This appeal arises from a writ petition challenging a notice under Section 24(1) of the Indian Electricity Act, 1910 issued by the Bihar State Electricity Board for disconnection of electricity to Hotel Satkar Pvt. Ltd. The core issue was whether charging could be based on contract demand in the absence of a formal agreement between the Board and the consumer, or whether charges should be restricted to actual consumption. The Patna High Court held that without an agreement the Board could not bill under contract demand and that any dispute should be referred to the Electrical Inspector under Section 24(2), quashing the notice and restraining disconnection. On appeal, this Court directed interim arrangements for payment based on actual consumption and later, by order dated 28 May 1984, agreed that a Chief Engineer, nominated by the Government, would determine the amount payable up to February 1984. The Chief Engineer’s report concluded that, for April 1977 to February 1984, the respondent was liable to pay Rs. 9,68,335.67 for energy consumed, with credits for amounts paid, leaving a balance of Rs. 3,84,559.33. The Court held that the Chief Engineer’s determination, grounded in actual consumption rather than contract demand, binds the parties and cannot be overridden by the Electrical Inspector’s later determination. The Supreme Court reversed the Patna High Court and disposed of the appeal, directing enforcement of the Chief Engineer’s liability with no costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • K. Ramaswamy
  • G.B. Paitanik
Judgment Date
1996-09-24
Court Decision / Holding
The appeal is disposed of; the liability of the respondent as determined by the Chief Engineer for energy consumed up to February 1984 becomes enforceable. After accounting for payments made, the outstanding amount is to be paid by the respondent. The decision emphasizes that the Chief Engineer’s determination, based on actual consumption and the agreement of the parties, binds the parties and cannot be overridden by later Electrical Inspector determinations. No costs are awarded.
Final Disposition
Appeal disposed of

Parties to the Case

Appellants / Petitioners

  • Bihar State Electricity Board

Respondents

  • Hotel Satkar Pvt. Ltd.
  • Others

Legal Representation & Advocates

Counsels for Petitioners

  • • Pramod Swarup
  • • Praveen Swarup

Counsels for Respondents

  • • S.B. Sanyal
  • • P.P. Singh

Provisions of Law Cited

Indian Electricity Act, 1910Section 24(1) of the Indian Electricity Act, 1910Section 24(2) of the Indian Electricity Act, 1910

Legal Doctrines & Maxims

  • Bona fide dispute
  • Without prejudice to rights and contentions
  • Binding effect of a court-approved agreement and officer determination

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the parties, by their agreement, directed that a Chief Engineer-nominated authority determine liability. The Court’s order of 28 May 1984, accepting this arrangement, binds the parties and obviates the need for further consideration of the original writ petition. The Chief Engineer’s determination was to be based on actual consumption, not on contract demand, and the Electrical Inspector’s later decision could not override this commitment. The Board argues that the notices under Section 24(1) were justified for non-payment and that the proceedings should not be curtailed by disputed bills or an unresolved contract demand issue. Once the Government-nominated officer determined the liability, the parties were bound to comply, and the Board’s right to disconnect under 24(1) could be exercised subject to the court’s order.

Contentions of Respondents

The respondent contends that, absent a contractual basis, charges must be calculated on actual consumption and that bills issued on contract demand were invalid if disputed. Since the dispute remained unresolved, no disconnection could be effected without following Section 24(2) and a decision by the Electrical Inspector. They argue that the 28 May 1984 order did not cover the pre-existing writ petition and the subsequent bills, and that the Chief Engineer’s report was erroneous and should not bind them. They further contend that any order must respect earlier High Court rulings and that the Court’s interim directions should not be construed to override statutory protections. Continuation of disconnection and the amounts claimed were therefore improper unless validated by a correct statutory procedure.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,207 words•~15 min read

