Chhattisgarh State Power Distribution Company Ltd. v. Chhattisgarh State Electricity Regulatory Commission and Another

Case / Petition Number:
Civil Appeal Nos. 2578-2579 of 2008; Civil Appeal Nos. 2941-2942 of 2008; Civil Appeal No. 2868 of 2008
Neutral Citation:/

Case Synopsis & Summary

These appeals arise from an order of the Chhattisgarh State Electricity Regulatory Commission (CSEERC) dated 14 October 2005 and a subsequent decision by the Appellate Tribunal for Electricity (APTEL) dated 6 December 2007, which dismissed SBPIL’s appeals. SBPIL established a captive generation plant of 103.68 MU per annum. Its sister concern, SBMPL, holds 27.6% equity in SBPIL. SBPIL petitioned for open access and wheeling of power through SBPIL’s transmission system to SBMPL for captive use, proposing to wheel 13 MW (54 MU) to SBMPL and sell the balance to the appellant grid, with SBMPL’s and SBPIL’s aggregate consumption exceeding 51% of generation. The Commission held that SBPIL’s supply to SBMPL would qualify as “own consumption” under Section 9 read with Section 2(8) of the Electricity Act, 2003, and Rule 3 of the Electricity Rules, 2005, subject to conditions including that captive consumption not be less than 51% of annual generation and that wheeling charges apply to the open access. The APTEL affirmed this. The appellants argue that Rule 3 requires at least 26% ownership and 51% annual captive consumption, calculated on an aggregate basis, which SBMPL satisfies, and that the combined captive use justifies treatment as own consumption, exempting from license and surcharges. The respondents contend for strict adherence to statute and the liberal policy in National Electricity Policy, 2005. The Supreme Court upholds the Commission and APTEL, and dismisses the appeals, holding no merit in interference.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • L. Nageswara Rao
  • B. R. Gavai
Judgment Date
2022-05-12
Court Decision / Holding
Appeals dismissed; pending applications, if any, disposed of; no order as to costs.
Final Disposition
Appeals dismissed; pending applications disposed of; no costs.

Parties to the Case

Appellants / Petitioners

  • Chhattisgarh State Power Distribution Company Ltd.

Respondents

  • Chhattisgarh State Electricity Regulatory Commission
  • Another

Legal Representation & Advocates

Counsels for Petitioners

  • • Nikhil Nayyar

Counsels for Respondents

  • • Naveen R. Nath
  • • Swapna Seshadri

Provisions of Law Cited

Section 2(8) of the Electricity Act, 2003 (Captive Generating Plant)Clause (8) of Section 2 of the Electricity Act, 2003Clause (49) of Section 2 of the Electricity Act, 2003Section 9 of the Electricity Act, 2003 (Captive generation)Section 42 of the Electricity Act, 2003 (Duties of distribution licensee and open access)Provisos to Section 9(2)Provisos to Section 42(2)Rule 3 of the Electricity Rules, 2005 (Requirements of Captive Generating Plant)Rule 3(1)(a)(i)Rule 3(1)(a)(ii)Rule 3(1)(b)Section 30 of the Electricity Act, 2003Section 3 of the Electricity Act, 2003Electricity (Amendment) Act, 2003National Electricity Policy, 2005 (Clauses 5.2.24-5.2.26)

Legal Doctrines & Maxims

  • Interpretation of statutes should advance the object and purpose of the Act (teleological/purposive interpretation).
  • A liberal, purposive approach to captive generation is favored in policy (National Electricity Policy, 2005).

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant argues that Rule 3 of the Electricity Rules, 2005 requires at least 26% ownership by captive users and that at least 51% of the electricity generated must be consumed by captive users, measured on an annual basis. Since SBMPL holds 27.6% of SBPIL’s equity and combined captive consumption exceeds 51%, the arrangement qualifies as a captive generating plant for its own use, justifying open access and disallowing licensing or surcharge. It relies on Rule 3(1)(a)(ii), Rule 3(1)(b) and the relevant provisos, as well as the Maharashtra State judgment to support no license is required for own use.

