST Reason: corresponding obligation to supply - 635 MW of electricity; the tenure of the agreement was 20 years. In terms of Section 43(A) of the Electricity Supply Act, 2 1948, (hereafter"the Act"), a generating company may enter into a contract for the sale of electricity with the Electricity Board and the tariff for the sale of electricity shall be determined by the authority through the notification issued by the Central Government. Prior the PPA in this case, the Central Government had issued a notification under Section 43A, on 30.03.1992, specifying the controlling norms, terms and conditions for determination of tariff for sale of electricity by the generating company to the Electricity Boards. One of those conditions was the provision for incentive to units using naphtha. On 17.01.1994, an amendment to the notification dated 30.03.1992 was made providing for Note (1) stating that the incentive for generation above the target availability of 68.49% for fixed cost recovery was to be capped. **3.** After the signing of the PPA between the parties, an amendment notification dated 06.11.1995 was issued by the Central Government amending the notification (dated 30.03.1992). By this, the Central Government provided that there would no longer be any deemed Generation Incentive payable to any generating company on available declaration of Naphtha as fuel. Based on this notification, the Electricity Board sought to enforce the said notification claiming that this generating company is not entitled to get the incentive for deemed generation. The Electricity Board also sent a letter dated 18.04.1996 informing the CLP, that it proposed to amend the Clause 7.5.2.1 of the PPA to the effect that no deemed generation shall be admissible beyond the level of generation in respect of Naphtha. CLP did not agree to the proposal and by its reply dated 24.04.1996 stated that the notification of 06.11.1995 was inapplicable. Gujarat Urja did not agree to CLP's position and reiterated its earlier position about the change in the incentive terms. A meeting was held in respect of various issues on 06.10.1997 during which several issues were discussed and decisions taken, between the parties. However, the minutes of meeting did not record any decision on the issue of incentive restricted in terms of the notification dated 06.11.1995. There was some more correspondence and meetings, which however, did not lead to any result in regard to both parties 3 accepting that the incentive was payable in terms of the notification of November,1995. Ultimately, with effect from December 1997, CLP started billing Gujarat Urja for the power supplied, including the incentive (ignoring the amending notification); Gujarat Urja continued to pay deemed generation incentive from June, 1998 to 2000. **4.** The Union Ministry of Power issued a notification (dated 09.06.1998) which clarified profits on operating norms; several components such as station heat rate, auxiliary consumption and secondary fuel consumption were eliminated and income tax on incentives was no longer permitted (as a pass through in tariff). It was stated that this was prospective in operation and would apply to power purchase agreements which were not executed and delivered by the parties by 09.06.1998. For a long time, incentive continued to be paid, ignoring the notification of 06.11.1995 by Gujarat Urja, to CLP. On 05.12.2003, CLP and Gujarat Urja entered into a supplementary agreement, amending the PPA, to incorporate concessions offered by CLP to reduce tariff. Pursuant to execution of the supplementary agreement dated 05.12.2003, Gujarat Urja issued a letter to CLP stating that all the outstanding issues stood fully and finally resolved. Gujarat Urja continued to pay deemed generation incentive from 05.12.2003 to 23.02.2005. In February, 2005, a high-level committee was constituted to examine the issue of recovery of excess payouts made on the basis of deemed generation incentive. The receipt of the report, of that committee, led Gujarat Urja to file an application for recovery of the amounts from CLP (Petition No.874/2006 under Section 86(1)(f) of the Act, before the Gujarat Electricity Regulatory Commission ("GERC"), claiming for recovery of deemed generation incentive paid to CLP during the period from 1997-98 to 200506. **5** . CLP resisted Gujarat Urja's application, contending that principles of estoppel precluded recovery; that in any event, parties had not agreed to change the terms of the PPA and that the previous correspondence evidenced that the matter had been closed, which meant that Gujarat Urja could not claim recovery of any so-called 4 excess amounts. The GERC, by its order held that Note 2 (introduced by the notification of 06.11.1995) was applicable to the project and thus deemed generation incentive is not payable to CLP. However, it permitted recovery of only for a period of three years prior to the date of filing of the petition: the recovery for the period prior to 14.09.2002 were held to be time-barred. **6.