In The Court Record

BIHAR STATE ELECTRICITY BOARD v. HOTEL SATKAR PVT. LTD. AND OTHERS

A BIHAR STATE ELECTRICITY BOARD _v._ ## HOTEL SATKAR PVT. LTD. AND OTHERS ## SEPTEMBER 24, 1996 B [K. RAMASWAMY AND G.B. PAITANAIK, JJ.) _Indian Electricity Act, 19lo-Discontinuance of supply of electricity-Wl1ether Electlicity Board justified in making demands on the basis of contract demand in the absence of agreement between pa1ties-Pa1ties agree to inter-dete1111ination of dispute for the period upto Febma1y 1984 by an officer not below rank of Chief Engineer to be nominated by Govemment-Clzief Engineer detennining the amount payable on the basis of actual consumption-Held : Decision of Chief Eligineer is binding 011 the pwties._ c The respondent filed a Writ Petition challenging the legality of notice D u/s. 24(1) of the Yndian Electricity Act 1910 for disconnection of electricity supplied to the Respondent by the appellant Board on the ground of non-payment of bills amounting to Rs. 3,01,449.30 upto March 1979 submitted by the Board to the respondent. The respondent's contention was that in the absence of any contract entered into with the appellant Board, charge could be levied only on the basis of actual consumption and not on E basis of contract demand. It was further contended that the bills submitted by the appellant'being disputed, no notice could have been issued u/s. 24(1) and the matter could only have been referred to be Electrical Inspector for a decision u/s. 24(2) of the Act. The High Court accepted the contentions of the respondent and quashed the notice of demand and issued a manF damns to the appellant Board not to disconnect the supply line so long as the dispute was not resolved in accordance with law. On appeal preferred by the Board, this Court, issued certain interim directions regarding payment of bills on the basis of actual consumption. G On 9th May, 1984, the appellant Board disconnected the supply of electricity as the respondent failed to pay the bills issued by the Board. On an application filed by the respondent, this Court by its order dated 28.5.1984, on the agreement and joint submissions of both parties, directed that the correct amount payable be determined by an officer, not below the rank of Chief Engineer to be nominated by Government. Subject to the H 673 674 - SUPREME COURT REPORTS (1996) SUPP. 6 S.C.R. - A respondent undertaking that the amount so determined shall be eaid within a week and compliance therewith, this Court directed the Board to restore the supply of electricity. Such payment however was to be without prejudice to the rights and contentions raised in the appeal. The Chief Engineer nominated by the Government, after hearing the parties came to the conclusion that for the period from 1st April 1977 to February 1984, - B the respondent was liable to pay a sum of Rs. 9,68,335.67 on the basis of actual consumption of energy and giving credits for amounts actually paid, the outstanding dues till February 1984 worked out to Rs. 3,84,559.33. Objections were filed by the respondent to the report of the Chief Engineer. - C Disposing of the appeal, this Court D HELD : 1. The Respondent could not seek to wriggle out of the Chief Engineer's report submitted pursuant to this Court's order dated 28.5.1984 which has been passed on the agreement of both parties,.on the ground that it was without prejudice to the contentions in the appeal.,[678-E-Gr 2. Though initially the dispute related to bills sub-milted upto 1979 on the date the Court pas_sed the order i.e. on 28.5.1984, the controversy was in respect of the amount charged till February 1984 and not the original amount which was the subject matter ofthe Writ Petition. ~679-B-C] E 3. The Chief Engineer had determined the liability not on the basis of contract demand but on the basis of actual consumption. [679-D·E] 4. The fact that the dispute regarding the bills raised upto 1979 had been referred to the Chief Inspector under section 24(2) of the Electricity F Act must be considered in the light of subsequent developments and any order that may be passed by the Electrical Inspector cannot over-ride the ultimate decision taken by the Chief Engineer in determining the liability of the respondent. [679-G-H, 680-A·B] G CIVIL APPELLATE JURISDICTION: Civil Appeal No. 921. of 1980 . . From the Judgment and Order dated 7.9.79 of the Patna High Court iii C.WJ.C. No. 1710of1979. H Pramod Swarup and Praveen Swarup for die ~llant. BIHARSfATEELECIRICITYBDv. HOTELSATKAR(P)LID.