Chennai Metropolitan Development Authority v Prestige Estates Project Ltd.

Case / Petition Number:
Civil Appeal Nos. 5642-5643 of 2019
Neutral Citation:/

Case Synopsis & Summary

These appeals arise from a Madras High Court judgment that upheld a writ petition challenging the Chennai Metropolitan Development Authority’s demand for development charges, infrastructure and amenities charges (I&A), and Premium FSI charges in a proposed multi-storey development at Ayyappan Thangal Village, Tamil Nadu. The CMDA, acting under the Tamil Nadu Town & Country Planning Act 1971, soughtDevelopment Charges under Section 59 and I&A charges under Section 63B, and Premium FSI under Regulation 36 of the Master Plan. In 2012, the government issued GO Ms No. 86, revising I&A charges by 50% and, subject to amendments to the Tamil Nadu Town and Country Planning Rules 2008, establishing higher rates. The Department’s conditions included road widening, NOC from water/sewerage boards, and compliance with development regulations. The applicant developer remitted charges in March 2012; however, the he High Court quashed the demand for revised rates, holding no amendment had been made to the Rules 2008, and that Premium FSI demands could not be enforced from August 2012. The Supreme Court, by a Division Bench, partially allowed the appeals: it held that Premium FSI charges could be enforced at revised rates since planning permission was granted after the revision, but the I&A charges could not be collected at revised rates absent an amendment to the Rules. The Court reaffirmed the principle that a vested right in planning permission does not arise merely from filing an application or making deposits. The appeals are disposed of with no costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Dr Dhananjaya Y. Chandrachud
  • Indira Banerjee
Judgment Date
2019-07-29
Court Decision / Holding
The appeals are disposed of. The Supreme Court partially allows the appeals: Premium FSI charges are enforceable at the revised rates (as planning permission was to be granted after revision), while I&A charges cannot be enforced at revised rates in the absence of an amendment to the Rules 2008. The High Court’s quashing of the I&A charges is left intact, and the matter is remitted to determine appropriate charges consistent with the statutory framework. There shall be no order as to costs.
Final Disposition
Appeals disposed of; partly allowed. Premium FSI charges at revised rates; I&A charges limited by rules requiring amendments; no costs.

Parties to the Case

Appellants / Petitioners

  • Chennai Metropolitan Development Authority

Respondents

  • Prestige Estates Project Ltd.

Legal Representation & Advocates

Counsels for Petitioners

  • • Mr K M Nataraj, Additional Solicitor General of India

Counsels for Respondents

  • • Mr Rana Mukherjee, Senior Counsel

Provisions of Law Cited

Tamil Nadu Town and Country Planning Act, 1971 – Section 49Tamil Nadu Town and Country Planning Act, 1971 – Section 63BTamil Nadu Town and Country Planning (Levy of Infrastructure and Amenities Charges) Rules, 2008 – Rule 4Tamil Nadu Town and Country Planning (Levy of Infrastructure and Amenities Charges) Rules, 2008 – Rule 5(2)Regulation 36 of the Second Master Plan for Chennai Metropolitan Area 2006 (Regulation)Section 48 of the Tamil Nadu Town and Country Planning Act, 1971

Legal Doctrines & Maxims

  • No one has a vested right to the grant or renewal of a lease; apply the rules in force on the date of disposal (as reiterated in Hind Stone).
  • No vested right to planning permission; sanctioning authority may impose conditions precedent and require compliance with development regulations.
  • Subordinate legislation must be in conformity with parent legislation; amendments and updates to rules require formal action.

Submissions & Arguments

Contentions of Appellants / Petitioners

The Planning Authority (CMDA) argued that charges are payable at rates applicable when planning permission is granted, not merely on filing or on pre-existing deposits. It contended that a vested right to planning permission does not arise until approval is granted, and that revised I&A rates, enacted via GO Ms No. 86 and related office orders, are applicable for demands issued after 28 March 2012. Since the Rules 2008 required amendment to implement new rates, pre-revision charges should apply where no amendment existed. The Planning Authority further maintained that Premium FSI charges are payable only upon grant of Premium FSI and that revision has to be considered in the context of the date of permission.

Contentions of Respondents

The developer contended that revised I&A rates and Premium FSI rates should apply to demands issued after 28 March 2012, and that the demand notice dated 22 August 2012 was based on revised charges post-March 2012. They argued that the admissible rates be determined by the date of payment or the date of grant of permission, citing Union of India v Mahajan Industries Ltd. They asserted that the balance of pre-revision rates should apply to earlier applications and that a formal amendment to the Rules was not strictly necessary for the revised charges to be applicable in certain circumstances.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
Union of India v Mahajan Industries Ltd.(2005) 10 SCC 203DistinguishedHeld in the context of conversion charges; the Court distinguished it as not controlling the date or basis for development charges at issue.
State of Tamil Nadu v Hind Stone(1981) 2 SCC 205PositiveCited as precedent for the principle that there is no vested right to a grant/renewal of a lease; rules in force on disposal apply.
Howrah Municipal Corporation v Ganges Rope Co. Ltd.(2004) 1 SCC 663PositiveCited for regulatory sanction principles and absence of vested rights in sanctioning process.
Usman Gani J. Khatri of Bombay v Cantonment Board(1992) 3 SCC 455PositivePrevailing rules at the time of sanction govern; no vested right to a particular sanction.
Commissioner of Municipal Corporation, Shimla v Prem Lata Sood(2007) 11 SCC 40PositiveReiterates that sanction is subject to conditions precedent and that rights accrue only after compliance.
New Delhi Municipal Council v Tanvi Trading and Credit Private Limited(2008) 8 SCC 765PositiveDates of approval and LBZ guidelines apply to building sanctions; governance of planning permissions.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•6,910 words•~32 min read

In The Court Record

Chennai Metropolitan Development Authority v Prestige Estates Project Ltd.

