Board of Control for Cricket in India v. Kochi Cricket Pvt. Ltd. and Ors.
Case Synopsis & Summary
The batch of Civil Appeals before the Supreme Court addresses a pivotal question of interpreting Section 26 of the Arbitration and Conciliation (Amendment) Act, 2015. The central issue is whether Section 36, as amended, must be read prospectively and applied to arbitral proceedings commenced after the Act’s date, and to related court proceedings, or whether its pre-amendment form continues to govern challenges filed prior to the amendment. The Court treats Section 26 as a bifurcated provision with two distinct parts separated by “but.” The first part states that nothing in the Act shall apply to arbitral proceedings commenced in accordance with the principal Act before the commencement of this Act, unless the parties agree otherwise. The second part states that the Act shall apply to arbitral proceedings commenced on or after the date of commencement of the Act, and to court proceedings in relation to such arbitral proceedings. The judgment traces the legislative history, including the Law Commission’s 246th Report, debates, and the transitional provisions, notably Section 85A and Section 27 (repeal and savings). It distinguishes earlier line of authority (Saw Pipes/Western Geco) and narrows the scope of retroactivity, concluding that the Amendment Act operates prospectively. The batch of appeals is dismissed, with enforcement and orderly transition explained.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- R.F. Nariman
- Navin Sinha
- Judgment Date
- 2018-03-15
- Court Decision / Holding
- The present batch of appeals is dismissed.
- Final Disposition
- Dismissed
Parties to the Case
Appellants / Petitioners
- Board of Control for Cricket in India
Respondents
- Kochi Cricket Pvt. Ltd. and Ors
Legal Representation & Advocates
Counsels for Petitioners
- • C. A. Sundaram
- • K. V. Viswanathan
- • Tushar Mehta
- • Arvind Datar
- • P. Chidambaram
- • Kapil Sibal
- • A. M. Singhvi
- • Nakul Dewan (adv.)
Counsels for Respondents
- • Neeraj Kishan Kaul
- • P. Chidambaram
- • Kapil Sibal
- • A. M. Singhvi
- • Nakul Dewan (adv.)
- • Anirudh Krishnan (adv.)
Provisions of Law Cited
Legal Doctrines & Maxims
- Vested rights doctrine: procedural rights do not vest; substantive rights may vest; see Hitendra Vishnu Thakur v State of Maharashtra (1994) 4 SCC 602
- Purposive interpretation and independent construction of new statutes; reference to UNCITRAL Model Law and Thyssen Stahlunion v. Steel Authority of India (1999) 9 SCC 334
- The expansive meaning of the phrase 'in relation to' versus the narrower 'to' in saving provisions (Thyssen)
- Saving and repeal principles: Section 6 of the General Clauses Act applies unless a contrary intention appears; two-limb bifurcation of saving provisions; see Transport and Dock Workers’ Union v. New Dholera Steamships Ltd. (1967) 1 LLJ 434; Kalawati Devi Harlalka v. CIT (1967) 3 SCR 833
- Enforcement vs execution distinction in the 1996 Act: Section 36 as enforcement of an arbitral award as a decree under CPC
- Two-limb construction of Section 26: the 'but' as separator indicating distinct regimes for arbitral proceedings and related court proceedings
- Importance of transitional provisions (85A) clarifying prospectivity for pending matters and pending arbitrations
Submissions & Arguments
Contentions of Appellants / Petitioners
The applicants urged that Section 26 of the Amendment Act consists of two distinct parts: the first saves old arbitral proceedings that commenced under the 1996 Act before the Amendment Act, unless the parties agree otherwise; the second makes the Amendment Act applicable to arbitral proceedings commenced on or after the date of commencement, and to court proceedings in relation to such arbitral proceedings. They argued that this bifurcation preserves vested rights and that the General Clauses Act’s Section 6 applies only where no contrary intention is evident. They contended that while the amendments are prospective, they do not impermissibly disrupt existing rights unless the parties agree; they urged a literal and purposive reading consistent with the Law Commission’s report (246th) and the scope of Section 85A (transitory provisions). They argued against automatic retroactive application to pending Section 34 petitions and emphasized the broader object of reducing court interference in arbitrations.
