Chief General Manager (IPC) MP Power Trading Co Ltd v. Narmada Equipments Pvt Ltd

Case / Petition Number:
Civil Appeal No. 1051 of 2021
Neutral Citation:[2021] 4 S.C.R. 430

Case Synopsis & Summary

This judgment concerns the appointment of an arbitrator in a long-running dispute arising from a 1999 Power Purchase Agreement (PPA) between the Madhya Pradesh Electricity Board (now MP Power Trading Co Ltd) and Narmada Equipments Pvt Ltd. The PPA, which contemplated a built-and-operated mini hydro-electric project, was terminated in 2001. The respondent challenged the termination in a writ petition, but the High Court declined to entertain it due to an arbitration clause. After unsuccessful writ petitions, the respondent invoked arbitration under Clause 12.3 of the PPA in 2011 and then filed an application under Section 11(6) of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator. The appellant contended that, given Section 86(1)(f) of the Electricity Act, 2003, which vests exclusive jurisdiction with the State Electricity Commission to adjudicate disputes between licensees and generating companies, the 1996 Act’s arbitration route is inappropriate and that the 2003 Act overrides the older framework. The High Court in 2016 held that the remedies under the 2003 Act and the 1996 Act are independent, allowing the Section 11(6) proceedings to proceed. The Supreme Court reversed, holding that Section 86(1)(f) is a special provision that overrides the general arbitration provision; the date of initiating arbitration is the date of the notice (30 May 2011), rendering pre-2003 events immaterial for commencement. It also affirmed that jurisdictional objections can be raised at any stage. The appeal was allowed and the High Court’s order appointing arbitrator was set aside; costs were denied.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Dr. Dhananjaya Y. Chandrachud
  • M. R. Shah
  • Sanjiv Khanna
Judgment Date
2021-03-23
Court Decision / Holding
Appeal allowed. The Supreme Court set aside the impugned High Court order appointing an arbitrator under Section 11(6) of the 1996 Act. It held that Section 86(1)(f) is a special provision that overrides the general arbitration framework, the commencement date for arbitral proceedings is the date of the referral (30 May 2011), and inherent lack of jurisdiction can be raised at any stage. There shall be no order as to costs. Pending application, if any, stands disposed of.
Final Disposition
Appeal allowed; High Court order appointing arbitrator set aside; no costs; pending application disposed of.

Parties to the Case

Appellants / Petitioners

  • Chief General Manager (IPC) MP Power Trading Co Ltd

Respondents

  • Narmada Equipments Pvt Ltd

Legal Representation & Advocates

Counsels for Petitioners

  • • Varun K Chopra
  • • Gurtejpal Singh
  • • M/S. VKC Law Offices, Advs.

Counsels for Respondents

  • • Sanjay K. Agrawal
  • • Sarthak Nema
  • • Ms. Ankita Khare
  • • J.K. Pillai, Advs.

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 – s.11(6)Electricity Act, 2003 – s.86(1)(f)Section 21 of the 1996 ActSection 174 of the 2003 Act

Legal Doctrines & Maxims

  • Special law overrides general law (lex specialis derogat legi generali)
  • Jurisdiction cannot be assumed by consent of the parties
  • Inherent lack of jurisdiction can be raised at any stage
  • A decree without subject matter jurisdiction is a nullity
  • The word 'and' between 'generating companies' and 'to refer any dispute for arbitration' can mean 'or'

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant argued that Section 86(1)(f) of the Electricity Act, 2003 is a special provision that overrides the general arbitration framework under the Arbitration and Conciliation Act, 1996. Since the PPA was executed before 2003 and terminated in 2001, the pre-Act events should not prevent the application of s.11(6). The decision in Gujarat Urja Vikas Nigam Limited v. Essar Power Limited (2008) 4 SCC 755, which held that s.86(1)(f) overrides s.11(6), should govern; the word 'and' in s.86(1)(f) is read as 'or'. They contend that Section 174 of the 2003 Act provides overriding effect and that jurisdictional objections can be raised at any stage, including in collateral proceedings. They emphasize that commencement of arbitral proceedings should be tied to the date of referral (30 May 2011) and not pre-Act dates, and that the High Court’s appointment of an arbitrator under s.11(6) was improper.