**REPORTABLE** ## **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** **Civil Appeal Nos. 5642-5643 of 2019 (@SLP (C) Nos. 31274-31275 of 2014)** **Chennai Metropolitan Development Authority …Appellants Rep. by its Member- Secretary & Anr** **Versus** **Prestige Estates Project Ltd. …Respondent** ## **J U D G M E N T** ## **Dr Dhananjaya Y Chandrachud, J** 1 These appeals arise from a judgment of a Division Bench of the High Court of Judicature at Madras in a Writ Appeal, affirming the judgment of a learned Single Judge in proceedings under Article 226 of the Constitution. The High Court set aside a demand raised by the appellant for revised charges on account of (i) Signature Not Verified Digitally signed byMANISH SETHIInfrastructure and Amenities[1] ; and (ii) Premium Floor Space Index[2] . Date: 2019.07.29 16:02:27 IST Reason: > 1 I & A 1 2 The respondent submitted an application on 22 March 2011 for planning permission to construct a multi-storeyed building complex at Ayyappan Thangal Village, Thiruperumbudur Taluk. The Housing and Urban Development Department of the Government of Tamil Nadu, to which the application was forwarded for approval in terms of the Development Regulations[3] , accorded its approval to the recommendation of the Multi-storeyed Building Panel. - 3 On 5 January 2012, the State government in a letter to the appellant approved the recommendation, subject to the following conditions: - “(i) Chennai Metropolitan Development Authority should ensure that the applicant gifts the road widening portions marked in the plan to the Chennai Metropolitan Development Authority along with OSR spaces before issue of Planning Permission. - (ii) The applicant shall furnish ‘No Objection Certificate’ from Chennai Metropolitan Water Supply and Sewerage Board for using their land in S. Nos. 51/1B2 and 1C2 for access before issue of Development Charges advice. - (iii) Subject to other usual condition.” The letter stated that before the issuance of planning permission, an undertaking should be obtained from the respondent to fulfill - (i) The provisions contained in the DR; and - (ii) The conditions imposed by the Director of Fire and Rescue Service and other Departments. > 2 Premium FSI > 3 DR 2 The appellant, as the planning authority, was requested to take up further action for issuance of a planning permission. 4 The appellant, which is a planning authority under the provisions of the Tamil Nadu Town & Country Planning Act 1971[4] , was required to consider the application for the grant of planning permission under Section 49. The Chennai Metropolitan Water Supply and Sewerage Board[5] addressed a letter on 6 February 2012 to the respondent stating that it would consider the issuance of its No Objection Certificate[6] subject to the acceptance of the following conditions: “1. RCC Compound wall shall be constructed on the boundaries of the proposed land adjacent to CMWSSB land with gate provisions of 6m. span at both ends as accesses to reach the other side of the proposed multistoried residential buildings as accepted in your Lr. dt. 28.01.2012. 2. The design and estimate for proposed R.C.C culvert of suitable length and width should be submitted for approval of CMWSSB, before construction of culvert. 3.The proposed R.C.C culverts with clearance of 1.5mtr all-round the pipeline should be constructed at both crossings to reach the property under the supervision of CMWSS Board. 4. Supervision charge @ 21% of the estimated construction cost should be deposited to CMWSSB before construction of culvert. 5. The existing pipeline should not be damaged at any point of time and if any damage is caused at the time of construction of culverts/compound wall, the entire repair cost should be borne by you. 6. If any leak or burst occurs in the pipeline in future within the culvert portion, the culvert will be demolished by the Board for attending leak/burst in future and the same has to be reconstructed at your risk and cost. > 4 The Planning Act 1971 5 The Sewerage Board 6 NOC 3 7. You should not have any rights, whatsoever to claim the ownership of the above board’s land. 8. The Board reserves the right to enter upon the premises for any inspection and to cancel the “No Objection Certificate” at any point of time without assigning any reason in the interest of public.” 5 On 2 March 2012, the respondent addressed a communication to the appellant, stating that it had accepted the conditions imposed by Sewerage Board by its letter dated 18 February 2012 and that a formal NOC was expected shortly. The appellant was requested to process the planning permission and to issue a notice of demand for development charges in order to enable the respondent to arrange for the funds required. The respondent, in its above letter dated 2 March 2012 stated : “Now we expect the formal NOC from CMWSSB very shortly. In view of the above progress on the NOC, we request that the processing of Planning Permit and the notice for development charges may kindly be issued to assess the fees amount involved and also to make arrangement for the funds required. We further assure you that before the payment of fees is effected by us the formal NOC from CMWSSB will be submitted.” 6 On 7 March 2012, the appellant requested the Sub-Registrar, Chennai South to furnish the guideline value of urban land for the survey numbers where development was proposed by the respondent for assessing the Premium FSI charges in relation to the development proposal. This was furnished by the SubRegistrar on 7 March 2012. 4 7 On 27 March 2012, the appellant issued a demand notice requiring the respondent to deposit the following charges in order to facilitate the processing of its application: ||“||**Rs. 63,10,000/-**<br>(Rupees sixty three Lakh and ten<br>Thousand Only)<br>**Rs.**<br>**50,000/-**<br>(Rupees<br>fifty<br>Thousand only)<br>**Rs. 25,10,000/-**(Rupees twenty<br>five lakh and ten thousand only)<br>**Rs. 4,64,15,000/-**(Rupees four<br>crore sixty four lakh and fifteen<br>thousand Only)<br>**Rs.