(PAITANAIK,J.)675 I S.B. Sanyal and P.P. Singh for the Respondents. A The Judgment of the Court was delivered by PATTANAIK, J. This appeal is directed against the judgment of Division Bench of the Patna High Court dated 7th September, 1979 in Civil B Writ Jurisdiction Case No. 1710 of 1978. The respondent filed the writ petition challenging the legality of the notice served by the appellant issued in exercise of power under Section 24(1) of the Indian Electricity Act, 1910 (hereinafter referred to as 'the Act') _inter alia_ on the ground that a _bona fide_ dispute exists between the c licensee and the consumer of electric energy and as such the provisions of Section 24(1) of the Act will not apply. The case of the respondent - consumer is that the appellant has been supplying energy to the respondent hotel but the said respondent has not entered into any agreement and therefore the appellant is entitled to be charged on the basis of the actual D consumption and not on the basis of any contract demand. The appellant, however, submitted bills in respect of the energy consumed on the basis of the contract demand which the respondent did not pay and for such default in payment of the amount charged under the bills the appellant issued notice of discontinuance under Section 24 of the Act. According to the respondent's case the bills submitted by the appellant being disputed, no E notice could have been issued by the appellant under sub-section (1) of ·section 24 and the matter can only be referred to the Electrica:l Inspector for a decision as provided under sub-section (2) of Section 24. The appellant disputed the aforesaid stand of the respondent and submitted that the respondent having failed to pay the bills raised by the appellant in respect F of the energy consumed, the appellant was fully justified in issuing notice under Section 24(1) of the Act and there is no illegality in the same. The High Court by the impugned judgment came to the conclusion that no agreement had been entered into between the licensee, namely, the Bihar State Electricity Board and the consumer, the respondent. It further came G to the concluSion that in the absence of any agreement between the parties the Board w~ not entitled to raise the bills on the basis of the contract demand and can only charge on the basis of the actual consumption of energy. Finally, the High Court came to the conclusion that there existed a _bona fide_ dispute between the licensee and the consumer, and therefore, until that dispute is resolved by a determination made by the Electrical H c SUPREME COURT REPORTS (1996) SUPP. 6 S.C.R. 676 A Inspector under sub-section (2) of Section 24, the licensee was not entitled to issue notice of disconnection in exercise of power under sub-section (1) of Section 24 of the Act. The High Court, therefore, q!lashed the notice of demand and the threat of disconnection and issued a mandamus to the licensee not to disconnect the supply line so long as the dispute is not B resolved in accordance with law. The High Court also further held that until the dispute is finally resolved, the consumer would be liable to be charged on the basis of actual consumption of energy. The amount of accumulated arrear which was indicated in the notice of disconnection to the licensee was Rs. 3,01,449,30 upto March, 1979 which demand was quashed by the High Court by the impugned judgment. This Court on 1st C May, 1981 directed that the respondents shall pay the amount due on the bills submitted to them by the appellant for the consumption and future bills will be paid by the respondents from time to time on the basis of actuals and such submission of bills and payment will be without prejudice to the rights and contentions of the parties. By another Order dated 5th D May, 1982 this Court further indicated that for the time being the Board will not collect any energy charges by the application of the multiplier of the two. Thereafter, as the respondent failed to pay the bills issued by the Board, the supply of electricity to the respondent was disconnected on 9th of May, 1984. The respondent, therefore, approached this Court by filing an application for necessary direction to th.e Boa.rd to restore the connecE tion of electricity supply and to injunct the Board from disconnecting the · supply without permission of this Court during the pendency of the appea~ which was registered as C.M.P. No. 23405 of 1984. In the said application it was alleged that the appellant Board went on giving inflated bills based on erroneous conclusion on the basis of 315 KV A of maximum contract F demand which has already been quashed by the Patna High Court and which is contrary to the interim orders issued by this Court as stated earlier. This application was disposed of by this Court with the following direction: G H "Counsel for both the parties have jointly submitted before me that the parties are agreeable that the correct amount payable by the respondent in the appeal by way of charges for actual consumption of electric energy as per tariff rates applicable may be determined by any officer not below the rank of Chief Engineer nominated by the Secretary, Department of Energy, Govt. of India. This suggestion appears to me just and fair which is accordingly accepted and ## BIHARSfATEELECfRICITYBDv. HOTELSATKAR(P)LTD.