This is a Civil Appeal arising from an ex-parte decree in a partition suit. Respondents Nos. 1–13 obtained a decree ex-parte in Regular Civil Suit No. 35 of 2007; the appellant Bhivchandra Shankar More, along with respondents Nos. 14 and 15, sought to set aside under Order IX Rule 13 CPC. After the trial court dismissed their application, they filed an appeal and later a writ petition in the High Court challenging the delay condonation. The High Court, citing the principle that two remedies—Order IX Rule 13 CPC and Section 96(2) CPC—are sequential, held that pursuing the Order IX Rule 13 remedy cannot be treated as ‘sufficient cause’ to condone delay in filing the regular appeal; it relied on Jotiba Limbaji Kanashenavar v. Ramappa Jotiba Kanashenavar. The Supreme Court reversed, holding that the scope of Order IX Rule 13 and Section 96(2) CPC is different. A defendant’s right of appeal under Section 96(2) is a statutory right and cannot be foreclosed merely because an Order IX Rule 13 application was dismissed. The court emphasized liberal construction of “sufficient cause,” noted that delays in appeals are typically condoned where there is no gross negligence or inaction, and rejected rigid, formulaic treatment of the two remedies. It condoned the delay, allowed the appeal, and directed the filing to proceed, while not expressing an opinion on merits.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- R. Banumathi
- R. Subhash Reddy
- Judgment Date
- 2019-05-07
- Court Decision / Holding
- Appeal allowed. The delay in filing the first appeal is condoned, the High Court’s judgment is set aside, and the appeal is restored. The first appellate court is to take on file the appeal titled Bhivchandra Shankar More & Ors. v. Balu Gangaram More & Ors. and proceed in accordance with law. The Court did not express any opinion on the merits of the case.
- Final Disposition
- Appeal allowed; delay condoned; High Court’s order set aside; matter to be taken up by the First Appellate Court to proceed with the appeal in accordance with law.
Parties to the Case
Appellants / Petitioners
- Bhivchandra Shankar More
Respondents
- Balu Gangaram More and Others
Legal Representation & Advocates
Counsels for Petitioners
- • Sushil Karanjkar
- • K. N. Rai
Counsels for Respondents
- • Vinay Navare
- • Gwen Karthika
- • Abha R. B Sharma
- • M. Y. Deshmukh
Provisions of Law Cited
Legal Doctrines & Maxims
- interest reipublicae ut finis litium (the interest of the state in ending litigation)
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellant contends that service of summons on Tanaji, the son of defendant No.2, while the appellants were in a neighbouring village, led to non-appearance and that the remedy under Order IX Rule 13 CPC and the regular appeal under Section 96(2) CPC are not mutually exclusive. They urge liberal interpretation of “sufficient cause” and rely on prior Supreme Court decisions (notably B. Madhuri Goud) to uphold condonation of delay so as to preserve the statutory right of appeal and to permit adjudication on merits rather than technical denial of rights.
Contentions of Respondents
The respondents contend that time spent pursuing the Order IX Rule 13 remedy is irrelevant to condonation of delay in filing the appeal; since the Order IX Rule 13 application was dismissed on merits, it does not bar a Section 96(2) appeal; condonation cannot be allowed on the ground of pursuing a separate remedy; the High Court correctly held that remedies are simultaneous and cannot be converted into consecutive remedies, and that the delay should not be condoned if there is lack of bonafide.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (8)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Jotiba Limbaji Kanashenavar v. Ramappa Jotiba Kanashenavar | 1937 Bom LR 957 | Distinguished | Cited by the High Court; Supreme Court noted that the High Court’s rigid view from this case on simultaneous vs consecutive remedies cannot be applied as the circumstances require a flexible, fact-specific approach. |
| B. Madhuri Goud v. B. Damodar Reddy | (2012) 12 SCC 693 | Positive | Used to support liberal construction of ‘sufficient cause’ and the permissibility of condonation to protect substantial rights. |
| Bhanu Kumar Jain v. Archana Kumar and Another | (2005) 1 SCC 787 | Positive | Cited to reaffirm that the right of appeal is statutory and cannot be curtailed solely due to interim proceedings. |
| N. Balakrishnan v. M. Krishnamurthy | (1998) 7 SCC 123 | Positive | Cited for principle that limitation rules are to preserve rights and that delays may be condoned to avoid negating substantive remedies. |
| Rani Choudhury v. Lt.-Col. Suraj Jit Choudhary | (1982) 2 SCC 596 | Positive | Cited for strict construction of the Explanation to Order IX Rule 13 and related guidance on procedural safeguards. |
| P. Kiran Kumar v. A.S. Khadar and Others | (2002) 5 SCC 161 | Positive | Part of the line of authority on strict construction of procedural provisions relating to Order IX Rule 13. |
| Shyam Sundar Sarma v. Pannalal Jaiswal and Others | (2005) 1 SCC 436 | Positive | Cited in the discussion on strict construction of the Explanation to Order IX Rule 13. |
| Deepal Girishbhai Soni v. United India Insurance Co. Ltd. | (2004) 3 SCC 734 | Positive | Quoted to support liberal approach to ‘sufficient cause’ in the context of condonation of delay. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Bhivchandra Shankar More v. Balu Gangaram More & Ors.
