High Court of KeralaKerala High Court · 2009Single JudgeWrit Petition allowed; Exts.P19, P20 and P20(a)...

Binani Zinc Limited v State of Kerala and Ors

Case / Petition Number:
WP(C).No.19925 of 2005(V)
Neutral Citation:/

Case Synopsis & Summary

This writ petition challenges penalties levied by the Kerala State Electricity Board (KSEB) for alleged unauthorised load following the installation of a 40 KA ×120 V rectifier unit in April 2003 at Binani Zinc Limited’s plant, an Extra High Tension (EHT) consumer with contract demand of 18,000 KVA. The petitioner asserts that the rectifier addition increased connected load but did not exceed the contract load, and that sanction from the Chief Electrical Inspector under Rule 63 of the Indian Electricity Rules and Ext.P5/Ext.P17 Board orders were obtained; accordingly, the penalty under Regulation 42(d) (as amended on 18.9.2002) is impermissible or misapplied. The Board contends that the installation increased the connected load and violated Regulation 14(b) of the contract, justifying misuse of energy under Regulation 42(d) and the amended penalties. The petition investigates definitions of consumer, connected load and contracted load, the role of sanction under Rule 63, and the interaction of Regulation 42(d) with the Supply Code, Rules and statutes. The Court analyses these provisions, including the 2002 amendment to 42(d), and notes ongoing debates about whether 42(d) is inconsistent with the Electricity Act 2003's Section 126. Ultimately, the court allows the writ petition, quashes Exts.P19, P20 and P20(a) orders, and directs the Appellate Authority to decide afresh in accordance with law within three months, with a hearing, also directing consideration of Ext.P15 (regularisation) under due process.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • K.M.Joseph
Judgment Date
2009-12-21
Court Decision / Holding
The writ petition is allowed; Exts.P19, P20 and P20(a) series are quashed. The Appellate Authority is directed to decide afresh in accordance with law, after hearing the petitioner, within three months from receipt of a copy of the judgment, and to take a decision on Ext.P15 (regularisation) in accordance with law.
Final Disposition
Writ Petition allowed; Exts.P19, P20 and P20(a) series quashed; Appellate Authority to decide afresh in accordance with law with hearing within three months; consider Ext.P15 for regularisation as per law.

Parties to the Case

Appellants / Petitioners

  • Binani Zinc Limited

Respondents

  • State of Kerala
  • Kerala State Electricity Board (KSEB)
  • The Chairman, KSEB
  • Special Officer (Revenue), KSEB
  • Dy. Chief Engineer (APTS), KSEB
  • Executive Engineer, Transmission South, KSEB

Legal Representation & Advocates

Counsels for Petitioners

  • • S. Ganesh, Senior Counsel
  • • S. Joseph Markose, Senior Advocate
  • • S. Joseph Kodianthara
  • • S. Mathews K. Uthuppachan

Counsels for Respondents

  • • Bejoy Chandran, Government Pleader
  • • C. K. Karunakaran, Senior Counsel for KSEB (R2 to R6)

Provisions of Law Cited

Electricity (Supply) Act, 1948 (Regulations made under Section 79(j))Indian Electricity Rules, 1956 (Rule 63, as amended)Electricity Act, 1910 (Section 39 on theft and related provisions)Electricity Act, 2003 (Section 126(5), 126(6))Electricity Supply Code, 2005Conditions of Supply of Electrical Energy Regulations (Regulations 11, 24, 42, and 14(b))Regulation 42(d) (misuse of energy) (amended 18.9.2002)Regulation 24 (Extensions/Alterations)Regulation 11 (Approval of Installation)Regulation 3, Regulation 5, Regulation 6Regulation 33, Regulation 37Rule 63(3) of Indian Electricity Rules, 1956Section 24 of the Electricity Act read with Section 32(C) of the Conditions of Supply of Electrical EnergyElectricity Supply Code, 2005 (definitions of consumer, connected load, contract load)

Legal Doctrines & Maxims

  • Contemporanea expositio (interpretation of contemporaneous statutory provisions)
  • Mens rea is not always essential for liability under penal or quasi-penal provisions; strict liability principles may apply (cited authorities: Hindustan Steel Ltd. v. State of Orissa; Union of India v. Dharamendra Textile Processors; R. S. Joshy v. Ajit Mills)
  • Penal provisions should be construed with liberal, remedial intent in mind when there is ambiguity or in the public interest (Krishi Utpadan Mandi Samiti v. Pilibhit Pantnagar Beej Ltd)

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends that Regulation 42(d) is penal and must be narrowly construed; as an EHT consumer, it did not exceed its contract load 18,000 KVA even after installing the rectifier, and sanction from the Electrical Inspector under Rule 63 existed; amendment of 18.9.2002 clarifies that penalty for unauthorised load pertains to unauthorised connected load for HT/EHT consumers, not to mere adherence to sanctioned loads; Regulation 24 (alterations) and the 2005 Supply Code also support regularisation rather than unconditional penalties; the petition filed Ext.P9, P12, P15, P16 etc. with bonafide belief that prior approvals sufficed. The petitioner also relies on Najeeb’s case to argue that connected load and contract load are to be treated in a nuanced manner and that the Board’s enforcement lacks due process; the court should interpret the penal provisions in light of the sanction from the Inspector.

Contentions of Respondents

The respondents insist that the rectifier installation increased the petitioner’s connected load, requiring sanction and compliance with Regulation 42(d) as amended; Regulation 11 requires Board approval and Rule 63(3) of the IE Rules ensures Inspector’s sanction before connection for HT/EHT consumers; the 2002 amendment clarifies that unauthorised additional load under HT/EHT is penal; the Board relied on Ext.P17 (Board Order) and Ext.P5 sanction to qualify the installation as unauthorised load and sought penalties under Regulation 42(d); Regulation 24 and 14(b) of Ext.P1 Agreement also support penal measures where alterations affect the supply system; the Board contends connected load can be treated as contract load for EHT consumers, and even with sanction the penalty is justified to safeguard the grid; the approach remains within the Board’s regulatory power and statutory framework.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (11)

Case NameCitationTreatmentExplanation
KSEB v. Najeeb2005 (1) KLT 406Partly Overruled / LimitedDivision Bench held Regulation 42(d) inconsistent with Section 126(6) of the Electricity Act, 2003; the present judgment acknowledges but does not overrule that ruling, instead directing reconsideration by the Appellate Authority.
Hindustan Steel Ltd. v. State of Orissa1969 (2) SCC 627PositiveCited to support the proposition that penalties under penal statutes may be imposed without mens rea; quasi-criminal nature of statutory penalties.
State of Madhya Pradesh v. Bharat Heavy Electricals1997 7 SCC 1PositiveCited for the discretionary nature of penalties and the need to consider circumstances before imposing penalties.
J.K. Industries Limited v. Chief Inspector of Factories and BoilersSCC p. 692 para 42PositiveCited for the principle that certain offences arise from strict liability without mens rea.
R. S. Joshy v. Ajit Mills Ltd.SCC p.110 para 19PositiveCited for the proposition that mens rea need not be proven in certain penalty provisions.
Krishi Utpadan Mandi Samiti v. Pilibhit Pantnagar Beej Ltd.2004 (1) SCC 391PositiveCited for liberal interpretation of penal provisions when the statute is ambiguous; beneficent construction.
Union of India v. Dharamendra Textile Processors2008 (231) ELT 3(SC)PositiveCited to support the view that mens rea is not always essential for penal liability.
Power Crisis in NCT of Delhi v. U.O.I. & Ors.2004 AIR SCW 5917Mentioned OnlyCited in context of regulatory implementation and remedial directions but not as a binding ratio for the present case.
London and North Eastern Rly. Co. v. Beriman—Mentioned OnlyCited for general principles on construction of penal provisions; not a central ratio in the decision.
Tuck & Sons v. Priest—Mentioned OnlyCited for general principle on interpreting penal statutes.
Apex Court in Hindustan Steel Ltd. v. The State of OrissaAIR 1970 SC 253PositiveAdditional confirmation of strict liability principles in statutory penalties.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•12,726 words•~58 min read

