Case Synopsis & Summary

This Supreme Court decision concerns the salary parity claim of staff and sub-staff employed in sick textile mills taken over by the Central Government and transferred to the National Textile Corporation Ltd. (NTC). The central issue is whether staff in mills are entitled to ‘equal pay for equal work’ with the staff at corporate offices. Two fact-finding bodies—the National Industrial Tribunal (NIT) and the Sathyam Committee—found no equal work between the two categories, highlighting wide disparities in emoluments and work norms; they recommended relief measures but not parity. The staff groups alleged discrimination, arguing that the offices’ CDA-based pay scales and the mills’ IDA-based scales are invidiously unequal and that the Central Government has a statutory liability under Section 5(2)(c) of the Sick Textile Undertakings (Nationalisation) Act, 1974. The Union of India contended that relief would jeopardize rehabilitation schemes before BIFR and would impose an additional financial burden. The Court did not overturn the factual findings but held that discrimination could not be justified solely by CDA/IDA patterns and that some relief was warranted. It directed the Central Government to determine the extent of relief (potentially via an expert) and to implement it within a specified time, while allowing a hearing for both sides. The decision ultimately disposed of the appeal and related petitions with a plan for interim relief and future action.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • BRIJESH KUMAR
  • ARUN KUMAR
Judgment Date
2003-10-14
Court Decision / Holding
The Court held that the claim for equal pay for equal work is not tenable where the two categories do not perform equal work, as per NIT and Sathyam Committee findings. However, it ruled that discrimination exists and relief is warranted for mill staff, though not parity with headquarters staff. It directed the Central Government to determine the extent of relief (potentially via an expert), provide a hearing to both sides, and decide within four months with implementation within two months thereafter. It also held that pendency of BIFR schemes cannot be used to deny relief, and that the Central Government must discharge its statutory wage responsibility irrespective of rehabilitation packages.
Final Disposition
Appeal and writ petitions disposed of in terms, with directions to determine and implement staff relief within prescribed timeframes; recognition of some relief while denying parity in pay scales.

Parties to the Case

Appellants / Petitioners

  • Chairman-Cum-Managing Director, National Textile Corporation Ltd. (NTC)

Respondents

  • N.T.C.(WBAB & O) Ltd. Employees Union and Ors.

Legal Representation & Advocates

Counsels for Respondents

  • • Altaf Ahmad
  • • T.C.R. Ray
  • • N.N Goswami
  • • P.P. Singh
  • • H.K. Puri
  • • Ujjwal Banerjee
  • • S.K. Puri
  • • B.S. Banthia
  • • Hemant C Sharma
  • • S. Wasim A. Quidri
  • • Ms. Sunita Sharma
  • • Ajay Sharma
  • • D.S. Mabra
  • • P. Parmeswaran
  • • B.V. Niren
  • • M. Veerappa
  • • Naresh Kaushik
  • • Ms. Shilpa Chohan
  • • Mrs. Lalitha Kaushik
  • • Mrs. Urmila Sirur
  • • Narender Kaushik
  • • Pankaj Kaushik
  • • Ashok Kumar Sharma
  • • Charan Lal Sahu
  • • Ms. Homa Sahu
  • • D.P. Mukherjee
  • • Ms. Nandini Mukherjee
  • • P.K. Mullick

Provisions of Law Cited

Sick Textile Undertakings (Nationalisation) Act, 1974 – Section 5(2)(c)Constitution of India – Article 14Constitution of India – Article 39(d)Sick Industries Companies (Special Provisions) Act, 1985 (SICA)

Legal Doctrines & Maxims

  • Equal pay for equal work
  • Model employer doctrine
  • Non-discrimination under Article 14

Submissions & Arguments

Contentions of Appellants / Petitioners

The staff in mills sought parity with corporate-office staff on the basis of equal work, pointing to historical pay disparities and alleged equalities in method of work; the appellants contend that though NIT and Sathyam Committee reports found no equal work, relief is warranted to redress long-delayed wage revisions and to prevent double standards, especially given the statutory liability of the Central Government for workers’ wages under Section 5(2)(c). They emphasize the need to avoid worsening rehabilitation efforts and to consider special relief measures that can be merged with future pay revisions.