Related Decisions & Precedents from Supreme Court of India (2019)
Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors.
Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors. concerns allegations that Uber, in its ride‑hailing network, abused a dominant position under the Competition Act, 2002. The case arose on appeals challenging the Competition Appellate Tribunal’s order in Appeal No. 31 of 2016, which upheld the Director General’s inquiry into whether Uber’s pricing and incentive practices violated Section 4. The Supreme Court analysed whether the information before it sufficed to constitute a prima facie case under Section 26(1) and whether there was abuse of a dominant position in the National Capital Region. It focused on the two ingredients for abuse: the existence of a dominant position and its misuse. The court considered, based on a statement summarizing driver incentives and a period when Uber reportedly paid high incentives to fleet owners, that Uber may have pursued a pricing strategy that would affect its competitors. Under Section 4(2)(a), abuse includes an unfair price, including predatory pricing. The Court accepted that there is a prima facie case for infringement, yet did not itself interfere with the Appellate Tribunal’s order and dismissed the appeals. It directed the Director General to complete the investigation within six months from today.
STATE OF BIHAR & ORS. v. DR. CHAITRAYA KUMAR SINGH & ORS.
This civil appeal concerns the reorganization of the erstwhile Bihar into Bihar and Jharkhand in 2000 and the post-allocation transfer of an employee. The first respondent, Dr. Chaitraya Kumar Singh, was initially allocated to Jharkhand in 2007 as an Ayurvedic Medical Officer and, following Union guidelines permitting transfer after final allocations, was re-allocated to Bihar on 6 September 2010 with mutual consent of both States. Bihar issued formal orders, and the respondent joined Jharkhand in 2007; however, he remained in Jharkhand and continued to work there until his retirement on 30 April 2017. A few days before retirement, he filed a writ petition in Jharkhand seeking relief to join Bihar and to be relieved by Jharkhand so that Bihar could accept joining. The Jharkhand High Court confirmed a Single Judge’s order directing Bihar to absorb him. The appellants contend that after the 2010 allocation there was no vacancy, the respondent did not pursue available remedies promptly, and seven years of service in Jharkhand after allocation render absorption in Bihar inappropriate. The Court agrees, noting the allocation to Bihar continued to hold and the petitioner failed to pursue remedies in time; his superannuation in Jharkhand eliminates the basis for absorption. The relieving order issued post-retirement is irrelevant. The appeal is allowed, the High Court’s order set aside, and there shall be no costs; pending applications are disposed.
PUNJAB FINANCIAL CORPORATION v. M/S PAULBRO LEATHERS PVT. LTD.
Punjab Financial Corporation (lender) filed against Paulbro Leathers Pvt. Ltd. after Paulbro defaulted on a loan. The dispute was settled under the Corporation’s One Time Settlement (OTS) policy on 01.04.2003, and a court-ordered reference to a Chartered Accountant (CA) was made to determine the remaining outstanding balance. After the CA submitted his report, a new dispute arose about the precise liability and how much had been paid, prompting the Corporation to issue a demand for Rs. 49,86,713 which Paulbro disputed in a writ petition before the Punjab and Haryana High Court. The High Court allowed the petition on the ground that the entire exercise had been carried out with consent and no objection had been raised, effectively barring re-opening of the settlement. The appellant challenged these rulings in this Court. The Supreme Court held that the settlement created a fresh dispute arising out of its terms and that the matter must be decided on its merits under the law. It emphasized that the High Court should record how and on what basis Paulbro satisfied the settlement and discharged liability, and if needed, refer the report to another CA. The Court remanded the case to the High Court to decide the writ petition afresh on merits, with a directions to decide expeditiously (preferably within six months).
RAJESH KUMAR DWIVEDI v. STATE OF U.P. & ANR.
Rajesh Kumar Dwivedi challenges the rejection of his candidature for the post of Instructor in Fitter at Government Industrial Training Institutes in Uttar Pradesh. An advertisement of 17 March 2008 required candidates to possess a certificate in the respective trade from the NCVT, in addition to experience. Dwivedi possessed three National Trade Certificates from Model Industrial Training Institute, Haldwani (one-year basic training in Mechanical, six-month Fitter General module, six-month Metrology and Engineering Inspection), but did not hold a two-year NCVT certificate. The High Court had dismissed his writ petition, holding that three separate courses could not be treated as equivalent to the NCVT qualification. Dwivedi relied on (i) the 16 December 1983 circular clarifying equivalence between the Restructured and Conventional patterns of the Craftsmen Training Scheme, and (ii) 1988 and 1992 UP circulars recognizing MITI, Haldwani training as equivalent to NCVT, including a two-year Fitter trade certificate. The State argued that the amended UP ITI Rules require NCVT certification and that the reliance on circulars cannot override the Rules. The Supreme Court held that the eligibility condition is to have a certificate in the respective trade from NCVT, and that if the State had earlier treated certain qualifications as equivalent through its circulars, such equivalence cannot be disregarded. Consequently, the appellant’s candidature could not be validly rejected, and the State was directed to appoint him within two months. The decision underscores how State-issued equivalence can complement or override rigid Rule-based qualifications when consistently recognized.