In The Court Record

Binani Zinc Limited v State of Kerala and Ors

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE K.M.JOSEPH MONDAY, THE 21ST DECEMBER 2009 / 30TH AGRAHAYANA 1931 WP(C).No. 19925 of 2005(V) -------------------------- PETITIONER(S): --------------------- BINANI ZINC LIMITED, BINANIPURAM, ERNAKULAM DISTRICT, REPRESENTED BY GEORGE THOMAS, DIRECTOR. BY SHRI S. GANESH, SENIOR COUNSEL. BY ADV. SRI.JOSEPH MARKOSE, SENIOR ADVOCATE SRI.JOSEPH KODIANTHARA SRI.MATHEWS K.. UTHUPPACHAN RESPONDENT(S): ------------------------- 1. STATE OF KERALA, REPRESENTED BY SECRETARY TO GOVERNMENT, POWER B DEPARTMENT, SECRETARIAT, THIRUVANANTHAPURAM. 2. KERALA STATE ELECTRICITY BOARD, VYDYUTHIBHAVANAM, PATTOM PALACE P.O., THIRUVANANTHAPURAM REPRESENTED BY ITS SECRETARY. 3. THE CHAIRMAN, KERALA STATE ELECTRICITY BOARD, VYDYUTHIBHAVANAM, PATTOM PALACE P.O., THIRUVANANTHAPURAM. 4. SPECIAL OFFICER (REVENUE), KERALA STATE ELECTRICITY BOARD, VYDYUTHIBHAVANAM, PATTOM PALACE, P.O.THIRUVANANTHAPURAM. 5. DY. CHIEF ENGINEER (APTS), KERALA STATE ELECTRICITY BOARD, VYDYUTHIBHAVANAM, PATTOM PALACE P O., THIRUVANANTHAPURAM. ## W.P.(C).NO.19925 OF 2005 V 6. EXECUTIVE ENGINEER, TRANSMISSION SOUTH, KERALA STATE ELECTRICITY BOARD, KALAMASSERY. R1 BY GOVERNMENT PLEADER SHRI BEJOY CHANDRAN. BY SRI.C.K.KARUNAKARAN, SC FOR KSEB FOR R2 TO 6 THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 15.07.2009, THE COURT 21/12/2009 DELIVERED THE FOLLOWING: ## APPENDIX IN W.P.(C).NO.19925 OF 2005 PETITIONER'S EXHIBITS: EXT.P1TRUE COPY OF THE AGREEMENT NO.03/93-94 DATED 22.11.1993 BETWEEN PETITIONER AND KERALA STATE ELECTRICITY BOARD. EXT.P2TRUE COPY OF THE COMMUNICATION FROM CHIEF ELECTRICAL INSPECTOR NO.B4-25177/93/C E 1 DATED 9.12.1993 TO PETITIONER REGARDING INSTALLATION OF 20 MVA TRANSFORMERS. EXT.P3TRUE COPY OF THE COMMUNICATION FROM CHIEF ENGINEER (TRANSMISSION) TO DIRECTOR, BINANI ZINC NO.COM.1/BINANI ZINC/EHT/1578 DT. 27.1.1994 REGARDING ALTERATION OF THE EXISTING 110 KV SWITCH YARD AND SUB STATION OF BINANI ZINC LTD. EXT.P4TRUE COPY OF THE ORDER NO.B4-25177/93/CEI DATED 30.7.1994 REGARDING UPGRADATION OF 110 KV SWITCH GEAR AND SUBSTATION. EXT.P5TRUE COPY OF THE ORDER OF CHIEF ELECTRICAL INSPECTOR BEARING NO.B31673/2003/CEI DATED 4.7.2003 REGARDING INSTALLATION OF RECTIFIER PLANT. EXT.P6TRUE COPY OF THE COMMUNICATION FROM ACCOUNTS OFFICER ISSUING PENAL BILL DT. 31.5.2004 ALONG WITH THE PENAL BILL. EXT.P7TRUE COPY OF THE ORDER PASSED BY THE 6TH RESPONDENT IN DP2 IN THE CASE OF MATA AMRITANANDAMAYI MATH DT. 12.8.2003. EXT.P8TRUE COPY OF THE COMMUNICATION FROM KERALA STATE ELECTRICITY REGULATORY COMMISSION DT. 27.5.2004 TO THE CHAIRMAN OF KERALA STATE ELECTRICITY BOARD. EXT.P9TRUE COPY OF THE COMMUNICATION DT. 10.6.2004 FROM PETITIONER TO ACCOUNTS OFFICER REGARDING EXHIBIT P6. EXT.P9(a) TRUE COPY OF THE NOTICE DATD 10.6.2004 ISSUED BY THE DEPUTY CHIEF ENGINEER, TRANSMISSION CIRCLE, KALAMASSERY. EXT.P9(b) TRUE COPY OF THE REPLY DATED 16.6.2004 ISSUED BY PETITIONER. EXT.P9(c) TRUE COPY OF THE REPLY DATED 18.6.2004 ISSUED BY THE PETITIONER. EXT.P10 TRUE COPY OF THE PETITION SUBMITTED BY THE PETITIONER BEFORE THE KERALA STATE ELECTRICITY REGULATORY COMMISSION DT. 16.6.2004. EXT.P11 TRUE COPY OF THE REPRESENTATION SUBMITTED TO CHAIRMAN OF THE BOARD DT. 22.6.2004 ALONG WITH ANNEXURES 1 AND III. EXT.P12 TRUE COPY OF THE COMMUNICATION DT. 23.7.2004 FROM ACCOUNTS OFFICER TO BINANI ZINC LTD. EXT.P13 TRUE COPY OF THE JUDGMENT OF THIS HONOURABLE COURT DATED 25.8.2004 IN W.P.(C).22400/2004. ## W.P.(C).NO.19925/05 V EXT.P14 TRUE COPY OF THE APPEAL FILED BEFORE DY. CHIEF ENGINEER ON 1.9.2004. EXT.P15 TRUE COPY OF THE REPRESENTATION FILED BEFORE EXECUTIVE ENGINEER ON 19.10.2004. EXT.P16 TRUE COPY OF THE ELECTRICITY SUPPLY CODE FRAMED BY THE ELECTRICITY REGULATORY COMMISSION. EXT.P17 TRUE COPY OF THE BOARD ORDER DT. 15.1.2003. EXT.P18 TRUE COPY OF THE BOARD ORDER DATED 10.9.1997. EXT.P19 TRUE COPY OF THE ORDER OF THE DY. CHIEF ENGINEER DATED 16.6.2005. EXT.P20 TRUE COPY OF THE INVOICE DT. 22.6.2005. EXT.P20(A) SERIES: TRUE COPY OF THE BILLS RAISED FROM JUNE 2004 TO JUNE 2008 BY THE 4TH RESPONDENT. EXT.P20(B) SERIES: TRUE COPY OF THE OBJECTIONS FILED BY THE PETITIONER. EXT.P21 TRUE COPY OF THE NOTIFICATION DT. 4.12.1989 ISSUED BY THE 2ND RESPONDENT ELECTRICITY BOARD. EXT.P22(A) TRUE COPY OF ORDER NO.T1-1361/80/EIE/ DT. 22.1.82 ISSUED BY THE ELECTRICAL INSPECTOR, COCHIN TO M/S. COMINCO BINANI ZINC LTD., EDAYAR AND COPY TO OTHERS. EXT.P22(B) TRUE COPY OF ORDER NO.B4-943/88/CEI. DATED 9.8.1988 ISSUED BY THE CHIEF ELECTRICAL INSPECTOR (STATUTES), TRIVANDRUM TO M/S. COMINCO BINANI ZINC LIMITED, BINANIPURAM AND COPY TO OTHERS. EXT.P22(C) TRUE COPY OF ORDER NO.B4.35672/91/CEI DATED 18.3.1992 ISSUED BY THE CHIEF ELECTRICAL INSPECTOR (STATUTES), TRIVANDRUM TO THE PETITIONER AND COPY TO OTHERS. EXT.P22(D) TRUE COPY OF ORDER NO.T1-1739/91/EIE/DT.5.6.1992 ISSUED BY THE ELECTRICAL INSPECTOR, ERNAKULAM TO M/S. COMINCO BINANI ZINC LIMITED, BINANIPURAM AND COPY TO OTHERS. EXT.P22(E) TRUE COPY OF ORDER NO.T1-6341/93/EIE/DT.28.3.1994 ISSUED BY THE ELECTRICAL INSPECTOR, ERNAKULAM TO M/S. COMINCO BINANI ZINC LIMITED, BINANIPURAM AND COPY TO OTHERS. EXT.P22(F) TRUE COPY OF ORDER NO.T1.7335/93/EIE DT. 5.4.1994 ISSUED BY THE ELECTRICAL INSPECTOR, ERNAKULAM TO THE PETITIONER AND COPY TO OTHERS. EXT.P22(G)TRUE COPY OF ORDER NO.T1-2565/94/EIE/20.9.1994 ISSUED BY THE ELECTRICAL INSPECTOR, ERNAKULAM TO THE PETITIONER AND COPY TO OTHERS. ## W.P.(C).NO.19925/05 V EXT.P22(H) TRUE COPY OF ORDER NO.T1-2565/94/EIE/DT.8.12.1994 ISSUED BY THE ELECTRICAL INSPECTOR, ERNAKULAM TO THE PETITIONER AND COPY TO OTHERS. EXT.P22(I) TRUE COPY OF ORDER NO.T1.8291/95/EIE DT. 17.10.1995 ISSUED BY THE ELECTRICAL INSPECTOR, ERNAKULAM TO THE PETITIONER AND COPY TO OTHERS. EXT.P22(J) TRUE COPY ORDER NO.31507/95/CEI DT. 30. 03.1996 ISSUED BY THE CHIEF ELECTRICAL INSPECTOR, GOVT. OF KERALA TO THE PETITIONER AND COPY TO OTHERS. EXT.P22(K) TRUE COPY OF ORDER NO.T1/8711/94/EIE DATED 13.06.1996 ISSUED BY THE ELECTRICAL INSPECTOR, ERNAKULAM TO THE PETITIONER AND COPY TO OTHERS. EXT.P22(L) TRUE COPY OF ORDER NO.T1.8711/94/EIE DATED 13.06.1996 ISSUED BY THE ELECT4RICAL INSPECTOR, ERNAKULAM TO THE PETITIONER AND COPY TO OTHERS. EXT.P22(M) TRUE COPY OF ORDER NO.T1.8992/96/EIE/DT. 24.1.1997 ISSUED BY THE ELECTRICAL INSPECTOR, ERNAKULAM TO THE PETITIONER AND COPY TO OTHERS. EXT.P22(N) TRUE COPY OF ORDER NO.B3-31507/95/CEI.DT.1.7.1997 ISSUED BY THE CHIEF ELECTRICAL INSPECTOR, TRIVANDRUM TO THE PETITIONER AND COPY TO OTHERS. EXT.P23 TRUE COPY OF ORDER OF STAY DATED 7.7.2005 PASSED BY THIS HONOURABLE COURT IN W.P.(C).NO.19925/05. EXT.P24 TRUE COPY OF JUDGMENT DATED 4.4.2008 OF THIS HONOURABLE COURT IN W.P.(C).NO.11492/2008. EXT.P24(A) TRUE COPY OF INTERIM ORDER DATED 8.4.2005 IN W.P.(C).NO.12085/2005 OF THIS HONOURABLE COURT. EXT.P24(B) TRUE COPY OF JUDGMENT DATED 25.10.2006 IN O.P.NO.17511/1998 OF THIS HONOURABLE COURT. EXT.P25 TRUE COPY OF DISCONNECTION NOTICE DATED 19.6.2008 ISSUED BY THE 4TH RESPONDENT SPECIAL OFFICER (REVENUE), KERALA STATE ELECTRICITY BOARD, TRIVANDRUM. EXT.P26 TRUE COPY OF PETITIONER'S LETTER DATED 27.6.2008 TO THE KSEB. RESPONDENTS' EXHIBITS: NIL. _**// True Copy //**_ _**PS to Judge**_ ## **K.M.JOSEPH, J.** **- - - - - - - - - - - - - - - - - - - - - - - - - WP.(C) No. 19925 of 2005 V** **- - - - - - - - - - - - - - - - - - - - - - - - - Dated this the 21st December, 2009** ## **JUDGMENT** Petitioner, inter alia, challenges Exts.P6, P9(a), P12, P19, P20 and P20(a) series in so far as they levy penalty for alleged unauthorised load and seeks a declaration that the imposition of penalty on the basis of the installation of new Rectifier in April, 2003 is illegal. 2. Petitioner is an Extra High Tension Consumer. Ext.P1 is the agreement dated 22.11.1993 between the petitioner and the Board. The contract demand is 18000 KVA. Supply is to be made on 110000 Volts. Petitioner manufactures Zinc Metal and other by-products. Ext.P1 agreement was executed in the context of enhancement of power allocation. One of the equipments in the factory is a RectifierTransformer unit. It is the case of the petitioner that till 2003 there were two Rectifier units. It is stated that Rectifier-Transformer Unit is not a power consuming unit, but a power transmitting equipment. The function of the Rectifier, it is stated, is to step down the voltage from 11 KV to 120 V and also to convert the alternating current into direct current. It was decided, it is stated, on the opinion of its Engineers that another Rectifier unit may be necessary so that the two existing units may work on their maximum capacity. Thus the petitioner installed one _**WPC.No.19925/05 V**_ _**2**_ 40 KA x 120 V high efficiency thyrister rectifier unit along with the existing rectifier units, the capacity of which is 4800 KW. It is stated that thus there are three rectifier units, but the power consumed by the three would remain the same. Acting under Rule 63 of the Indian Electricity Rules the scheme for installation of new rectifier and connected equipment was submitted before the Chief Electrical Inspector. It is stated that after approval of the same, the equipment was installed and it was preceded by the requisite sanction from the Chief Electrical Inspectorate under Rule 63(2). Ext.P5 is the sanction. Ext.P6 is the communication dated 31.5.2004 accompanied by penal bill. This is on the basis of an inspection conducted by the Anti Power Theft Squad on 15.5.2004. Ext.P6 contains a demand for Rs.1,65,57,550.48 and purports to be under Clause 42(d) of the Conditions of Supply of Electrical Energy. It is the case of the petitioner that Ext.P6 was not preceded by any notice or hearing. Petitioner submitted Ext.P9 purporting to request that Ext.P6 be withdrawn. Ext.P9(a) is a notice by which the Deputy Chief Engineer, Transmission Circle, Kalamassery issued notice to the petitioner to remove the alleged unauthorised load. Petitioner submitted Exts.P9(b) and P9(c) replies. Petitioner moved Ext.P10 before the Regulatory Commission. It also filed a representation before the Chairman. However Ext.P12 came to be issued, which is _**WPC.No.19925/05 V**_ _**3**_ purportedly issued under Section 24 of the Electricity Act read with Section 32(C) of the Conditions of Supply of Electrical Energy. Thereafter pursuant to Ext.P13 judgment rendered by this court, petitioner preferred Ext.P14 appeal before the Deputy Chief Engineer. Pending appeal, petitioner filed Ext.P15 representation requesting the Executive Engineer to take note of the installation of 4800 KW rectifier and its auxiliaries. Ext.P16 is the Supply Code of 2005. Ext.P17 is the amendment to Clause 42(b) of the Conditions of Supply of Electrical Energy. By Ext.P19, the Deputy Chief Engineer confirmed the finding that there was unauthorised additional load of 4800 KW (5647 KVA) and that it has to be penalised at 1.5 times the fixed charges for a period of six months prior to the date of inspection. Following the same, Ext.P20 bill for Rs.3,73,21,433/- came to be issued. Subsequently petitioner has also produced Ext.P20(a) series bills received from June, 2004 till June, 2008. 