Supreme Court of IndiaSupreme Court · 2024Division BenchPetition dismissed.

Choudappa & Anr. v. Choudappa since Deceased by Lrs. & Ors.

Case / Petition Number:
Special Leave Petition (Civil) No. 3056 of 2023
Neutral Citation:[2024] 9 S.C.R. 229 : 2024 INSC 691

Case Synopsis & Summary

Choudappa & Anr. v. Choudappa since Deceased by Lrs. & Ors. concerns a Special Leave Petition challenging a 2022 revision order in a Karnataka matter over mesne profits arising from a 1963 suit for possession and mutation correction. The Court reviewed the 1973 decree directing an inquiry into mesne profits under Order XX Rule 12 CPC. After decades of execution leading to possession in 2005, the respondents in 2014 moved for determination of mesne profits under Section 141 CPC or Order XX Rule 12. The petitioners sought dismissal under Order VII Rule 11(d) on the ground that the application was barred by limitation and a second, belated attempt to execute the decree. The Trial Court rejected the limitation plea and so did the High Court on revision. The petition contends that the mesne profits inquiry is a fresh or second execution and therefore time-barred. The respondents argued the request is not a fresh suit but a continuation of the original suit’s inquiry, a process akin to final decree preparation that carries no fixed time limit. The Court recalled that Order XX Rule 12 contemplates an ongoing inquiry, and that the absence of a statutory limitation means a holistic, fact-driven assessment is required. It affirmed that there is no absolute bar on initiating such inquiries; ultimately, the petition was dismissed, permitting respondents to participate in the inquiry.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Pankaj Mithal
  • R. Mahadevan
Judgment Date
2024-09-03
Court Decision / Holding
Petition dismissed. Petitioners are permitted to participate in the mesne profits inquiry; pending applications, if any, disposed of.
Final Disposition
Petition dismissed.

Parties to the Case

Appellants / Petitioners

  • Choudappa & Anr.

Respondents

  • Choudappa since Deceased by Lrs. & Ors.

Legal Representation & Advocates

Counsels for Petitioners

  • • C. Nageswara Rao
  • • Vikram Hegde
  • • Chitwan Sharma

Counsels for Respondents

  • • Ameet Deshpande
  • • Akshat Shrivastava
  • • Satvic Mathur

Provisions of Law Cited

Code of Civil Procedure, 1908Order XX Rule 12 CPCSection 141 CPCOrder VII Rule 11(d) CPC

Legal Doctrines & Maxims

  • Continuation of the suit and preparation of final decree under Order XX Rule 12 CPC
  • No limitation as an absolute rule; depends on facts and circumstances
  • Holistic assessment of facts and circumstances when no limitation is prescribed

Submissions & Arguments

Contentions of Appellants / Petitioners

Applicants contended that the 2014 mesne profits determination request is not a fresh action but a late reminder to complete the inquiry directed in the 1973 decree. They argued it falls within the ambit of Order XX Rule 12 CPC as part of final-decree preparation, and that there is no specific limitation prescribed for initiation of such inquiries. Therefore, the application cannot be treated as barred by laches or delay, as the court should not treat it as a second execution. They relied on precedents that equate the inquiry for mesne profits with continuation of suit and emphasize that the absence of a statutory time-bar requires a case-by-case assessment. They urged dismissal of the petition as the remedy is solely to complete the existing inquiry rather than restarting proceedings.

Contentions of Respondents

Respondents argued that the 2014 application is not a fresh suit or second execution but a reminder to complete the inquiry into mesne profits as directed by the 1973 decree. They asserted there is no time limit for such inquiries and that the courts are obliged to undertake the inquiry, as it is part of the ongoing process. They claimed the trial court’s and High Court’s decisions were correct to reject a limitation-based challenge and dismissed the petition, noting that pursuing mesne profits inquiry decades after the decree is not a separate suit and is consistent with Order XX Rule 12. The respondents further relied on relevant case-law to justify the interpretation that no absolute limitation applies to such inquiries.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Kattukandi Edathil Krishnan and Anr. v. Kattukandi Edathil Valsan and Ors.[2022] 7 SCR 1120 : (2022) 16 SCC 71 : AIR Online 2022 SC 2841PositiveCited and relied upon to support the proposition that final decree preparation can follow from a decree directing inquiry under Order XX Rule 12, and that limitations may not bar such proceedings.
M/s. North Eastern Chemicals Industries (P) Ltd. & Anr. v. M/s. Ashok Paper Mill (Assam) Ltd. & Anr.[2023] 15 SCR 821; CA No. 2669 of 2013, dated 11.12.2023 passed by the Supreme CourtPositiveReferenced to endorse the principle that in the absence of a prescribed limitation, courts should holistically assess delay and that no absolute rule of limitation applies to initiation of mesne profits inquiries.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,125 words•~10 min read

In The Court Record

Choudappa & Anr. v. Choudappa since Deceased by Lrs. & Ors.