Contentions of Respondents

The staff/sub-staff in mills claim ongoing disparities amounting to inequity; they argue that the CDA/IDA pattern difference should not justify denying relief and that the Central Government must act as a model employer by revising pay or grants of relief; they point to the protracted litigation and the Sathyam Committee recommendations for special relief (including VRS-related adjustments and a two-category mill division) as a framework for relief, independent of BIFR rehabilitation schemes.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
A.K. Bindal & Anr. v. Union of India[2003] 5 SCC 163Mentioned OnlyCited by counsel but expressly stated as not attracted/applicable to the facts of this case; thus not relied upon.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•5,138 words•~24 min read

In The Court Record

CHAIRMAN-CUM-MANAGING DIRECTOR N.T.C. LTD. v. N.T.C.(WBAB & O) LTD. EMPLOYEES UNION

A # CHAIRMAN-CUM-MANAGING DIRECTOR, NATIONAL TEXTILES CORPORATION LTD. AND ORS. _v._ N.T.C. (W.B.A.B. &.O) LTD. EMPLOYEES UNION AND ORS. B OCTOBER 14, 2003 [BRIJESH KUMAR AND ARUN KUMAR, JJ.] ## _SERVICE LAW:_ C C _Sick Textile Undertakings (Nationalisation) Act, 1974-Section 5(2)(c)-Sick textile mills taken over by Central Government under the Act-Staff working in mills seeking parity in pay scales with staff working in corporate offices-Claim of-National Industrial Tribunal and a Committee, appointed for the purpose, holding that there is no equal work between two categories of staff-Disparity widening during the period_ D _under litigation-Plea of additional financial burden since rehabilitation schemes already pending before BIFR-Held, on facts, the claim of equal pay for equal work not tenable on the basis of the findings of the two fact finding bodies-However, there is no justification in discrimination by Central Government between two categories of staff-Since both the_ E _categories belong to one parent company, the financial burden should be shared by both-Central Government has to discharge its responsibility de hors the BIFR schemes-Central Government to work out the extent of relief to staff working in mills within four months and to implement it within two months thereafter-Constitution of India, Articles 14 and 39(d)-_ F _Equal pay for equal work._ _t J_ The Central Government took over various sick textile mills in different parts of the country under the Sick Textile Undertakings (Nationalisation) Act, 1974 and transferred them to National Textile Corporation Ltd. (NTC). The staff/sub staff working in the mills G claimed parity with the pay scales given to the staff working in the corporate offices of NTC and its subsidiaries on the basis of 'equal pay equal work'. They claimed that the nature of work performed by them is the same as those working in the corporate offices. Some associations filed petitions before various High Courts seeking revision of pay scales H on the plea of 'equal pay for equal work'. This Court directed the cases 722 CHAIRMAN-CUM-MANAGING DIRECTOR N.T.C. LTD. _v._ NT.C.(WBAB & 0) LTD. EMPLOYEES UNION 723 to be transferred to itself from different High Courts. In 1989, this A Court, with a view to find an amicable settlement, directed the National Industrial Tribunal to look into and resolve the controversies. The Tribunal submitted a Report in 1996 finding that then! is no equal work between the two categories of staff. The Tribunal, however, failed to resolve the controversies. In the mean time, during the pendency of B the matter, the management refused to revise the pay scales of the staff working in the mills on the plea that the matter was subjudice. This resulted in widening the disparity in pay scales between the two groups from 159% in 1987 to 642% in 2000. > On the direction of this Court, the Central Government in 1999 C appointed a one man Committee (Sathyam Committee) to look into the grievances of the staff and sub staff of the NTC mill regarding their > pay structure. The Committee gave a report in October 2000 stating that the two categories of employees are not performing equal work > and that they are not entitled for equal pay. The Committee, however, D recommended some 'special relier to the staff working in the mills on > account of delay in settlement of the dispute. The Union of India contended that the recommendations of the Sathyam Committee have been implemented in full and nothing survives; that various mills were declared sick under the Sick Industries E Companies (Special Provisions) Act, 1985 (SICA) and that the proceedings before the Board oflndustrial and Financial Reconstruction (BIFR) for rehabilitation are pending; that for some sick mills, the BIFR had already formulated and sanctioned schemes and are being implemented; that any grant of further relief to the workers will put F additional financial burden and would upset the rehabilitation; and that there is disparity since the staff of corporate offices is on the Central Dearness Allowance (CDA) pattern while the staff working in the mills is on the variable Industrial Dearness Allowance (IDA) pattern governed by region-cum-industry awards. G