Contentions of Respondents

The respondents contend that the scheme must comply strictly with the statutory text: 26% ownership and 51% annual captive consumption must be satisfied, and open access must follow the governance in Section 9 and Section 42. They emphasize the need to adhere to Rule 3, and rely on the National Electricity Policy, 2005 to support regulatory oversight rather than a broad interpretation that would circumvent licensing and surcharge regimes.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
Maharashtra State Electricity Distribution Company Limited v. JSW Steel Limited and Others(2022) 2 SCC 742PositiveCited to support the proposition that no permission is required from the Commission for supply of electricity for its own use.
Administrator, Municipal Corporation, Bilaspur v. Dattatraya Dahankar, Advocate and Another(1992) 1 SCC 361PositiveCited as authority for purposive interpretation of the Act to advance its object and purpose.
S. Gopal Reddy v. State of A.P.(1992) 1 SCC 361PositiveCited as part of the same interpretive approach to statutory provisions.
Ahmedabad Municipal Corporation v. Nilaybhai R. Thakore and Another(1999) 8 SCC 139PositiveCited as supportive authority for purposive interpretation and regulatory stance.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,667 words•~17 min read

In The Court Record

Chhattisgarh State Power Distribution Company Ltd. v. Chhattisgarh State Electricity Regulatory Commission and Another