** The second appeal, i.e. CA 2793/2010 by CLP Limited, questions the impugned order of the APTEL which had upheld the rejection of its claim for interest on deemed loan component. **7.** The facts as far as this appeal is concerned are that a supplementary agreement was executed between the parties on 05.12.2003. In terms of Article 4.6 of the Supplementary Agreement, original clause 7.5.14(a) of the PPA dated 03.02.1994 was substituted[1] . CLP stated that the amount, i.e. ₹ 53.90 crores was in fact due as a loan. If it was deemed as a loan, then interest was payable on the basis of normative repayment of principal amount during the period of the loan, i.e. the loan would not remain as a constant. In this regard, CLP had relied upon Clause 1.5 of the notification dated 30.03.1992[2] . The PPA dated 03.02.1994 by Schedule VII Clause 7.5.10 defined _"Interest on Loan Capital"_ in the following terms: `"` _7.5.10: Interest on Loan Capital-shall mean the sum of all payment of interest along with bank charges and all associated financing costs paid to the bank annually on the outstanding loans paid by GTEC, converted, as of the first day of the fortnight for the applicable fixed charge, into the currencies in which it is payable employing exchange rates at bank's_ 1 _The substituted term, i.e. the new clause 7.5.14(a) reads as follows:_ `"` _The parties have agreed to recognize an amount of Rs.53.90 crores as"Own Capital"deployed to meet with the Capital Cost and allowance of Payment of cost in the form of "Cost of Own Capital"@ the rate of 14% per annum effective from 1.7.2003 and up to 31.12.2009. No payment of any nature will accrue after the said date on the said amount."_ > _Clause 1.5 reads as follows:_ `"` _1.5…………….(a) Interest on loan capital shall be computed on the outstanding loans, including the schedule of repayment, as per the financial package approved by the Authority….."_ 2 5 _selling rate prevailing on that day obtained from the source mutually agreed."_ **8.** The _CERC Tariff Regulations, 2001_ which provided for _"Interest on loan capital”_ `[` clause 2.7(a)] and _CERC Tariff Regulations,2004_ were relied upon. They are set out below: `"` _2.7(a)Interest on loan capital_ _Interest on loan capital shall be computed on the outstanding loans, duly taking into account the schedule of repayment as per the financial package approved by the Authority or an appropriate independent agency, as the case may be."_ **9.** CERC Tariff Regulations, 2004 _inter alia_ provides as under: _“20.Debt-Equity Ratio:(1) In case of alia generating stations, declared under commercial operation on or after 1.4.2004,debt-equity ratio as on the date of commercial operation shall be 70:30 for determination of tariff. Where equity employed is more than 30%,the amount of equity for determination of tariff shall be limited to 30% and the balance amount shall be considered as the normative loan._ _Provided that in case of a generating station where actual equity employed is less than 30%, the actual debt and equity shall be considered for determination of tariff._ _(2) The debt and equity amount arrived at in accordance with clause (1) shall be used for calculating interest on loan, return on equity, Advance against Depreciation and Foreign Exchange Rate Variation."_ **10.** Gujarat Urja resisted this claim. After adjudication, the GERC rejected the CLP's argument on a plain reading of the clause, saying that for the first time in the supplementary agreement, which stated that the agreement too recognized ₹ 53.9 crores as own Capital for which the cost of Own Capital @ 14% was to be a pass through. The effective date for such recognition was from 01.07.2003 to 31.03.2009 and no amounts were due and payable as interest after that date. It was specifically stated that this condition constituted the complete bargain to the extent it provided for treatment of cost of Own Capital @ 14% per annum for a defined period. The 6 agreement had to be and was given prospective operation. This excluded any liability on part of Gujarat Urja for the past period, i.e. December 1997. It was also held that the claim made in 2010 was substantially barred to the extent it sought for any amount of interest beyond a period of three years. **11.** The CLP claimed on another issue, i.e. interest on ₹ 14.48 crores @ 16% per annum from July 2000 to 30.06.2003 was payable. In terms of the supplementary agreement, the condition specifically stated that GPEC (i.e. CLC) had further deployed a sum of ₹ 14,48,40,831/- from its internal accrual to complete shortfall and disbursal of loan by the lenders, which agreed to allow payment on this amount @ 16% per annum from July 2000 to 30.06.2012. Gujarat Urja stated that this interest was payable on reducing balance terms, not as bullet payment of interest. **12.