**<br>**10,000/-**<br>(Rupees<br>Ten<br>Thousand Only)<br>**Rs. 27,15,000/-**(Rupees twenty<br>seven lakh and fifteen Thousand<br>Only)<br>**Rs. 8,34,40,000/-**(Rupees eight<br>crore thirty four lakh and forty<br>Thousand Only)<br>**Rs. 44,75,88,000/-**(Rupees Forty<br>four crore and seventy five lakh<br>eightythousand only)<br>.”| |---|---|---|---| ||i)|Development<br>charge for land and<br>building under Sec.<br>59 of the T&CP<br>Act,1971|**Rs. 63,10,000/-**<br>(Rupees sixty three Lakh and ten<br>Thousand Only)| ||ii)|Balance<br>Scrutiny<br>Fee|**Rs.**<br>**50,000/-**<br>(Rupees<br>fifty<br>Thousand only)| ||iii)|Regularisation<br>charge<br>for<br>unauthorized<br>sub<br>division<br>&<br>amalgamation|**Rs. 25,10,000/-**(Rupees twenty<br>five lakh and ten thousand only)| ||iv)|Security<br>Deposit<br>(For Building)|**Rs. 4,64,15,000/-**(Rupees four<br>crore sixty four lakh and fifteen<br>thousand Only)| ||v)|Security Deposit for<br>DisplayBoard|**Rs.**<br>**10,000/-**<br>(Rupees<br>Ten<br>Thousand Only)| ||vi)|Security Deposit for<br>STP|**Rs. 27,15,000/-**(Rupees twenty<br>seven lakh and fifteen Thousand<br>Only)| ||vii)|Infrastructure<br>&<br>Amenities Charges|**Rs. 8,34,40,000/-**(Rupees eight<br>crore thirty four lakh and forty<br>Thousand Only)| ||viii)|Premium<br>FSI<br>charge<br>for<br>78690.55 sq.m.|**Rs. 44,75,88,000/-**(Rupees Forty<br>four crore and seventy five lakh<br>eightythousand only)| ||||| The appellant also required the respondent to comply with the following ## requisitions : - “a. Furnish the letter of your acceptance for the following conditions stipulated by virtue of provisions available under DR 4(i) d of Annexure III:- 5 - (i) The construction shall be undertaken as per sanctioned plan only and no deviation from the plans should be made without prior sanction. Construction done in deviation is liable to be demolished. - (ii) In cases of Multi-storied Building both qualified Architect and qualified structural Engineer who should be a Class-I Licensed Surveyor shall be associated and the above information to be furnished. - (iii) A report in writing shall be sent to Chennai Metropolitan Development Authority by the Architect/Class-I Licensed Surveyor who supervises the construction just before the commencement of the erection of the building as per the sanctioned plan, similar report shall be sent to CMDA when the building has reached up to plinth level and thereafter every three months at various stages of the construction/development certifying that the work so far completed is in accordance with the approved plan. The Licensed Surveyor and Architect shall inform this Authority immediately if the contract between him/them and the owner/developer, has been cancelled or the construction is carried out in deviation to the approved plan. - (iv) The owner shall inform Chennai Metropolitan Development Authority of any change of the Licensed Surveyor/Architect. The newly appointed Licensed Surveyor/Architect shall also confirm to CDMA that he has agreed for supervising the work under reference and intimate the stage of construction at which he has taken over. No construction shall be carried on during the period intervening between exit of the previous Architect/Licensed Surveyor and entry of the new appointee. - (v) On completion of the construction the applicant shall intimate CDMA and shall not occupy the building or permit it to be occupied until a completion certificate is obtained from CMDA. - (vi) While the applicant makes application for service connection such as Electricity, Water Supply, Sewerage he should enclose a copy of the completion certificate issued by CMDA along with his application to the concerned Department/Board/Agency. - (vii) When the site under reference is transferred by way of sale/lease or any other means to any person before completion of the construction, the party shall inform CMDA of such transaction and also the name and address of the persons to whom the site is transferred immediately after such transaction and shall bind the purchaser to those conditions to the Planning Permission. 6 - (viii) In the Open space within the site, trees should be planted and the existing trees preserved to the extent possible; - (ix) If there is any false statement, suppression or any misrepresentation of acts in the applicant, planning permission will be liable for cancellation and the development made, if any will be treated as authorized. - (x) The new building should have mosquito proof overhead tanks and wells. - (xi) The sanction will be revoked, if the conditions mentioned above are not complied with. - (xii) Rainwater conservation measures notified by CMDA should be adhered to strictly. - (a) . Undertaking (in the format prescribed in Annexure –XIV to DCR, a copy of it enclosed in Rs. 20/- stamp paper duly executed by all the land owner, GPA holders, builders and promoters separately. The undertakings shall be duly attested by a Notary Public. - (b) Details of the proposed development duly filled in the format enclosed for display at the site. Display of the information at site is compulsory in cases of Multi-storied buildings, Special buildings and Group developments” The letter further stipulated that : “7. **The issue of planning permission depends on the compliance/fulfilment of the conditions/payments stated above. The acceptance by the Authority of the pre-payment of the Development charge and other charges etc. shall not entitle the person to the Planning Permission but only refund of the Development Charge and other charges (excluding Scrutiny Fee) in cases of refusal of the permission for non-compliance of the conditions stated above or any of the provisions of DR, which has to be complied before getting the Planning permission or any other reason provided the construction is not commenced and claim for refund is made by the applicant** .” **(Emphasis supplied)** 7 8 On 28 March 2012, the respondent paid the charges which were demanded by the appellant on 27 March 2012. In the meantime, on 26 March 2012, the Government revised the guideline values with effect from 1 April 