Contentions of Respondents

The respondent argued that Gujarat Urja does not apply since the relevant events occurred before the 2003 Act’s enforcement, and the appellant did not raise the issue in the first proceedings. It was urged that the arbitral proceedings commenced on 30 May 2011, and that s.11(6) disputes could proceed independently of s.86(1)(f). The respondent contended that the State Electricity Commission could adjudicate or refer disputes, but the 2003 Act’s overriding provision does not automatically cancel the Section 11 proceeding where consent to appoint arbitrators had occurred earlier. It was argued that the High Court properly considered the independent functioning of remedies under the two statutes and that the appellate court should not interfere with the arbitration process already set in motion.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (3)

Case NameCitationTreatmentExplanation
Gujarat Urja Vikas Nigam Limited v Essar Power Limited(2008) 4 SCC 755PositiveTwo-judge bench held that s.86(1)(f) is a special provision that overrides s.11; deemed to apply to disputes between licensees and generating companies.
Hindustan Zinc Limited v Ajmer Vidyut Vitran Nigam Limited(2019) 17 SCC 82PositiveThree-judge bench reaffirmed that jurisdictional objections can be raised at any stage and that lack of jurisdiction nullifies decrees; cited to support the principle.
NHAI v Sayedabad Tea Company Limited(2020) 15 SCC 161PositiveFollowed; related to interpretation of Section 86(1)(f) and the overriding effect of the 2003 Act.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,545 words•~17 min read

In The Court Record

Chief General Manager (IPC) MP Power Trading Co Ltd v. Narmada Equipments Pvt Ltd