The respondent-Associations contended that there is equality and parity in the work and the working conditions between the two categories and hence are entitled for equal pay. Disposing of the matters, the Court H 724 A SUPREME COURT REPORTS (2003] SUPP. 4 S.C.R. HELD : 1.1. The National Industrial Tribunal found against the staff of the Mills. The finding of the Tribunal was endorsed by the Satlttyam Committee. In the face of the findings of the two fact finding bodies, this Court is unable to take a different view of the issue. This Court has no reason to differ with the finding of fact on this issue arrived at by the two B independent bodies. Hence the claim of the staff based on the principle of equal pay for equal work is not tenable. Wheit the work is not l:qual, the question of equal pay does not arise. [732-D-F] 1.2. The staff/sub staff working in the Mills have unfortunately received a step motherly treatment. They have not had a pay revision for C years. The Sathyam Committee had noticed the sorry plight of the workers. The Committee gave some _ad hoc_ relief to the workers which is not enough. The Sathyam Committee noticed disparity in the pay scales of the two categories of workers which is highly unjust and unfair. The staff working in the corporate offices of the Mills is also staff of the D parent body. If the mill is incurring losses, the impact has to be on ev1?ryone connected with the mills in whatever capacity. There cannot be double standards. There will be financial burden even if the pay scales of the office staff are revised. There can be no case for total denial of revision of pay to the staff/sub staff working in the mills. The Government has a E statutory lilability for the wages, salaries and dues of the workers. The pay revision was being allowed in case of one category of workers within the same organisation, while it was being denied to another category of workers, giving rise to discrimination. [732-F-H, 733-A-C, 734-D] .. _A.K. Bindal & Anr._ v. _Union of India,_ [2003) 5 SCC 163, refe'rred F to. 1.3. Discrimination between the two categories of staff cannot be justified on the basis of applicability of the CDA pattern and titie IDA pattern to the respective categories of staff. The IDA pattern cannot G be taken to debar any revision of pay scales. The Central Government has to act as a model employer and such specious pleas on its part are highly improper an~ unjustified. (733-D] 1.4. A case for relief to the staff/sub staff working in the Mills is H definitely made out. The workers deserve some relief though not parity CHAIRMAN.CUM-MANAGING DIRECTOR N.T.C. LTD. _v._ N.T.C.(WBAB & 0) LTD. EMPLOYEES UNION 725 of pay scales with -staff/sub-staff working in corporate offices but A certainly on account of revision of pay scales/increase of D.A. or emoluments from time to time as and when fell due during the period of nearly three decades since when, no revision of their pay scale has been made. [733-E] B 1.5. This Court is ill-equipped to work out the extent ofreliefwhich can be granted to the workers in the mills. Therefore, the Central Government is directed to take appropriate steps which if so required may include appointment of an expert to work out the extent of relief which oughtto be granted to the workers in the mills. Some considerations C may be had about the financial constraints, if any, but it cannot be to the extent of virtual denial of any benefit. Before taking a final decision in the matter, an opportunity of hearing be allowed to the management as well as to the workers to enable them to place their respective stands before the decision making authority. The decision should be taken within D four months from the date of this judgment and the same should be implemented within two months thereafter. [733G-H, 734-A-B) 1.6. The proceedings before BIFR has been pending since 1993 i.e. for more than ten years. The management was all along fully aware of the demand of the workers of the mills in this behalf. Their cases E have been pending in courts since much before the rehabilitation schemes were conceived of. In the various deliberations with the workers it has been noted that rehabilitation schemes are independent of any orders that may be passed by this Court. Therefore, pendency of the rehabilitation schemes before BIFR is not a sufficient ground to F deny relief to the staff/sub staff working in the mills. As per the provisions of sections 5(2)(c) of the Sick Textile Undertakings (Nationalisation) Act, 1974, the wages, salaries and other dues of the employees of the sick textile undertakings after the takeover of their managements by the Central Government are the responsibility of the G Central Government. It has failed to discharge its responsibility for all these years by raising such specious pleas. [734-F-H, 735-A] > CIVIL APPELLATE JURISDICTION: Civil Appeal No. 14572 of 1996. H 726 SUPREME COURT REPORTS [2003] SUPP. 4 S.C.R. A From the Judgment and Order dated 7.10.88 of.the Calcutta High Court in W.P. No. Nil of 1988., ## WITH W.P (C) No. 34/88, 1073, 1074/89 T.P. (C) No. 289/88, W.P. (C) **B** Nos. 152/88, 214/89, 218, 44, 134, 211/88, 161/87, 579/89, T.P.