3. I heard Sri.S.Ganesh, learned Senior Counsel appearing on behalf of the petitioner and Sri.C.K.Karunakaran, learned Senior Counsel appearing on behalf of the respondent Board. ## **4. Contentions of the Petitioner:** (1) Regulation 42(d) is penal and it has to be strictly and narrowly construed. The benefit of doubt should go to the petitioner. _**WPC.No.19925/05 V**_ _**4**_ (2) Petitioner is an EHT consumer. It has a contract demand of 18,000 KVA. Petitioner is penalised under Ext.P6 with reference to the powers under Regulation 42(d). Even after the installation of the Rectifier in question, there is no increase in the contract demand, which is 18,000 KVA. There is no dispute regarding this aspect, it is pointed out. If that be so, it is contended that the petitioner cannot be penalized under Regulation 42(d). It is pointed out that there is no dispute that the other limb of the opening part of Regulation 42(d) is inapplicable to the petitioner. (3) It is pointed out that though there is an amendment to Regulation 42(d) on 18.9.2002, and the amendment clothes the authority with power to levy penalty at two times the unauthorised additional load, in this case it is inapplicable for the reason that in view of the sanction given by the Electrical Inspector, and having regard to the terms of Regulation 11, the additional load cannot be treated as unauthorised. (4) It is contended that by the amendment effected on 18.9.2002 even though the regulation contained definition of the word 'connected load', what is referred to is unauthorised additional load and not unauthorised connected load. He would therefore point out that having regard to the fact that petitioner had not exceeded the contract load as provided in Regulation 42(d) as it stood, it cannot be treated as an _**WPC.No.19925/05 V**_ _**5**_ unauthorised additional load and hence petitioner cannot be penalised. A perusal of Clause 14(b) of Ext.P1 agreement would also reinforce the petitioner's contention that any alteration etc is not permitted only if it exceeds the contract load, which has not happened in this case, he contends. He further points out that if support is drawn from the second limb of the first part of Clause 14(a), namely, that the load causes detriment to the interests of the Board, it would be plainly impermissible as no such case is raised against the petitioner either in the original order or even in the appellate order. An argument cannot be raised, which is not even supported by the affidavits filed in the case. It is further contended that the petitioner acted in a bonafide manner. In this context reference is made to Ext.P5 sanction obtained from the Electrical Inspector and the fact that in the past nearly 20 years, the petitioner had made several installations on the strength of the sanction obtained from the Electrical Inspector. It is the petitioner's bonafide impression, it is contended, that being a EHT consumer, all that it had to comply with was to get the sanction of the Electrical Inspector for connecting the equipment to the petitioner's system. No objection was raised in the past to the petitioner's installations based on sanction from the Electrical Inspector, it is contended. Hence for the first time that on the basis of the inspection in question petitioner is being visited with penalty. Being a _**6**_ _**WPC.No.19925/05 V**_ penalty, it is contended that, this aspect of bonafides is highly relevant. It is also contended that the petitioner had never paid the service connection charges, as contended, in the past. It is also stated that the demands raised in Ext.P20(a) series for the period from June, 2004 to June, 2008 are illegal. Regulation 42(d), it is contended, permits levy of penalty only for a period of six months and what is more, petitioner had made Ext.P15 application seeking regularisation of the connection and it is not open to visit the petitioner with continuous levy of penalty, despite the petitioner seeking regularisation. 5. Learned Senior Counsel also contended that in the Electricity Supply Code, 2005 connected load has been defined in the case of EHT consumers with reference to the contract load as it is stated that in the case of EHT consumers, the contract load will be the connected load. He would further contend that if reference is made to the explanation to Section 126(5) Clause (b) is called into play, the petitioner having obtained sanction from the Electrical Inspector, there is no unauthorised use and in view of the Division Bench judgment in **Najeeb's case** petitioner cannot be penalized. ## **6. Contentions of the respondents:** Petitioner is a consumer as defined in Regulation 1(d) of the Conditions of Supply of Electrical Energy. Connected load is defined in _**WPC.No.19925/05 V**_ _**7**_ Regulation 1(n). It is therefore pointed out that upon installation of the rectifier in question, undoubtedly there is an increase in the connected load of the petitioner. Regulation 11 provides only that in the case of EHT consumer for connecting an additional requirement, sanction from the Electrical Inspector has to be produced. This does not mean, it is contended, that the petitioner is freed from the obligation contained in Regulation 24. Learned counsel for the Board invited my attention to Form 3, which provides for the consumer's installation completion report and the test report and submitted that upon such a report being given, the officer has to verify it and it is thereafter alone it can be connected. Otherwise it would be unauthorised additional load, it is contended. He would point out that the Board has to supply electrical energy and the quantum of energy to be supplied may increase upon additional load being created. In this case, it is pointed out that the additional load is very huge as it is 4800 KW. He would submit that the Board, which is a licensee and which is to ensure the supply is entitled to safeguard its interests, which can be predicated properly only upon even EHT consumer following the procedure contemplated in Regulation 13 read with the approvals contemplated under the Conditions of Supply of Electrical Energy. He further contends that the interpretation placed by the petitioner on Regulation 42(d) is not correct. Regulation 42(d) _**WPC.No.19925/05 V**_ _**8**_ provides inter alia that misuse of energy will be penalised. He would submit that misuse of energy is not to be confined to the two cases which are specifically mentioned in Regulation 42(d). He referred to Clauses (a), (b) and (c) of Regulation 42. He contended that in this case, the case of the petitioner could be treated as a misuse of supply under Regulation 42(c). He would submit that the procedure contemplated under Rule 11 (a) read with Rule 63 of Electricity Rules must be treated as an extra burden to ensure that in the case of EHT consumers the requirements under the Electricity Rules are observed and sanction is obtained from the Electrical Inspector. But this does not mean, it is contended, that the petitioner's obligation to the Board is undermined. He also seeks to draw support from Clause 14(b) of Ext. P1 agreement. He further contends that with the amendment made on 18.9.2002 in Regulation 42(d), the matter is put beyond the pale of doubt. He submits that the unauthorised additional load referred to in the instrument dated 18.9.2002 can only be unauthorised connected load. He also referred to Regulations 33 and 37. He contended that Rectifier is a power consuming device. In this connection he referred to page 23 of the judgment in O.P.9565 of 1996 filed by the writ petitioner, wherein, in the course of the statement made by the Electrical Inspector, it is stated that rectifier is the most important part of the plant and it consumes the major share of electricity. He _**WPC.No.19925/05 V**_ _**9**_ pointed out that undoubtedly with the installation of the rectifier there is a substantial increase in the load. With respect to Section 126, it is pointed out that in the explanation clause (b) the word 'authority' is defined in the Act and it will not include the Electrical Inspector. He submitted that it may not suffice under the Regulations to merely make an application as was made vide Ext.P15. It must be followed up by setting the proper report made as in Form 3 and verified on inspection by the officer and then alone would the petitioner be freed from the obligation to pay penalty within the meaning of Regulation 42(d) as it stood amended by notification issued on 18.9.2002. He submitted that the penalty, though called a penalty, cannot be characterised as penal as having penal implications as understood in law. He would further contend that in fact under Section 126 penalty has to be imposed at a rate equal to one and half times of the tariff. But in this case penalty is levied at one and a half times of the fixed charges and that too it is only limited for a period of six months. He would submit that there cannot be any estoppel against the exercise of power under the Regulation on the score that on earlier occasions a particular practice was countenanced, namely, of the petitioner approaching the Electrical Inspector and adding to the load without following the procedure under the Conditions of Supply of Electrical Energy. He would submit that the load added is a _**WPC.No.19925/05 V**_ _**10**_ very substantial one and petitioner cannot be heard to say that they need not follow the law. 7. In reply, learned counsel for the petitioner points out that there is no reference to Regulation 42(c) in the orders. He further contended that this is a fit case where the principle of contemporanea expositio may be invoked as the stand of the Board approving sanction of the Electrical Inspector as sufficing spoke eloquently on the subject. He would submit that Ext.P5 specifically provided for energisation. No condition was incorporated therein that the petitioner must get sanction from the Board. He also pointed out that a perusal of Regulation 24 would make it clear that it cannot be made applicable to an EHT consumer like the petitioner. He further contended that having regard to the fact that specific provisions will prevail over the general, if sanction is obtained by an EHT unit from the Electrical Inspector, the case would not be covered by Regulation 24. 8. In order to appreciate the contentions of the parties, it is necessary to refer to certain provisions. Regulations made under Section 79(j) of the Electricity (Supply) Act, 1948 and other enabling provisions provide the definition of the following words,. They are extracted hereunder: _**WPC.No.19925/05 V**_ _**11**_ “1.