Bharti Cellular Limited v. Union of India and Ors.

Case / Petition Number:
Civil Appeal No. 7026 of 2003
Neutral Citation:[2010] 12 S.C.R. 725

Case Synopsis & Summary

Bharti Cellular Limited (Bharti) challenged a Telecom Disputes Settlement Appellate Tribunal order upholding the Union of India's licence-fee computation under the Delhi Metro licence. The Licence Agreement provided for a fixed licence fee for the first three years and a per-subscriber charge in later years, with the rate and the number of subscribers to be determined by specific formulae. Bharti argued that commercial operations commenced only on 15 November 1995, not 26 September 1995, and that the basis for calculating the subscriber counts should reflect activated connections. It also pressed for a lower Unit Call Rate and contended that certain charges—including interest, penal interest and liquidated damages—were improperly assessed. The Telecom Tribunal framed four issues: (i) the methodology for counting subscribers from the 4th year; (ii) the entitlement to interest on overdue amounts; (iii) the benefit of unit-rate reductions from 1 May 1999; and (iv) the right to levy penal interest from 1 February 2000. The Tribunal ultimately held in Bharti’s favour only on the pre-migration package dispute, but upheld the broader direction to re-work dues with interest. The Supreme Court dismissed the appeal, reaffirming that unconditional acceptance of the Migration Package barred later challenges to pre-migration disputes, and endorsing the Tribunal’s re-work directions.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Markandey Katju
  • T. S. Thakur
Judgment Date
2010-10-05
Court Decision / Holding
Appeal dismissed; Tribunal’s directions to re-work the licence-fee dues along with interest were upheld; no interference with the order and no costs.
Final Disposition
Appeal dismissed

Parties to the Case

Appellants / Petitioners

  • Bharti Cellular Limited

Respondents

  • Union of India
  • Ors.

Legal Representation & Advocates

Counsels for Petitioners

  • • Gopal Jain
  • • Ankur Saigal
  • • Abhay Jena
  • • Bina Gupta

Counsels for Respondents

  • • Indira Jaisingh
  • • ASG
  • • S. Wasim A. Qadri
  • • Padmalakshmi Nigam
  • • Arvind Kumar Sharma
  • • Saima Bakshi
  • • Shreekant N. Terdal

Provisions of Law Cited

Telecom Regulatory Authority of India Act, 1997 – Section 14(a)(I) and Section 18

Legal Doctrines & Maxims

  • Qui approbat non reprobat (one who approbates cannot reprobate)
  • Doctrine of benefits and burdens (accepting an instrument entails accepting its burdens)

Submissions & Arguments

Contentions of Appellants / Petitioners

Applicants contend that the licence commenced only from 15 November 1995, aligning with the date of commercial readiness, and that the date used by the respondents (26 September 1995) distorts liability. They challenge the IMSI-based subscriber-count methodology, arguing for activation-based counting and that 1999 unit-rate reductions should apply from 1 May 1999 for calculations in the 4th year onward. They contend the Migration Package offered a full settlement and included a clause declaring that all disputes relating to the Licence Agreement up to 31 July 1999 would stand abandoned; Bharti accepted the Migration Package unconditionally on 27 July 1999. They stress there was no room to question pre-migration terms after acceptance and that the Tribunal erred in imposing penalties beyond the contract’s terms. They further maintain that charging interest on overdue amounts and the treatment of quarterly pre-payments were improper and seek relief to reflect start date, subscriber calculation basis, unit-rate treatment, and migration-package scope.

