BHASKARAN EDAYATH and others v. Appellate Authority Under Payment of Gratuity Act, Regional Joint Labour Commissioner, Kozhikode; Controlling Authority Under Payment of Gratuity Act, District Labour Officer, Kannur; Kerala State Electricity Board
Case Synopsis & Summary
The petition is filed by retired employees of the Kerala State Electricity Board (KSEB) seeking gratuity under the Payment of Gratuity Act. Ext.P1 and Ext.P2 comprise orders dated 15.09.2006 by the controlling authority, which allowed their gratuity claims; these orders have grown final and the Board has not challenged them. The court references a Division Bench decision in KSEB v. Mohankumar (2008 (3) KLT 73), which held that KSEB employees are entitled to gratuity under the Act, indicating a well-established entitlement, and cites a related direction in W.A.439/2009 that additional gratuity be released subject to a bond if the Supreme Court’s decision favors the Board. The Board contends that the matter before the Supreme Court (via SLP) requires refraining from payment. Petitioners submit that as retirees they should not be made to provide guarantors among serving employees; they are willing to execute a bond to refund gratuity if the Supreme Court ultimately decides against it. The Court finds merit in avoiding forced guarantees from serving staff and notes that the petitioners’ orders have already become final. It directs the appellate authority to disburse gratuity already deposited to the petitioners, with interest as determined, and allows six months for payment of interest; if the Supreme Court decision remains pending, the Board must provide a bond to refund interest, on a Rs.50 stamp paper.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- High Court of Kerala
- Hon'ble Judges
- V. Giri
- Judgment Date
- 2009-08-27
- Court Decision / Holding
- Writ petition disposed of directing the appellate authority under the Payment of Gratuity Act to disburse to the petitioners the amount deposited by the Electricity Board with such authorities as gratuity payable to the petitioners, on production of a copy of this judgment. Board shall pay the interest as directed by the competent authority under the Payment of Gratuity Act provided such orders passed by the authorities have become final. Board shall be allowed six months’ time from today to pay the interest and if within that period the issue regarding eligibility of retired employees of the Board to receive gratuity under the Act is yet to be decided by the Supreme Court, then the Board shall pay interest as directed by the competent authority on condition that the petitioners execute a bond agreeing to refund the interest portion, if ultimately the issue is decided in favour of the Board by the Supreme Court. Such bond shall be executed on a Rs.50 stamp paper.
- Final Disposition
- Writ petition disposed with directions to disburse gratuity amounts deposited by Board to petitioners; six months to pay interest; bond to refund interest if Supreme Court decision favors Board; bond to be executed on Rs.50 stamp paper.
Parties to the Case
Appellants / Petitioners
- Bhaskaran Edayath
- K.P.Ravindran
- E.V.Sebastian
- A.C.Padmala1tha
- Padmini.M.E
- K.Balan
- K.Gopinathan Nambiar
- E.P.Raveendran
- K.O.Thomas
- A.V.Mohanann Nambiar
- V.T.Shaduli
- Basheer
- A.M.Scaria
- M.Balan
- K.Gangadharan
- A.Janardhanan
- C.K.Phalgunan
- T.Rajan
- K.K.Bhaskaran
- K.Ramakrishnan
- K.K.Chacko
- P.O.Gangadharan Nambiar
- C.Chandran
- JAYAKRISHNAN.U.P
- K.Rajan
- A.Vasu
- K.Hassan
- G.Shanmughan
- C.Balakrishnan
- Sri.K.Purushothaman
- C.P.Raveendran
- P.Jayadevan
- M.E.Pavithran
- P.Kanakavally
- P.K.Valsarajan
- K.Janardhanan
- N.Ramachandran
- P.Mukundan
- K.Chinnan
- V.K.Abdul Razak
- M.J.Vargheese
- Kelappan.N.K
- K.Balan
- K.K.Gouri
- C.J.John
- C.P.Abdul Hameed
- E.M.Premarajan
- Sri.P.K.Surendran
- K.V.Chandran
- E.K.Pavithran
- K.V.Chandran
- T.Sreedharan
- M.P.Jayarajan
- M.Balan
- K.C.Rajan
- K.Rajan
Respondents
- Appellate Authority Under Payment of Gratuity Act, Regional Joint Labour Commissioner, Kozhikode
- Controlling Authority Under Payment of gratuity Act, District Labour Officer, Kannur
- Kerala State Electricity Board, represented by its Secretary, Thiruvananthapuram
Legal Representation & Advocates
Counsels for Petitioners
- • P.M.Pareeth
- • Mohammed Shameel
Counsels for Respondents
- • Sri K.S Anil (Standing Counsel), Govt Pleader
- • Sri P.N Santhosh
Provisions of Law Cited
Submissions & Arguments
Contentions of Appellants / Petitioners
The petitioners argued that they are retired employees of the Board and should not be compelled to obtain a bond from serving employees as guarantors. They are willing to execute a bond to refund the gratuity sum if the Supreme Court ultimately holds that gratuity under the Payment of Gratuity Act is not applicable to Board employees. They submitted that Ext.P1 and Ext.P2 awards have become final and the Board should not stall payment while the legal question is pending before the Supreme Court. They requested immediate disbursement of gratuity along with interest as determined by the controlling authority, subject to a bond toRefund if required by final Supreme Court decision.
Contentions of Respondents
The Board contended that the questions involved are sub judice before the Supreme Court via a Special Leave Petition; hence, payment should not be effectuated until the Supreme Court decides. It highlighted the pendency of the matter and proposed compliance in line with other cases like W.A.439/2009, where gratuity and additional amounts could be released with a bond in case the Supreme Court reverses or modifies the present view. It stressed that the issue is legal and may require a fresh clarification by higher courts before payment beyond the already-deposited amounts.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (2)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| KSEB v. Mohankumar | 2008 (3) KLT 73 | Positive | Division Bench held that KSEB employees are entitled to gratuity under the Payment of Gratuity Act; the decision supports the petitioners’ entitlement. |
| W.A.439/2009 | W.A.439/2009 | Positive | Division Bench directed release of additional gratuity upon the bond condition; cited as precedent for a similar approach in the present case while Supreme Court decision is pending. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
BHASKARAN EDAYATH and others v. Appellate Authority Under Payment of Gratuity Act, Regional Joint Labour Commissioner, Kozhikode; Controlling Authority Under Payment of Gratuity Act, District Labour Officer, Kannur; Kerala State Electricity Board
Related Decisions & Precedents from High Court of Kerala (2009)
Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality
This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.
Abdul Majeed Kalathil v. District Collector, Malappuram & Others
This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.
WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)
This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."
M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others
The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.