Contentions of Respondents
The respondents contended that Section 26 should be read as a comprehensive provision: the second limb should apply to derive a uniform regime for both arbitral and related court proceedings arising after the Act’s date, including those arising from arbitrations begun before the date if tied to later proceedings. They urged that the Amendment Act’s objective to expedite enforcement and reduce court interference supports prospective operation, and that it abrogates earlier jurisprudence (Saw Pipes/Western Geco) and the old regime’s concept of automatic stay. They argued that the word 'in relation to' adequately covers court proceedings linked to arbitral actions, and that vested rights should be considered with caution, as procedural rights generally do not vest. They relied on purposive interpretation and the Law Commission’s report to argue that pending matters should not be governed by the old regime if they relate to post-enactment arbitral proceedings.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (18)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Thyssen Stahlunion v. Steel Authority of India | (1999) 9 SCC 334 | Positive | Used to guide interpretation of Section 26, especially the distinction between 'to' and 'in relation to' and the purposive approach to new Acts. |
| N.S. Nayak & Sons v. State of Goa | (2003) 6 SCC 56 | Positive | Cited in context of vested rights and saving provisions; supports interpretation that rights may be affected under new law. |
| Milkfood Ltd. v GMC Ice Cream Pvt. Ltd. | (2004) 7 SCC 288 | Distinguished | Milkfood’s conclusion about retroactivity in the related context is distinguished from the present Section 26 interpretation. |
| Garikapati Veeraya v. N. Subbiah Chaudhry | (1957) SCR 488 | Positive | Cited for the doctrine on vested rights and the effects of repeal/saving provisions. |
| National Aluminium Co. Ltd. v. Pressteel & Fabrications (P) Ltd. | (2004) 1 SCC 540 | Positive | Cited regarding expectations of modifications to Section 36 and saving provisions. |
| ONGC v. Saw Pipes Ltd. | (2003) 5 SCC 705 | Overruled | Decision relied upon to be superseded by the amendments enacted in 2015. |
| ONGC Ltd. v. Western Geco International Ltd. | (2014) 9 SCC 263 | Overruled | Similarly superseded by the 2015 amendments in the context of grounds of challenge to awards. |
| Transport and Dock Workers' Union & Ors. v. New Dholera Steamship Ltd., Bombay & Ors. | (1967) 1 LLJ 434 | Positive | Supports the principle that saving clauses operate unless a contrary intention appears. |
| Kalawati Devi Harlalka v. CIT | (1967) 3 SCR 833 | Positive | Cited for saving and retroactivity principles in repeal-and-savings contexts. |
| Lalji Raja and Sons v. Hansraj Nathuram | (1971) 1 SCC 721 | Positive | Cited regarding enforcement and execution of decrees; informs whether rights are vested. |
| Satish Kumar v. Surinder Kumar | (1969) 2 SCR 244 | Positive | Cited to discuss nature and vitality of arbitral awards during enforcement. |
| R. Rajagopal Reddy v. Padmini Chandrasekharan | (1995) 2 SCC 630 | Positive | Cited for clarificatory amendments and retroactivity concepts. |
| Fuerst Day Lawson Ltd. v. Jindal Exports Ltd. | (2001) 6 SCC 356 | Positive | Cited in discussions on retroactivity and enforcement principles. |
| Sedco Forex International Drill. Inc. v. CIT | (2005) 12 SCC 717 | Positive | Cited for interpretation and impact of amendments on proceedings. |
| Hameed Joharan v. Abdul Salam | (2001) 7 SCC 573 | Positive | Cited to discuss circumstances where execution/enforcement contexts affect interpretation. |
| Renusagar Power Plant Co. Ltd. v. General Electric Co. | (1994) Supp (1) SCC 644 | Positive | Cited as a foundational authority for the scope of grounds under the Act and the evolution of enforcement. |
| Thyssen (supra) | (supra) | Positive | Used extensively to analyze the structure of Section 26 and to contrast limb interpretations. |
| Nitya Ranjan Jena v. Tata Capital Financial Services Ltd. | (2017) SCCOnline Cal 9388 | Mentioned Only | Cited among High Court decisions as part of the policy discussion on applicability of amendments. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Board of Control for Cricket in India v. Kochi Cricket Pvt. Ltd. and Ors.
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.