Contentions of Respondents

Respondents argued that commencement for fee purposes was 26 September 1995, the date of interface/service clearance, and that the Licence Agreement was operative from that date. They defended the IMSI-based subscriber calculation as clarified by authorities and maintained that the Migration Package abrogated disputes up to 31 July 1999, though the Tribunal partially disagreed. They asserted that the Unit Call Rate revision is limited to increases (up to 75% of the overall increase) and that no downward revision was intended. They contended that interest on overdue amounts is permissible to enforce the agreement and that penalties accrued under the contract’s terms. They urged that the Tribunal correctly held pre-migration disputes barred post-Migration Package and that there is no legal flaw in the re-work directions.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
Shyam Telelink now Sistema Shyam Teleservices Ltd. v. Union of IndiaCivil Appeal No. 7236 of 2003PositiveCited and relied upon to affirm the principle that one cannot approbate and reprobate after accepting a package.
City Montessori School v. State of Uttar Pradesh and Ors.2009 (14) SCC 253PositiveCited in support of the maxim governing approbation and reprobation in the context of settlements.
New Bihar Biri Leaves Co. v. State of Bihar1981 (1) SCC 537PositiveCited as authority for the no-approbate/no-reprobate concept.
R.N. Goswain v. Yashpal OhirAIR 1993 SC 352PositiveCited as supportive authority for the maxim and related doctrine.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,442 words•~16 min read

In The Court Record

Bharti Cellular Limited v. Union of India and Ors.