[2024] 9 S.C.R. 229 : 2024 INSC 691 ## **Choudappa & Anr.** ## **v.** ## **Choudappa since Deceased by Lrs. & Ors.** (Special Leave Petition (Civil) No. 3056 of 2023) 03 September 2024 ## **[Pankaj Mithal and R. Mahadevan, JJ.]** ## **Issue for Consideration** In 2014, an application purported to be u/s. 141 CPC or under Order XX Rule 12 CPC was filed by the respondents for the determination of the mesne profits as directed by the judgment, order and decree dated 12.07.1973. Whether such an application is barred by limitation. ## **Headnotes[†]** **Code of Civil Procedure, 1908 – Or.XX, r.12 and s.141 – A suit for recovery of possession and for correction of mutation entries was filed by respondents in the year 1963 and it was decreed on 12.07.1973 – The said judgment, order and decree specifically directs for holding an inquiry regarding mesne profits from the date of the suit i.e., 24.09.1963 in accordance with Order XX Rule 12, CPC – Respondents applied for execution and were put into possession of the suit land property in the year 2005 – Thereafter, in 2014 an application was filed by respondents for the determination of the mesne profits – Petitioners moved an application u/Or.VII, r.11(d) CPC contending that such an application was hopelessly barred by limitation – Application u/Or.VII, r.11 (d) CPC rejected by the trial Court – Revision filed against the said order was dismissed by the High Court – Propriety:** **Held:** The Court of first instance while passing the judgment and order dated 12.07.1973 had specifically stated for holding an inquiry regarding mesne profits from the date of the suit i.e., 24.09.1963 in accordance with Order XX Rule 12, CPC – Such an inquiry is nothing but a continuation of the suit and is in the nature of preparation of the final decree and as such, it cannot be said that any application moved as a reminder for completing the inquiry is barred by limitation or is liable to be dismissed on the ground of delay or laches – It is settled that in a situation where no limitation stands provided either by specific applicability of the Limitation Act or by the special statute governing the dispute, the [2024] 9 S.C.R. 230 ## **Digital Supreme Court Reports** Trial Court must undertake a holistic assessment of the facts and circumstances of the case to examine the possibility of delay – When no limitation stands prescribed, it would be inappropriate for a Court to supplement the legislature’s wisdom by its own and provide a limitation – No limitation as an absolute rule could be provided in such matters and it depends upon the facts and circumstances of each case whether the proceedings have been initiated in a fairly reasonable time – In the instant case, the two Courts below having held that the proceedings are not barred by limitation and that actually the proceedings are not in the nature of a fresh proceedings, rather than a continuation of the old suit in the form of a preparation of the final decree – No fault can be found in the said decisions. [Paras 12, 13, 15, 16, 17] ## **Case Law Cited** _Kattukandi Edathil Krishnan and Anr. v. Kattukandi Edathil Valsan and Ors._ **[2022] 7 SCR 1120 : (2022) 16 SCC 71 : AIR Online 2022 SC 2841;** _M/s. North Eastern Chemicals Industries (P) Ltd. & Anr. v. M/s. Ashok Paper Mill (Assam) Ltd. & Anr._ **[2023] 15 SCR 821** [C.A.No. 2669 of 2013, dated 11.12.2023 passed by the Supreme Court] **– referred to.** ## **List of Acts** Code of Civil Procedure, 1908. ## **List of Keywords** Order XX Rule 12 of Code of Civil Procedure, 1908; Mesne profits; Determination of mesne profits; Limitation; Inquiry regarding mesne profits; Continuation of old suit; Preparation of final decree; Reminder for completing inquiry. ## **Case Arising From** EXTRA-ORDINARY APPELLATE JURISDICTION: Special Leave Petition (Civil) No. 3056 of 2023 From the Judgment and Order dated 22.07.2022 of the High Court of Karnataka at Kalaburagi in CRP No. 200017 of 2022 ## **Appearances for Parties** C. Nageswara Rao, Sr. Adv., Vikram Hegde, Chitwan Sharma, Advs. for the Petitioners. Ameet Deshpande, Sr. Adv., Akshat Shrivastava, Satvic Mathur, Advs. for the Respondent. [2024] 9 S.C.R.  231 **Choudappa & Anr. v. Choudappa since Deceased by Lrs. & Ors.** ## **Judgment / Order of the Supreme Court** ## **Order** Heard learned senior counsel for the parties. The challenge in the present special leave petition is to the revisional order dated 22[nd] July, 2022 passed by the High Court dismissing the revision of the petitioners arising from the rejection of their application alleged to have been filed under Order VII Rule 11(d) of the Code of Civil Procedure, 1908 (for short, ‘C.P.C.’). A suit for recovery of possession and for correction of mutation entries was filed by the respondents in the year, 1963 and it was decreed on 12.07.1973. The said judgment, order and decree specifically directs for holding an inquiry regarding mesne profits from the date of the suit i.e., 24.09.1963 in accordance with Order XX Rule 12, C.P.C. The aforesaid judgment, order and decree of the Court of first instance attained finality with the dismissal of the appeal filed by the petitioners in the year, 1980. The respondents applied for the execution so as to obtain possession of the suit land sometime in the year, 1993 and after going through the entire exercise of execution, issuance of warrant for possession, the respondents were put into possession of the suit land property in the year, 2005. It appears that sometime in 2014, an application purported to be under Section 141 C.P.C. or under Order XX Rule 12 C.P.C. was filed by the respondents for the determination of the mesne profits as directed by the judgment, order and decree dated 12.07.1973. Once such an application was filed, the petitioners moved application under Order VII Rule 11(d) C.P.C. contending that such an application is hopelessly barred by limitation and as such, it should be rejected outright. The aforesaid application filed under Order VII Rule 11(d) C.P.C. was rejected by the Trial Court and the revision thereof also met the same fate at the hands of the High Court. Thus, the Special Leave Petition. Learned counsel for the petitioners has argued that the application