430 SUPREME COURT REPORTS [2021] 4 S.C.R. 430 [2021] 4 S.C.R. A ## CHIEF GENERAL MANAGER (IPC) MP POWER TRADING CO LTD & ANR. v. ## NARMADA EQUIPMENTS PVT LTD B (Civil Appeal No. 1051 of 2021) ## MARCH 23, 2021 ## **[DR. DHANANJAYA Y CHANDRACHUD, M. R. SHAH AND SANJIV KHANNA, JJ.]** - _Arbitration: Appointment of arbitrator – Madhya Pradesh_ - C _Electricity Board entered into a Power Purchase Agreement (PPA) in 1999 with the respondent – PPA was terminated in 2001 – High Court declined the writ petition filed by respondent in view of arbitration clause contained in the PPA – In 2011, respondent issued notice to the Board invoking arbitration as contained in the PPA –_ - D _As no reply was received, respondent filed application under s.11(6) of AC Act seeking appointment of arbitrator – High Court allowed the application declining the plea of appellant that in view of the provisions of s.86(1)(f) of the Electricity Act, 2003, it was the State Electricity Commission which was vested with the exclusive jurisdiction to adjudicate upon disputes between licencees and_ - E _generating companies – On appeal, held: It is well settled that the special law overrides the general law – s.86(1)(f) of 2003 Act is a special provision and hence will override the general provision in s.11 of the AC Act for arbitration of disputes between the licensee and generating companies – Hence, s.11 of the AC Act has no_ - F _application to the question as to who can adjudicate/arbitrate disputes between licensees and generating companies, and only s.86(1)(f) shall apply in such a situation – Arbitration and Conciliation Act, 1996 – s.11(6) – Electricity Act, 2003 – s.86(1)(f)._ - _Jurisdiction: Jurisdiction cannot be assumed by consent of_ - G _parties – If there is inherent lack of jurisdiction, the plea can be taken at any stage and also in collateral proceedings._ ## **Allowing the appeal, the Court** **HELD: 1. In the present case, the notice for the initiation of arbitration under Clause 12.3 of the PPA was issued by the** H 430 431 C. G. M. (IPC) MP POWER TRADING CO LTD v. NARMADA EQUIPMENTS PVT LTD **respondent on 30 May 2011. The commencement of the arbitral** A **proceedings by the invocation of the arbitration agreement would, therefore, relate to 30 May 2011, when the notice invoking Clause 12.3 was issued. Hence, the fact that the PPA and the notice of termination predate the 2003 Act would not constitute material circumstances. Section 21 of the 1996 Act specifies that unless** B **otherwise agreed by the parties, the arbitral proceedings in respect of a particular dispute would commence on the date on which a request for that dispute to be referred to arbitration is received by the respondent. Hence, there can be no manner of doubt that 30 May 2011 would be the material date, since it is on this date that the notice invoking Clause 12.3 was issued by the** C **respondent to the appellant. [Para 9][434-G-H; 435-A-C]** A **2. In** _**Hindustan Zinc Limited v. Ajmer Vidyut Vitran Nigam Limited**_ **and** _**NHAI v. Sayedabad Tea Company Limited,**_ **it was held that Section 86(1)(f) of the 2003 Act is a special provision which overrides the general provisions contained in Section 11 of the 1996 Act. Section 86(1)(f) vests a statutory jurisdiction with the State Electricity Commission to adjudicate upon disputes between licensees and generating companies and to refer any dispute for arbitration. The “and” between “generating companies” and “to refer any dispute for arbitration” is to be read as an “or”, since the State Electricity Commission cannot obviously resolve the dispute itself and also refer it to arbitration. Section 174 of the 2003 Act provides overriding effect to the 2003 Act notwithstanding anything inconsistent contained in any other law for the time being in force or in any instrument having effect by virtue of any law other than the 2003 Act itself. [Paras 10, 11 and 12][436-D-F; 437-A-B]** D E F **3. It was held in** _**Hindustan Zinc Limited v. Ajmer Vidyut Vitran Nigam Limited**_ **that if there is inherent lack of jurisdiction, the plea can be taken at any stage and also in collateral proceedings. A decree passed by a court without subject matter jurisdiction is a nullity, and that its invalidity could be set up whenever and wherever it is sought to be enforced or relied upon. Such a defect of jurisdiction cannot be cured even by the consent** G H 432 SUPREME COURT REPORTS [2021] 4 S.C.R. - A **of the parties. This dictum would apply to the present case. The order of the High Court appointing an arbitrator under Section 11(6) of the 1996 Act is unsustainable. [Paras 14 and 15][438-B-D]** _Hindustan Zinc Limited v. Ajmer Vidyut Vitran Nigam_ B _Limited_ **(2019) 17 SCC 82 : [2019] 15 SCR 113;** _NHAI v. Sayedabad Tea Company Limited_ **(2020) 15 SCC 161 : [2019] 11 SCR 725 – followed.** ## **Case Law Reference** ||**[2019]**|**15**|**SCR**|**113**|**followed**|**Para**|**10**| |---|---|---|---|---|---|---|---| |C|||||||| ||**[2019]**|**11**|**SCR**|**725**|**followed**|**Para**|**10**| CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1051 of 2021. - From the Judgment and Order dated 30.11.2016 of the High Court - D of Madhya Pradesh at Jabalpur in A.C. No. 1 of 2015. Varun K Chopra, Gurtejpal Singh, M/S. Vkc Law Offices, Advs. for the appellants. E Sanjay K. Agrawal, Sarthak Nema, Ms. Ankita Khare, J.K. Pillai, Advs. for the respondent. The Judgment of the Court was delivered by ## **DR. DHANANJAYA Y CHANDRACHUD, J.