## **REPORTABLE** ## **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** ## **­ CIVIL APPEAL NOS. 2578 2579 OF 2008** **CHHATTISGARH STATE POWER DISTRIBUTION COMPANY LTD. ...APPELLANT(S) VERSUS** **CHHATTISGARH STATE ELECTRICITY REGULATORY COMMISSION AND ANOTHER** **...RESPONDENT(S)** **WITH** **­ CIVIL APPEAL NOS. 2941 2942 OF 2008 CIVIL APPEAL NO. 2868 OF 2008** ## **J U D G M E N T** ## **B.R. GAVAI, J.** **1.** These appeals challenge the judgment dated 6[th] December 2007 passed by the Appellate Tribunal for Electricity (hereinafter referred to as the “APTEL”), thereby dismissing the appeals filed by the present appellant. **2.** The facts in brief giving rise to the present appeals are as under: 1 M/s Shri Bajrang Power and Ispat Ltd. (hereinafter referred to as “SBPIL”) has established a Captive Generation Plant. M/s Shri Bajrang Metallics and Power Ltd. (hereinafter referred to as “SBMPL”) is a sister concern of SBPIL. SBPIL submitted a petition to the Chhattisgarh State Electricity Regulatory Commission (hereinafter referred to as “the Commission”) for providing open access and wheeling of power through the transmission system of the appellant for captive use by SBMPL. The petition of the SBPIL was for permission to wheel 19 lakh units, corresponding to 13 MW, to SBMPL. It was stated in the said petition that SBMPL holds 27.6% of the equity shares of SBPIL and that more than 51% of the electricity generated by the captive power plant would be consumed by them. It was submitted that the generating capacity of the captive generation plant set up by SBPIL would be 103.68 MU per annum. It was further submitted that out of the said 103.68 MU per annum power generated, 13.22 MU per annum would be utilized in its sponge iron plant. It was further submitted that 54 MU per annum would be supplied to SBMPL through the appellant grid and the balance would be sold to the appellant. 2 **3.** The said petition came to be resisted by the appellant. It was contended by the appellant that SBPIL holds more than 72% of the shares of the company. However, its consumption would be limited only to 14.16% (13.22 MU), whereas the consumption of SBMPL holding 26.67% shares, would be 57.87% (54 MU). It was submitted that this was not proportionate to the ownership of the power plant. **4.** The Commission, vide its order dated 14[th] October 2005, rejected the contention of the appellant and held that SBPIL was entitled to supply electricity to its sister concern SBMPL and the same would qualify to be treated as ‘own consumption’ within the ambit of Section 9 read with Section 2(8) of the Electricity Act, 2003 (hereinafter referred to as “the said Act”) and Rule 3 of the Electricity Rules, 2005 (hereinafter referred to as “the said Rules”). While allowing the said petition, the Commission imposed the following conditions: - (i) “The consumption of electricity by the captive users shall not be less than 51% over a financial year, and in case it is not so it would be treated as of a ‘supply electricity by 3 generating company’ in terms of provision of rule 3(2) of the Rules. - (ii) The CSEB is entitled to charge for wheeling of electricity and levy other charges as per their present rates which shall be subject to revision as per the provisions in regulations on the charges for open access to be notified by the Commission shortly. - (iii) The company may enter into necessary agreement with the CSEB for the sale of balance power under the present terms and conditions of the CSEB, is subject to revision as per the directions of the Commission from time to time.” **5.** Being aggrieved thereby, the appellant preferred appeals before the APTEL. The said appeals came to be dismissed by the APTEL vide impugned judgment dated 6[th] December 2007. Being aggrieved thereby, the present appeals. **6.** We have heard Shri Nikhil Nayyar, learned Senior Counsel appearing on behalf of the appellant and Shri Naveen R. Nath, learned Senior Counsel and Smt. Swapna Seshadari, learned counsel appearing on behalf of the respondents. **7.** Shri Nayyar submitted that the order passed by the Commission and the impugned judgment passed by the 4 APTEL are contrary to the plain language used in Rule 3 of the said Rules. He submitted that SBMPL is a sister concern of SBPIL which has established the captive power plant. It is submitted that unless SBPIL consumes 51% of the aggregate electricity generated by it, it will not be entitled to get the benefit under Section 9 of the said Act. He submitted that in sub­rule (1) of Rule 3 of the said Rules, the words used are “Captive Generating Plant”. He submitted that upon a plain and literal interpretation of Rule 3 of the said Rules, it will be abundantly clear that unless the sister concern establishes captive generating plant utilization of 51% of the electricity generated, it will not be entitled to get benefit under Section 9 of the said Act. **8.** Shri Nath submitted that the Commission, as well as the APTEL, has rightly construed the provisions of the said Act and the said Rules. He submitted, that this Court, in the case of _**Maharashtra State Electricity Distribution Company Limited v. JSW Steel Limited and Others[1]**_ , has held that no permission is required from the Commission for supply of electricity for its own use. He further submitted 1 **(2022) 2 SCC 742** 5 that this Court has also held that insofar as captive users are concerned, they are not liable to pay the additional surcharge under Section 42(4) of the said Act. **9.