allegedly moved by the respondents for an inquiry for mesne profits is in the nature of a second execution and since, it has been filed [2024] 9 S.C.R. 232 ## **Digital Supreme Court Reports** decades after the decree has attained finality, it is liable to be dismissed on the ground of limitation. Learned counsel for the respondents on the other hand contends that the aforesaid application is not in a nature of a second execution or in the form of a fresh suit or a plaint, rather it is only a reminder to the Court to complete the process of inquiry with regard to determination of mesne profits as has been directed by the Court of first instance vide judgment and order dated 12.07.1973. The said proceedings are actually proceedings under Order XX Rule 12 C.P.C. wherein the Court is obliged to hold an inquiry with regard to determination of the mesne profits from the date of institution of the suit and till the delivery of the possession. Admittedly, the said inquiry has not been conducted and completed and that the law nowhere provides for any specific time limit for initiation of such proceedings rather the Court is obliged to undertake this exercise on its own. In _Kattukandi Edathil Krishnan and Anr. Vs. Kattukandi Edathil Valsan and Ors._ , _[1]_ the Court while dealing with the matter regarding a preliminary decree and the final decree in connection with the decree passed in a suit for partition opined that fundamentally there is a distinction between a preliminary and a final decree and that proceedings for final decree can be initiated at any point of time as there is no limitation for initiation of such proceedings. Either of the parties to the suit can move an application for preparation of the final decree or the Court may take action in this regard _suo moto._ In fact, after the passing of the preliminary decree, the Trial Court is obliged to proceed for the preparation of the final decree and should not adjourn the matter _sine die._ There is no need to file any separate application for the preparation of the final decree. The aforesaid analogy with regard to the preparation of the final decree pursuant to the preliminary decree for partition can very well be applied to the cases where a decree is passed with a direction to hold an inquiry with regard to determination of mesne profits. This is evident from the plain reading of Order XX Rule 12 C.P.C. For the sake of convenience, Order XX Rule 12 C.P.C. is reproduced herein below:- 1 [2022] 7 SCR 1120 : 2022 (16) SCC 71 : AIR Online 2022 SC 2841 [2024] 9 S.C.R.  233 ## **Choudappa & Anr. v. Choudappa since Deceased by Lrs. & Ors.** “12. Decree for possession and mesne profits.— (1) Where a suit is for the recovery of possession of immovable property and for rent or _mesne_ profits, the Court may pass a decree— (a) for the possession of the property; (b) for the rents which have accrued on the property during the period prior to the institution of the suit or directing an inquiry as to such rent; (ba) for the _mesne_ profits or directing an inquiry as to such mesne profits; (c) directing an inquiry as to rent or _mesne_ profits from the institution of the suit until— (i) the delivery of possession to the decree-holder, (ii) the relinquishment of possession by the judgment-debtor with notice to the decree-holder through the Court, or (iii) the expiration of three years from the date of the decree, whichever, event first occurs. (2) Where an inquiry is directed under clause (b) or clause (c), a final decree in respect of the rent or _mesne_ profits shall be passed in accordance with the result of such inquiry.” It is in the light of the aforesaid provision that the Court of first instance while passing the judgment and order dated 12.07.1973 had specifically stated as under: - “An inquiry be held regarding future mesne profits of the said suit lands from the date of the suit, that is 24-9-1963 under Order 20 Rule 12(a) C.P.C.” Now, such an inquiry is nothing but a continuation of the suit and is in the nature of preparation of the final decree and as such, it cannot be said that any application moved as a reminder for completing the inquiry is barred by limitation or is liable to be dismissed on the ground of delay or laches. Learned counsel for the petitioners has placed reliance upon a recent decision of this Court in _M/s. North Eastern Chemicals Industries (P) Ltd. & Anr. Vs. M/s. Ashok Paper Mill (Assam) Ltd. & Anr._ passed in [2024] 9 S.C.R. 234 ## **Digital Supreme Court Reports** Civil Appeal No. 2669 of 2013 on 11[th] December, 2023 to contend that where no limitation is provided, steps ought to be taken for initiation of proceedings within a reasonable time and not decades later. In the aforesaid relied upon decision, the Court has clearly stated that in a situation where no limitation stands provided either by specific applicability of the Limitation Act or by the special statute governing the dispute, the Trial Court must undertake a holistic assessment of the facts and circumstances of the case to examine the possibility of delay. When no limitation stands prescribed, it would be inappropriate for a Court to supplement the legislature’s wisdom by its own and provide a limitation. In view of the aforesaid decision also, no limitation as an absolute rule could be provided in such matters and it depends upon the facts and circumstances of each case whether the proceedings have been initiated in a fairly reasonable time. The two Courts below having held that the proceedings are not barred by limitation and that actually the proceedings are not in the nature of a fresh proceedings, rather than a continuation of the old suit in the form of a preparation of the final decree, we cannot find fault with the said decisions. We are not inclined to grant any indulgence in the matter. The present petition is, accordingly, dismissed. The petitioners are set at liberty to participate in the inquiry before the Trial Court in so far as the determination of mesne profits are concerned. Pending application(s), if any, shall stand disposed of. _Result of the case:_ Petition dismissed. > _†Headnotes prepared by:_ Ankit Gyan
End of Judgment Record
Browse All Supreme Court of India (2024) Decisions
2024-04-09