(C) No. 290 of 1988. Altaf Ahmad, Additional Solicitor General, T.C.R. Ray, N.N Goswami, P.P. Singh, H.K. Puri, Ujjwal Banerjee, S.K. Puri, B.S. Banthia, Hemant C Sharma, S. Wasim A. Qu:idri, Ms. Sunita Sharma, Ajay Sharma, D.S. Mabra, P'. Parmeswaran, B.V. Niren, M. Veerappa, Naresh Kaushik, Ms. Shilpa Chohan, Mrs. Lalitha Kaushik, Mrs. ,Urmila Sirur, Narender Kaushik, Pankaj Kaushik, Ashok.Kumar Sharma, Charan Lal Sahu, Ms. Homa Sahu, D.P. Mukherjee, Ms. Nandini Mukherjee and P.K. Mullick for the Appearing **D** parties. ## The Judgment of the Court was delivered by **ARUN KUMAR, J.** : Various textile mills in the country came to be vested in the Central Government by virtue of the provisions under E Section 3 (1) of the Sick Textile Undertakings (Nationalization) Act, 1974. The Central Government transferred all such mills to the National Textile Corporation Ltd. (hereinafter referred to as 'NTC') which was brought into existence for this purpose. Under Section 5 of the said Act the liability towards wages, salaries and other dues of workers of such mills aft1!r the **F** takeover of management by the Central Government, is that of the Central Government. The issue involved in these cases is regarding the claim of the staff/ sub staff engaged by the various textile mills under the NTC for 'equal pay for equal work'. The staff working in the mills. is claiming pay equal to G or in parity with the pay scales prevailing for the staff working in the corporate offices of the mills. It is not in dispute that the office staff/sub staff is on the Central Dearness Allowance pattern (for short CDA) while the staff/sub staff working in the mills is on the variable Industrial Dearness Allowance pattern (for short IDA) governed by region: cum : Industry **H** awards. It is to be noted that there has never been any parity in the pay CHAIRMAN.CUM-MANAGING DIRECTOR N.T.C. LTD. _v._ N.T:C.(WBAB &. 0) LTD. EMPLOYEES UNION (ARUN KUMAR. l.) 727 scales between the staff working i.n the corporate offices of the NTC and A its subsidiaries and the staff working in the mills. However, over the years the disparity between the pay scales of the staff working in the corporate offices and staff working in the mills has become highly disproportionate. It has been noticed by the Sathyam Committee, to which reference will be made in detail subsequently, that as against 159% increase in the emoluments B of the staff working in the corporate offices over the staff working in the mills in the year 1987, the proportion has increased by the year 2000 to 642%. It is this disproportion between the pay scales of the staff working in the corporate offices and the staff working in the mills which has Jed to tremendous discontent amongst the staff working in the mills and it is this discontentment which is the root cause of this entire litigation. The C problem is further aggravated by the fact that the NTC as well as most of its subsidiaries have been constantly incurring losses and majority of them are sick companies facing proceeding under the Sick Industrial Companies (Special Provision) Act, 1985 (in short 'SICA'). D > In support of their plea of "equal pay for equal work" the staff > working in the mills claimed that the nature of work performed by them is the same as the staff working in the corporate offices. They have gone to the extent of saying that there is interchangeability between the staff working at the two places. The subsidiaries of the NTC are spread over E in different parts of the country.· The staff working in some of the subsidiaries through their associations approached the respe~tive High Courts in the country for relief regarding revision of pay scales raising the plea of "equal pay for equal work". Ultimately these cases stood transferred to this Court and were bunched together. The matter has been pending in this Court for quite some time. The effort of the Court has been F to find an amicable settlement of the problem. In fact, by an order dated > 29th September, 1989, by consent of all the counsel appearing for the parties, reference was made to the National Industrial Tribunal in a bid to resolve the controversy. The Tribunal deliberated on the issues involved > over a long period of time. It ultimately submitted its report on 17th July, G 1996. This report did not succeed in resolving the issues. The report found that the "workmen in the mills are getting lesser emoluments than those comparable categories of employees serving in the corporate offices. The workmen have succeeded in showing that there are some similarities in the work done by two sets of employees but they have failed to show H SUPREME COURT REPORTS [2003] SUPP. 4 S.C.R. 728 A satisfactorily that employees working in the mills discharge similar functions when judged on the yardstick of reliability, quality, responsibility, confidentiality etc." The finding of the Tribunal regarding absence of equality or parity on working between' the staff working in the corporate offices and the other working in the mills has an important'bearing on the B claim of the staff working in the mills. The long time that elapsed