High Court of KeralaDivision BenchRevision petition dismissed

C.K. Ashalatha Divakaran v. T.K. Sahira and others

Case / Petition Number:RCR 363/2017

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • K. Harilal
  • Annie John
Judgment Date
2018-07-11
Court Decision / Holding
RCR 363/2017 dismissed. The Revision Petition is rejected; the High Court upholds the concurrent orders of the Rent Control Court and Rent Control Appellate Authority granting permission to reconstruct, with directions to the Municipality to act under existing Building Rules. It clarifies that the Municipality is at liberty to decide per current norms, and that construction costs may be adjusted against rent accruals.
Final Disposition
Revision petition dismissed

Parties to the Case

Appellants / Petitioners

  • C.K. Ashalatha Divakaran

Respondents

  • T.K. Sahira
  • C.K. Chandra Prabha
  • Subha Sasidharan
  • Susanth Sasidharan
  • Sushil Sasidharan

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri. Jeswin P. Varghese
  • • Smt. K.P. Surya

Counsels for Respondents

  • • Sri. Abdul Raoof Pallipath
  • • Sri. K.R. Avinash (Kunnath)

Case Synopsis & Summary

This Rent Control Revision arises from concurrent orders in a dispute over permission to reconstruct a tenanted shop following eviction and demolition under Section 11(4)(iv) of the Kerala Buildings (Lease and Rent Control) Act. The revision petitioner (landlord) challenged the Rent Control Court’s and the Rent Control Appellate Authority’s orders permitting the tenants to reconstruct the building with municipal permission, arguing the Rent Control Court lacks power to direct renewal of permits and that the second proviso to Section 11(4)(iv) should be read as applying to the Munsiff’s Court, not the Rent Control Court. He contends that the tenant did not surrender possession voluntarily, that the redevelopment hinges on municipal permissions and amended Building Rules, and that long delays, increased construction costs, and changes in open-space requirements render reconstruction impracticable, with the application filed beyond a year from the eviction order falling foul of limitation. The respondents/tenants contend that the Rent Control Court has broad, supervisory power to issue directions to effectuate eviction orders, including permission to reconstruct in line with the approved permit and plan, and that the municipality may adjust or renew permits to facilitate reconstruction. The High Court ultimately upholds the concurrent orders, finds the Rent Control Court empowered to entertain such applications, and dismisses the revision, while clarifying that the Municipality may act under current Building Rules.

Provisions of Law Cited

Kerala Buildings (Lease and Rent Control) Act, Sec. 11(4)(iv) (including first and second provisos)

Legal Doctrines & Maxims

  • Discretionary power of the Rent Control Court to issue directions to give effect to eviction orders; ‘any manner’ includes reconstruction as a last resort.
  • Harmonious reading of provisos with the principal section to interpret the scope of the Court’s powers.

Submissions & Arguments

Contentions of Appellants / Petitioners

The revision petitioner argued that the Rent Control Court has no power to direct the Municipality to renew or issue a fresh permit for reconstruction; the second proviso to Section 11(4)(iv) should be read as applying to the Munsiff’s Court, not the Rent Control Court, and thus the Rent Control Court’s jurisdiction to authorize reconstruction is improper. He also contended that the eviction order, surrender of possession, demolition, delays in obtaining a new permit, and changes in Building Rules render reconstruction legally or practically impossible, and that the petition was filed beyond the permissible period, constituting a bar by limitation.