Kizhakke Vattakandiyil Madhavan (Dead) Thr. Lrs. v. Thiyyurkunnath Meethal Janaki and Ors

This appeal concerns partition of a family property in Eravattur, Kozhikode, governed by pre-1956 Mitakshara succession. Madhavan died before 1910; his widow Chiruthey remarried Neelakandan, triggering Section 2 of the Hindu Widow’s Remarriage Act, 1856, which extinguishes a widow’s rights in her deceased husband’s property on remarriage. Chiruthey’s second marriage, and a sequence of instruments dated 1910–1925—back-to-back deeds creating a lease in favour of Cheriyamma and her son (Exhibits A-20 and A-1) and an assignment (Exhibit A-2)—formed the basis for Chandu (the plaintiff) and Sankaran’s successors-in-interest to seek partition in OS 157/1985. The Trial Court granted partition to the plaintiff; the First Appellate Court dismissed; the Kerala High Court restored the Trial Court’s decree. The Supreme Court, however, allowed the appeal. It held that on remarriage the widow’s title over Madhavan’s property stood lapsed under Section 2; yet the back-to-back deeds involved Nangeli (Madhavan’s mother) and Sankaran, who retained an interest. Exhibit A-20 was treated as a valid conveyance, but Chiruthey’s own title did not survive; the lease purportedly created by A-1 could not extend beyond its 12-year term. Consequently, the plaintiff’s claim for partition could not be sustained, and the appeal was allowed with the trial/decree of the lower courts set aside.