2012. One of the conditions subject to which the State government had granted its approval to the respondent was the obtaining of an NOC from the Sewerage Board. On 28 March, 2012, G.O.Ms No. 86 was issued by the Housing and Urban Development Department whereby the I & A charges for different categories and buildings falling under the jurisdiction of the appellant and of the Commissioner of Town and Country Planning were to stand increased by 50 per cent over the then prevailing rates. The Sewerage Board issued its NOC on 30 March 2012, subject to the condition that the respondent execute a gift deed in respect of a piece of land. This requirement was complied with on 27 April 2012. When the file pertaining to the grant of planning permission to the respondent was under consideration, guideline values were revised by the State government with effect from 1 April 2012. A demand notice was issued on 22 August 2012 by the appellant by which the demand was revised for charges under two heads: “ |i)|Balance<br>I<br>&<br>A<br>Charges|**Rs.**<br>**4,17,15,000/-**<br>(Rupees Four Crore<br>Seventeen Lakh and<br>Fifteen<br>thousand<br>Only)| |---|---|---| |ii)|Balance<br>Premium<br>FSI Charge|**Rs.**<br>**90,76,75,000/-**<br>(Rupees<br>ninety<br>crore<br>seventy<br>six<br>lakh<br>and<br>seventy<br>five thousand only)| |||| 8 9 The demand notice was questioned by the respondent in writ proceedings before the High Court. A learned Single Judge, by a judgment dated 13 December 2012, allowed the writ petition holding that a right had accrued to the respondent to obtain planning permission and that it could not be divested by the subsequent amendment made with effect from 1 April 2012. The demand was quashed and set aside. The Writ Appeal has been dismissed by a Division Bench of the High Court on 1 August 2014. The Division Bench held that : - (i) Insofar as the levy of I & A Charges are concerned, no amendment has been made to the Tamil Nadu Town and Country Planning (Levy of Infrastructure and Amenities Charges) Rules 2008[7] and in consequence, the demand of Rs. 4,17,15,000/- is without the authority of law; - (ii) The respondent had remitted the I & A charges and Premium FSI charges on 29 March 2012; - (iii) Office Order No. 7/2012 dated 16 April 2012 made it clear that the I & A charges were applicable for applications for planning permission where the advice for the payment of development charges was sent on or after 28 March 2012. In the present case, since the demand had been remitted prior to 28 March 2012, the pre-revised I & A charges were applicable; and - (iv) The charges for Premium FSI as revised with effect from 1 April 2012 could not be made applicable to the respondent. The NOC of the Sewerage Board was dated 30 March 2012 and the mere fact that it 7 The Rules 2008 9 was received by the appellant on 2 April 2012 was not a valid ground for the demand notice and hence the demand could not be justified. 10 Assailing the decision of the High Court, Mr K M Nataraj, learned Additional Solicitor General of India formulated two issues which need to be addressed in these proceedings: “(i) Whether charges namely Infrastructure & Amenities charges and Premium FSI charges are required to be collected as per rates prevailing as on the date of submission of planning permission application or on the date of granting approval of planning permission; (ii) Whether the respondent herein has accrued any vested right before granting approval of planning permission merely because they remitted the charges as per demand notice dated 27-03-2012.” The learned ASG urged that the appellant, as a planning authority, is under a statutory obligation to levy and collect the charges as applicable when planning permission is granted. The pendency of an application or the deposit of the payment earlier by the applicant does not create a vested right. If the planning permission is not granted, the planning authority would have to refund the amount deposited. Hence, the crucial date for determining the applicable charges is the date on which planning permission is granted by the planning authority. In the present case, the planning permission was granted only in 2013, pursuant to the interim order of the High Court subject to a further deposit of Rs 10 Crores as ordered. Insofar as I & A charges are concerned, it was urged that the High Court erroneously relied on the Office Order dated 16 April 2012 which records that the old rates would be applicable where the development charges’ advice was sent 10 before 28 March 2012. This, it has been urged, is in conflict with the GO dated 28 March 2012 according to which, I & A charges were to stand increased by 50 per cent over the then prevailing rates. The learned ASG argued that an amendment to the Rules was not necessary since the charges are determined and are leviable under an order issued pursuant to Section 63B while according building permission and hence the order of the High Court needs to be interfered with. - 11 On the other hand, Mr Rana Mukherjee, learned Senior Counsel appearing on behalf of the respondents submitted that: - (i) As regards **I & A charges** : - (a) Clause 6 of G.O.Ms No. 86 by which the charges were revised required that the Commissioner of Town and Country Planning submit a proposal for an amendment to the Rules of 2008. As a matter of fact, no amendment has been carried out; and - (b) Clause (i) of the Office Order dated 16 April 2012, states that revised I & A charges shall be applicable for demands made on or after 28 March 2012. Hence, the revised charges would not be applicable to the respondent against whom a demand had been raised on 27 March 2012 by the appellant. - (ii) As regards charges for **Premium FSI** : - (a) All payment related obligations were completed by the appellant on 29 March 2012 prior to the revision of the guideline values on - 1 April 2012. Consequently, the revised rates would not be 11 applicable and if any date after payment is to be taken into account that would only enable the government to unlawfully and unfairly delay the issuance of permissions and thereafter raise enormous demands. To obviate this, the cut-off date ought to be treated as the date of payment; - (b) The principle which has been enunciated in the judgment of this Court in **Union of India** v **Mahajan Industries Ltd.