** The CERC ruled that it was quite clear that the parties had agreed to allow interest at the said rate, @ 16% on the said sum, i.e. ₹ 14.48 crores. Therefore, Gujarat Urja could not argue that interest was payable on the reducing balance method and that the payment of interest on a bullet repayment method was not permissible. The Commission, i.e. GERC noted that the statutory notification, i.e. clause 1.5 of the notification dated 30.03.1992 did not prohibit calculation of interest on bullet repayment as regards clause 7.5.10 in Schedule VII of the PPA dated 03.02.1994, the subject matter or its content was deemed loan. On this second aspect, therefore, the terms of the contract contained in the supplementary agreement directing 16% per annum interest on ₹ 14.48 crores is bullet repayment, was upheld. **13.** The CLP Limited was aggrieved by that portion of GERC's order which rejected its claim on the deemed loan component prior to the period 2003. It appealed to the APTEL (Appeal No.44/2009). The APTEL concurred with the decision of the GERC and held that clause 7.5.14(a) of the supplementary agreement did not oblige Gujarat Urja to refund interest paid upon the deemed loan component upon the equity portion treated as deemed loan, i.e. ₹ 53.9 crores for any 7 period prior to 01.07.2003. Therefore, CLP's appeal was rejected. It, therefore, has appealed to this Court on the said findings. **==> picture [477 x 33] intentionally omitted <==** ## _**Analysis and Findings**_ **14.** Section 43A of the Electricity (Supply) Act, 1948 (hereafter "the Supply Act") reads as follows: `"` _43A. Terms, conditions and tariff for sale of electricity by Generating Company.-_ `(` _1) A Generating Company may enter into a contract for the sale of electricity generated by it-_ `(` _a) with the Board constituted for the State or any of the States in which a generating station owned or operated by the company is located;_ `(` _b) with the Board constituted for any other State in which it is carrying on its activities in pursuance of sub-section(3) of section 15A; and_ _(c) with any other person with consent of the competent government or governments._ _(2) The tariff for the sale of electricity by a Generating Company to the Board shall be determined in accordance with the norms regarding operation and the Plant Load Factor as may be laid down by the Authority and in accordance with the rates of depreciation and reasonable return and such other factors as may be determined, from time to time, by the Central Government, by notification in the Official Gazette:_ _Provided that the terms, conditions and tariff for such sale shall, in respect of a Generating Company, wholly or partly owned by the Central Government, be such as may be determined by the Central Government and in respect of a Generating Company wholly or partly owned by one or more State Governments be such as may be determined, from time to time, by the government or governments concerned."_ **==> picture [446 x 33] intentionally omitted <==** **15** . At the outset, it is noticeable that on the issue, whether amounts paid to CLP, for the period 1998 to 2005 onwards, were in excess of what was actually payable by Gujarat Urja, the findings of GERC and the APTEL are concurrent. This court does not discern any unreasonableness or facial omission of material factors, 8 to warrant appellate review. Nevertheless, the court would proceed to deal with the submissions made on this aspect. Gujarat Urja contends that the concurrent findings, to the extent they limit the refund to a period up-to 2002 are erroneous, because in effect CLP has been unjustly enriched. Learned senior counsel for Gujarat Urja, Mr. C.A. Sundaram, argued that once the GERC found, on a plain reading and interpretation of the tariff order of 1992 – as amended by the notification dated 06.11.1995, that incentive could not be paid in the same manner as was contemplated by the parties, when they entered into the PPA (on 03.02.1994), as a matter of law, the amounts paid were excess; consequently, both in law as well as in equity, CLP was under an obligation to refund the entire excess, from the time it was not entitled to those amounts. **16.** On the question of limitation, learned senior counsel argued that the APTEL erred in law, in not following the decisions of this court in _Hari Shankar Singhania v. Gaur Hari Singhania[3]_ and _Sri Ram Mills Ltd.v. Utility Premises Ltd.[4]_ in considering that the issue was not time-barred. Counsel submitted that the question was engaging the attention of the parties and CLP was aware of the fact that the Central Electricity Authority and the Central Government had taken decisions on this aspect. Moreover, as a matter of law, by reason of the amendment, to the notification (dated 06.11.1995), CLP could not have legitimately claimed more tariff based on the incentive policy that was no longer applicable. Therefore, the amounts paid _to the extent they were not in conformity with the said amendment, had to be refunded in entirety._ **17.