(d) “Consumer” means the owner or occupier of the premises which are for the time being connected for supply of Electrical Energy with the Board's power system and in whose name the installation stands registered.” (n) “Connected load” means the sum total of the installed capacities of all the energy consuming devices on the consumer's premises connected to the system which can be operated simultaneously. (p) “Contracted load/Contract demand” means the maximum KVA/KW for supply of which the Board undertakes to provide a facility from time to time. (x)”High Tension/Extra High Tension Consumers” means all such consumers who obtain supply from the Board at High Voltage of Extra High Voltage as the case may be.” Regulation 3 provides as follows: ## “ **3. Application for supply of energy** Prospective consumers shall furnish the details as per the Application for Supply of Electricity in Form I annexed, obtainable from the Assistant Engineer/Asst. Executive Engineer's Office.” Regulation 5 provides for power allocation. Regulation 6 provides for permission for wiring and it reads as follows: ## “ **6. Permission for wiring** If the application is from an area where Board's distribution mains already exist and service can be effected by constructing service line alone, seven clear day's notice shall be given by the Asst. Engineer to the applicant for _**WPC.No.19925/05 V**_ _**12**_ supply or to the contractor or representative acting in his behalf for purpose of inspecting the premises and investigating the feasibility of power supply. If service can be effected by extending service line alone, the consumer will be given a written permission to start the wiring (Form 2(b) Annexed).” Regulation 11 is crucial, and it reads as follows: ## “ **11. Approval of Consumer's Installation** (a) Before any wiring or apparatus (in the case of low tension consumers) and transformers, switchgear and other electrical equipment (in the case of H.T Consumers) is connected to the system, the same shall be subjected to the inspection and approval of the Board's engineer and no connection will be made without his approval. Before any wiring or apparatus (in the case of H.T. And E.H.T. Consumers) is connected to the Board's supply, approval in writing of the Electrical Inspector should be produced under Rule 63 of I.E Rules 1956. (b) Before any wiring or apparatus in case of High rise buildings, X-ray Units and Neon signs is connected to the Board's supply, it may be verified that the required notice under “I.E.Rules 1956” has been given by the owner of the installation to the Electrical Inspector. The connection shall not be given in case the Electrical Inspector has prohibited the connection by written communication addressed to the Board's Engineer.” _**WPC.No.19925/05 V**_ _**13**_ Regulation 24 reads as follows: ## **“24.Extensions, Alterations & Renovation of Installations** Should the consumer, at any time after the supply of energy has been commenced, desire to increase the number or wattage or capacity of lights, fans or motors etc., on his premises on a temporary or permanent basis or in any way alter the position of his wiring therein, notice thereof must be sent by the consumer in writing to the Board whose representative will call and inspect the alteration and, if necessary change meters and fuses and alter the service line. For this purpose if a single phase service line is to be converted to three phase or change of size of conductor to meet increased maximum demand is necessitated, the work shall be done at the cost of consumer on deposit work basis. A test report signed by a licensed wiring contractor should also be produced by the consumer along with his application for extension and alteration. The consumer should remit the testing fee. Failure to give such notice may derange the supply system and will render the supply liable to be summarily discontinued. During such time as alterations, additions or repairs are being executed, the supply to the circuit, which is being altered, added to or repaired, must be entirely disconnected and it shall remain disconnected until the alterations, additions or repairs have been tested and passed by the Board. In the event of any unauthorised extensions, alterations or repairs resulting in any damage to the system of the Board, the consumer will have to pay the _**WPC.No.19925/05 V**_ _**14**_ Board all expenses on account of such damages also.” Regulation 33 provides for rating of installation. Regulation 37 provides for the system of supply and it provides the declared pressure of supply under normal conditions for various categories of supply. It inter alia provides that where connected load exceeds 6000 KVA, supply shall be given at EHT. Regulation 42 reads as follows: ## **“42. Misuse of Energy** (a) The consumer shall not keep connected to Board's supply system any apparatus which the Board deems to interfere with or affect supply injuriously to other consumers. (b) Consumers availing three phase supply should keep their load balanced. The maximum difference in current in any two phases should not be more that 5%. (c) The consumer shall not make such use of the supply given to him by the Board as to act prejudicially to the Board in any manner whatsoever. (d) If the consumer exceeds the contracted load without prior permission of the Board or energy supplied for a specific purpose under a particular tariff is used without the Boards knowledge and approval for a different purpose not contemplated in the contract for supply and for which higher tariff is applicable coming under misuse of energy within the meaning of the I.E. Act, 1910. Misuse of energy will be billed and three times the rate applicable to _**WPC.No.19925/05 V**_ _**15**_ the respective tariff for the previous six months from the date of detection of misuse unless there are convincing reason for adopting different periods and supply disconnected without notice. The imposition of this higher rate will not relieve the consumer from any penalties imposed by law. (e) If at any time the consumer exceeds his contracted load without prior permission of the board, the Board have the right to disconnect the supply and recover the damages caused, if any, from him on account of his exceeding the contract load.” The definition of “consumer” in the Electricity Supply Code, 2005 reads as follows: “(m) “Consumer” means any person who is supplied with electricity for his own use by a Licensee or the Government or by other person engaged in the business of supplying electricity to the public under the Act or any other law for the time being in force and includes any person whose premises are for the time being connected for the purpose of receiving electricity with the works of a Licensee, the Government or such other person, as the case may be.” Definition of “connected load” in the Electricity Supply Code is as follows: ““Connected Load” means the sum of rated capacities in terms of KW or KVA of all connected energy consuming _**16**_ _**WPC.No.19925/05 V**_ devices in the consumer's installation. For the purpose of levy of any charges or tariffs or determining connected load, plugs with no appliance connected, having 5 amps/15 amps shall be treated 60W500W respectively. If any equipment is connected to a plug point, equipment's load alone shall be considered. Load of fire protection equipment shall not be considered for assessing the connected load, if the same is connected to standby generator. _**In case of HT and EHT connections, the contract demand shall be treated as the connected load.”**_ I would also refer to the Indian Electricity Rules, 1956. Rule 63 therein reads as follows: ## “ **63. Approval by Inspector:** (1) Before making an application to the Inspector for permission to commence or recommence supply after an installation has been disconnected for one year or above at high or extra-high voltage to any person, the supplier shall ensure that the high or extra-high voltage electric supply lines or apparatus belonging to him are placed in position, properly joined and duly completed and examined. The supply of energy shall not be commenced by the supplier unless and until the Inspector is satisfied that the provisions of rules 65 to 69 (both inclusive) have been complied with and the approval in writing of the Inspector has been obtained by him: Provided that the supplier may energise the aforesaid electric supply lines or apparatus for the purpose of tests _**WPC.No.19925/05 V**_ _**17**_ specified in rule 65. (2) The owner of any high or extra-high voltage installation shall, before making application to the Inspector for approval of his installation or additions thereto, test every high or extra-high voltage circuit or additions thereto, other than an overhead line, and satisfy himself that they withstand the application of the testing voltage set out in sub-rule (1) of rule 65 and shall duly record the results of such tests and forward them to the Inspector: Provided that an Inspector may direct such owner to carry out such tests as he deems necessary or, if he thinks fit, accept the manufacturer's certified tests in respect of any particular apparatus in place of the test required by this sub-rule. (3) The owner of any high or extra-high voltage installation who makes any additions or alterations to his installation shall not connect to the supply his apparatus or electric supply line, comprising the said alterations or additions unless and until such alterations or additions have been approved in writing by the Inspector.” 9 **.** Undoubtedly petitioner is a consumer. Petitioner is an EHT consumer. The contract load, which is the same as contract demand in the case of the petitioner is 18000 KVA. There is no dispute that the petitioner has not exceeded the contract demand. It is also not in dispute that the latter limb of Regulation 42(d) , namely that energy supplied for _**WPC.No.19925/05 V**_ _**18**_ a specific purpose under a particular tariff is used without the Board's knowledge and for a different purpose not contemplated in the contract of supply and for which higher tariff is applicable coming under the misuse of energy under the Indian Electricity Act, 1910, is not applicable. The further question that is to be answered is whether the petitioner is right in contending that if neither limb of Regulation 42(d) providing for misuse are satisfied, could the petitioner be billed on the ground of that the petitioner has committed misuse of energy? 10. On the one hand learned counsel for the petitioner contends that it cannot be so done, on the other hand learned counsel for the respondents would contend that misuse of energy is to be billed at three times and Regulation 42(d) is not limited to the two contingencies specified in Regulation 42(d) and it covers also cases covered by Clauses (a), (b) and (c). In particular, he refers to clause (c) and contends that it is inconceivable that if a consumer commits violations of clauses (a), (b) and (c), it could get away scot free and not be apprehended with the scope of the words “misuse of energy”. 11. I feel that there is merit in the contention of the learned Standing Counsel appearing on behalf of the Board that the words 'misuse of energy' being billed at three times cannot be limited to the two contingencies specified in the earlier part of Clause (d). If, for instance, _**WPC.No.19925/05 V**_ _**19**_ it is found that the consumer is making use of the supply given to him by the Board prejudicial to the Board, in any manner, it would also be comprehended as a case of misuse. In such situation, it could not be said that it would be limited only to specific conditions of contingencies in clause (d). 