Contentions of Respondents

The tenants contended that the Rent Control Court has wide discretionary power under the second proviso to 11(4)(iv) to issue directions to give effect to the eviction order, including permission to reconstruct in accordance with the municipal permit and plan. They argued the provision contemplates the Rent Control Court as the proper forum to grant reconstruction when all other measures have failed, and that the municipal authorities may renew or adjust permits to facilitate reconstruction; the plan remains in force and the building, once reconstructed, would be the landlord’s property.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Karthiyani Amma v. Lakshmi Amma1992 (1) KLT 138PositiveCited to support the view that the Rent Control Court possesses wide discretionary power to issue necessary orders, including permission to reconstruct, when evictions have not complied with timelines.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against C.K. Ashalatha Divakaran v. T.K. Sahira and others and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT: THE HONOURABLE MR.JUSTICE K.HARILAL & THE HONOURABLE MRS. JUSTICE ANNIE JOHN WEDNESDAY, THE 11TH DAY OF JULY 2018 / 20TH ASHADHA, 1940 RCRev..No. 363 of 2017 RCA 135/2010 of RENT CONTROL APPELLATE AUTHORITY, THALASSERY RCP 306/2005 of RENT CONTROL COURT (MUNSIFF), KANNUR REVISION PETITIONER(S)/3RD APPELLANT/4TH RESPONDENT C.K. ASHALATHA DIVAKARAN, AGED 62 YEARS, D/O. (LATE) C.T. SREEDHARAN, SUSHEELA VILLA, MILL ROAD, KANNUR. BY ADVS.SRI.JESWIN P.VARGHESE SMT.K.P.SURYA ## RESPONDENT(S)/PETITIONERS: 1. T.K. SAHIRA AGED 45 YEARS, D/O. SHAHEED, UNIVERSAL MEDICALS, KL-VI, 250 SHOP, NEAR TO HOTEL KALYANA KRISHNA BHAVAN, SOUTH BAZAR, KANNUR - 2, PIN - 670 002. 2. C.K. CHANDRA PRABHA, D/O. (LATE) C.T. SREEDHARAN, SUSHEELA VILLA, MILL ROAD, KANNUR, PIN - 670 001. 3. SUBHA SASIDHARAN, W/O. (LATE) SASIDHARAN, SUSHEELA VILLA, MILL ROAD, KANNUR, PIN - 670 001. 4. SUSANTH SASIDHARAN, W/O.(LATE), SASIDHARAN, SUSHEELA VILLA, MILL ROAD, KANNUR, PIN - 670 001. ## 5. SUSHIL SASIDHARAN, W/O. (LATE) SASIDHARAN, SUSHEELA VILLA, MILL ROAD, KANNUR, PIN - 670 001. R1 BY ADV. SRI.ABDUL RAOOF PALLIPATH R1 BY ADV. SRI.K.R.AVINASH (KUNNATH) THIS RENT CONTROL REVISION HAVING COME UP FOR ADMISSION ON 11-07-2018, THE COURT ON THE SAME DAY PASSED THE FOLLOWING: ## **'CR'** **K. HARILAL & ANNIE JOHN, JJ. ------------------------------------------RCR No. 363 of 2017 (A) -----------------------------------------Dated this the 11[th] day of July, 2018.** ## **ORDER** ## K. Harilal,J. The revision petitioner is the third appellant/landlord in RCA No. 135 of 2010 of the Rent Control Appellate Authority, Thalassery. The aforesaid appeal was filed challenging the judgment passed by the Rent Control Court, Kannur in I.A.No. 1658 of 2009 in RCP No. 306 of 2005. The said application was filed by the first respondent/tenant herein seeking permission to construct building as per the plan approved in the name of the revision petitioner/landlord and to intimate the same to the Municipality for further steps and renewal of permit, if necessary. 2. The first respondent is the tenant who was evicted from the petition schedule shop room in execution of an order passed against him under Section 11(4)(iv) of the Kerala Buildings (Lease and Rent Control) Act (‘the Act’ for short). 3. According to the first respondent, he had surrendered the tenanted shop room in compliance with the order of eviction passed against him under Section 11(4)(iv) of the Act and the appellant RCR No.363/2017 -2- demolished the entire building before 1 1/2 years. In spite of the lapse of more than one year after the surrender of the petition schedule shop room and demolition of the entire building, reconstruction work of the new building is not yet started. The building plan granted by the Municipality is in force and he along with the other tenants are ready to construct one room each in the ground floor as per the plan. According to him, the appellant wilfully neglected to reconstruct the building and on the failure of compliance with the direction in the order of eviction, he is entitled to get permission to reconstruct the petition schedule room in accordance with the building permit and plan. So he prayed for the same. The other tenants also filed similar petitions with the very same relief. 4. The revision petitioner filed objection contending that the Rent Control Court has no power to direct the Municipality to renew the permit. The Rent Control Court ceased to have power and it is for the Munsiff Court to execute the order passed by the Rent Control Court. The first respondent did not surrender vacant possession of the building voluntarily. Eventually, the petitioner filed an EP and the tenanted premises was vacated pursuant to the order passed in the said EP. On account of the delay in getting the vacant possession of the building, the permit granted by the Municipality for the reconstruction of the building was lapsed. Moreover, there is material change in the Municipal Rules regarding the open space to be left in front of the building. The cost of materials required for construction RCR No.363/2017 -3- considerably also went high. He has not neglected to re-construct the building. The aforesaid petition was filed more than one year after the delivery of the petition schedule building and therefore, it is barred by limitation. 5. After considering the rival pleas stated above, the Rent Control Court passed the common order allowing all the petitions as prayed for. Even though the revision petitioner preferred appeals, the Rent Control Appellate Authority also concurred with the findings of the Rent Control Court and dismissed all the appeals, by a common judgment. The legality and propriety of the common findings, whereby the courts below granted permission to the respondent/tenant to reconstruct the building, after obtaining necessary permission from the Municipality are challenged in this RCR. 6. Heard the learned counsel for the revision petitioner and the learned counsel for the first respondent. 