** On behalf of CLP it was urged, by Mr. Sajan Poovayya, learned senior counsel, that both the authorities below erred in their interpretation of the terms of the PPA, the notification of 30.03.1992 and the amendment of 06.11.1995. It was argued that CLP's generation station is gas-based and not a Naphtha based station. The notification dated 06.11.1995 applied only to 100% Naphtha based stations and > 3 _(2006) 4 SCC 658_ 4 _(2007) 4 SCC 599_ 9 not to gas based stations like that of CLP, where Naphtha was used as a secondary fuel when the Gas was not available. The expression "Naphtha based station" used in the notification is a term of art; it refers merely to the physical characteristic of the plant and not to the nature of fuel to be used. It was further contended that the amending notification of 06.11.1995 itself makes a distinction between gas based stations and naphtha based stations. CLP's plant, in terms of PPA is a gas based, not Naphtha based. Therefore, the notification dated 06.11.1995 would not apply to its plant. Also, urged counsel, since the PPA was entered into on 03.02.1994, the amendment notification dated 06.11.1995 would not apply to the pre-existing PPA, since it has a prospective effect. It was lastly submitted that Clause 6.5 of the PPA dated 03.02.1994 regarding change of law is clarificatory in nature. It deals only with the earlier part to protect the interest of the GPEC for change in law. "The change in law" referred to in Clause 6.5 covers amendment to notification dated 30.03.1992. Therefore, the financial difficulties resulting from the amendment notification dated 06.11.1995 are to be compensated in favour of the CLP. **18.** It was argued that Note(2) of the amended notification dated 06.11.1995 unambiguously states that it applies only to Naphtha based stations for whom generation incentive was inapplicable. Therefore, the gas based units like CLP were clearly not covered by Note(2) since they used naphtha only as an alternative fuel or substitute fuel. Therefore, the findings given by the GERC and APTEL to the effect that Naphtha based station include those that are capable of firing Naphtha also as a fuel, and not mean those which are capable of firing only Naphtha, is wrong. **19.** The submissions of parties are with respect to two notifications dated 30.03.1992 and 06.11.1995. These Notifications were under Section 43(A) of the Supply Act. Concededly, these notifications are statutory and are binding on the parties. Any PPA between a generating company and the purchaser of electricity is subject to such statutory notifications; parties by agreement cannot override statutory provisions, or such notifications, as far as they relate to matters of tariff. 10 **20.** Therefore, the rights and obligations of the parties under the PPA have to be read subject to the statutory provisions. The provisions of the PPA, if they are contrary to the statutory provisions, cannot be given effect to. In terms of the PPA of 03.02.1994, "fuel" is defined as follows: `"` _Fuel natural gas and/or any liquid fuel selected by Gujarat Torrant Electricity Company (GTEC) (now CLP) for use in power station for generating electricity"_ _‘fuel management'_ is defined as follows: `"` _Fuel Management:-The power station of the GTEC is designed to use natural gas and liquid fuel as fuel. GTEC shall decide selection and use and proportion gas and other fuel in best economic way depending on the situation from time to time."_ **21.** The kind of alternative fuel and its long-term purchase contract could be jointly decided by CLP and Gujarat Urja. The cost of the alternate fuel when used by CLP shall be taken into account for calculation of variable charges as defined in Schedule VII (of the PPA). Clause 7.1 and Clause 7.4 of Schedule VII to the PPA are relevant.[5] Under the former, Gujarat Urja had to purchase power from CLP on the basis of the notification of 30.03.1992 of the Central Government. It further provided that the tariff for the first 6000 Kwh/kw (i.e 68.5% PLF – i.e. plant load factor) of net availability in any year was to be the sum of (a) the fixed charge and 5 _For convenience,they are set out as follows:_ `"` _**7.1 Tariff** GEB shall purchase power from GTEC, generally on the basis of GOI notification No.SO 251(E) dtd. 30-3-1992. The Tariff for the first 6,000 kWH/KW (i.e. 68.5 PLF) of Net Availability in any year during the terms of this Agreement shall be the sum of_ `(` _a)the Fixed Charge and (b) the Variable Charge. For all the energy of actual and deemed generation in excess of 68.4 % PLF in any Year ,the Tariff payable by GEB shall be the sum of (a) the Incentive described below and (b) the Variable Charge. Any tax or impost on or pertaining to sale of energy or capacity shall be payable by GEB over and above the Tariff._ _… …… …… …..._ _**7.4 Incentive** The incentive referred to in 7.1 above with respect to any fortnight shall be in the form of additional return on equity at the rate of 0.575% for every 1% increase in the generation above the normative level of 6000 hours per kWH/KW(i.e 68.5% PLF) in accordance with the amendment dated 17.1.94 to the said notification No.SO 251(E)."