during the pendency of the matter in this Court and before the National Industrial Tribunal resulted in further prejudice to the claim of the staff in the rriills because the management refusedto entertain any request for pay revision during this period on the plea of matter being subjudice. While the claitn C for revision of the pay scale for the staff working in the mills remained pending, the pay scales of the staff working in the corporate offices continued to be revised from time to time which resulted in the situation as noticed earlier that is, from a disparity in pay scales cifthe two categories being 159% in the year 1987, it became 642% in the year 2000. D The fond hope of this Court that the matter will be settled equitably before the National Industrial Tribunal did not fructify. This Court continued its effort to see that some amicable settlement to the issue is found. The Central Government was persuaded to rriake positive efforts· in this direction. As a result by a notification dated 27th October, 1999 E the Government of India appointed a one man Committee of Shri S.R. Sathyam, a retired IAS officer and a former Secretary in the Ministry of Textile to look into the grievances of the staff and sub staff of the NTC mills regarding their pay .structure. ,A.,s per the notification the findings of the Committee were to be of a recommendatory nature. The Committee F was expected to keep in view: - I. The capacity of NTC to pay wages and salaries; - II. The pay structure of other employees in the mills; ## G - III. The pay structure of NTC Headquarters; - IV. The pay structure of similarly .placed private mills; H - V. The observations of the National Industrial Tribunal and of this Court. CHAIRMAN-CUM-MANAGING DIRECTOR N.T.C. LTD. _v._ N.T.C.(WBAB 4 OJ LTD. EMPLOYEES UNION (ARUN KUMAR. I.( 729 The Sathyam Committee gave its report on 31st October, 2000. The A Committee found that the different identity of workers working in the corporate offices and workers working in the mills has always been maintained. The pay structures in the two cadres had been different. The pay scales for the staff in the corporate offices were substantially better as compared to the pay scales of the staff working in the mills. Most B importantly the Sathyam Committee endorsed the find,ing of the National Industrial Tribunal that the two categories of employees were not perfonning equal work. When there was no equal wort, there was no question of equal pay. However, the Committee found that the staff working in the mills cannot be legitimately denied some relief on account of delay in settlement of the dispute. Some of the recommendations of the Committee are as C under: - "23 .10 The relief to be provided can be called 'special relier . It must count for all pay-related benefits although it can formally be merged with pay only at the time of the next D pay revision [Paragraph 15 .4] - 23.11 The 'special relief must also count for VRS. The Guidelines issued by the OPE for implementation of the VRS may be amended to accommodate this provision E [Paragraph 16.1] - 23.12 The VRS itself will have to be implemented in a timebound manner. Otherwise, the purpose of counting the 'special relief for VRS so as to make it more attractive may not be (fully) realized. [Paragraph 16.2.l] · F - 23.13 For purposes of computation of VRS benefits, the Gujarat model may be adopted. [Paragraph 16.2.2.] - 23.14 In the context of voluntary retirements, it will be a thoughtful gesture to allow some flexibility regarding transfer of Staff/sub-Staff between 'closure' and 'revival' mills. [Paragraph 16.2.3.] - 23 .15 For the purpose of providing 'special relier, the mills of the NTC may be divided into two categories: H 730 - SUPREME COURT REPORTS [2003] SUPP. 4 S.C.R. A - (i) 'Revival Mills' i.e., sick mills identified by the BIFR to be revivable. - (ii) 'Closure Mills' i.e., sick mills ordered by the BIFR to be -'.closed. [Paragraph 17.1] B - 23.16 The approach towards providing 'special relief in respect of these. three categories can be as follows: - (i) For 'Good Mill', payment shall made with immediate effect with reference to a 'cut-off date' c - (ii) (a) For 'Revival Mills', the benefit of the 'special relief' shall be available immediately for purposes of YRS. D E F G H - (b) If the Staff/sub-Staff chooses to stay with the Mill, then, the 'special relief will be available with effect from the 'cut-off date', but only after the Mill is revived. - (c) In case, the rehabilitation plan fails and the Mill cannot be revived, the staff/sub-staff can, at that stage, opt for VRS and claim the benefit of the special relief. Only, there can not be any claim for arrears. - (iii) For 'Closure Mills', the benefit of the 'special relief' shall be available immediately to staff/sub-staff opting for VRS. The benefit shall not be available to staff not - - proceeding on VRS. [Paragraph 17.2] - 23.17 It will be necessary to define the 'cut-off date' without any ambiguity. It will be reasonable to identify the date of-the meeting in the Ministry of Textiles in which an _ad hoc._ relief was proposed-as the 'cut-off date'. [Paragraph 18.1. and 18.2) - 23.18 It will be more convenient to exclude the retired employees from the-scope of the benefit proposed. [Paragraph 19 .1] CHAIRMAN-CUM-MANAGING DIRECTOR N.T.C. LTD."