** Smt. Seshadari, learned counsel appearing on behalf of the Commission submitted that if the arguments advanced on behalf of the appellant are accepted, the same would be contrary to the provisions of the said Act. She, therefore, submitted that the order passed by the Commission and the impugned judgment passed by the APTEL warrant no interference. **10.** For appreciating the rival contentions, it will be apposite to refer to Clauses (8) and (49) of Section 2 as well as Section 9 and sub­sections (1) and (2) of Section 42 of the said Act, which read thus: ## “ **2. Definitions.­** ………. (8) “Captive generating plant” means a power plant set up by any person to generate electricity primarily for his own use and includes a power set or plant up by any cooperative society association of persons for generating electricity primarily for use of members of such cooperative society or association; ………… 6 (49) “person” shall include any company or body corporate or association or body of individuals, whether incorporated or not, or artificial juridical person; **9. Captive generation.** —(1) Notwithstanding anything contained in this Act, a person may construct, maintain or operate a captive generating plant and dedicated transmission lines: Provided that the supply of electricity from the captive generating plant through the grid shall be regulated in the same manner as the generating station of a generating company: Provided further that no licence shall be required under this Act for supply of electricity generated from a captive generating plan to any licensee in accordance with the provisions of this Act and the rules and regulations made thereunder and to any consumer subject to the regulations made under sub­section (2) of Section 42. (2) Every person, who has constructed a captive generating plant and maintains and operates such plant, shall have the right to open access for the purposes of carrying electricity from his captive generating plant to the destination of his use: Provided that such open access shall be subject to availability of adequate transmission facility and such availability of transmission facility shall be determined by the Central Transmission Utility or the State Transmission Utility, as the case may be: Provided further that any dispute regarding the availability of transmission facility shall be adjudicated upon by the Appropriate Commission. **42. Duties of distribution licensee and open access** . —(1) It shall be the duty of a distribution licensee to develop and maintain an efficient, co­ ordinated and economical distribution system in his area of supply and to supply electricity in 7 accordance with the provisions contained in this Act. (2) The State Commission shall introduce open access in such phases and subject to such conditions, (including the cross subsidies, and other operational constraints) as may be specified within one year of the appointed date by it and in specifying the extent of open access in successive phases and in determining the charges for wheeling, it shall have due regard to all relevant factors including such cross­subsidies, and other operational constraints: Provided that such open access shall be allowed on payment of a surcharge in addition to the charges for wheeling as may be determined by the State Commission: Provided further that such surcharge shall be utilised to meet the requirements of current level of cross­subsidy within the area of supply of the distribution licensee: Provided also that such surcharge and cross­ subsidies shall be progressively reduced in the manner as may be specified by the State Commission: Provided also that such surcharge shall not be leviable in case open access is provided to a person who has established a captive generating plant for carrying the electricity to the destination of his own use: Provided also that the State Commission shall, not later than five from the date of years commencement of the Electricity (Amendment) Act, 2003, by regulations, provide such open access to all consumers who require a supply of electricity where the maximum power to be made available at any time exceeds one megawatt. ……….” 8 **11.** It could thus be seen that in view of Section 9 of the said Act, any person may construct, maintain or operate a captive generating plant and dedicated transmission lines. The first proviso to Section 9 of the said Act provides that the supply of electricity from the captive generating plant through the grid shall be regulated in the same manner as the generating station of the generating company. The second proviso to Section 9 of the said Act provides that no licence shall be required under the said Act for supply of electricity generated from a captive generating plant to any licensee in accordance with the provisions of the said Act and the rules and regulations made thereunder and to any consumer, subject to the regulations made under sub­ section (2) of Section 42 of the said Act. Sub­section (2) of Section 9 of the said Act provides that every person, who has constructed a captive generating plant and maintains and operates such plant, shall have the right to open access for the of from his purposes carrying electricity captive generating plant to the destination of his use. The first proviso to sub­section (2) of Section 9 of the said Act provides that such open access shall be subject to availability of 9 adequate transmission facility and such availability of transmission facility shall be determined by the Central Transmission Utility or the State Transmission Utility, as the case may be. The second proviso to sub­section (2) of Section 9 of the said Act provides that if there is any dispute regarding the availability of transmission facility, it shall be adjudicated upon by the Appropriate Commission. **12.