_ **==> picture [477 x 33] intentionally omitted <==** 11 (b) the variable charge (i.e those terms defined by clauses 7.2 and 7.3). For all excess energy of actual and deemed generation in excess of 68.5%, the tariff payable was to be the sum of (a) incentive and (b) variable charge. Clause 7.4 provided for incentive, which was to be @ 0.575% for every 1% increase in the generation above the normative level of 6000 hours per kWH/KW (i.e 68.5% PLF) in accordance with the notification S.O. 251(E), dated 30.03.1992 (as amended on 17.01.1994). **22.** The argument of CLP that its unit was essentially gas-based and that the definition of naphtha-based unit meant only that unit which depended entirely on naphtha as a fuel, or that which used naphtha at least to the extent of 50%, in our opinion is not correct. **23.** The judgment of this court in _India Thermal Power Ltd. vs. State of M.P. & Ors.[6]_ is an authority for the proposition that parties can agree to terms as they deem appropriate, for generation and sale of electricity under Section 43A except that the tariff is to be in accordance with the provision contained in Section 43A. The decision in _Binani Zinc Ltd. v. Kerala State Electricity Board[7]_ ; _Tata Power_ 6 _(2000) 3 SCC 379, where it was held pertinently that:_ `"` _Section 43 empowers Electricity Board to enter into arrangement for purchase of electricity on such terms as may be agreed. Section 43-A(1) provides that a generating company may enter into a contract for the sale of electricity generated by it with Electricity Board. As regards the determination of tariff for the sale of electricity by a generating company to the Board, Section 43(1)(2) provides that the tariff shall be determined in accordance with the norms regarding operation and plant load factor as may be laid down by the authority and in accordance with the rates of depreciation and reasonable return and such other factors as may be determined from time to time by the Central Government by a notification in the official gazette. These provision clearly indicate that the agreement can be on such terms as may be agreed by the parties except that the tariff is to be determined in accordance with the provision contained in Section 43-A(2)and notifications issued thereunder. Merely because a contract is entered into in exercise of an enacting power conferred by a statute that by itself cannot render the contract a statutory contract. If entering into a contract containing prescribed terms and conditions is a must under the statute than that contract becomes a statutory contract. If a contract incorporate certain terms and conditions in it which are statutory then the said contract to that extent is statutory. A contract may contain certain other terms and conditions which may not be of a statutory character and which have been incorporated therein as a result of a mutual agreement between the parties. Therefore, the PPAs can be regarded as statutory only to the extent that they contain provisions regarding determination of tariff and other statutory requirements of Section 43A(2)."_ 7 _(2009) 11 SCC 244_ 12 _Company Ltd. vs. Adani Electricity Mumbai Ltd. and Ors.[8]_ too have taken a similar approach. **24.** Clause 6.5 of the PPA of 03.02.1994 dealt with a situation concerning change of law. It also stated that any amendment in the Central Government's notification dated 30.03.1992 would be taken into account for tariff calculation.[9] The relevant part of the notification of 30.03.1992 which dealt with charges recoverable by the generating company was clause 1.6.[10] That condition was amended by the notification dated 06.11.1995 which clearly stated, by Note(2) that: `"` _Note:2-For Naptha based thermal plants, the extent of backing down, as ordered by Regional Electricity Boards, beyond plant Load Factor of 6000 kwh/kw/year, shall not be reckoned as generation achieved for incentive purpose."_ **25.** There is no dispute that the PPA which the parties entered into specifically referred to the notification of 30.03.1992 and further went on to state that for the 8 _2019(7) SCALE 297_ 9 _The stipulation reads as follows:_ `"` _6.5 Change in Law: In the event that as a result of any laws or regulations of any Governmental Authority or any national ,regional or municipal authority thereof coming into effect after the date hereof, and in force at the date hereof being amended, modified or repealed, the interest of GTEC in the Project and/or GTEC's projected economic return net of tax (or other imposition) on its investment in the Project is materially reduced prejudiced or otherwise adversely affected (including without limitation, any restriction on the ability to convert Rupees or remit funds in foreign currencies outside of India) then the parties hereto shall meet and endeavour to agree on amendments to this Agreement to the effect that all of the increased cost or lost return on investment incurred by GTEC that would result from complying with or being subject to any such change in law shall be passed through to GEB under GTEC Tariff. Any amendment in Government of India Notification No.S.O.251(E)dated 30.3.92 shall be taken into account for Tariff calculation."