A ## [2010] 12 S.C.R. 725 # BHARTI CELLULAR LIMITED _V._ UNION OF INDIA AND ORS. (Civil Appeal No. 7026 of 2003) ## OCTOBER 5, 2010 B ## **[MARKANDEY KAT JU AND T.S. THAKUR, JJ.]** _Leave and Licence_ - _Licence agreement executed by and between appellant-licencee and Government for providing cellular mobile telephone services_ - _Dispute relating to_ C _computation of licence fee dues, interest, penal interest, liquidated damages etc._ - _Tribunal upheld the computation of licence fee demanded and realized by the respondentUnion of India in terms of the Licence Agreement holding that appellant gave_ its _unconditional acceptance to the entire_ D _Migration package, thus, it_ was _not entitled to raise any_ issue _relating to pre-migration period; and further issued directions for re-working the licence fee dues along with interest_ - _Propriety of_ - _Held: Proper_ - _Once the appellant had specifically and unconditionally agreed to accept the_ E _Migration Package and given up all disputes relating to Licence Agreement, it_ was _not open to it to tum around and agitate any such dispute after availing of the Migration Package_ - _No legal flaw in the directions issued by the Tribunal and consequently no reason to interfere with the order_ F passed _by it_ - _Telecom Regulatory Authority of India Act, 1997_ - ss. _14(a)(I) and 18_ - _Maxim, "qui approbat non reprobate"- Applicability of_ D F **The appellant-company held a licence to provide cellular mobile telephone services for Delhi Metro area. The Licence Agreement executed between the appellant on the one hand and the Union of India on the other, inter alia, provided for payment of fixed amount towards** G 725 **H** 726 SUPREME COURT REPORTS (2010] 12 S.C.R. A licence fee for the first three years of the licence period. From the fourth year onwards the licence fee payable was to be on the basis of number of subscribers of the service provider subject to the minimum stipulated in the agreement. ## B The appellant filed a petition before the Telecom Disputes Settlement Appellate Tribunal under Section 14(a)(I) of the Telecom Regulatory Authority of India Act, 1997 contending that although it had a provisional C operational clearance from the respondent effective from 29th August, 1995 and an interface/service approval from 26th September, 1995, it could commence commercial services only from 15th November, 1995 and, therefore, the Licence Agreement should be deemed to have become operative only from 15th November, 1995 but the D respondents treated 26th September 1995 as the date of commencement of the Licence Agreement and computed the licence fee dues, interest, penal interest, liquidated damages etc. with reference to the said date. The appellant also questioned the method of computing E the number of subscribers for determining the licence fee payable from the fourth year onwards and the calculation of the interest and penal interest on the overdue amount. One other grievance of the appellant was regarding the Unit Call Rate for the purpose of calculation of the licence F fee. The respondent contested the petition on several grounds giving rise to the following four issues which the Tribunal framed for determination: (i) whether the G methodology adopted by the respondent for arriving at the number of subscribers from the 4th year of the Licence Agreement was in order; (ii) whether the respondent could charge interest on the licence fee payable by the petitioner as demanded by the H respondent in letters dated 10th August, 2009 and 6th BHARTI CELLULAR LIMITED _v._ UNION OF INDIA 727 AND ORS. March, 2000; (iii) whether the petitioner is entitled to the A benefit of reduction in the unit call rate with effect from 1st May 1999 for calculating the per subscriber licence fee and iv) whether the respondent can levy penal interest on the licence fee from 1st February 2000 till the actual date of payment. The Tribunal ultimately dismissed in B part the petition filed by the appellant. Dismissing the appeal, the Court HELD: 1. As regards the first issue, there is no legal infirmity in the view taken by the Tribunal that the C respondents had clarified to the appellant and other cellular operators that the basis for calculating the number of subscribers for determining the licence fee shall be the total figure of IMSI in the Home Location Register. Once the petitioner-appellant had specifically D and unconditionally agreed to accept the Migration Package and given up all disputes relating to Licence Agreement for the period upto 31st July 1999, it was not open to it to turn around and agitate any such dispute after availing of the Migration Package. A party who has E unconditionally accepted the package cannot after such a·cceptance reject the conditions subject to which the benefits were extended to him under the package. It cannot reject what is inconvenient and onerous while accepting what is beneficial to its interests. The package F having been offered subject to the conditions that all disputes relating to the Licence