Tenetowl LogoTenetowl
Landmark CasesDivision BenchPartly Allowed

Bharat Sanchar Nigam Ltd. and Others vs M/S Tata Communications Ltd.

Case / Petition Number:
Civil Appeal No(s).1699-1723 of 2015
Neutral Citation:-

Case Synopsis & Summary

BSNL, a Government of India enterprise, and other service providers challenged a Telecom Disputes Settlement and Appellate Tribunal order concerning charges for infrastructure facilities provided to interconnecting operators. The central issue is whether BSNL could revise infrastructure charges for Active Links with retrospective effect from 1 April 2009 based on circular dated 12 June 2012, which itself relied on a reclassification of cities and revised house‑rent‑like rates. Interconnect Agreements dated 31 March 2004 fixed that charges be paid upfront and that BSNL had no absolute obligation to provide infrastructure; rates could be revised only on terms fixed by BSNL. The Tribunal held that the circular could revise rates but not retrospectively, directing that charges up to 31 March 2013 would be at the rates under the 2006 circular, and that any excess paid would be refunded with interest, while 1 April 2013 onward would be at revised rates under the 12 June 2012 circular. BSNL urged retrospective applicability and notional 10% annual increases from 2009. Respondents argued that executive circulars cannot be given retrospective effect and that notional increases would impose a burden on service providers already charged. The Supreme Court examined retrospective legislation principles and the nature of executive orders, upheld the Tribunal’s core view, and partly allowed the appeals, permitting notional rate fixation from 1 April 2013 in line with 12 June 2012, while maintaining rates up to 31 March 2013.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Ajay Rastogi
  • B.V. Nagarathna
Judgment Date
2022-09-22
Court Decision / Holding
Appeals partly allowed; The Tribunal’s orders are modified: circular dated 12 June 2012 shall be applicable with effect from 1 April 2013; charges up to 31 March 2013 shall be at rates and classifications as per circular dated 30 May 2006; excess charges realized shall be refunded with interest; BSNL may revise notional rates by 10% annually from 1 April 2013; if service providers fail to pay, consequences under the interconnection agreements will follow.
Final Disposition
Partly Allowed

Parties to the Case

Appellants / Petitioners

  • Bharat Sanchar Nigam Ltd.

Respondents

  • M/S Tata Communications Ltd.

Provisions of Law Cited

Indian Telegraph Act, 1885 - Section 4

Legal Doctrines & Maxims

  • Power to make retrospective legislations enables the Legislature to make laws operative for past periods; administrative/executive orders or circulars cannot be given retrospective effect unless legislatively authorized.
  • Retrospective applicability of executive instruments requires explicit legislative authorization; otherwise, such instruments operate prospectively.

Submissions & Arguments

Contentions of Appellants / Petitioners

BSNL contends that the circular dated 12 June 2012, which revises infrastructure charges for Active Links, can be applied from 1 April 2009, based on the Government’s city classification and the parties’ interconnection agreements. It argues that the Tribunal erred in limiting retrospective application and that it is entitled to notional increases (10% annually) from 2009 onward, with adjustments and refunds as appropriate, to reflect commercial viability and past payments. BSNL maintains that its authority to revise charges stems from its regulatory role and interconnection framework and that any delay in applying revised rates should be absorbed within the contractual and regulatory guarantees already in place.

Contentions of Respondents

The respondents contend that the circular dated 12 June 2012 cannot be given retrospective effect and that any revision from 1 April 2013 should be prospective. They argue that the Tribunal’s approach, which kept 2006 circular rates up to 31 March 2013 and permitted only future revisions from 1 April 2013, is correct, and that notional increases from 2009 are unwarranted. Having paid upfront under older agreements, respondents emphasize the financial burden of retroactive charges and assert that any adjustments must be consistent with the instrumentality of executive circulars and the interconnection contracts. They seek to avoid retrospective liabilities and stress adherence to the existing framework until a properly enacted regulation permits changes.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Civil Appeal No.1438 of 2020Civil Appeal No.1438 of 2020Mentioned OnlyCited as part of procedural history; not relied upon in the ratio of the present decision.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•5,470 words•~25 min read

In The Court Record

Bharat Sanchar Nigam Ltd. and Others vs M/S Tata Communications Ltd.