** 1. Leave granted. - F 2. This appeal arises from a judgment and order of a learned Single Judge of the High Court of Madhya Pradesh dated 30 November 2016 where it appointed an Arbitrator in the dispute between the parties, in an application[1] filed by the respondent under Section 11(6) of the Arbitration and Conciliation Act 1996[2] . 3. The genesis of the matter is from when the Madhya Pradesh G Electricity Board[3] , entered into a Power Purchase Agreement[4] on 20 May 1999 with the respondent. Under the PPA, the respondent was to - 1 “AC No 1 of 2015" 2 “1996 Act” > 3 “Board” H - 4 “PPA” 433 C. G. M. (IPC) MP POWER TRADING CO LTD v. NARMADA EQUIPMENTS PVT LTD [DR. DHANANJAYA Y CHANDRACHUD, J.] establish a mini hydro-electric project on a built and operate basis. However, the PPA was terminated on 27 September 2001 by the Board. The respondent initially filed a writ petition[5] challenging the termination of the PPA. The High Court, by its order dated 4 November 2009, declined to entertain the petition in view of an arbitration agreement contained in Clause 12.3[6] of the PPA. Thereafter, the respondent filed a review petition[7 ] which was dismissed by the High Court by an order dated 10 December 2009. 4. As a consequence of the orders dated 4 November 2009 and 10 December 2009, on 28 December 2009, the respondent issued a notice to the Board under Clause 12.1 of the PPA, seeking to resolve the dispute by mutual discussion. Since the respondent did not receive a reply to the notice dated 28 December 2009 from the Board, on 30 May 2011, the respondent issued another notice to the Board invoking arbitration under Clause 12.3 of the PPA. In the notice, the respondent stated that if the Board did not act upon the notice within 30 days of its receipt, it would approach the High Court under Section 11(6) of the 1996 Act. 5. Having received no reply from the Board, an application[8] was filed under Section 11(6) of the 1996 Act by the respondent seeking the appointment of an arbitrator. The High Court, by its order dated 21 January 2014, recorded that the respondent and the appellant had agreed to nominate their arbitrators, and observed that the two arbitrators would proceed to appoint a third arbitrator, in accordance with the procedure in Clause 12.3(a) of the PPA. The nominated Arbitrators fixed their first A B C D E 5 “WP No 2642 of 2002" > 6 “ _12.3 Arbitration:_ _(a) If dispute cannot be salted within Thirty (30)days mutual discussions as (sic) by section 12.1 and (sic) to Conciliation is not elected by the Parties pursuant to Section 12.2 of if a Parties so requests in accordance with Section 12.2 the Dispute shall in dally be settled by an Umpire to be appointed by two arbitrators one to be appointed by the Board and other by the Company Provisions of the Indian Arbitration and Conciliation Act 1996 9or any enactment that replaces the said Act) shall apply in such arbitrator. The arbitration proceedings shall be held at head Quarter of the Board i.e. at Jabalpur. (b) The award rendered shall apportion the costs of the arbitration._ F G _(c) The award rendered in any arbitration commended here under shall be final conclusive and binding upon the Parties and award may be entered in any Court havingjurisdiction as darned under article 15.1._ ” 7 “Review Petition No 716 of 2009” 8 “AC No 76 of 2011” H 434 SUPREME COURT REPORTS [2021] 4 S.C.R. - A meeting on 7 May 2014, when both parties appeared and the Arbitrators’ fee was fixed. However, the Arbitrators, by a letter dated 7 July 2014, highlighted their inability to proceed with the arbitration proceedings on the ground that their fees had not been paid. 6. Thereafter, the respondent filed AC No 1 of 2015 on 8 December B 2014, seeking the appointment of an arbitrator under Section 11(6) of the 1996 Act. This application was opposed by the appellant on the ground that, in view of the provisions of Section 86(1)(f) of the Electricity Act 2003[9] , it was the State Electricity Commission which was vested with the exclusive jurisdiction to adjudicate upon disputes between licensees and generating companies. By the impugned judgment and order dated C 30 November 2016, the Single Judge of the High Court allowed the application filed by the respondent under Section 11(6) of the 1996 Act. The Single Judge held that the remedies under Section 86(1)(f) of the 2003 Act and under Section 11(6) of the 1996 Act are independent of each other, and it was open to the High Court to exercise its jurisdiction D under Section 11(6). The appellant now comes before this Court in appeal. 7. The submission of the appellant, which has been urged before this Court by MrVarun Chopra, learned counsel, is that the view which has been taken by the High Court is contrary to the law which has been laid down by a two-Judge Bench of this Court in **Gujarat Urja Vikas** E **Nigam Limited** v **Essar Power Limited**[10] . 