_ 10 _The said condition in the notification is as follows:_ `"` _1.6 Full fixed charges shall be recoverable at generation level of 5500-6000 hours/KW/year: Payment of fixed charges below the level of 5500 KWh/KW/year shall be on prorata basis. There shall not be any payment of fixed charges for generation levels above 6000 hours./KW/year: However generation above 6000 hours./KW/Year shall be at negotiated rates between the Generating companies and the Board, which shall not include fixed cost element. While computing the level of generation, the extent of backing down, as ordered by the Regional Electricity Board shall be reckoned as generation achieved. The payment of fixed charges shall be on monthly basis, proportionate to the electricity drawn by the respective Boards. Necessary adjustment based on actual sales and deemed sales shall be made at the end of each year:"_ 13 first Kwh/KW, a plant load factor of 68.5% fixed charges and variable charges were deployed. For generation achieved over and above this by the concerned unit – CLP, an incentive @ 5.75% for every 1% increase over and above the fixed and variable charge payable was agreed to. Significantly, the fixed and variable charges are in consonance with the statutory notification of 30.03.1992 (which was also later amended on 17.01.1994). This much is clear from a plain reading of clause 7.1 of the Schedule VII to the PPA itself. In view of the fact that the notification amended on 06.11.1995 was a statutory one, there cannot be any doubt that it was binding upon the parties. Therefore, the earlier notification which left it free to the parties to negotiate on various aspects, including on the incentive payable, stood amended by Note 2, which was added to clause 1.6 of the tariff. The effect of this statutory incorporation by way of amendment was that incentive no longer became payable. The arguments by the CLP, in the opinion of the Court, that the parties were bound only by the terms of the agreement and that the amendment notification being prospective, could not have altered the terms of the tariff, especially the incentive payable, are insubstantial and have no force. The concurrent findings on this aspect, therefore, are sound and do not call for interference. Likewise, the change of law provision (Clause 6.5 of the PPA) clearly contemplated that any amendment to the prevailing tariff notification (dated 30.03.1992) would bind the parties. Since Note (2) was an amendment, which dealt with the issue of incentive, it cannot now be said that it was inapplicable. The findings of the lower authorities, therefore, are correct; no interference is called for. **26.** The next question is whether the GERC and APTEL fell into error in granting restricted refund calculable for the 3 year period prior to Gujarat Urja's application. The concurred findings on this aspect, in the opinion of this court, are reasonable. There is merit in CPL's submission that the earliest point in time, when the cause of action arose, was in May,1996, when Gujarat Urja rejected its contention that incentive was payable in terms of the PPA, notwithstanding the notification of 06.11.1995. Despite this stated position, meetings continued to be 14 held and, what is more, incentive amounts, were paid to CLP. No doubt, no document conclusively stated that CLP's claim was accepted. We do not find any merit in the submission of Gujarat Urja that the issue was kept alive, due to a series of communications. In this regard, APTEL's findings about inapplicability of Section 18 of the Limitation Act, are correct. There was no admission on the part of CLP, at least of the kind, that extended the time for preferring an application for recovery of excess payments. It has been consistently ruled by this court that repeated letters, or exchange of communications, do not extend the period of limitation, provided by law.[11] **27.** The third, and last issue, is with respect to payment of interest on deemed equity. Clause 1.5 of the 30.03.1992 notification provided for interest on loan, as a component of tariff; it stipulated that interest (on outstanding loan) shall be computed as per financial package approved by the Authority (CEA). The PPA of 03.02.1994 (Schedule VII) clause 7.5.10 defined interest on loan capital as `"` _the sum of all payments of interest along with bank charges and all associated financing costs paid to the bank annually on the outstanding loans paid by GTEC.…"_ The Central Commission's order of 21.02.2000 led to a stipulation in the tariff regulations of 2001. Eventually, the Tariff Regulations of 2004 was brought into force; it provided for a debt ratio of 70:30 for determination of tariff. It also provided that: `"` _Where equity employed is more than 30%, the amount of equity for determination of tariff shall be limited to 30% and the balance amount shall be considered as the normative loan"_ **28.