[PATIANAIK,J.)677 the Secretary, Department of Energy will forth with nominate any A one officer underhim of the rank indicated above to go into the question as to what amount, if any, remains payable upto date by the Hotel Satkar (P) Ltd. to the Bihar State Electricity Board, Patna by way of consumption charges taking into account actual consumption. Such determination will be made after hearing both B the parties of their representatives at Delhi or atPatna as will be convenient to the officer nominated by the Secretary, Department of Energy. The entire process or determination of the amount should be completed within four weeks from today. The Respondent shall file an undertaking during the course of the day today to pay to the Bihar Electricity Board within one week from the C date of such determination of the exact amount by the Officer nominated by the Secretary, Department of Energy. Subject to the fulfilment of this condition the Bihar State Electricity Board is hereby directed to restore forthwith the electric connection to the respondent Hotel Stakar (P) Ltd. If the respondent Hotel Stakar fails or defaults in the payment within one week of determination D of the amount due, it will be open to the Bihar State Electricity Board to disconnect electric connection. The payment to be made by the Respondent in pursuance of this order will be without prejudice to the rights and contentions raised in the appeal pending before this Court." B E Pursuant to the aforesaid order of this Court the Chief Engineer, Central Electricity Authority was nominated by the Secretary, Department of Power Ministry of Energy to go into the question as to what amount, if any, remains payable upto date by the respondent. The said Chief Engineer heard the parties and gave opportunity to present their respective case and F after analysing all the relevant papers and docm:pents produced before him, came to the conclusion that for the period from April 1977 to February 1984 the respondent is liable to pay the appellant a sum of Rs. 9,68,335.67 for the energy consumed on the basis of actual consumption and out of the said amount the consumer has paid a total of Rs. 5,83,776.34 and, therefore, the outstanding dues till February 1984 work out to Rs. 3,84,559.33. On G behalf of the respondent an objection to the aforesaid report of the Chief Engineer has also been filed in this Court. Mr. Pramod Swarup, learned counsel appearing for the appellant contended that in view of the agreement between the parties this Court H SUPREME COURT REPORTS (1996) SUPP. 6 S.C.R. 678 A having passed the order on 28th May, 1984 requiring an officer not below the rank of Chief Engineer be nominated by the Secretary, Department of Energy, Govt. of India to go into the entire controversy and the said Chief Engineer having gone into the controversy and having determined the liability of the respondent, the parties are bound by the same and it is no B longer necessary to examine the legality of the conclusion arrived at by the Patna High Court. Mr. Sanyal, learned senior counsel appearing for the respondent on the other hand contended that the report submitted by the said Chief Engineer is patently erroneous, and therefore could not bind the respondent for liability as found and further the judgment of the Patna High Court is unassailable. The learned counsel further contended that the C very order of this Court dated 28th May, 1984 indicates that payment to be made by the respondent will be without prejudice to the rights and contentions raised in appeal pending before this Court. Mr. Sanyal, further contended that the aforesaid order passed by this Court was in relation to a fresh demand having been raised by the Board during the pendency of D the appeal and disconnection of the electric supply for non-payment of the same and it would not cover the demand for the period which was the subject matter in the writ petition before the Patna High Court and which is the subject matter of appeal in this Court. Having considered the rival submissions and having applied our mind E to the relevant documents and several orders passed by this Court we are of the considered opinion that this Court was persuaded to pass the order of 28th May, 1984 on the agreement of the parties to get the controversy examined by an officer not below the rank of Chief Engineer to be nominated by the Secretary, Department of Energy, Govt. of India. The F said Chief Engineer