12. The further question is whether the respondents can be permitted to refer to Clause (c). The orders impugned are passed by statutory functionaries. The orders are therefore to be justified on the reasons stated in the order. It is pointed out by the learned Senior Counsel Sri. Ganesh that no case has been put across attracting clause C of Regulation 42. It is pointed out that the system has been working for quite sometime and there has been no complaint of the system of the Board being prejudiced by the installation of the rectifier in question. He would submit that by the introduction of the new rectifier, productivity and efficiency has increased and the consumer has not breached the contract load. 13. No doubt, learned Standing Counsel would point out that when rectifier is introduced, it is a drag on the system. Admittedly, the petitioner has installed a rectifier of 40 KA X 120 V high efficiency thyrister rectifier unit. It has, admittedly, the capacity of 4800 KW. Ext.P6 is the notice issued alleging that the petitioner has connected _**WPC.No.19925/05 V**_ _**20**_ unauthorised load of 4800 KW which attributed illegal extraction of energy and violation of the terms of the Agreement, and that it is liable to be penalised under Section 42(d) of the Conditions of Supply of Electrical Energy and the Board Order dated 15.1.2003. The Board Order dated 15.1.2003 is produced as Ext.P17. There is no dispute that the petitioner has not obtained permission of the Electricity Board for connecting the Rectifier. Petitioner has obtained sanction from the Chief Electrical Inspector prior to the connection being done. Ext.P5 dated 4.7.2003 would show that in continuation of the provisional sanction, regular sanction was accorded under Rule 63(3) of the Electricity Rules. I have already referred to Section 42(d). Section 42(d) speaks of the consumer exceeding the contracted load without prior permission of the Board or energy supplied for a particular purpose under a particular tariff being used for another purpose and thereafter, it is further stated that misuse of energy will be billed at three times. In Ext.P6, reference is made to Ext.P17 order. Ext.P17 is dated 15.1.2003. It is stated that it will take effect from 18.9.2002. I have already referred to the portion dealing with high tension and extra high tension consumers. What is crucial is that it provides that unauthorised additional load shall be charged at the rate of twice the demand charges per KVA for the additional load till it is removed or regularised. The period is six _**WPC.No.19925/05 V**_ _**21**_ months, unless there is convincing reason to adopt a different rate. No penalty is charged on the energy charges. Clause (6) of Ext.P17 would show that Clause 42(d) of the Conditions will stand amended to the above extent. In the impugned proceedings, namely Ext.P6, reference is specifically made to this Order. If Ext.P17 is applicable, then the contention of the petitioner that there can be no recourse to Section 42 (d), as neither is there exceeding of contracted load without permission, nor use for a different purpose and, therefore, penalty is unjustified, may wane into insignificance. No doubt, the further question may arise whether in view of the sanction obtained under Rule 63(3) of the Rules, it can be treated as unauthorised. 14. In this context, it is necessary to refer to the Board Orders which are read in Ext.P17. The Board Order dated 20.10.1998 reads as follows: “1. Where a Low Tension Consumer exceeds the contracted load and/or connected unauthorised additional load and if the connected load had exceeded 100 KVA, unauthorised additional load shall be disconnected by the consumer within twenty-four hours of detection of unauthorised load by the Board's Officers. If he fails to disconnect the unauthorised load within the time stipulated, the power supply to the premises shall be disconnected after the expiry of 24 hours. A notice to _**WPC.No.19925/05 V**_ _**22**_ this effect shall be issued to the consumer immediately by the Board's Officer on detection of the unauthorised load. 2. The unauthorised additional load shall be charged at Low Tension tariff at three times for the fixed charge as well as the proportionate energy charge both for a period of previous six months if there are no convincing reasons to believe a different date and invoice shall be issued to pay the amount. The tariff applicable for charging the penalty shall be the Low Tension tariff that would have been applicable for the unauthorised load depending upon the purpose for which the connection was utilised. If the consumer fails to pay the bill amount, the service shall be disconnected without notice. It shall be reconnected only after payment of penalty and other regular monthly electricity charge, if any, payable and removal of the additional load by the consumer. 3. If the consumer wants to continue to reconnect additional load and if his total connected load exceeds 100 KVA, he has the option to convert the Low Tension service into High Tension for which he shall be given three months time from the date of application for this purpose. But, the penalty as in para (2) shall be payable by the consumer till conversion of the service is permitted by the competent authority. 4. In cases of Low Tension consumers whose connected load does not exceed 100 KVA, but who have exceeded the contracted load and connected unauthorised _**WPC.No.19925/05 V**_ _**23**_ additional load, the procedure suggested in paras (1) and (2) shall be applicable. The unauthorised load shall be regularised by the Assistant Executive Engineers on application from the consumer and after payment of additional security deposit. The regularisation shall be given effect to from the date of collection of additional security deposit. The Assistant Executive Engineers shall issue proceedings to this effect. Penal charges as mentioned in paras (1) to (2) shall be paid till the date of payment of additional security deposit. 5. The pending cases, if any, on similar issues, shall be disposed of in the manner indicated above. The clause 42(d) of the Conditions of Supply of Electrical Energy issued vide the B.O. read as first paper will stand amended to the above extent.” The Board Order dated 18.9.2002 brings about an amendment to Clause 42(d). It reads as follows: “(i) In the case of LT domestic consumers, the penalty for unauthorised additional load shall be Rupees 50 per KW per month or part thereof for the additional load till the said unauthorised additional load is removed or regularised as per rules. (ii) In the case of L.T. consumers other than domestic consumers, the penalty for unauthorised additional load shall be levied at the rate of twice the fixed charges per KW of additional load per month or part thereof till the said unauthorised additional load is _**WPC.No.19925/05 V**_ _**24**_ removed or regularized as per rules. (iii) In the case of HT and EHT consumers the penalty for unauthorised additional load shall be levied at the rate of twice the demand charges per KVA for the additional load till the said unauthorised additional load is removed or regularized as per rules. (iv) All other terms and expressions appearing under Clause 42(d) of the existing Regulations notified under paper (1) above stand unaltered. This amendment shall come into force from the date of this order.” 15. Thus, it may not be open to the petitioner to contend that there is no basis to levy penalty for the reason that neither is the contracted load exceeded, nor is there use for a different purpose. This is for the reason that going by the various amendments, the law as it stood as per the Conditions, was that if there is additional load, in the case of an extra high tension consumer, it is liable to be visited with a penalty as provided in Ext.P17. Apparently, reference to Clause 42(b) in Ext.P17 appears to be a case of an error. In Ext.P19, it is found that the authorised connected load of the petitioner is 24641 KW for which it submitted completion report and remitted the S.C. charges. The petitioner has a case that even then, since there is no criterion that additional load is to be calculated with reference to connected load, there cannot be a penalty. I _**WPC.No.19925/05 V**_ _**25**_ shall deal with the same. 16. The further question to be considered is whether, in view of the fact that the petitioner has obtained sanction under Rule 63(3), it is freed from the obligation to obtain sanction from the Board. A perusal of Clause 14(b) of Ext.P1 Agreement would appear to show that the petitioner has committed violation of the said provision. Of course, the case of the petitioner is that there is no contravention in so far as there is no increase in the obligation of the Board to supply electrical energy in excess of the agreed maximum demand. The agreed maximum energy is 18000 KVA. It is pointed out that even with the installation and connecting of the Rectifier in question, there is no increase in the maximum demand. It is further pointed out that there is no case that it may affect the supply system of the Board to its detriment. 17. On going through the Counter Affidavit of respondents 2 to 6, it is necessary to refer to paragraphs 4 and 5 of the Counter Affidavit which read as follows: “4. Any electrical system for consumption of energy installed by the consumer requires certain standards to be maintained as prescribed in Indian Electricity Rules, Grid Code, etc. This is for the purpose of energy efficiency and safety of the equipment, system as well as of the manpower working in the area. Therefore, a Certificate to the said effect has to be obtained from the Chief Electrical _**26**_ _**WPC.No.19925/05 V**_ Inspector or Electrical Inspector as the case may be as stipulated in the Indian Electricity Rules, 1958. Such Certificate is only to ascertain that the electrical system installed by the consumer confirms to the standards prescribed in the Electricity Rules and such other relevant standard specifications. It is not a licence or sanction to connect that system to the Board's supply mains. 