8. Controverting the submissions, Mr Sanjay K Agrawal, learned counsel appearing on behalf of the respondent, however, urged that the decision in **Gujarat UrjaVikas Nigam Limited** (supra) would not apply to the facts of the present case since the PPA was executed on 20 May F 1999 and the termination by the Board was on 27 September 2001; both of these events have taken place before the enforcement of the 2003 Act on 10 June 2003. It was further urged that the appellant did not raise its objection stemming from Section 86(1)(f) of the 2003 Act when the High Court appointed Arbitrators by the consent of both parties in its order dated 21 January 2014 in AC No 76 of 2011 and also before the G Arbitrators so appointed, and hence it cannot be raised at this stage. 9. In the present case, the notice for the initiation of arbitration under Clause 12.3 of the PPA was issued by the respondent on 30 May 9 “2003 Act” H > 10 (2008) 4 SCC 755, hereinafter referred to as “ **Gujarat UrjaVikas Nigam Limited** ” 435 C. G. M. (IPC) MP POWER TRADING CO LTD v. NARMADA EQUIPMENTS PVT LTD [DR. DHANANJAYA Y CHANDRACHUD, J.] 2011. The commencement of the arbitral proceedings by the invocation of the arbitration agreement would, therefore, relate to 30 May 2011, when the notice invoking Clause 12.3 was issued. Hence, the fact that the PPA and the notice of termination predate the 2003 Act would not constitute material circumstances.Section 21[11] of the 1996 Act specifies that unless otherwise agreed by the parties, the arbitral proceedings in respect of a particular dispute would commence on the date on which a request for that dispute to be referred to arbitration is received by the respondent. Hence, there can be no manner of doubt that 30 May 2011 would be the material date, since it is on this date that the notice invoking Clause 12.3 was issued by the respondent to the appellant. 10. The first issue which is raised in this appeal is governed by **Gujarat Urja Vikas Nigam Limited** (supra). In that case, the power purchase agreement between the parties was entered into on 30 May 1996, and the notice for referring the dispute to arbitration was sent by one of the parties on 14 November 2005. The other party opposed the notice by stating that the State Electricity Commission had exclusive jurisdiction in accordance with Section 86(1)(f) of the 2003 Act.The Gujarat High Court thereafter appointed an Arbitrator in an application under Section 11(6) of the 1996 Act, which was impugned before this Court. Speaking for the two-Judge bench, Justice Markandey Katju settled the position of law in paragraphs 26, 27 and 28 of the judgment, which are extracted below for convenience of reference: “26. It may be noted that Section 86(1)( _f_ ) of the Act of 2003 is a special provision for adjudication of disputes between the licensee and the generating companies. Such disputes can be adjudicated upon either by the State Commission or the person or persons to whom it is referred for arbitration. In our opinion the word “and” in Section 86(1)( _f_ ) between the words “generating companies” and “to refer any dispute for arbitration” means “or”. It is well settled that sometimes “and” can mean “or” and sometimes “or” can mean “and” (vide G.P. Singh’s _Principles of Statutory Interpretation_ , 9th Edn., 2004, p. 404). A B C D E F G 27. In our opinion in Section 86(1)( _f_ ) of the Electricity Act, 2003 > 11 “ _**21. Commencement of arbitral proceedings.** —Unless otherwise agreed by the parties, the arbitral proceedings in respect of a particular dispute commence on the date on which a request for that dispute to be referred to arbitration is received by the respondent._ ” H 436 SUPREME COURT REPORTS [2021] 4 S.C.R. - A the word “and” between the words “generating companies” and the words “refer any dispute” means “or”, otherwise it will lead to an anomalous situation because obviously the State Commission cannot both decide a dispute itself and also refer it to some arbitrator. Hence the word “and” in Section 86(1)( _f_ ) means “or”. - B 28. Section 86(1)( _f_ ) is a special provision and hence will override the general provision in Section 11 of the Arbitration and Conciliation Act, 1996 for arbitration of disputes between the licensee and generating companies. It is well settled that the special law overrides the general law. Hence, in our opinion, Section 11 of the Arbitration and Conciliation Act, 1996 has no application to - C the question who can adjudicate/arbitrate disputes between licensees and generating companies, and only Section 86(1)( _f_ ) shall apply in such a situation.” - This position has subsequently also been approved by two three- - Judge benches of this Court in **Hindustan Zinc Limited** v **Ajmer Vidyut** - D **Vitran Nigam Limited**[12 ] and **NHAI** v **Sayedabad Tea Company Limited**[13] . 11. From the above judgment, it is evident that this Court has held that Section 86(1)(f) of the 2003 Act is a special provision which overrides the general provisions contained in Section 11 of the 1996 Act. Section E 86(1)(f) vests a statutory jurisdiction with the State Electricity Commission to adjudicate upon disputes between licensees and generating companies and to refer any dispute for arbitration. The “and” between “generating companies” and “to refer any dispute for arbitration” is to be read as an “or”, since the State Electricity Commission cannot obviously resolve F the dispute itself and also refer it to arbitration. Section 86(1)(f) is extracted below: “ **86.Functions of State Commission.