** The debt-equity ratio in this case, was disturbed; accordingly ₹ 53.9 crores was treated as “deemed” or normative loan, for which the parties had to agree the rate of interest payable, in accordance with the tariff notification. It was in the light > 11 _S.S.Rathore v State of Madhya Pradesh 1989 (4) SCC 582; Union of India v Har Dayal 2010 (1) SCC 394; Schlumberger Asia Services Ltd vs. Oil and Natural Gas Corporation Ltd. 2013 (7) SCC 562._ 15 of these developments that the supplementary agreement was entered into. That amended the existing PPA, to the following effect[12] : `"` _The parties have agreed to recognize an amount of Rs.53.90 crores as "Own Capital" deployed to meet with the Capital Cost and allowance of Payment of cost in the form of "Cost of Own Capital"@ the rate of 14%per annum effective from 1.7.2003 and up to 31.12.2009. No payment of any nature will accrue after the said date on the said amount."_ **29.** It is thus apparent, that the parties did not harbor any doubt about the period for which the specified interest was payable on such deemed loan. The rate of interest was fixed; likewise, the date from which payment obligations were to arise, too were known. Also, the date upto which the interest on such deemed loan payments were to be made, was known and fixed. In these circumstances, CLP's claim that the payment of interest for a prior period was outstanding, and constituted Gujarat Urja's liability, is insubstantial. In a recent judgment[13] a similar issue had arisen. The court quoted from the decision in _National Thermal Power Corporation Ltd. v. Madhya Pradesh State Electricity Board[14]_ where another previous decision was cited with approval on the issue that the express provision for something, in an agreement, meant that other similar matters stood excluded.[15] 12 _f.n.1 ibid._ 13 _Uttar Haryana Bijli Vitran Nigam Ltd.and Ors. vs. Adani Power Ltd. and Ors. 2019 (5) SCC 325_ > 14 _(2011)15 SCC 580_ 15 _The relevant portions of this court's observations, in Uttar Haryana (f.n.13 ibid) are as under.:_ `"` _25. In this connection, it is material to note that the claim in South Eastern Coalfields_ _(2003) 8 SCC 6487 was essentially covered Under Section 61 of the Sale of Goods Act,1930, and the interest by way of damages was payable as per this statutory provision itself. The liability had been crystallised and the interest had become payable because of the failure to pay the amount as per the liability. Besides, there was nothing in the agreement between the parties to the contrary on the issue of grant of interest. In the present matter, we have the second proviso to Regulation 79(2) of the 1999 Regulations which permitted the generating company to continue to charge the existing tariff for such period as may be specified in the notification by the Commission, and the notifications permitted continuation of the existing tariff as on 31-3-2001, until the final tariff was determined. There was no provision for payment of interest therein. The very fact that interest came to be provided subsequently by a notification under the Regulations of_ 16 **30.** A somewhat analogous issue, i.e. interest on normative deemed loan (i.e. deemed loan), in the context of changed debt-equity ratios, under tariff regimes was considered in a decision of this court[16] , where it was held that: `"` _20. In the order of the Appellate Tribunal dated 23.11.2007 the matter came to be dealt with under the heading 'debt equity ratio'.The Tribunal went on to accept the case of the Appellant in respect of all old projects of DVC and normative debt equity of 50:50 was assigned, commissioned prior to 1992. In respect of recent projects such as Mejina, it was assigned debt equity ratio of 70:30 on capital structure as specified in the Regulations. This finding has become final. It was contended on behalf of the Appellant that equity has been the primary source of capital. Thereafter,in paragraph A-10, it was found by the Appellate Tribunal that owners take upon themselves business related risk and are entitled to interest on capital investment,but the return is to be governed by the scheme of determination of tariff for the supply of electricity as mandated by the law in place. The Appellate Tribunal further proceeds to hold that the scheme provides for assured Return on Equity (ROE) which is at the rate of 14% on the equity employed for the purpose of supplying electricity. The scheme does not permit return on investment made on projects other than for supply of electricity to be recovered from supply of electricity. The Tribunal went on to hold that the DVC Act does not recognise capital as borrowings and there is no reference about repayment of such capital to the participating Governments. The Appellate Tribunal proceeds to hold that the capital infused by participating Governments is in the nature of equity capital and for the determination of tariff, the same would be eligible for return on equity but the Appellate Tribunal does not end there. It clearly provides that the return on equity is as may be permitted by the tariff Regulation of 2004. It is thereafter that the Appellate Tribunal in para 15 proceeded to hold that the DVC Act provides for interest on capital which is contributed by the participating Governments. The accrued interest due to the Governments apparently has been allowed to be retained by the Appellant. The same however came to be ploughed back into the capital with the tacit consent of the participating Governments. Thereafter, it is stated that this has to be provided to the DVC as per the provisions of Section 38 of the DVC Act. It is thereafter paragraph A-16 which we have already extracted, the Tribunal proceeded to observe that_ > _2004 is also indicative of a contrary situation in the present matter viz. that interest was not payable earlier."