5. In this regard, it may please be appreciated that the generation and consumption has to match for maintaining a sound electrical supply system. When the consumption load increases over and above the generations, the frequency of the system will be at peril. In order to safe-guard the costly equipments, a device called under frequency relays are connected to the system so that the entire system will trip if the frequency falls below the stipulated level. When one line trips and the energy flow through that line stops while the load remains the same, this will further widen the gap between the supply of energy and the load demand, leading to further fall of frequency and tripping of that line. This will be repeated for each line in phased manner, which is called cascading effect. This may also lead to tripping of the entire system by cascade effect. Therefore, increase of load beyond permissible limit will affect the system adversely.” Petitioner has filed a reply Affidavit wherein what is stated in reply to paragraph 4 of the Counter Affidavit may be, inter alia, stated as follows: The Board's interest would be affected only if the contract _**WPC.No.19925/05 V**_ _**27**_ demand is exceeded by reason of the said connection. Where there is no additional contract demand either required by the consumer or otherwise brought about by the connection itself, the Board's interest cannot be considered to be affected thereof. Installation of an additional equipment might or might not bring about additional consumption of energy which would be reflected in the meter. On account of the installation in question, it is stated, there is no additional consumption. In reply to paragraph 5 of the Counter Affidavit, it is, inter alia, stated that the observations are general and cannot be considered as having any application to the facts and circumstances of the present case. Power failures are attributed to other reasons. It is also stated that the installation of a power transforming device like Rectifier, need not result in overload as long as the consumer restricts the load with the contract load. The installation of a transformer rectifier in the instant case, has not altered the contracted load. The Board has filed an Additional Counter Affidavit reiterating what it is stated. Subsequently, the petitioner has amended the Writ Petition by incorporating a further ground that Clause 14(b) is attracted only if the installation results in drawal of power in excess of the contracted load. It is contended that it is found that there is no excess of contract load and consequently, there is no question of violation of Clause 14(b). _**WPC.No.19925/05 V**_ _**28**_ 18. I cannot ignore the case of the Board based on the second limb of Clause 14(b). In other words, if any alteration is made which may affect the supply system to the Board's detriment, it may attract Clause 14 (b). Clause 14(b) is not limited to a case of the installation leading to excess demand. In this case, I cannot also ignore regulation 24 which I have already extracted. It also contemplates alterations to an existing connection. Actually, this is a case which would attract regulation 24 also which I have already referred to. It may not be correct on the part of the petitioner to canvass that the said regulation is applicable only to low tension consumers. Any such interpretation would result in HT and EHT consumers being able to carry out extensions, alterations and renovations without the involvement of the officers of the Board. 19. The addition of the Rectifier would amount to an additional of a machinery. Admittedly, there were also two Rectifiers. It is the further admitted case that in excess of the said two existing Rectifiers, the petitioner has added another Rectifier, thus there is an addition to the extent of 4800 KW. Thus, instead of two Rectifiers, three were operating at the time of the inspection which culminated in Ext.P6 notice. The additional load is fairly huge and there is a definite case based on the second limb of Clause 14(b). Thus, I find that the Board is correct in contending that there is violation of Clause 14(b) of Ext.P1 Agreement. _**WPC.No.19925/05 V**_ _**29**_ 20. The further question which would arise is that even with the installation of the Rectifier in question and an addition of 4800 KW, whether it could be treated as a case of unauthorised load, in view of the fact that the petitioner has obtained consent under Section 63(3) of the Electricity Rules. According to petitioner, in respect of extra high tension consumers like the petitioner, the law declares that the petitioner must obtain the sanction of the Inspector under Rule 63(3) of the Electricity Rules before connecting to the supply line. The Electricity Rules have been made under the Electricity Act, 1910. It falls under Chapter VII of the Rules. Chapter VII has the following heading: “Electric Supply Lines, Systems and Apparatus for High and Extra High Voltages”. Undoubtedly, Rule 63(3) provides that the owner who makes additions or alterations to his installation shall not connect to the supply his apparatus of electric supply lines comprising the said alterations or additions unless and until the alterations or additions have been approved in writing by the Inspector. Reliance is also placed, as already noted, on Clause (11) of the Conditions of Supply. It is pointed out by the petitioner that all that Clause (11) mandates is approval in writing of the Electrical Inspector under Rule 63 of the Electricity Rules, 1956 in the case of an _**WPC.No.19925/05 V**_ _**30**_ Extra High Tension consumer. It is pointed out that the inspection and approval of the Board's Engineer is mandated in the case of Low Tension consumers and transfers switch gear and other electrical equipment in the case of High Tension consumers. It is, thus, pointed out that the approval obtained from the Electrical Inspector clearly sufficed and, therefore, the load cannot be treated as unauthorised. It is pointed out that there is inspection done as contemplated before the approval is granted by the Inspector under Rule 63. The question is posed when once a consumer gets sanction after following the procedure which entails carrying out an inspection also and stipulation of conditions, what is the need for another round of inspection and approval from the Board. Per contra, the learned senior standing counsel would reiterate that it is highly necessary in the interest of the Board which is generating and supplying electricity to the consumers, that it is made aware from time to time of the increase in load. Reference has been made in the Counter Affidavits to the technical aspects which render it necessary that an Extra High Tension consumer, in particular, keeps the licensee posted about any addition it makes to the equipments. Additions to be made to the electrical equipments may have the repercussions which are being detailed in the Counter Affidavit. It is contended that in the case of Extra High Tension consumers, having regard to the nature of the equipment _**WPC.No.19925/05 V**_ _**31**_ and the nature of supply, it was contemplated that the approval must be obtained also from another Authority, namely the Inspector under Rule 63. Apparently, the Electrical Inspectorate is concerned with safety aspects, when approval is granted. The considerations in insisting for approval under the Conditions pertained to other aspects as well, he contends. Clause 24 which I have referred to, cannot be brushed aside as inapplicable to an Extra High Tension consumer like the petitioner for the reason that the wording of the Clause would speak about increase in the number or wattage or capacity of lights, fans or motors, etc. Regulation 17B dealing with high tension consumer, speaks about the Board testing the high tension installation. It also speaks about testing of the installation before the consumer applies for safety certificate from the Electrical Inspector. It is to be noted that Regulation 11 of the Conditions of Supply of Electrical Energy Regulations actually speaks about the need to produce the approval in writing of the Electrical Inspector under Rule 63 of the Electricity Rules. It is important to notice that the requirement is that before it is connected to the Board's supply, it is indispensable in the case of HT and EHT consumers that the approval as aforesaid under the Electricity Rules from the Electrical Inspector is to be produced. Therefore, when the Regulation refers to the need to produce the approval in writing, it must be that it is to be produced _**WPC.No.19925/05 V**_ _**32**_ before somebody. It is clear that it is before the Officers of the Board concerned that such approval in writing is to be produced and it does not dispense with the requirements to be satisfied for obtaining the previous permission of the Board in accordance with law. 21. It is no doubt true that the Indian Electricity Act, 1910 and the Electricity Supply Act, 1948 have been repealed vide Section 185 of the Electricity Act, 2003. A Division Bench of this Court has, in KSEB v. Najeeb (2005 (1) KLT 406), taken the view that Regulation 42(d) is inconsistent with Section 126(6) of the Electricity Act, 2003 and the Board has no power to charge at three times as provided in Regulation 42 (d), but only at the rate of one and a half times. The Division Bench has held as follows: “18. We have therefore to examine whether Regulations 42(d) is in any inconsistent with S.126 of the Electricity Act, 2003. Under S.126, the Assessing Officer has to be designated by the State Government. As per S.126 “Assessing Officer” means an Officer of a State Government or Board or licensee, as the case may be, designated as such by the State Government. The assessing authority on the basis of an inspection or after the inspection of records maintained by any person comes to the conclusion that any person is indulging in unauthorised use of electricity, he shall provisionally _**WPC.No.19925/05 V**_ _**33**_ assess to the best of his judgment the electricity charges payable by such person or by any other person benefitted by such use. Before final order of assessment is made, he must given an opportunity to file objection and should also hear the person who is alleged to have indulged in unauthorised use of electricity. “Unauthorised use of electricity” means the usage of electricity by any artificial means, or by a means not authorised by the concerned person or authority or licensee or through a tampered meter or for the purpose other than for which the usage of electricity was authorised. So far as this case is concerned, we are of the view S.126 of the Electricity Act would squarely apply since the provisions of S.126 are more beneficial to the consumer compared to Regulation 42 even though the Assessing Officer has not been designated by the State Government. 19. In our view, the Board Officials could exercise the power of the Assessing Officer till State Government designates the Assessing Officer. Electricity is being public property, such a direction is highly necessary in public interest. Further, the consumers like the petitioner have already declared while availing of the supply that they would be bound by the Regulations of Conditions of Supply and have agreed that regulation forms an integral part of their agreement. Board Official could, therefore, follow the procedure laid down under S.126. Regulation 42(d) stipulates that misuse of energy will be billed at three times the rate applicable to the respective tariff for _**WPC.No.19925/05 V**_ _**34**_ the previous six months from the date of detection of misuse. S.126(6) stipulates that the assessment under this Section shall be made at a rate equal to one-and-half times the tariff applicable for the relevant category of services specified in sub-s.