· N.T.C.(WBAB & 0) LTD. EMPLOYEES UNION (MUN KUMAR. J.] 73} - 23.19 The 'benefit order' must incorporate revised work norms. A [Paragraph 19.2) - 23.20 The 'special relief to be given can only partially neutralize the gap in emoluments. [Paragraph 20.1] - 23.21 The prescription of partial neutralization need not B necessarily apply equally at all levels. It will be more equitable to apply the 'special relief in a graded manner. Towards this end, the staff/sub-staff in Mills can be divided into four categories. [Paragraphs 20.2. l ., 20.2.2, and 20.2.3.) C - 23.22 The graded relief to be provided can be as follows: - (i) Rs.1,500 per month for category (i); - D - (ii) Rs.1,250 per month~for category (ii); - (iii) Rs.1,000 per month for category (iii); and - (iv) Rs.750 per month for category (v). [Paragraph 20.2.4.)" E The learned counsel for the Union of India submitted that the recommendations of the Sathyam Committee have been implemented and nothing further survives. The learned counsel appearing for the Union of India further pointed out that various sick mills were declared as sick under the SICA and proceedings before the Board of Industrial and Financial ~ Reconstruction (hereinafter referred to as 'BIFR') for rehabilitation of the concerned mills are pending. In fact, it appears that the BIFR has already formulated and sanctioned schemes in relation to some of the sick mills and the sanctioned schemes are being implemented. In view of this, the submission is that any financial burden placed on the management by G virtue of any financial relief granted to the workers at this stage would upset the rehabilitation scheme. Further financial burden which is not under consideration of the rehabilitation package cannot be foisted on the mills. Such a burden would result in, the entire scheme falling through. For this reason it is contended that this Court should not grant any relief H 732 SUPREME COURT REPORTS [2003) SUPP. 4 S.C.R. A to the workers. > The plea of discrimination in the matter of revision of pay scales between staff working in the corporate offices/headquarters and the staff working in the Mills is sought to be met by contending that office staff B is governed by the CDA pattern while Mills staff is governed by the IDA pattern. On the other hand, the argument on behalf of the staff/sub staff of the Mills is that great injustice has been done to the workers working in the Mills. While their counterparts working in the corporate offices have C been getting pay revisions in nonnal course as and when it is allowed to other Government servants, the staff working in the mills has been deprived of the said benefit. As a result of this, It is submitted that during the last two decades while the cost of living has gone up several times the salary and allowances of the workers working in the Mills have remained D constant. The emphasis on behalf of the workers has been that there is equality and parity in the work and working conditions of the workers of the corporate offices and the workers working in the Mills. Therefore, it is a case for equal pay. On this aspect however, as noticed earlier, the National Industrial Tribunal found against staff of the Mills. The finding E of the Tribunal was endorsed by the Sathyam Committee. In the face of the findings of the two fact finding bodies we find ourselves unable to take a different view on this issue. Neither necessary facts have been placed before us nor we would like to go into such a question of fact. We have no reason to differ with the finding of fact on this issue arrived at by the two independent bodies. So far as the claim of the staff based on the F principle of equal pay for equal work is concerned, it is therefore, not tenable. When the work is not equal, the question of equal pay does not arise. But we cannot ignore the fact that the staff/sub staff working in· the Mills has unfortunately received a step motherly treatment. They have not had a pay revision for years. The litigation has been pending for more than G a decade. They have been told that the matter is subjudice. The Sathyam Committee noticed this sorry plight of the workers. The Committee gave some ad hoc relief to the workers. But that is not enough. The Sathyam Committee noticed disparity in the pay scales of the two categories of workers which was 159% in 1987 and had risen to 642% in the year 2000. H. This is highly unjust and unfair. So far as the staff working in the mills CHAIRMAN-CUM-MANAGING DIRECTOR N.T.C. LTD. _v._ N.T.C.