_ > 16 _Damodar Valley Corporation vs. Central Electricity Regulatory Commission & Ors. 2018 (15) SCALE 451._ 17 _under the DVC Act if there is any deficit in the capital contributed by the participating Governments,it is to be made good by taking loan on behalf of the participating Governments. The said debt would attract interest. The average interest rate of the repayment payable is to be applied on a 50:50 normative debt capital. This means that out of the aggregate equity including reserves, equity considering the normative debt ratio of 50:50 would be eligible for return on equity as specified in the Regulations and the excess of equity,if any, over the equity earning ratio of 14% is to be considered as interest bearing debt. In the example which has been given it is shown that if the debt equity ratio is 40:60, return on equity at 14% will be available on 50% equity whereas interest would be available at 10% portion of equity and 40% loan which were reduced by repayments._ _21. On the basis of the remand, the Commission has worked out the debt equity ratio as directed by the Appellate Tribunal. It has further provided return on equity at the rate of 14% on the equity portion, namely 50%. In respect of the debt portion, interest has been calculated no doubt after deducting depreciation, the legality of which is the subject matter of the other contention which we will deal with separately. It is quite clear to us that Appellant has already been given return on equity in terms of the tariff Regulation in respect of capital on the basis of debt equity ratio which has been fixed by the Appellate Tribunal on a ratio which has become final between the parties._ _22. Though a perusal of para A-9 of order dated 23.11.2007 may appear to show that equity has been found to be the main source of capital, a perusal of paragraph A-10,A-16 and more importantly E-13 would show that capital Under Section 38 of the DVC Act has been understood as the value of the operating assets when they were first put to commercial use. Capital is also understood not as equity alone but it has been understood both as loan and equity. The ratio between loan and equity is also fixed in respect of the old projects at 50:50 and under the new projects it is at 70:30.It is further clear from paragraph E-13 of the order of the Appellate Tribunal dated 23.11.2007 that the appellate Tribunal contemplated that the equity component would remain static and it would earn the rate of return as provided in the tariff Regulation. As far as the loan component is concerned, it would get reduced on account of repayments. Therefore, the recovery as contemplated under the Regulations was found to be in two forms, namely, either as return on equity in respect of the equity portion and as interest on the loan component."_ 18 **31.** In the present case, the clear agreement between the parties was that interest on the sum of ₹ 53.90 crores was payable for the specified period 01.07.2003 to 31.12.2009.Therefore, CLP's claim that any amount was payable, for any period prior to 01.07.2003, was not tenable. Had CLP wished so, nothing prevented it to claim for it during negotiations and have it included as a term of the contract. Once having settled for a specified sum, on an amount (₹ 53.90 crores) that was only fictionally a loan - and treated as such, for purpose of fixing interest payable, considering the equity infused, in excess of the tariff regulations, the absence of any like item, such as interest for prior period, precludes a claim. But it was really part of the equity component. Therefore, interest was _per se_ not payable, but could be paid in terms of the tariff notification or the agreement. No claim on any other legal or equitable considerations could have been made. The findings of the lower authorities are therefore, sound and reasonable. **32** . In view of the foregoing analysis and conclusions, both appeals have to fail. They are accordingly dismissed, without order on costs. **==> picture [477 x 73] intentionally omitted <==** _**..........................................**_ **...J.** **[ARUN MISHRA]** **==> picture [477 x 68] intentionally omitted <==** **.............................................J. [VINEET SARAN] .............................................J. [S. RAVINDRA BHAT]** **New Delhi, May 06, 2020**
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.