Bikram Chatterji & Ors. v. Union of India & Ors.
Case Synopsis & Summary
This Supreme Court order concerns the Amrapali La Residentia project, arising from Writ Petition (Civil) No. 940 of 2017 filed by Bikram Chatterji and others (the applicants) challenging actions of the Union of India and associated authorities regarding the Amrapali Group projects. The Court had earlier undertaken forensic audit of several Amrapali-linked entities and passed orders on 23 July 2019 and 14 October 2019, holding that funds of homebuyers in some projects were diverted by the Amrapali Group. The investigations found that La Residentia had 19.75% Amrapali holdings, directing recovery of 632 flats or its monetary equivalent. The judgments relevant to Heartbeat City and other Amrapali projects were cited, and the Forensic Auditor’s observations were approved in the 2019 judgment. In IA proceedings filed in 2018–2021, the applicants (Association and homebuyers) sought recall or revisiting of the orders or declaration that La Residentia is part of the Amrapali Group so NBCC could complete the project under court supervision. On 29 June 2021, the Court declined to recall or revisit the orders but issued focused directions: the 632 flats may be sold under Court Receiver supervision at a fair value, with proceeds and costs to be accounted for, and the project to continue under Receiver oversight, with modified injunctions and non-costs-order avoidances.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- Uday Umesh Lalit
- Ashok Bhushan
- Judgment Date
- 2021-06-29
- Court Decision / Holding
- The Court refused to recall or revisit the orders dated 23 July 2019 and 14 October 2019 or declare La Residentia as part of the Amrapali Group. It directed that 632 flats previously subject to those orders may be sold by the Company to interested buyers under Court Receiver supervision, at a fair price, with all transactions counter-signed by the Receiver; sale proceeds and costs to be placed in a separate Receiver-controlled account; the cost of construction relating to those flats to be accounted for; and the injunction modified accordingly. The Court left the project to continue under Court Receiver and NBCC considerations as appropriate, but did not order a blanket transfer of the entire project to NBCC or recall the earlier protections. No costs were awarded.
- Final Disposition
- Applications disposed of in terms: the recall/revisit of the orders dated 23.07.2019 and 14.10.2019 was not entertained; however, the Court allowed the 632 flats to be sold under the Court Receiver’s supervision at a fair value, with proceeds and costs routed through a separate Receiver-controlled account and with construction costs accounted for. The injunction over the 632 flats was modified accordingly; the Company may continue construction under Receiver oversight; no order as to costs.
Parties to the Case
Appellants / Petitioners
- Bikram Chatterji and others
Respondents
- Union of India
Legal Representation & Advocates
Counsels for Petitioners
- • Gopal Sankaranarayanan, Senior Advocate
- • M. L. Lahoty, Advocate
- • Manoj V. George, Advocate
Counsels for Respondents
- • V. Giri, Senior Advocate
Provisions of Law Cited
Submissions & Arguments
Contentions of Appellants / Petitioners
The applicants contended that the Amrapali Group’s control over La Residentia and related projects demonstrates, in effect, an Amrapali stake of 19.75% in La Residentia, entitling the Group to 632 flats or its value. They urged recall or revisiting of the orders dated 23 July 2019 and 14 October 2019 or, at least, extension of Amrapali-group protections to La Residentia, including maintaining NBCC/Receiver supervision and escrow-based funding to complete the project. They argued for declaring La Residentia as part of the Amrapali Group and for ensuring homebuyers’ funds are safeguarded, with consistent construction progress and timely completion, while addressing GNIDA and bank dues. They highlighted the progress made (hundreds of flats delivered) and pressed for continued construction under Court Receiver oversight with protections for homebuyers and payments to creditors.
Contentions of Respondents
The respondents argued that La Residentia is not a full Amrapali Group asset beyond the 19.75% stake and that the 632 flats are part of the homebuyers’ own funds, with the court’s prior orders properly balancing interests. They cautioned against recall of the orders and against misclassifying La Residentia as a Group entity, noting that NBCC handover would raise costs and potentially prejudice buyers and creditors. They urged maintaining the existing framework and ensuring that GNIDA and banks’ dues are addressed within the Court-supervised process, while allowing continued construction with appropriate oversight rather than wholesale reallocation of assets to NBCC.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (2)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| / | 4 (2019) 19 SCC 161 | Positive | The judgment quotes and relies on observations from this 2019 SCC case as approved by the Court (footnote 4) in relation to the forensic-audit findings and the Amrapali matter. |
| / | 3 (2020) 16 SCC 375 | Mentioned Only | Cited in the text, but the case name is not provided and its precise role in the reasoning is not articulated in the excerpt. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Bikram Chatterji & Ors. v. Union of India & Ors.
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.