having examined the documents produced before him by the parties concerned and having determined the entire liability upto February, 1984 the respondent cannot wriggle out of the said order on the ground that the said order was without prejudice to the contentions to be raised in the appeal. As it appears, the controversy between the parties was, whether the Board was justified in raising demands on the basis of the G contract demand in the absence of any agreement between the parties and the High Court had ordered that demand can be raised only as per the actual consumption of energy. It further appears from the materials on record that the meters which had been installed to record the consumption of energy were only suitable for 5 Amp. and had their dials calibrated to H register consumption corresponding to loads of 100 Amp., 200 Amp., 300 ## BIHARSfATEELECfRICfIYBDv. HOTELSATKAR(P)LTD.[PATIANAIK,J.]679 Amp. or 400 Amp. It further transpires that though initially the dispute A related to the bills which had been submitted upto the year 1979 but during the pendency of the appeal in this Court when fresh bills were also submitted by the Board and the respondent did not pay the same, the appellant took action of disconnection and respondent, therefore, approached this Court for necessary direction for reconnection. It is on B consideration of all these materials and on the agreement between the parties this Court passed the order on 28th May, 1984 requiring the entire controversy to be re-examined by any officer not below the rank of Chief Engineer to be nominated by the Secretary, Department of Energy, Govt. of India. Thus on the date this Court passed the order on 28th May, 1984 the controversy between the parties was in respect of amount charged till C February, 1984 and not the original amount which was the subject matter of the writ petition. This being the position and the matter having been duly scrutinised by an officer of the Government of India and amount having been arrived at and the parties having agreed the controversy to be re-examined by such officer it is not permissible for the respondent to D contend that they are not bound by the decision thus arrived at. So far as the merits of the objections to the report of the Chief Engineer is concerned we find that the said Chief Engineer has not determined the liability on the basis of contract demand but on the basis of the actual consumption of energy. Mr. Sanyal's argument, however, was that in terms of sub-section E (2) of Section 24 of the Act when the matter has been referred to the Electrical Inspector and the said Electrical Inspector has determined the dispute in favour of the respondent, such statutory determination cannot be given a go-bye unless and until it is annulled by any superior authority. He further contended that multiplying factor as applied by the Chief F Engineer is not at all applicable to the facts an~ circumstances of the present case when there was no defect with the meter at any point of time. We find ourselves unable to accept these objections raised by Mr. Sanyal appearing for the respondent. In respect of the dispute with regard to the liability of the respondent to make the payment as per the bills raised upto 1979 no doubt had been referred to the Electrical Inspector under sub-sec- G tion (2) of Section 24 of the Act. But during the pendency of the appeal in this Court when further bills were raised by the appellant and for non-payment of the same the electrical connection was disconnected and respondent challenged the same and ultimately agreed before this Court to get the entire controversy examined by an independent officer of the H 680 SUPREME COURT REPORTS (1996) SUPP. 6 S.C.R. - A Government of India and this Court ultimately passed the order on 28th May, 1984, the entire eontroversy with regard to the liability of the respondent to pay for the energy consumed was before the Chef Engineer and consequently any order passed by the Electrical Inspector under sub-section (2) of Section 24 cannot override the ultimate decision taken by the - B[Chief Engineer in determining the liability of the respondent. The objec-] tions of Mr. Sanyal, therefore cannot be sustained. In the aforesaid premises the impugned judgment of the Patna High Court stands reversed and the liability of the respondent as determined by the Chief Engineer for the energy consumed upto February 1984 becomes C enforceable. The respondent would be liable to pay in accordance with the said determination after adjusting the amount already paid. The appeal is disposed of with the aforesaid direction. There will be no order as to costs. R.D. Appeal disposed of.
End of Judgment Record
Browse All Supreme Court of India (1996) Decisions
1996-08-16