**[8] is applicable; and - (c) The subject matter of the demand pertains to payment levied by - the respondent and not a change in the development control rules such as involving a change in floors, setbacks etc. Moreover, it was urged that the planning permission in the present case was granted on 30 May 2012 and therefore the withholding of a copy and the basis of the impugned demand is a mere after thought. The revised demand does not indicate any reasons or basis. - 12 The rival submissions now fall for consideration. - 13 Section 48 of the Planning Act 1971 imposes a restraint upon the construction of buildings and making a material change in the use of land except with the written permission of the planning authority and in accordance with the conditions specified in the grant of permission[9] . > 8 (2014) 5 SCC 199 > 9 **48. Restrictions on buildings and lands, in the area of the planning authority.-** On or after the date of the publication of the resolution under sub-section (2) of section 19 or of the notice in the Tamil Nadu Government Gazette under section 26, no person other than any State Government or the Central Government or any local authority, shall, erect any building or make or extend any excavation or carry out any mining or other operation, in, on, over or under any land or make any material change in the use of land or construct, form or layout any 12 Section 49 which provides for an application for permission is in the following terms: “ **49. Application for permission.- (1)** Except as otherwise provided by rules made in this behalf, any person not being any State Government or the Central Government or any local authority intending to carry out any development on any land or building on or after the date of the publication of the resolution under sub-section (2) of section 19 or of the notice in the Tamil Nadu Government Gazette under section 26, shall make an application in writing to the appropriate planning authority for permission in such form and containing such particulars and accompanied by such documents as may be prescribed. (2) The appropriate planning authority shall, in deciding whether to grant or refuse such permission, have regard to the following matters, namely:- (a) the purpose for which the permission is required; (b)the suitability of the place for such purpose; (c) the future development and maintenance of the planning area (3) When the appropriate planning authority refuses to grant a permission to any person, it shall record in writing the reasons for such refusal and furnish to that person, on demand, a brief statement of the same.” The Planning Act 1971 requires the grant of planning permission before development or a change in the use of land can take place. The mere filing of an application does not entitle the applicant to permission. Nor is there a vested right to the grant of permission. Section 63B provides for the levy of I & A charges: work except with the written permission of the appropriate planning authority and in accordance with the conditions, if any, specified therein. 13 “63-B. Levy of infrastructure and amenities charges .-(1) Every local authority or the planning authority, as the case may be, while according building permit under the relevant laws or according permission under this Act, as the case may be, shall levy charges on the institution of use or change of use of land or building or development of any land or building in the whole area or any part of the planning area so as to meet the impact of development and for ensuring sustainable development of urban and rural areas by providing adequate infrastructure and basic amenities at the rates as determined in accordance with such procedure as may be prescribed which shall not be less than minimum and not more than the maximum as may be prescribed, and different rates may be prescribed for different parts of the planning area and for different uses. (2) The infrastructure and amenities charges shall be leviable on any person who undertakes or carries out any such development or institutes any use or changes any such use. (3) The collection of the infrastructure and amenities charges shall be made in such manner as may be prescribed. Explanation.- For the purpose of this Section “relevant laws” means in case of- - (i) the Chennai Metropolitan Development Authority, the Tamil Nadu Town and Country Planning Act, 1971 (T.N.Act 35 of 1972); - (ii) the Chennai City Municipal Corporation, the Chennai City Municipal Corporation Act, 1919 (T.N.Act 4 of 1919); - (iii) the Madurai City Municipal Corporation, the Madurai City Municipal Corporation Act, 1971 (T.N.Act 15 of 1971); - (iv) the Coimbatore City Municipal Corporation, the Coimbatore City, Municipal Corporation Act, 1981 (T.N.Act 25 of 1981); - (v) the Tiruchirappalli City Municipal Corporation, the Tiruchirappalli City Municipal Corporation Act, 1994 (T.N.Act 27 of 1994); - (vi) the Tirunelveli City Municipal Corporation, the Tirunelveli City Municipal Corporation Act, 1994 (T.N.Act 27 of 1994); - (vii) the Salem City Municipal Corporation, the Salem City Municipal Corporation Act, 1994 (T.N.Act 29 of 1994); - (viii) the Municipalities and Town Panchayats, the Tamil Nadu District Municipalities Act, 1920 (T.N.Act 5 of 1920); and - (ix) the Panchayat Unions and Village Panchayats, the Tamil Nadu Panchayats Act, 1994 (T.N.Act 21 of 1994).” 14 Section 63B provides for the levy of I & A charges while according a building permit either under relevant laws or while according permission under the Planning Act 1971. These charges are leviable on the institution of use or change of use of land or building or development of any land or building. The rates are determined in accordance with such procedure as may be prescribed. The rates are not to be less than the minimum and more than the maximum that is prescribed. 