Agreement for the period ending 31st July 1999 shall stand abandoned by the operators there was no room going back on that representation. No one can approbate and reprobate and G anyone who has accepted with full knowledge or notice of facts, benefits under a transaction which he might have rejected or contested, cannot question the transaction or take up an inconsistent position qua the same. [Paras 5- 7] [732-C-D; 732-G-H; A; 733-C] D E F G H 728 SUPRE.ME COURT REPORTS [2010] 12 S.C.R. A _Shyam Tele/ink now Sistema Shyam Teleservices Ltd. v. Union of India,_ Civil Appeal No. 7236 of 2003 - relied on _City Montessori School v. State of Uttar Pradesh and_ Ors. 2009 (14) SCC 253, _New Bihar Biri Leaves_ Co. _v. State_ B _of8ihar1981_ (1) SCC 537 and _R.N. Goswain v. Yashpa/ Dhir_ AIR 1993 SC 352 - referred to. 2. The order of the Tribunal to the extent it related to the second issue has not been assailed by the appellant because the view taken by the Tribunal has gone in its C favour and the matter remitted back for re-working the dues along with interest by the end of July 1999, keeping in view the observations made by the Tribunal in its order. The Ge>vernment has also not assailed the said part of the order. [Para 9] [734-A, BJ D 3. As regards the issue with regard to Unit Call Rate and the effect of any revision in such rate, the Tribunal rightly held that the limiting of the revision is confined to increase only. The expression "revision will be limited to E 75% of the overall increase in the unit rate" in clause 19.1 (f) of the Licence Agreement is indicative of the fact that revision was envisaged only in the case of increase in Unit Call Rate and not in the case of fluctuation resulting in a decrease in the said rate. That apart, the Tribunal has rightly held that the petitioner-appellant had F not led any evidence before it and that the question regarding Unit Call Rate was not raised by it at any stage either before ()r after the licence was issued for the year 1994 and that the issue relating to the Licence Agreement could not be agitated being a pre-migration package. G [Para 11] [734-E-G] 4. On issue no.iv, the Tribunal has rightly taken the view that the respondents were entitled to recover not only the outstanding licence dues but also interest due H on the same for the period of default. The Tribunal rightly BHARTI CELLULAR LIMITED _v._ UNION OF INDIA 729 AND ORS. held that to the extent condition stipulated a deadline i.e. 31st January, 2000 it was open to the respondent to charge simple interest on the overdue amount for keeping the licence valid instead of terminating the same on the ground of default. [Para 12] [735-A-B] A B 5. In the totality of the above circumstances, there is no reason to interfere with the order passed by the Tribunal nor is there any legal flaw in the directions issued by the Tribunal for re-working the dues along with interest keeping in view the observations made in the order under appeal. [Para 13] [735-C] C ## Case Law Reference: |keeping in view the observations made in the<br>order under appeal. [Para 13] [735-C]<br>Case Law Reference:|keeping in view the observations made in the<br>order under appeal. [Para 13] [735-C]<br>Case Law Reference:|keeping in view the observations made in the| |---|---|---| |2009(14)sec253|referred to|Para 7| |1981(1)sec537|referred to|Para 7| |AIR 1993SC352|referred to|Para 7| D CIVIL APPELLATE JURISDICTION : Civil Appeal No. 7026 of 2003. E From the Judgment & Order dated 23.05.2003 of the Telecom Disputes Settlement Appellate Tribunal in Pet. No. 15/01. Gopal Jain, Ankur Saigal, Abhay Jena, Bina Gupta for the Appellant. F Indira Jaisingh, ASG, S. Wasim A. Qadri, Padmalakshmi Nigam, Arvind Kumar Sharma, Saima Bakshi, Shreekant N. Terdal for the Respondents. G The Judgment of the Court was deliverd by T.S. THAKUR, J. 1. This appeal under Section 18 of the Telecom Regulatory Authority of India Act, 1997 is directed against an order dated 23rd May, 2003 passed by the H 730 SUPREME COURT REPORTS [2010] 12 S.C.R. A Telecom Disputes Settlement Appellate Tribunal, New Delhi, whereby the Tribunal has dismissed in part the petition filed by the appellant under Section 14 (a)(I) of the Act and upheld the computation of licence fee demanded and realized by the respondent-Union of India in terms of the Licence Agreement B executed between the parties. 2. The appellant-company holds a licence to provide cellular mobile telephone services for Delhi Metro area. The Licence Agreement executed between the appellant on the one hand and the Government of India on the other, inter alia, C provided for payment of fixed amount towards licence fee for the first three years of the licence period. From the fourth year onwards the licence fee payable was to be on the basis of number of subscribers of the service provider subject to the minimum stipulated in the agreement. Clause 19 of the Licence D Agreement in particular dealt with this aspect and, inter alia, provided that for the first three years a lump sum licence fee shall be chargeable annually and that the year shall be reckoned as the period of twelve months beginning with the date of commissioning of the services or completion of twelve months E from the date of the signing of the licence whichever is earlier. 