(5). S.126(5) stipulates that if the Assessing Officer reaches the conclusion that unauthorised use of electricity has taken place, it shall be presumed that such unauthorised use of electricity was continuing for a period of three months immediately preceding the date of inspection in case of domestic and agricultural services and for a period of six months immediately preceding the date of inspection for all other categories of services. Provisions of regulation 42(d) and S.126(6) to that extent is inconsistent and provision of S.126 would prevail. The State Government has also not designated the Appellate Authority so far, therefore, in an appropriate case this Court's jurisdiction under Art. 226 can be invoked. Further, S.145 of the Act states that Civil Courts have been barred from entertaining suits or proceedings in respect of matters which the assessing Officers refers to in S.126 or the Appellate authority referred to in S.127 or an adjudicating Officer appointed under the Act has to be determined. Unless authorities are designated the consumer would be left with no remedies. In this connection, reference may be made to the decision of the Apex Court in Power Crisis in NCT of Delhi v. U.O.I. & Ors., 2004 AIR SCW 5917, by which Apex Court gave certain directions to implement the _**WPC.No.19925/05 V**_ _**35**_ provisions of the Act.” 22. Petitioner has a case that the petitioner has been acting bonafide in the matter. Petitioner points out that from the past nearly two decades, upon approaching and obtaining approval from the Electrical Inspectorate, it has been making additions. It was all done bonafide under the impression that no permission is needed from the Board., it is contended. Imposition of penalty should not be done in a mechanical manner and in the facts of this case, no penalty was called for and the levy of penalty as done is clearly unjustified, counsel contends. It is further pointed out that the petitioner has also made the necessary applications for regularisation and thereafter continuing to levy penalty is clearly unjustified. It is also pointed out that after the Supply Code was enacted, at any rate, the petitioner cannot be visited with penalty for the reason that as per the Supply Code, connected load in the case of Extra High Tension consumer means the contract demand and clearly the petitioner has not exceeded the contract demand by the installation and connecting of the Rectifier. It is also contended that even if there is violation of Clause 14(b) of Ext.P1, it cannot attract Clause 42(d). 23. The further question is whether in view of the fact that the word used is “contract load” and the petitioner's contract load having not been exceeded, whether regulation 42(d) is violated. I have already _**36**_ _**WPC.No.19925/05 V**_ referred to the definition of connected load. No doubt, it is contended by the learned senior counsel that there is no connected load as such to the petitioner and what they have, is contract load. In the order dated 18.9.2002 amending regulation 42(d), in regard to a low tension consumer, there is reference to a situation where the said consumer exceeds the contract load or connected unauthorised additional load whereas in respect of extra high tension consumers, reference is made to the unauthorised additional load being disconnected. No doubt, the words “connected load” as such are not used in the order, in the context of extra high tension consumers. It is also contended that even though it is an amendment effected to regulation 42(d), it has not displaced the words referring to “the consumer exceeding the contracted load without prior permission of the Board or energy supplied for a specific purpose being used for different purpose for which higher tariff is applicable” . Petitioner would point out that as the law now stands, care has been taken to include the connected load in the agreement of the extra high tension consumer and this aspect is missing in Ext.P1 agreement. In other words, the connected load, it is pointed out, may not be relevant in the case of the petitioner going by the terms of the agreement also. Learned standing counsel would point out that the concept of “contract load” has a specific purpose. He would contend that if the contract load _**WPC.No.19925/05 V**_ _**37**_ is exceeded, Clause 15 of the agreement contemplates that when the maximum demand of any month exceeds the contract demand, the excess demand will be charged at a per centage as shown in the tariff notification which at the time of execution of the agreement was 150 per cent of the normal tariff rate. He would, therefore, point out that what was contemplated in case there is excess of contract demand, was that the consumer will have to pay at a higher rate for consumption in excess of the contract demand specified in the agreement and this itself will clearly show that what is contemplated as additional load in regulation 42(d) is the connected load. I see force in the said contention. The finding in this regard in Ext.P19, would appear to me to be correct. Admittedly, the petitioner has added an additional load of 4800 KW by way of the Rectifier. No doubt, under the Electricity Supply Code, the definition of “connected load” in respect of an extra high tension consumer treats the connected load and contract load as one and the same. The concept of connected load is already provided by the definition in the Regulations which I have already referred to. When the Rectifier in question was connected, admittedly there is an increase in the load. I would think that going by the terms of the order dated 18.9.2002, there was additional load and that the said order contemplated arriving at the additional load in the case of an EHT consumer like the petitioner, with reference to its _**WPC.No.19925/05 V**_ _**38**_ connected load. The Clause in question specifically refers to the removal of the additional load. Thus, it cannot be said that regulation 42(d) as such is not attracted. 24. Then the only question which arises is whether there is justification for imposing penalty in the facts of this case and if penalty can be imposed, what is to be the quantum ? A Division Bench of this Court in Writ Appeal No.1231 of 2003 and connected cases has held as follows: “9. Penal statutes normally operates prospectively. Statutory notification dt. 18.9.2002 was brought in by the Board so as to lessen the burden on the consumers from the penal provisions. It is a cadinal rule of construction that a statutory notification is prima facie prospective unless it is expressly or necessary implication is made to have retrospective operation. However, since the notification was brought in to lessen the burden on the consumers, notification has to be construed liberally, and the inhibition of the rule against retrospective operation may be applied with less insistence. See Corpus Juris Secundum Vol. 82. Reference may also be made to the decision of the Apex Court in Rattan Lal v. State of Punjab (AIR 1965 SC 444). But, liberal interpretation does not confer any right to the consumers to contend that the notification would operate retrospectively, especially when the notification itself says that it will come into effect from _**WPC.No.19925/05 V**_ _**39**_ the date of the order. Hence we hold that the notification dated 18.9.02 would operate prospectively though we advocate for a liberal approach depending upon the fact situation of each case. 10. Question now remains to be considered is whether the Board is justified in imposing the maximum penalty at the rate of three times fixed charge and two times proportionate current charge in the case of petitioners. Counsel for the petitioners brought to our knowledge a Board order No.291/99(pig.Com.3568/98) dated 2.2.1999 in respect of Surabhi Movies, Chalakudy wherein the Board granted considerable amount of remission when an offence of additional connected load was detected. Counsel submitted similar orders have been passed by the Board in the case of various other consumers in the State as well and therefore imposition of maximum penalty is not warranted in the case of petitioners since they had already paid the charges for the energy consumed and that due to the excess connected load, no damage has been caused to the Board installations. Petitioners also submitted that imposition of maximum penalty is confiscatory and therefore ultravires the provisions of Section 79(j) of the Electricity Supply Act. We may point out in case where there is no theft of energy or illegal abstraction of energy or cases where no damage has been caused to Board installation the imposition of maximum penalty in all cases is unwarranted, so found by the Board itself in several cases prior to 18.9.2002. The Board has _**WPC.No.19925/05 V**_ _**40**_ therefore to decide each case on its merits, after hearing the objectors. 11. Apex Court in Hindustan Steel Ltd. v. State of Orissa (1969 (2) SCC 627), held that an order imposing penalty for failure to carry out a statutory obligation is the result of a quasi-criminal proceeding and penalty will not ordinarily be imposed unless the party obliged either acted deliberately in defiance of law or acted in conscious disregard of its obligations. Penalty will not also be imposed merely it is lawful to do so. Where penalty should be imposed for failure to perform a statutory obligation is a matter of discretion of the authority to be exercised judicially and on a consideration of all the relevant circumstances. Apex Court in State of M.P. and Others v. Bharat Heavy Electricals ((1997) 7 SCC 1) interpreting penalty provisions of sections 7 (5) and 3(1) of M.P. Sathaniya Kshetra Me Mal Ke Pravesh Par Kar Adhiniyam, 1976 (52 of 1976) held that the penalty of ten times the amount of entry tax stipulated therein only the maximum amount which could be levied and the assessing authority has the discretion to levy lesser amount, depending upon the facts and circumstances of each case. 12. The Board is, therefore, directed to reconsider the petitioners' cases bearing in mind the reasons which weighed with the Board in lessening the penalty vide notification dt. 18.9.02. We are of the view in a case where imposition of penalty is disproportionately high compared to the culpability, a liberal interpretation of _**WPC.No.19925/05 V**_ _**41**_ provision is warranted. Though we have found that the amended provision would not operate retrospectively and the petitioners would not get benefit of the amended provisions as such we are of the considered view that the Board would reconsider the petitioners' request for reduction of penalty imposed since they had not indulged in theft of energy, or acted with evil intention with the knowledge that they are committing a wrong act. In the absence of any mens rea, imposition of maximum penalty has to be reconsidered.” Learned counsel for the petitioner would submit that what is involved is a statutory