2024-10-04

Banshidhar Construction Pvt. Ltd. v. Bharat Coking Coal Limited & Others

Banshidhar Construction Private Limited (the appellant) challenged Bharat Coking Coal Limited’s tender for a mega project to salvage, develop, and operate a coal mine under a revenue-sharing arrangement for 25 years. The tender NIT dated 16.08.2023 imposed stringent eligibility criteria, including Clause 10 requiring financial capacity documentation and a Power of Attorney for signing bids. The appellant contended that its Power of Attorney (dated 07.11.2023 and notarised 14.11.2023) was valid, and its bid documents were uploaded before the last submission date (01.12.2023). Technical bids opened on 04.12.2023, yet the appellant was declared technically disqualified on 06.05.2024 on grounds that it did not meet Clause 10. Meanwhile, Respondent No.8 was declared technically qualified and later found to be the successful bidder after financial bids were opened on 07.05.2024, despite non-compliance with the “mandatory” Clause 10 documents, including delayed Audited Balance Sheets. The High Court dismissed the writ petition. The Supreme Court, while acknowledging limited review in mega-project tenders, held that public authorities must act with fairness, transparency, and without arbitrariness or malafides. It held that the Power of Attorney requirement was satisfied and that accepting the non-compliant Respondent No.8 while rejecting the appellant was arbitrary. The Court set aside the impugned decision and permitted a fresh tender process in accordance with law, reaffirming that Article 14 requires equal treatment and non-arbitrariness in public procurement.

2024-03-21

Union of India v. M/s Indian Oil Corporation Ltd.

This Supreme Court judgment concerns an appeal by the Union of India challenging a batch of Allahabad High Court orders that directed refunds to IOCL for a difference of approx. 110 km in freight charges on the Baad–Hisar route. IOCL had been charged on the basis of a distance of 444 km under the old Local Distance Table; following Railway Ministry circulars in 2004 and 2005 rationalizing the rounding-off of chargeable distance, the distance was reduced to 333.18–334 km in practice. IOCL issued notices under Section 106 of the Railways Act, 1989 (formerly Section 78-B of the Railways Act, 1890) seeking refunds of the alleged overcharge, and 122 consignments were paid at the old distance before the authorities corrected the distance. The Railway Claims Tribunal dismissed most claims as time-barred, while the Allahabad High Court allowed IOCL’s appeals, holding that the original 444 km charge was an “illegal charge” rather than an overcharge, and thus protected by equity. The Union of India challenged this, arguing that Section 106(3) only covers refunds of overcharges and not illegal charges; that the change in distance stemmed from policy rationalization and circulars, not an erroneous charge. The Court distinguishes Hindustan Petroleum, clarifies the overcharge/illegal charge distinction, and ultimately holds that the 444 km distance was illegal. As a result, the Union’s appeals are dismissed, and IOCL’s refunds for the difference would be payable to IOCL. The matter underscores the nuanced interplay between statutory time limits, chargeable distance, and the nature of the charge in refund claims.

2024-07-23

Gene Campaign & Anr. v. Union of India & Ors.

This is a batch of writ petitions initiated in 2004–2005 addressing the environmental and regulatory treatment of GM crops, specifically the environmental release of transgenic mustard DMH-11 (Dhara Mustard Hybrid-11). The Supreme Court examined whether GEAC’s 18.10.2022 conditional approval and the 25.10.2022 decision were legally sound, whether they violated Article 21 (right to a safe environment) and whether the precautionary principle was properly applied. The court undertook a comprehensive review of the regulatory framework under the Environment Protection Act, 1986 and the 1989 Rules, as well as the Technical Expert Committee (TEC) reports and Parliamentary Standing Committee recommendations. A key feature is the dual opinions: Justice Nagarathna (with Justice Karol concurring but delivering a separate opinion) upheld a robust judicial review of executive policy in GM regulation and found serious irregularities in the decision-making process, quashing the impugned approvals and directing a national policy on GM crops, greater public transparency, and safe-guarded field testing. Justice Karol, in a separate opinion, while endorsing the need for precaution, cautioned against an outright ban on HT crops and emphasized policy matters be left to the legislature. The judgment thus emphasizes environmental rule of law, public trust, intergenerational equity, and a precautionary approach, while mandating further regulatory reform and public participation.