14 Rule 4 of the Rules 2008 contains provisions for the imposition of the I & A charges: “ **4. Infrastructure and Amenities Charges. –** The infrastructure and amenities charges shall be collected for new construction, additions to existing constructions and change of use of existing buildings at the rates not exceeding the maximum rate and not less than the minimum rates indicated in the Table below, in case of different categories of buildings referred to in the Table: ## **THE TABLE** |Sl No.|Type of building|Minimum rates per<br>square metre|Maximum<br>rates per<br>square<br>metre| |---|---|---|---| |**(1)**|**(2)**|**(3)**<br>Rs.|**(4)**<br>Rs.| |1.|Multistoryed<br>buildings<br>accommodating<br>residential or commercial<br>or<br>Information<br>technology or industrial<br>of<br>institutional<br>or<br>combination<br>of<br>such<br>activities|500|1,000| |2.|Commercial<br>building.<br>Information Technology<br>building,<br>Group|200|500| 15 ||development<br>and<br>Special<br>building<br>(not<br>covered under Sl. No. 1)||| |---|---|---|---| |3.|Institutional building (not<br>covered under Sl. No.I)|100|200| |4.|Industrial building (not<br>covered under Sl. No. 1)||| ||||| 15 Rule 5 empowers the Director Of Town and Country Planning to fix the rates of charges in respect of areas other than the Chennai Metropolitan Planning Area. In respect of the Chennai Metropolitan Planning Area, the power to fix the charges, subject to due observance of the minimum and the maximum specified in Rule 4, is conferred on the Vice-Chairman of the Chennai Metropolitan Development Authority. Rule 5 (2) provides thus: ## “ **5. Fixation of rates of Charges.-** (2) In respect of the Chennai Metropolitan Planning Area, the Vice Chairman, Chennai Metropolitan Development Authority shall fix the rates of such charges for each of the above categories of buildings which shall not be less than the minimum and not more than the maximum as prescribed in Rule 4, taking into account the various aspects of developments including infrastructure needs. He may fix different rates for different categories of buildings or for different areas.” 16 The power to levy charges for the Premium FSI is in Regulation 36 of the Second Master Plan for Chennai Metropolitan Area 2006 (Regulation)[10] . Regulation 36 is in the following terms : “ **36. Premium FSI.-** The Authority may allow premium FSI over and above the normally allowable FSI, in any case not exceeding 0.5 for special building and group developments, and not exceeding 1.0 for multistoreyed > 10 Regulation 2006 16 buildings in specific areas which may be notified, on collection of a charge at the rates as may be prescribed with the approval of the Government. The amount collected shall be kept in an escrow amount for utilizing it for infrastructure development in that area as may be decided by the Government.” 17 Premium FSI is the Floor Space Index over and above that which is normally allowable and is not to exceed 0.5 for special buildings and group developments or 1.0 for multi-storeyed buildings in specific areas. The rates for premium FSI are prescribed with the approval of the Government. 18 On 27 March 2012, the appellant raised a demand on the respondent for the payment of charges including: - (i) I & A charges of Rs. 8,34,40,000/-; and - (ii) Premium FSI charges for 78690.55 sq.mtrs in the amount of Rs. 44,75,88,000/-. While raising the demand, the respondent was informed of the conditions required to be complied with in order to ensure the grant of planning permission. The letter specifically stated that while the grant of planning permission depended upon the fulfillment of the conditions stipulated in the letter, pre-payment of the development charges and other charges would not entitle the respondent to planning permission but only to a refund if planning permission were to be refused. 17 19 On 28 March 2012, the Housing and Urban Development Department of the Government of Tamil Nadu issued G.O.Ms No. 86 stipulating that: - (i) The minimum and maximum rates as specified in Rule 4 of the I & A Rules 2008 “shall be done away with”; and - (ii) The I & A charges for different categories and buildings falling under the jurisdiction of the appellant and of the Commissioner of Town and Country Planning were to stand increased by 50 per cent over the then prevailing rates. Thus, for instance, the I & A charges for multi-storeyed residential buildings were sought to be revised for the Chennai Metropolitan Development Planning Areas from Rs. 250 per sq. mtr to Rs. 375 per sq.mtr. Clause (6) of G.O.Ms contemplates an amendment to the Rules 2008 : “6) The Commissioner of Town and Country Planning is directed to send necessary proposal on amendment to the Tamil Nadu Town and Country Planning (Levy of Infrastructure and Amenities Charges) Rules, 2008 to Government accordingly.” 20 It was in view of the provisions contained in clause (6) extracted above that the Division Bench in its judgment dated 1 August 2014 recorded, having enquired of the Advocate General, as to whether any proposal for the amendment of the rules had been initiated. The Advocate General informed the High Court that while steps to amend the rules had been initiated, it would take 18 about two months to complete the process of amending them. It was in this view of the matter and the statement of the Advocate General that the High Court recorded that as on the date of its judgment, no amendment was made to the Rules 2008 for the purpose of increasing the I & A charges. Rule 4 as it stands prescribes the minimum and the maximum rates for the levy of I & A charges. Rule 5(2) empowers the Vice-Chairman of Chennai Metropolitan Development Authority to fix the rates for the Chennai Metropolitan Development Planning Areas, while observing the minimum and the maximum rates set out in Rule 4. The proposal which was initiated by the government on 28 March 2012 envisaged the elimination of the minimum and maximum rates specified in Rule 4 as a result of