3. The appellant's case before the Tribunal was that although it had a provisional operational clearance from the respondent effective from 29th August, 1995 and an interface/ F service approval from 26th September, 1995, it could commence commercial services only from 15th November, 1995 meaning thereby the Licence Agreement should be deemed to have become operative only from 15th November, 1995. The respondents, however, treated 26th September 1995 i.e. the G date when the interface/service clearance was given as the date of commencement of the Licence Agreement and computed the licence fee dues, interest, penal interest, liquidated damages etc. with reference to the said date. The appellant also questioned the method of computing the number of H BHARTI CELLULAR LIMITED _v._ UNION OF INDIA 731 AND ORS. [T.S. THAKUR, J.] subscribers for determining the licence fee payable from the A fourth year onwards contending that the term "subscribers" should be understood to be such as have activated cellular mobile telephone connection from the appellant and as are currently activated and used by a person for which bills are issued by the appellant. A few other disputes were also raised B by the appellant in the petition filed on its behalf. One of them related to the alleged illegality and arbitrary computation of the advance payment stipulated for the entire quarter as due in the month of June itself and calculation of the interest and penal interest on the overdue amount. One other grievance of the c appellant was regarding the Unit Call Rate for the purpose of calculation of the licence fee. It was contended by the appellant that in terms of the Licence Agreement the rate of Rs.5 lakhs per 100 subscribers was based on the Unit Call Rate of Rs.1.10\ This rate was revised by the respondent to Rs.6.023 0 lakhs per 100 subscribers or part thereof on 30th July 1998 based on the Unit Call Rate of Rs.1.40 prevalent at that time. Unit Call Rate was then reduced to Rs.1.20 from 1st May, 1999. The appellant, therefore, claimed that the calculation of the licence fee payable for the period from 1st May, 1999 to E 31st July, 1999 should be on the basis of the then Unit Call Rate prevalent, namely, Rs.1.20 only. E 4. The respondent contested the petition on several grounds giving rise to the following four issues which the Tribunal framed for determination: F - (i) Whether the methodology adopted by the. Respondent for arriving at the number of subscribers from the 4th year of the Licence Agreement was in order? G - (ii) Whether the Respondent could charge interest on the licence fee payable by the Petitioner as demanded by the Respondent in letters dated 10th August 1999 and 6th H SUPREME COURT REPORTS [2010] 12 S.C.R. 732 A ## March 2000? B - (iii) Whether the Petitioner is entitled to the benefit of reduction in the unit call rate with effect from 1st May 1999 for calculating the per subscriber licence fee? - (iv) Whether the respondent can levy penal interest on the licence fee from 1st February 2000 till the actual date of payment? c 5. In so far as issue No.(i) above is concerned, the Tribunal took the view that the respondents had clarified to the appellant and other cellular operators that the basis for calculating the number of subscribers for determining the licence fee shall be the total figure of IMSI in the Home Location Register. The 0 Tribunal found that the representation made on the subject by the petitioner-appellant on 1st April, 1999 was rejected by the respondent on 23rd April, 1999 and the appellant offered a Migration Package on 22nd July, 1999 which, inter alia, contained a clause that no dispute relating to the Licence E Agreement for the period upto 31st July 1999 shall be raised at any future date. The appellant gave its unconditional acceptance to the entire Migration package on 27th July, 1999. Having done so, the appellant was not entitled to raise any issue that relatE3d to the pre-migration period. c E F 6. There is, in our opinion, no legal infirmity in the view taken by the Tribunal. Once the petitioner-appellant had specifically and unconditionally agreed to accept the Migration Package and given up all disputes relating to Licence Agreement for the period upto 31st July 1999, it was not open G to it to turn around and agitate any such dispute after availing of the Migration Package. A party who has unconditionally accepted the package cannot after such acceptance reject the conditions subject to which the benefits were extended to him under the package. It cannot reject what is inconvenient and H onerous while accepting what is beneficial to its interests. The BHARTI CELLULAR LIMITED _v._ UNION OF INDIA AND 733 ORS. [TS. THAKUR, J.] package having been offered subject to the conditions that all disputes relating