(WBAB & 0) LTD. EMPLOYEES UNION (ARUN KUMAR. J.J 733 is concerned we are told that all the mills are incurring losses and that does A not justify any increase in the pay package of the workers. But the staff working in the corporate offices of the Mills is also staff of the parent body. If the mill is incurring losses the impact has to be on everyone connected with the mill, in whatever capacity. You cannot have double standards. When you give ·revised pay scales to office staff is there no financial B burden? In view of the fact that the nature of duties of the staff in the two categories has been found to be not at par, parity in pay scales may not be possible. Yet there can be no case for total denial of revision of pay C to the staff/sub staff working in the mills. Discrimination between the two categories of staff cannot be justified on the basis of applicability of the CDA pattern and the IDA pattern to the respective categories of staff. The IDA pattern cannot be taken to debar any revision of pay scales. The Central Government has to act as a model D employer and such specious pleas on its part are highly improper and unjustified. In our view, a case for relief to the staff/sub staff working in the Mills is definitely made out. The workers deserve some relief though not parity E of pay scales with staff/sub-staff working in corporate offices, but certainly on account of revision of pay scales/increase of D.A. or emoluments from time to time as and when fell due during period of nearly three decades since when, no revision of their pay scale has been made. _..1·_ Relief to what extent is the next question? Nothing has been placed before us nor has been brought to our notice which may enable us to spell out the extent of relief. Even on behalf of the workers the emphasis has been on the fact that they are entitled to revision of pay scales as in the case of staff in the headquarters or corporate offices. Nothing more has been urged. Even otherwise we feel we are ill-equipped to work out the extent of relief which can be granted to the workers in the mills. Therefore, we direct the Central Government to take. appropriate steps which if so required may include appointment of an expert to work out the extent of relief which ought to be granted to the workers in the mills. Some considera.tion may be had about the financial constraints, if any, but it 734 SUPREME COURT REPORTS [2003] SUPP. 4 S.C.R. A cannot be to the extent of virtual denial of any benefit. Before taking a final decision in the matter, an opportunity of hearing be allowed to the management as well as to the' workers to enable them to place their respective stands before the decision making authority. The decision should be taken within four months from the date of this judgment and the B same should be implemented within two months thereafter. > The learned counsel for the Union of India relied on a recent judgment of this Court in _A.K. Bindal and Another_ v. _Union of India,_ - (2003] 5 SCC 163 in support of his contention that pay revision should > not be allowed. This·was a case of public sector company employees C seeking revision of their pay scales. It was held that employees could not claim such a right and such additional financial burden could not be placed on the Government in the absence of material placed before Court justifying the same. This case pertains to public sector undertaking namely Fertilizer Corporation of India. This case is not attracted in the facts of D the.present case. First, here the Government has a statutory liability for > the wages, salaries and dues of the workers. Second, pay revision was being allowed in case of one category of workers within the same > organisation, while it was being denied to another category of workers, giving rise to discrimination. Therefore, _Bindal 's_ case has no relevance so E far as the present case is -concerned. _'1_ So far as the argument regarding no relief being admissible to the workers in the Mills in view of rehabilitation schemes being worked out before the BIFR, we have to note that the proceedings have been pending since 1993, i.e. for more than ten years. The management was all along F fully aware of the demand of the workers of the Mills in this behalf. Their cases have been pending in courts since much before the rehabilitation schemes were conceived of. How long shall the concerned workers be continued to be denied their legitimate claims? In-the various deliberations with the workers it has been noted that rehabilitation schemes. are G independent of any orders that may be passed by this Court. Therefore, pendency of the rehabilitation schemes before the BIFR is not a sufficient ground for us to deny relief to the staff/sub staff working in the Mills. As per the provisions of Section 5 (2) (c) of the Sick Textile Undertakings (Nationalisation) Act, 1974, the wages, salaries and other dues of the H employees of the sick textile undertakings after the takeover of their CHAIRMAN-OIM·MANAGING DIRECTOR N.T.C. LTD."· N.T.C.(WBAB & 0) LTD. EMPLOYEES UNION [ARUN KUMAR. J.) 73 _5_ managements by the Central Government are the responsibility of the Central Government. The Central Government has failed to discharge its responsibility for all these years by raising such specious pleas. The Central Government has to discharge its responsibility _de hors_ the BIFR schemes. The argument therefore, is rejected. The appeal as well as the various writ petitions and transfer petitions are disposed of in above terms. B.S. Matters disposed of.
End of Judgment Record
Browse All Supreme Court of India (2003) Decisions
2003-09-22