which clause (6) of G.O.Ms. 86 incorporates a requirement of amending the Rules 2008. Absent an amendment to the Rules 2008, the High Court held that the demand for I & A charges at the revised rate could not be enforced against the respondent. A revision of the I & A charges could have been effected by the Vice-Chairman of the appellant in terms of Rule 5(2) without a formal amendment to the Rules 2008, so long as the minimum and maximum provided in Rule 4 is not breached. However, it appears that the government took the view that an amendment to the rules was necessitated since the table specifying the minimum and maximum in Rule 4 was to be abrogated. It was for the above reason that the High Court came to the conclusion that a revised demand for I & A charges could not be enforced in the absence of an amendment to the Rules 2008. Section 63B requires that the minimum and maximum rates should be prescribed. This will have to be borne in mind by the government. Subordinate legislation has to be in conformity with parent legislation. 19 21 The High Court also adverted to the Internal Office Circular/Order dated 16 April 2012 of the appellant which specified that while the revised I & A charges were leviable with effect from the issuance of G.O.Ms. No. 86 on 28 March 2012: “i.The revised rate of Infrastructure & Amenities charges are applicable for the Planning Permission Applications, where Development Charges advice was sent on or after 28.03.2012. In the case of Planning Permission Applications for which DC advice dated prior to 28.03.2012, the pre-revised rates only applicable.” In terms of the above office order, cases where the “Development Charges advice” was sent prior to 28 March 2012 would be governed by the pre-revised rates. The government is bound by its own decision. Consequently, on this aspect of the matter, we are in agreement with the view of the High Court that the revised I & A charges were not lawfully demanded from the appellant to whom the development charges advice had been issued prior to 28 March 2012. 22 The second aspect of the matter which needs scrutiny is in regard to the levy of Premium FSI charges. The levy of Premium FSI charges under Regulation 36 is incident to the planning authority allowing Premium FSI over and above the FSI which is normally allowable. In other words, it is upon and subject to the grant of Premium FSI that the authority can demand Premium FSI charges. If no Premium FSI is sanctioned, obviously there would be no occasion to demand a charge for Premium FSI. Similarly, if planning permission were to be refused, the deposit which is made by the developer would be refunded. This was categorically stated in the demand which was raised on the respondent on 27 March 2012. 20 23 Planning permission is granted by the planning authority upon an application for permission which is made under Section 49 of the Planning Act 1971. In the present case, the planning permission was granted upon an interim order of the High Court, subject to the deposit of Rs. 10 Crores on 13 March 2013. Though the appellant received the approval of the Housing and Urban Development Department on 5 January 2012 following the recommendation of the Multi-storyed Building Panel, the grant of planning permission was still to be considered by the Planning Authority. The letter dated 5 January 2012 of the Housing and Urban Development Department contemplates that several steps were still to be taken including the transfer to the road widening portion to Chennai Metropolitan Development Authority, the issuance of an NOC by the Sewerage Board and the fulfillment of all requisite conditions under the development regulations. Moreover, even after compliance with those conditions, the appellant had to process the grant of planning permission. The letter of demand that was issued by the appellant on 27 March 2012 similarly required the fulfillment of several conditions precedent upon which the application for the grant of planning permission would be considered. 24 On 27 March 2012, while issuing a demand notice to the respondent, it was made clear by the appellant that the planning permission was still to be issued. The submission of the application for permission and the steps taken by the respondent to comply with the conditions and the deposit of the charges did not confer a vested right in the respondent for the grant of planning permission. The grant of planning permission would only ensue upon the appellant 21 scrutinizing the application and determining that the permissions which were sought were in accordance with the development regulations and all other planning requirements holding the field. Before the planning permission was issued, the revised charges for Premium FSI came to be enforced. Once the revised charges came into force with effect from 1 April 2012, the respondent, as the applicant for planning permission, was bound to pay the revised charges. As on 1 April 2012, the respondent had no planning permission in its favour. The submission of the respondent that planning permission was issued in May 2012 evidently will not advance the case of the respondent. The grant of any permission post the revision of the Premium FSI charges would necessarily be subject to the revised charges. Hence, in raising the demand on the basis of the revised charges on 22 August 2012, the appellant was acting in accordance with law. 25 The principle which we have adopted accords with a consistent line of precedent of this Court. In **State of Tamil Nadu** v **Hind Stone**[11] , Justice O Chinnappa Reddy speaking for a Bench of two learned judges of this Court, while interpreting the provisions of Rule 2 (A) of the Mines and Minerals (Regulation and Development) Act 1957 observed : > “13…While it is true that such applications should be dealt with within a reasonable time, it cannot on that account be said that the right to have an application disposed of in a reasonable time clothes an applicant for a lease with a right to have the application disposed of on the basis of the rules in