to the Licence Agreement for the period ending 31st July 1999 shall stand abandoned by the operators there was no room going back on that representation. A 7. Relying upon the decision of this Court in _City Montessori School v. State of Uttar Pradesh and_ Ors. 2009 (14) SCC 253, _New Bihar Biri Leaves_ Co. _v. State of Bihar_ 1981 (1) SCC 537 and _R.N. Goswain v. Yashpal Ohir_ AIR 1993 SC 352, this Court has in Civil Appeal No. 7236 of 2003 - Shyam Telelink now _Sistema Shyam Teleservices Ltd. v. Union of India_ held that no one can approbate and reprobate and anyone who has accepted with full knowledge or notice of facts, benefits under a transaction which he might have rejected or contested, cannot question the transaction or take up an inconsistent position qua the same. We have said: "The maxim qui approbat non reprobat (one who approbates cannot reprobate) is firmly embodied in English Common Law and often applied by Courts in this country. It is akin to the doctrine of benefits and burdens which at its most basic level provides that a person taking advantage under an instrument which both grants a benefit and imposes a burden cannot take the former without complying with the latter. A person cannot approbate and reprobate or accept and reject the same instrument." 8. In the light of the above, the view taken by the Tribunal is legally unexceptionable. 8 C D E F 9. That brings us to the second issue formulated by the Tribunal for determination. The Tribunal has answered this issue in favour of the appellant holding that while respondent was G entitled to recover licence fee together with interest from the earlier unpaid amounts upto and for the month of July 1999, it was not entitled to recover both advance quarterly licence fee for July-September 1999 and revenue-sharing fees for August 1999 and September 1999 in terms of the Migration Package. H 734 SUPREME COURT REPORTS [2010] 12 S.C.R. - A This part of the order of the Tribunal has not been assailed before us by the appellant obviously because the view taken by the Tribunal has gone in its favour and the matter remitted back for re-working the dues along with interest by the end of July 1999, keeping in view the observations made by the - B Tribunal in para 23 of its order. It is noteworthy that the Government has also not assailed the said part of the order. 10. The third issue which had been taken up by the Tribunal for consideration related to the Unit Call Rate and the effect of C any revision in such rates. Condition 19.1 (f) which is relevant in this context reads: "19.1 (f): The rate of Rs.five lakhs per hundred subscribers or part thereof is based on the unit call rate of Rs.1.10. Fourth year onwards, as defined in clause 19.1 (d), the rate 0 of Rs.five lakhs will be revised based on the unit call rate. The revision will be limited to 75% of the overall increase in the unit rate during the period preceding such revisions." 11. Relying on the above provisions Tribunal held that even E though there is no specific exclusion of downward revision in the clause extracted above, the limiting of the revision is confined to increase only. The expression "revision will be limited to 75% of the overall increase in the unit rate" appearing in clause 19.1 (f) (supra) is indicative of the fact that revision was envisaged only in the case of increase in Unit Call Rate F and not in the case of fluctuation resulting in a decrease in the said rate. That apart, the Tribunal has rightly held that the petitioner-appellant had not led any evidence before it and that the question regarding Unit Call Rate was raised by it at any stage either before or after the licence was issued for the year G 1994 and that the issue relating to the Licence Agreement could not be agitated being a pre-migration package. 12. That leaves us with issue no.4 formulated by the Tribunal relating to the levy of interest on the licence fee from 1st January H 2000 till actual date of payment. The Tribunal has taken the BHARTI CELLULAR LIMITED _v._ UNION OF INDIA AND 735 ORS. [T.S. THAKUR, J.] view, and in our opinion rightly so, that the respondents were entitled to recover not only the outstanding licence dues but also interest due on the same for the period of default. The Tribunal has rightly held that to the extent condition stipulated a deadline i.e. 31st January, 2000 it was open to the respondent to charge simple interest on the overdue amount for keeping the licence valid instead of terminating the same on the ground of default. 13. In the totality of the above circumstances, we see no reason to interfere with the order passed by the Tribunal nor do we see any legal flaw in the directions issued by the Tribunal for re-working the dues along with interest keeping in view the observations made in the order under appeal. 14. There is no merit in this appeal which is hereby dismissed but without any order as to costs. B.B.B. Appeal dismissed. Appeal dismissed. A B C D
End of Judgment Record
Browse All Supreme Court of India (2010) Decisions
2010-09-24