** Clause (8) of Section 2 of the said Act defines “Captive generating plant”. It states that “Captive generating plant” means a power plant set up by any person to generate electricity primarily for his own use and includes a power plant set up by any co­operative society or association of for for use of persons generating electricity primarily members of such co­operative society or association. **13.** Clause (49) of Section 2 of the said Act defines “person”. It states that “person” shall include any company or body corporate or association or body of individuals, whether incorporated or not, or artificial juridical person. **14.** A combined reading of Section 9 and Clause (8) of Section 2 of the said Act would reveal that a person is entitled to construct, maintain or operate a captive 10 generating plant. Such a plant should be primarily for his own use. Clause (8) of Section 2 of the said Act would further show that it includes a power plant set up by any co­ operative society or association of persons for generating electricity. The requirement is that it should be primarily for the use of the members of such co­operative society or association. **15.** The definition of “person” is wide enough to include any company or body corporate or association or body of individuals, whether incorporated or not, or artificial juridical person. **16.** It is thus clear that a person, to get benefit under Section 9 of the said Act, could be an individual or a body corporate or association or body of individuals, whether incorporated or not. It could thus be seen that even an association of corporate bodies can establish a captive power plant. The only requirement would be that the said plant must be established primarily for their own use. The fourth proviso to sub­section (2) of Section 42 of the said Act would also reveal that surcharge would not be leviable in case open access is provided to a person who has established a captive 11 generating plant for carrying the electricity to the destination of his own use. **17.** Therefore, the question that would arise is as to whether the open access for transmitting electricity from SBPIL to SBMPL would be for own use or not. **18.** We find that Rule 3 of the said Rules would clarify the position, which reads thus: “ .— **3. Requirements of Captive Generating Plant** (1) No power plant shall qualify as a ‘captive generating plant’ under Section 9 read with clause (8) of Section 2 of the Act unless— ( _a_ ) in case of a power plant— ( _i_ ) not less than twenty­six per cent of the ownership is held by the captive user(s), and ( _ii_ ) not less than fifty­one per cent of the aggregate electricity generated in such plant, determined on an annual basis, is consumed for the captive use: Provided that in case of power plant set up by registered cooperative society, the conditions mentioned under paragraphs at ( _i_ ) and ( _ii_ ) above shall be satisfied collectively by the members of the co­operative society: Provided further that in case of association of persons, the captive user(s) shall hold not less than twenty­six per cent of the ownership of the plant in aggregate and such captive user(s) shall consume not less than fifty­one per cent of the electricity generated, determined on an annual basis, in proportion to their shares in 12 of the within a ownership power plant variation not exceeding ten per cent; ( _b_ ) in case of a generating station owned by a company formed as special purpose vehicle for such generating station, a unit or units of such generating station identified for captive use and not the entire generating station satisfy(ies) the conditions contained in paragraphs ( _i_ ) and ( _ii_ ) of sub­clause ( _a_ ) above including— _Explanation_ .—(1) The electricity required to be consumed by captive users shall be determined with reference to such generating unit or units in aggregate identified for captive use and not with reference to generating station as a whole; and (2) The equity shares to be held by the captive user(s) in the generating station shall not be less than twenty­six per cent of the proportionate of the equity of the company related to the generating unit or units identified as the captive generating plant.” **19.** The provisions made in Rule 3 of the said Rules are clear. Sub­rule (1) of Rule 3 of the said Rules provides that no power plant shall qualify as a “Captive Generating Plant” under Section 9 read with Clause (8) of Section 2 of the said Act unless the conditions stated therein are fulfilled. The first requirement is that not less than 26% of the ownership is held by the captive user(s). The second requirement is that not less than 51% of the aggregate electricity generated in such plant, determined on an annual basis, is consumed 13 for the captive use. The second proviso to Rule 3(1)(a)(ii) of the said Rules provides that in case of association of persons, the captive user(s) shall hold not less than 26% of the ownership of the plant in aggregate and such captive user(s) shall consume not less than 51% of the electricity generated, determined on an annual basis, in proportion to their shares in ownership of the power plant within a variation not exceeding 10%. **20.