instrument imposing penal liability. In such circumstances, he points out that assuming that the petitioner ought to have got permission before the Rectifier was connected, having regard to the fact that for a long period of time the petitioner Company had been adding apparatus on the strength of the sanction given by the Electrical Inspector under Rule 63 of the Electricity Rules and it was being accepted and there was no action on the part of the Electricity Board, this is not certainly a fit case where any penalty is to be imposed. He relied on the decision of the Apex Court in M/s. Hindustan Steel Ltd. v. The State of Orissa (AIR 1970 SC 253). Therein, the Apex Court held as follows: “7. Under the Act, penalty may be imposed for failure to register as a dealer: Section 9(1) read with Section 25(1)(a) of the Act. But, the liability to pay _**WPC.No.19925/05 V**_ _**42**_ penalty does not arise merely upon proof of default in registering as a dealer. An Order imposing penalty for failure to carry out a statutory obligation is the result of a quasi-criminal proceeding, and penalty will not ordinarily be imposed unless the party obliged either acted deliberately in defiance of law or was guilty of conduct contumacious or dishonest, or acted in conscious disregard of its obligation. Penalty will not also be imposed merely because it is lawful to do so. Whether penalty should be imposed for failure to perform a statutory obligation, is a matter of discretion of the authority to be exercised judicially and on a consideration of all the relevant circumstances. Even if a minimum penalty is prescribed, the authority competent to impose the penalty will be justified in refusing to impose penalty, when there is a technical or venial breach of the provisions of the Act or where the breach flows from a bona fide belief that the offender is not liable to act in the manner prescribed by the statute. Those in charge of the affairs of the Company in failing to register the Company as a dealer acted in the honest and genuine belief that the Company was not a dealer. Granting that they erred, no case for imposing penalty was made out.” He has also contended that it is settled law that if there is any doubt or ambiguity whatsoever in the interpretation of a penal law, the subject should get the benefit and no penalty should be imposed. In this regard, the petitioner relied on various decisions of the Apex Court. It suffices _**WPC.No.19925/05 V**_ _**43**_ to refer to the following passage from the Judgment of the Apex Court in Krishi Utpadan Mandi samiti v. Pilibhit Pantnagar Beej Ltd. ((2004) 1 SCC 391: “58. In the case of _**London and North Eastern Rly. Co**_ . v. _**Berriman,**_ Lord Simonds quoted with approval (at All ER p.270 C-D), the following observations of Lord Esher, M.R. in the case of _**tuck & sons**_ v. _**Priester,**_ QBD at p.638: “We must be very careful in construing that section, because it imposes a penalty. If there is a reasonable interpretation which will avoid the penalty in any particular case, we must adopt that construction. If there are two reasonable constructions, we must given the more lenient one. That is the settled rule for the construction of penal sections.” It is trite that fiscal statute must not only be construed literally, but also strictly. It is further well known that if in terms of the provisions of a penal statute a person becomes liable to follow the provisions thereof, it should be clear and unambiguous so as to let him know his legal obligations and liabilities thereunder.” In other words, it was on a bonafide understanding of the provisions which was only buttressed further by the conduct of the statutory authorities themselves fortifying the perception of the petitioner that the petitioner had not sought any sanction from the Board even in the case of the Rectifier in question, runs the petitioner's argument. Such conduct _**WPC.No.19925/05 V**_ _**44**_ certainly should not have invited the wrath of regulation 42(d) providing for imposition of the penalty. He would submit that, at any rate, at the worst, even assuming that a penalty has to be imposed, certainly it, in the facts of this case, would not warrant imposition of the penalty as was done. He reiterated that regulation 11 unmistakably speaks of the obligation of the extra high tension consumer, to seek the approval of the Electrical Inspector. In such circumstances, he poses the question, was it a case for imposition of penalty, when, for nearly two decades, the petitioner had been applying for sanction from the Electrical Inspector who was granting sanction and authorised appliances were being connected, alterations made and never, was action taken by the Board. 25. Learned standing counsel would submit that the decision of the Division Bench of this Court only lays down that being a penal provision, the authority must consider the facts and decide whether the maximum penalty is to be imposed. He contends that this Court has not laid down that even if the conduct is bonafide, no penalty need be imposed. He referred to the decision of the Apex Court in Union of India v. Dharamendra Textile Processors (2008 (231) ELT 3(SC)), wherein the Court, inter alia, held as follows: _“12. In Corplus Juris Secundum, Vol.85, at p.580,_ _**WPC.No.19925/05 V**_ _**45**_ _para 1023, it is stated thus:_ _'A penalty imposed for a tax delinquency is a civil obligation, remedial and coercive in its nature, and is far different from the penalty for a crime or a fine or forfeiture provided as punishment for the violation of criminal or penal laws.'_ _13. We are in agreement with the aforesaid view and in our opinion, what applies to tax delinquency equally holds good for the blameworthy conduct for contravention of the provisions of FERA, 1947. We, therefore, hold that mens rea (as is understood in criminal law) is not an essential ingredient for holding a delinquent liable to pay penalty under Section 23(1)(a) of FERA, 1947 for contravention of the provisions of Section 10 of FERA, 1947 and that penalty is attracted under Section 23(1)(a) as soon as contravention of the statutory obligation contemplated by Section 10(1)(a) is established. The High Court, apparently fell in error in treating the blameworthy conduct under the Act as equivalent to the commission of a criminal offence, overlooking the position that the blameworthy conduct in the adjudicatory proceedings, is established by proof only of the breach of a civil obligation under the Act, for which the defaulter is obliged to make amends by payment of the penalty imposed under Section 23(1)(a) of the Act, irrespective of the fact whether he committed the breach with or without any guilty intention._ _(b) J.K. Industries Limited v. Chief Inspector of_ _**46**_ _**WPC.No.19925/05 V**_ _Factories and Boilers (SCC p. 692 para 42)._ _42. The offences under the Act are not a part of general penal law but arise from the breach of a duty provided in a special beneficial social defence legislation, which creates absolute or strict liability without proof of any mens rea. The offences are strict statutory offences for which establishment of mens rea is not an essential ingredient. The omission or commission of the statutory breach is itself the offence. Similar type of offences based on the principle of strict liability, which means liability without fault or mens rea, exists in many statutes relating to economic crimes as well as in laws concerning the industry, food adulteration, prevention of pollution, etc. in India and abroad. Absolute offences are not criminal offences in any real sense but acts which are prohibited in the interest of welfare of the public and the prohibition is baked by sanction of penalty._ _(c) R. S. Joshy v. Ajit Mills Ltd. (SCC p.110 para_ _19)._ _Even here, we may reject the notion that a penalty or a punishment cannot be cast in the form of an absolute or no fault liability, but must be preceded by mens rea. The classical view that no mens rea, no crime has long ago been erroded and several laws in India and abroad, especially regarding economic crimes and departmental penalties, have created severe punishments even where the offences have been defined to exclude mens rea. Therefore, the contention that Section 37(1) fastens a_ _**WPC.No.19925/05 V**_ _**47**_ _heavy liability regardless of fault has no force in depriving the forfeiture of the character of penalty.”_ He would, therefore, contend that the concept of mens rea as such may not be strictly necessary, to sustain the penalty which is provided for in regulation42 (d). No doubt, he also pointed out that the provisions of the Electricity Act, 1910 which are referred to in regulation 42(d) must have contemplated Section 39 which deals with theft. No doubt, regulation 43 specifically deals with theft of energy. 26. It is to be noted that in this case, the petitioner has also mounted a challenge to Ext.P20 series. They are orders calling upon the petitioner to remit penalty on the basis apparently that the load is not yet regularised. It is the case of the petitioner hat the petitioner had already applied for regularisation and still, the petitioner is being issued with bills demanding huge sums. 27. I would think that the Authority has to reconsider the matter. What is in question, is the imposition of a penalty. I cannot ignore the fact that, as an EHT consumer, petitioner has been connecting various equipments to its electrical connection over a long period of time on the basis that it has obtained the requisite permission from the Electrical Inspector under rule 63 of the Electricity Rules. Apparently, the Electrical Inspector was marking copies of his communications to the _**WPC.No.19925/05 V**_ _**48**_ Officers of the Board also. Therefore, there is some substance in the contention of the petitioner that it cannot be said that it was not done in a bonafide manner. There is also some confusion arising out of the use of the words “contracted load” in Regulation 42(d) of the Regulations. Having regard to all these circumstances, I feel that the impugned orders cannot be sustained and the matter must be reconsidered by the Appellate Authority. I also notice that the petitioner has been making applications for regularisation of the connection and even then Bills are being issued. I feel that the entire matter shall be reconsidered in the light of the Judgment in W.A.No.1231 of 2003 and connected cases. Accordingly, the Writ Petition is allowed and Exts.P19, P20 and P20(a) series of orders are quashed. There will be a direction to the Appellate Authority to take a decision afresh in accordance with law, with an opportunity of hearing to the petitioner, within a period of three months from the date of receipt of a copy of this Judgment. There will be a further direction to the sixth respondent to consider and take appropriate decision on Ext.P15 in accordance with law. **==> picture [414 x 44] intentionally omitted <==** _**PS to Judge**_ _**WPC.No.19925/05 V 49**_
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.