force at the time of the making of the application. No one has a vested right to the grant or renewal of a lease and none can claim a vested right to have an > 11 (1981) 2 SCC 205 22 application for the grant or renewal of a lease dealt with in a particular way, by applying particular provisions. In the absence of any vested rights in anyone, an application for a lease has necessarily to be dealt with according to the rules in force on the date of the disposal of the application despite the fact that there is a long delay since the making of the application. We are, therefore, unable to accept the submission of the learned counsel that applications for the grant of renewal of leases made long prior to the date of GOMs No. 1312 should be dealt with as if Rule 8-C did not exist.” ## The same principle was followed by another two judge Bench of this Court in **Howrah Municipal Corporation** v **Ganges Rope Co. Ltd.**[12] . Justice D M Dharmadhikari speaking for the court held : “17…The statutory provisions regulating sanction for construction within the municipal area are intended to ensure proper administration of the area and provide proper civic amenities to it. The paramount considerations of regulatory provisions for construction activities are public interest and convenience. On the subject of seeking sanction for construction, no vested right can be claimed by any citizen divorced from public interest or public convenience.” This Court held that the provisions contained in the Howrah Municipal Corporation Act 1980 contemplate an express sanction before a person can be allowed to construct or erect a building. Hence, in ordinary course, no vested right is created merely by the submission of an application for sanction to construct a building. Adverting to the decision in **Usman Gani J. Khatri of** ## **Bombay** v **Cantonment Board**[13] , the Court held thus: “30. This Court, thus, has taken a view that the Building Rules or Regulations prevailing at the time of sanction would govern the subject of sanction and not the Rules > 12 (2004) 1 SCC 663 > 13 (1992) 3 SCC 455 23 and Regulations existing on the date of application for sanction.” ## In **Commissioner of Municipal Corporation, Shimla** v **Prem Lata Sood**[14] , Justice S B Sinha speaking for a two judge Bench observed thus: “30…even in the order of sanction passed in favour of the respondents by the State, a condition was imposed that before undertaking the development activities by way of erection of the building, the respondents would take the requisite sanction from the Municipal Corporation. Even if such a condition had not been imposed, the provisions of the Municipal Corporation Act, as noticed hereinbefore, would operate. 36. It is now well settled that where a statute provides for a right, but enforcement thereof is in several stages, unless and until the conditions precedent laid down therein are satisfied, no right can be said to have been vested in the person concerned. The law operating in this behalf, in our opinion is no longer res integra.” The same view has been taken by a Bench of three judges of this Court in **New** ## **Delhi Municipal Council** v **Tanvi Trading and Credit Private Limited**[15] .Justice ## J M Panchal speaking for the court held : “39. It is well settled that the law for approval of the building plan would be the date on which the approval is granted and not the date on which the plans are submitted. This is so in view of para 24 of the decision of this Court in _Usman Gani J. Khatri_ v. _Cantonment Board_ [(1992) 3 SCC 455] . It would not be out of place to mention that on 7-2-2007, the Master Plan, 2021 has been approved in which the LBZ guidelines have been incorporated and since the plan submitted by the respondents was not approved up to the date of coming into force of Master Plan of 2021, the LBZ guidelines will apply with full force to the plan submitted by the > 14 (2007) 11 SCC 40 > 15 (2008) 8 SCC 765 24 respondents and the plan which is contrary to the LBZ guidelines could not have been directed to be sanctioned.” 26 Mr Rana Mukherjee, learned Senior Counsel appearing on behalf of the respondent sought to make a distinction on the ground that this principle will apply as regards regulatory aspects of the development regulations, not in regard to the demand of Premium FSI charges. We are unable to accept the contention simply because the demand on account of Premium FSI charges arises upon the grant of planning permission to avail of Premium FSI. The respondent, as the developer, is liable to pay the revised charges which are applicable post 1 April 2012 when planning permission has been granted. Learned counsel for the respondent also relied on the decision in **Union of India** v **Mahajan Industries Ltd.**[16] . The case is clearly distinguishable since the judgment of this Court adverted to the position which was laid down in a judgment of the Delhi High Court that the “crucial date” for calculating conversion charges has to be the date of the receipt of the application for conversion. Significantly, the counsel for the Union of India did not contest the correctness of the view of the High Court in that regard. The factual situation in the present case is clearly distinguishable. 27 For the above reasons, we allow these appeals in part by setting aside the impugned judgment and order of the High Court insofar as it quashed the > 16 (2005) 10 SCC 203 25 demand raised by the appellant on 22 August 2012 for the levy of Premium FSI charges. 28 The appellant, in our view, was justified in demanding Premium FSI charges at the revised rates and would be entitled to enforce its demands. However, we maintain the order of the High Court insofar as the demand for I & A charges is concerned. 29 The appeals are disposed of. There shall be no order as to costs. **…..…………..........................................J. [Dr Dhananjaya Y Chandrachud]** **..……..…………………………...............J.** **[Indira Banerjee]** **New Delhi; July 29, 2019** 26
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.