7. The scope and the extent of consideration in this revision petition is confined to the legality and propriety of the concurrent findings of the courts below whereby the first respondent along with the other tenants were granted permission to re-construct the tenanted building with the permission of the Municipality in the place where the old tenanted building was situated. Going by the impugned order, it is seen that the revision petitioner has contended that the Rent Control Court ceased to have power and it is for the Munsiff’s Court to execute the order passed by the Rent Control Court. RCR No.363/2017 -4- According to the learned counsel appearing for the revision petitioner, the expression 'court' in second proviso to Section 11(4)(iv) of the Act means and includes the Munsiff's Court and not the Rent Control Court. Therefore, the Munsiff's Court alone has the jurisdiction and power to grant permission to the tenants to re-construct the building. The Appellate Authority has considered the said contention and rejected. 8. The question to be considered in this Revision is whether the Rent Control Court has jurisdiction and power to entertain an application filed under the second proviso to Section 11(4)(iv) of the Act and issue necessary directions to the landlord to see that the tenant is put back in possession of the tenanted building. On a reading of the second proviso to Section 11(4)(iv) of the Act, it could be seen that the aforesaid provision confers power to the 'Court' to issue directions regarding the re-construction of the building, on failure of compliance by the landlord. In the first proviso, the expression ‘Rent Control Court’ is used; but in the second proviso, it seems reduced to ‘Court’. We are of the opinion that the expression 'Court' in the second proviso is also intended to mean the Rent Control Court and not Munsiff's Court. The word ‘Court’ used in the second proviso cannot be interpreted in isolation and both provisos must be read and interpreted together harmoniously with the principal section. So, on a combined reading of the principal section with both provisos, it is well discernible that the Rent Control Court itself is empowered to entertain RCR No.363/2017 -5- applications and issue directions to give effect to the order in any manner the Rent Control Court deems fit and in appropriate cases to put the tenant back in possession. In the above view, the courts below are justified in finding that the Rent Control Court is the proper court empowered to pass such an order granting permission to reconstruct the building by the tenant himself. 9. Another question to be considered is whether the Rent Control Court has power to pass an order granting permission to the tenant to re-construct the building. This Court is of the view that by employing the wording "the Court shall have power to issue directions to give effect to the order in any manner the Court deems fit and in appropriate cases to put the tenant back in possession", the Rent Control Court has been given very wide discretionary power to issue the necessary orders to see that the tenant is put back in possession of the new building and the expression "any manner" includes power to grant permission to the tenant to re-construct the tenanted building in accordance with the approved permit and plan and to occupy the same. But such permission can be granted as last resort, where all other measures are exhausted. The above view is supported by the decision of this Court in _**Karthiyani Amma v. Lakshmi Amma**_ (1992 (1) KLT 138). 10. In the above view, the courts below are fully justified in granting permission to re-construct the tenanted room in the building where the old tenanted building was originally situated, when the RCR No.363/2017 -6- landlord failed to re-construct the building within the time specified by the Rent Control Court in the order passed under Section 11(4)(iv) of the Act. 11. Further, it is contended by the learned counsel for the revision petitioner that the re-construction of the proposed building became impossible as per the present Building Rules. But no materials had been produced before the Rent Control Court or the appellate authority to substantiate the said contention that the re-construction became impossible due to change in the Building Rules. In the absence of any materials in this regard, the courts below are justified in rejecting the said contention. With abundant caution, the Rent Control Court has made it clear that if any modification is required in the permit and plan to comply with the amendment, if any, in the Building Rules, the same can be done by the Municipality and a further direction was issued to communicate a copy of the order to the Kannur Municipality also. Further, we notice that with abundant caution, the courts below have concurrently held that the respondent/tenant is entitled to re-construct the building as per the plan and permit issued to the landlord by the Municipality and the cost of construction can be adjusted by the tenant from the rent of the building which accrues later. It is needless to say, the building after re-construction would belong to the appellant/landlord. We find that the appellate authority has considered all the legal issues and answered the same correctly. We do not find any reason to interfere with the orders passed by the RCR No.363/2017 -7- courts below. Accordingly, this RCR is dismissed. However, it is made clear that the Municipality is at liberty to take a decision in accordance with the present Building Rules. **K. HARILAL, JUDGE.** **ANNIE JOHN, JUDGE.** _Rv_