Pfizer Ltd. v Mazdoor Congress and ors.

Pfizer Ltd. v Mazdoor Congress and ors is a Supreme Court appeal arising from writ petitions under Article 227 challenging the Bombay High Court’s reversal of Labour Court and Industrial Court findings that Pfizer had not committed an unfair labour practice in terminating two security staff, Waman S. Surve and R.B. Sail. The matter centers on the terminations of Surve and Sail after arrests in a theft case involving Pfizer property and the company’s loss of confidence in their suitability as watch and ward personnel. The Labour Court dismissed the complaints under Section 28 of the MRTU & PULP Act, and the Industrial Court upheld that dismissal; the High Court, however, intervened in a petition under Article 227, allowing an unfair labour practice claim under Item 1(1) of Schedule IV on the grounds of undue haste and ordering reinstatement with back wages. The apex court reverses, holding that undue haste is a question of fact to be determined on evidence and that no case under Item 1(1) was pleaded or proven before the lower fora or the High Court. It stresses that new arguments cannot be introduced at the Article 227 stage absent prior pleadings and evidence. The Court restores the Labour Court’s and Industrial Court’s decisions and allows Pfizer’s appeals, clarifying the evidentiary and pleading boundaries for unfair labour practices in industrial relations law.

1996-01-09

Union of India v. S.S. Uppal and Anr.

This appeal concerns the fixation of seniority for an officer absorbed into the Indian Administrative Service (IAS) from a state civil service quota. Respondent No.1, S.S. Uppal, a Development Officer in Madhya Pradesh’s Commerce and Industry Department, was considered for IAS absorption under Rule 8(2) of the IAS (Recruitment) Rules, 1954. A panel of four officers was prepared for vacancies arising up to 1 February 1989, with Uppal placed at serial No.4, making him eligible only for the February 1989 vacancy. Although the vacancy arose earlier, he was not appointed until 15 February 1989, and on 3 February 1989 the IAS (Regulation of Seniority) Rules were amended to introduce a weightage-based method for determining Year of Allotment (YOA) for those appointed by selection. Uppal challenged Rule 2 of the 1989 Amendment Rules as ultra vires and argued his seniority should be determined by the rules in force on 1 February 1989. The Central Administrative Tribunal accepted that the vacancy occurred before the amendment, so unamended rules should apply. The Supreme Court held that seniority in the IAS is determined by the rules in force on the date of appointment, not the date of vacancy, and that weightage cannot be retrospective unless provided. It emphasized that mere inclusion in a panel does not guarantee appointment and that the Central Government may amend seniority rules from time to time. The appeal was allowed, and the Tribunal’s order set aside.

1996-03-29

Thimmappa v. Siddaramakka

Thimmappa v. Siddaramakka concerns a deed of reconveyance attached to a sale of land. The reconveyance deed provided that if the respondent vendor repaid Rs. 5,000 within eight years from the sale date (July 20, 1968), the sale deed would be executed and registered in her favor. The respondent contended she offered payment before the eight-year period expired and sought specific performance through reconveyance; the appellant allegedly refused. The trial court accepted the respondent's evidence of offer within the period; the appellate court reversed, holding time was the essence of the contract and thus the suit was barred by limitation. The Karnataka High Court then set aside the appellate decree and restored the trial court’s decree. The Supreme Court held that, unless the deed of agreement of sale fixes a date for performance, time is not necessarily the essence of the contract. It found that Thimmappa had agreed to reconveyance conditioned on repayment within eight years, and that the respondent offered payment before expiry while the appellant refused to reconvey. The cause of action arose on expiry of eight years from July 20, 1973, but the suit was filed on July 20, 1976, within the period from the date of refusal (July 19, 1976). The Court concluded the suit was not barred by limitation, dismissed the appeal, and upheld the High Court’s restoration of the trial court’s decree.

1996-11-19

STATE OF UTTAR PRADESH AND ORS. v. V.K. JAIN

State of Uttar Pradesh and Ors. v. V.K. Jain concerns the regulation of compounded entertainment tax for cinema theatres under the Uttar Pradesh Entertainments and Betting Tax Act, 1979 and related Rules. The respondent cinema proprietor sought to reduce seating capacity from 540 to 450 for the 1995-96 year and to opt for the compounded tax system under Rule 24-A. The District Magistrate rejected both applications; the Allahabad High Court quashed that rejection, holding that the District Magistrate had no power to ignore or alter the seating capacity indicated in the option application. The State appealed to the Supreme Court. The Court held that a proprietor cannot enter into a composite agreement indicating a reduced seating capacity from the maximum stated in the licence, and the District Magistrate cannot adopt any seating capacity other than the maximum in the licence for Rule 24-A purposes. To reduce seating capacity, the proprietor must approach the licensing authority under Rule 14 of the U.P. Cinematograph Rules, 1951 to amend the licence, and only then can the amended capacity be used for Rule 24-A calculations. The decision emphasizes that the maximum seats fixed in the licence, not ad hoc figures, determine the governing base for taxation and that post-composition adjustments require proper licensing amendments. The Government suggests a clarifying recast of sub-rule (4) for the post-composition period to avoid litigation.