State of Punjab v. Pohla Singh and Anr.

This is a Supreme Court of India decision (September 22, 2003) arising from Criminal Appeal No. 901 of 1996, where the State of Punjab challenges acquittal by the Punjab and Haryana High Court of two respondents for offences under Section 302 read with Section 34 IPC. The trial court had convicted Pohla Singh and Balkaur Singh for homicidal death of Mandip Singh around 5.30 a.m. on 11 June 1991; the other two accused were given the benefit of doubt. The High Court acquitted the two respondents on the ground of delay in lodging the FIR and questioned the time of occurrence, treating these as improbable factors that undermined the prosecution case. The State contends that there is no embargo on appellate review of acquittals and that the High Court’s reasoning rests on surmises and conjectures, ignoring the eye-witnesses’ detailed testimony and the trial court’s careful evaluation. The Supreme Court agrees to re-appreciate admissible evidence to prevent miscarriage of justice, noting that unexplained delay, standing alone, is the relevant factor, and that the prosecution need not answer every hypothetical question. It faulted the High Court’s approach, upheld the credibility of witnesses, reversed the acquittal, and restored the trial court’s verdict, directing the respondents to serve their sentences.

2003-05-01

Parwati Bai v. Radhika

This Supreme Court decision concerns eviction of a sub-tenant from municipal non-residential premises in Khargaon, Madhya Pradesh. The appellant (Parwati Bai) had leased the premises from the Municipal Council and sub-let to the respondent (Radhika). The ownership of the premises vested in the municipality, and the landlord sought eviction on the ground of non-payment of rent and need for self-occupation under the Transfer of Property Act, while contending that the Madhya Pradesh Accommodation Control Act, 1961 should not apply since the property is owned by a local authority used for non-residential purposes. The Trial Court and the First Appellate Court, and the High Court, held that the accommodation-control Act applied and dismissed the eviction suit for lack of proven grounds under Section 12. The Supreme Court held that the premises, being owned by a local authority, are immune from the Act itself, and between the landlord (appellant) and sub-tenant (respondent), the landlord-tenant relationship arises with the municipality as the landlord. The key issue is whether tenancy was terminated validly under Section 106 of the Transfer of Property Act; there is no infirmity in the notice. Consequently, the appeal is allowed: the suit for eviction is decreed, the respondent to vacate within six months (with undertaking), rent arrears to be determined by the Executing Court, and no order as to costs. The decision aligns with existing rulings on premiss-based immunity and the applicability of transfer-only remedies.

2003-03-31

T. Lakshmipathi v. P. Nithyananda Reddy

This Supreme Court judgment deals with an eviction challenge under the Andhra Pradesh Buildings (Lease, Rent and Eviction) Control Act, 1960, over a property in Chittoor whose ownership status arose from a partition among co-owners. Respondent No. 1, P. Nithyananda Reddy, remained a co-owner and landlord after partition, while several co-owners sold their interests. Tenants of the property temporarily yielded possession to transferees (appellants Nos. 3–5) and later to appellants Nos. 1–2 through sale deeds; eviction petitions were filed on grounds of bona fide need and rent arrears. The Rent Controller decreed eviction, confirmed by the Appellate Authority and High Court. The central issue was whether eviction could proceed when tenancy rights persisted despite transfers, and whether the doctrine of merger could terminate the tenancy. The Court held that merger requires complete coalescence of the lessee’s and lessor’s interests in the whole property at the same time in one person; because the appellants acquired only a portion of the co-owners’ interests, there was no merger, and tenancy rights remained. Demolition of the superstructure by tenants did not destroy the tenancy since the land continued. The judgment relies on several precedents concerning co-ownership, merger, and estoppel, reinforcing that partial acquisitions do not extinguish tenancy. Consequently, the appeal was dismissed and the eviction decree upheld with costs.

2003-11-17

Nair Service Society v. District Officer, Kerala Public Service Commission and Ors.

Nair Service Society (NSS) challenged a Kerala High Court order directing the Kerala Public Service Commission (KPSC) to advise candidates from the Muslim supplementary list against not-joining-duty vacancies (NJD) in the recruitment for Sub-Engineers for the Kerala State Electricity Board (KSEB). The case turns on the Kerala State and Subordinate Service Rules, 1958, particularly Rules 14–17, which provide a rotating chain of appointments between open competition (merit) and reserved categories (SC/ST/OBC) with a 50% aggregate ceiling for reservation in any recruitment year. KPSC had prepared a main rank list of 177 and a supplementary list of 62 to satisfy reservation requirements. After the main list exhausted, KPSC advised Muslims from the supplementary list for NJD vacancies, prompting NSS to file petitions. The High Court and Division Bench had held that the supplementary list could continue to operate, even after the main list expired, to fill NJD vacancies, thereby potentially breaching the 50% ceiling. The Supreme Court held that the supplementary list has no survival once the main list is exhausted and that advising from it would violate the 50:50 rule, as envisaged by Article 16(4) and related provisions. Nevertheless, appointments already made pursuant to the impugned judgment were not to be disturbed. The appeals were disposed of with no costs.