Department of Telecommunications v. Gujarat Co-operative Milk Marketing Federation Ltd.

This Supreme Court decision concerns a billing dispute arising from two bi-monthly telephone bills totaling Rs. 4,54,652 raised against the Managing Director of the Gujarat Co-operative Milk Marketing Federation Ltd. for calls categorized as international “party” or “sex talk” calls. The respondent subscriber alleged mischarging and that calls were made from another number, prompting a complaint to the Department. Verification upheld the bills; an administrative appeal was dismissed; the matter was referred to arbitration under section 7B of the Indian Telegraph Act, 1885, following a High Court direction. The arbitrator, Vineet Bhatia, concluded the bills were proper. The respondent challenged this award by writ petition, which the High Court (Single Judge) quashed, holding that the arbitrator was junior to the appellate authority, and proceeded to find the award invalid on presumptions and inferences unsupported by evidence; a Letters Patent Appeal was dismissed. The Supreme Court reversed, holding that the High Court exceeded its judicial review scope, misapplied the standard for review of arbitral awards under section 7B, and erred in imputing bias based on rank. It affirmed that the arbitrator’s findings were grounded in the department’s records and meters, and that independence was maintained. The appeal is allowed and the writ petition dismissed, with the High Court orders set aside.

2010-11-23

BHAGWAN BUDHA PRATHMIK TECHNICAL TRAINING COLLEGE NIRMALI v. STATE OF BIHAR

This is a consolidated Supreme Court decision in Civil Appeal Nos. 9896 and 9897 of 2010 arising out of Bihar. Bhagwan Budha Prathmik Technical Training College, Nirmali, a minority Buddhist institution established in 1987, challenged Bihar’s and other authorities’ recognition/approval decisions for its teacher-training course in light of the National Council for Teacher Education Act, 1993 (NCTE Act). The central issue is whether, after the NCTE Act’s appointed day (1 July 1995), State Governments retain power to grant recognition to teacher-education institutes and whether students of unrecognized colleges may sit for qualifying examinations. The matter traces a long litigation history: initial directions in the early 1990s required the Government to decide recognition while allowing students to appear at their own risk; subsequent orders and representations culminated in a 16 March 2007 order recognizing the college from 1987-89 on the ground that inspection warranted it, followed by a 2 September 2008 order withdrawing that recognition in light of NCTE’s sole jurisdiction post-appointed day. The High Court affirmed the sequence, but this Court held that a power to issue an order includes a power to withdraw it for valid reasons, and that recognition is vested in the NCTE after the appointed day. The judgment emphasizes that the NCTE Act must be implemented with full force to protect standards in teacher education. Ultimately, the Supreme Court dismissed the appeals, modified a cost order, and held there should be no further costs in these appeals, while acknowledging the students’ plight and the need for orderly implementation of the regulatory regime.

2010-06-03

State of Punjab & ors. v. G.S. Randhawa

This Civil Appeal arises from a petition challenging a demand for additional price under the Punjab Urban Estate (Sale of Sites) Rules, 1965. The Supreme Court hears counsel for the appellant and notes that the respondent did not enter appearance. Relying on the decision in Smt. Fuljit Kaur v. State of Punjab & Ors., (2010) 7 SCR 317, the Court states that, for the reasons recorded in Civil Appeal No. 5292 of 2004 (the Fuljit Kaur decision) decided on this date, the appeal must be allowed. The High Court’s December 6, 2006 order is set aside and the Demand Notice is upheld. The appellant is entitled to recover the additional price in accordance with law. The decision clarifies that liability to pay additional price under the Punjab Urban Estate Rules can be enforced consistent with the Fuljit Kaur framework, upholding the validity of the demand and permitting recovery by the State. The judgment thus resolves the previous split on allotment price adjustments and prescribes a uniform approach for enforcing such recoveries in analogous cases going forward.

2010-07-15

Harish Singh Nagra & Ors. v. Kapil Sibal & Ors.

Mehfil-e-Wukala, a Supreme Court cultural-literal association of lawyers, published a souvenir containing messages, articles, and poems by judges and senior advocates. Kapil Sibal, a senior advocate and then a candidate for President of the Supreme Court Bar Association, sent a message criticizing the junior Bar and urging reforms, which was circulated within Mehfil’s members but not released to the press or sold publicly. Petitioners, five practicing advocates from the Punjab and Haryana High Court, filed criminal contempt proceedings under Article 215 of the Constitution alleging that Sibal conspired with others to bring the administration of justice into disrepute. The High Court transferred the case to this Court. The central issue was whether the message, read in its proper context, amounted to contempt under Section 2(c) of the Contempt of Courts Act, 1971. The Court held that the message, read in its prospective context, did not scandalize or tend to scandalize any court, nor obstruct the administration of justice; it was a fair critique aimed at improving the system. Citing P.N. Duda, Mulgaokar, Ambard, Vishwanath, and others, the Court reaffirmed that freedom of expression under Article 19(1)(a) protects fair, reasoned criticism of judgments and judicial institutions. It noted that the Times of India article excerpt misrepresented the message, but the souvenir’s limited internal distribution and the respondent’s apology supported dismissal. Accordingly, the contempt petition was dismissed and notices discharged.