** —(1) The State Commission shall discharge the following functions, namely:- - *** *** *** G - (f) adjudicate upon the disputes between the licensees and generating companies and to refer any dispute for arbitration;” - 12 (2019) 17 SCC 82; hereinafter, referred to as “ **Hindustan Zinc Limited** “ - H 13 (2020) 15 SCC 161 437 C. G. M. (IPC) MP POWER TRADING CO LTD v. NARMADA EQUIPMENTS PVT LTD [DR. DHANANJAYA Y CHANDRACHUD, J.] 12. Section 174 of the 2003 Act provides overriding effect to the A 2003 Act notwithstanding anything inconsistent contained in any other law for the time being in force or in any instrument having effect by virtue of any law other than the 2003Act itself. Section 174 provides thus: “ **174. Act to have overriding effect.** — Save as otherwise provided in Section 173, the provisions of this Act shall have effect notwithstanding anything inconsistent therewith contained in any other law for the time being in force or in any instrument having effect by virtue of any law other than this Act.” 13. We refer now to the second argument raised on behalf of the respondent, that the appellant cannot raise an objection relying on Section 86(1)(f) of the 2003 Act in the second application filed by it under Section 11(6) of the 1996 Act, when it had not raised the same objection in the first application under Section 11(6) of the 1996 Act or before the Arbitrators so appointed. It is pertinent to note that this argument was rejected by the Single Judge of the High Court in the impugned judgment and order dated 30 November 2016 in the following terms” “9. I will be failing in my duty if the basic objection raised by Shri Manoj Dubey about maintainability of this application is not dealt with. Merely because in earlier round of litigation, the objection of maintainability was not taken, it will not preclude the other side to raise such objection if it goes to the root of the matter. This is trite law that jurisdiction cannot be assumed by consent of the parties. If a statute does not provide jurisdiction to entertain an application/ petition, the petition cannot be entertained for any reason whatsoever. Thus, I am not inclined to hold that since for the reason that in the earlier round of litigation i.e. A.C. No.76/2011 parties reached to a consensus for appointment of Arbitrators, this application is also maintainable. I deem it proper to examine whether because of operation of Section 174 of the Act of 2003, the present application under the Act of 1996 is not maintainable.” B C D E F G 14. A similar issue was raised before a three-Judge bench of this Court in **Hindustan Zinc Limited** (supra), where an arbitrator was appointed by the State Electricity Commission under Section 86(1)(f) of the 2003 Act with the consent of the parties. Subsequently, the arbitral H 438 SUPREME COURT REPORTS [2021] 4 S.C.R. - A award was challenged under Section 34 of the 1996 Act before a Commercial Court, and the Commercial Court’s decision was challenged in an appeal under Section 37 of the 1996 Act where it was held that the State Electricity Commission had no jurisdiction to appoint the arbitrator since Section 86(1)(f) refers to disputes only between licensees and generating companies, and not licensees and consumers. When the matter - B reached this Court, the contention was that the objection to jurisdiction could not have been raised in a proceeding under Section 37 of the 1996 Act once the parties had consented to arbitration earlier. Speaking for the Court, Justice Rohinton F Nariman held that if there is inherent lack of jurisdiction, the plea can be taken at any stage and also in collateral - C proceedings. He highlighted the well-established principle that a decree passed by a court without subject matter jurisdiction is a nullity, and that its invalidity could be set up whenever and wherever it is sought to be enforced or relied upon. Such a defect of jurisdiction cannot be cured even by the consent of the parties. The above dictum would apply to the present case. - D 15. In the above view of the matter, the order of the High Court appointing an arbitrator under Section 11(6) of the 1996 Act is unsustainable. We accordingly allow the appeal and set aside the impugned judgment and order of the High Court dated 30 November 2016 in AC No 1 of 2015. However, this will not come in the way of the E respondent in taking recourse to such remedies as are available in law. However, we have expressed no opinion either on the merits or the objections of the appellant which, when urged, would be considered by the appropriate forum. There shall be no order as to costs. F 16. Pending application, if any, stands disposed of. Devika Gujral Appeal allowed. G H
End of Judgment Record
Browse All Supreme Court of India (2021) Decisions
2021-01-05

HARI OM @ HERO v. STATE OF U.P.

This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.

2021-01-22

INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL

This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.

2021-11-29

Hasmat Ali v. Amina Bibi & ORS.

This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.

2021-02-15

Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.

This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.