** Admittedly, SBMPL holds 27.6% equity shares in SBPIL. As such, the requirement of not less than 26% of shares is fulfilled by SBMPL. As already discussed hereinabove, even an association of corporate bodies can establish a power plant. Since SBMPL holds 27.6% of the ownership, the use of electricity by it would be for captive use under the provisions of the said Act. The other requirement would be that the consumption of SBIPL and SBMPL together should not be less than 51% of the power generated. Admittedly, the joint consumption by SBIPL and SBMPL is more than 51%. As such, both the conditions as provided under Rule 3 of the said Rules are satisfied. 14 **21.** We find that it will also be appropriate to refer to the National Electricity Policy, 2005 (hereinafter referred to as “the said Policy”) as notified by the Government of India, in exercise of its powers under Section 3 of the said Act, on 12[th] February 2005. Clauses 5.2.24 to 5.2.26 deal with the “Captive Generation”, which read thus: ## “ **Captive Generation** 5.2.24 **The liberal provision in the Electricity Act, 2003 with respect to setting up of captive power plant has been made with a view to not only securing reliable, quality and cost­effective power but also to facilitate creation of employment opportunities through speedy and efficient growth of industry.** 5.2.25 **The provision relating to captive power plants to be set up by group of consumers is primarily aimed at enabling small and medium industries or other consumers that may not individually be in a position to set up plant of optimal size in a cost­effective manner. It needs to be noted that efficient expansion of small and medium industries across the country would lead to creation of enormous employment opportunities.** 5.2.26 **A large number of captive and standby generating stations in India have surplus capacity that could be supplied to the grid continuously or during certain time periods.** 15 **These plants offer a sizeable and potentially competitive capacity that could be harnessed for meeting demand for power. Under the Act, captive generators have access to licensees and would get access to consumers who are allowed open access. Grind inter­connections for captive generators shall be facilitated as per Section 30 of the Act.** This should be done on priority basis to enable captive generation to become available as distributed generation along the grid. Towards this end, non­conventional energy sources including co­ generation could also play a role. Appropriate commercial arrangements would need to be instituted between licensees and the captive generators for harnessing of spare capacity energy from captive power plants. The appropriate Regulatory Commission shall exercise regulatory oversight on such commercial arrangements between captive generators and licensees and determine tariffs when a licensee is the off­taker of power from captive plant.” [emphasis supplied] **22.** It could thus be seen that the provision with respect to establishing captive power plant has been made with a view to not only securing reliable, quality and cost­effective but also to facilitate creation of power employment opportunities through speedy and efficient growth of industry. The said Policy further states that the provision relating to captive power plants to be set up by a group of consumers has been made primarily for enabling small and medium industries or other consumers that may not 16 individually be in a position to set up plant of optimal size, in a cost­effective manner. It also states that the efficient expansion of small and medium industries across the country would lead to creation of enormous employment opportunities. Clause 5.2.26 of the said Policy further states that the captive and standby generating stations in India have surplus capacity that could be supplied to the grid continuously or during certain time periods. **23.** The said Policy is issued under Section 3 of the said Act and as such, has a statutory flavour. In any case, the said Policy is in tune with the provisions as contained in Section 9 and Clause (8) of Section 2 of the said Act. A liberal provision has been made in Section 9 of the said Act so as to promote establishment of captive power plants. **24.** It is a settled position of law that the interpretation which advances the object and purpose of the Act, has to be preferred. A reliance in this respect can be placed on the judgments of this Court in the cases of _**Administrator,**_ _**Municipal Corporation, Bilaspur v. Dattatraya Dahankar, Advocate and Another[2]**_ , _**S. Gopal Reddy v.**_ 2 **(1992) 1 SCC 361** 17 _**State of A.P.[3]**_ and _**Ahmedabad Municipal Corporation and Another v. Nilaybhai R. Thakore and Another[4]**_ . **25.** We are, therefore, of the considered view that no case is made out for interfering with the order dated 14[th] October 2005 passed by the Commission and the impugned judgment dated 6[th] December 2007 passed by the APTEL. **26.** In the result, the present appeals are found without merit and as such, are dismissed. **27.** Pending application(s), if any, shall stand disposed of in the above terms. No order as to costs. **……..….......................J. [L. NAGESWARA RAO]** **…….........................J. [B.R. GAVAI]** **NEW DELHI; MAY 12, 2022.** > 3 **(1996) 4 SCC 596** > 4 **(1999) 8 SCC 139** 18
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.