**REPORTABLE** ## **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** ## **­ CIVIL APPEAL NO(S).1699 1723 OF 2015** **BHARAT SANCHAR NIGAM LTD. AND OTHERS ETC.** **….APPELLANT(S)** ## **VERSUS** **M/S TATA COMMUNICATIONS LTD. ETC.** ## **….RESPONDENT(S)** ## **J U D G M E N T** ## **Ajay Rastogi, J.** 1. The instant batch of appeals has been preferred by the appellant, Bharat Sanchar Nigam Ltd. assailing the judgment dated 20[th] August, 2014 passed by the Telecom Disputes Settlement and Appellate Tribunal, New Delhi, followed with the order dated 14[th] October, 2014 rejecting the application filed by the appellant seeking clarification of judgment dated 20[th] August, 2014 to the Signature Not Verified Digitally signed by NEETA SAPRA Date: 2022.09.22 extent that the rate of infrastructure charges for Active Links of 17:19:29 IST Reason: Licensed Telecom Service Providers to be charged in terms of the 1 circular dated 12[th] June, 2012 has been made effective from 1[st] April, 2013 instead of 1[st] April, 2009 taking note of increase of 10% per annum between 1[st] April, 2009 to 31[st] March, 2013 as payable on 1[st] April, 2013. As consequence thereto, the revised rates introduced by the appellant as per circular dated 12[th] June, 2012, which although were proposed from 1[st] April, 2009, shall be applicable with effect from 1[st] April, 2013 but that was declined by the Tribunal under the order impugned. 2. It will be apposite to take a narration of facts for better appreciation of the controversy raised in the instant appeals. 3. The respondents herein who have been granted licenses under Section 4 of the Indian Telegraph Act, 1885, for providing telecom services such as Universal Access Service/Cellular Mobile Telephone Service/National Long Distance Service, etc. and the service providers entered into Interconnection Agreements with the appellant which is a public sector undertaking for interconnection of their telecom networks with that of the appellant. 4. Whenever a new operator wishes to start operations, it is necessary for such an operator to interconnect with various other 2 networks of the incumbent operators that are already in existence. It is for this reason that interconnection as well as the terms on which the same is to be provided, is regulated by the telecom regulations. The various operators designate some of their switches/exchanges as points of interconnect (POI) from which the interconnection facility is provided by a physical connection on the ports available in such points of interconnect. Sometimes, the newcomer called the interconnection seeker in common parlance, may ask for certain other facilities/resources from the incumbent operators, which may not be mandated by the regulations, on mutually agreeable terms. 5. The dispute in the present batch of appeals pertains to charges for infrastructure facilities which are being provided by the appellant to the batch of respondents, which were increased by a circular dated 12[th] June, 2012, w.e.f. 1[st] April, 2009. The question that arose was as to whether the appellant was justified in raising charges for infrastructure facilities with retrospective operation from 1[st] April, 2009, more so, when the yearly charges are paid by the service providers (respondents) upfront in advance every year. 3 6. Interconnect Agreements are executed between the parties and as per clause 2.1.9, infrastructure facilities will be provided, subject to availability and feasibility. Rental for use of such space and mounting shall be determined by the provider of such facility. As per clause 6.3.3 of the Interconnect Agreement, it is not mandatory for the appellant to provide any infrastructure to the respondents, which they are themselves supposed to arrange. The extract of clauses 2.1.9 and 6.3.3, which are relevant for the purpose is reproduced hereinbelow: ## “Clause 2.1.9 Irrespective of who owns a transmission system of the link interconnecting one party’s exchange to the exchange of the other party, each party subject to availability and feasibility may provide accommodation for the terminals of such equipment of the other party located in its premises. Each party may permit mounting of antennae for interconnect link owned by the other party on its transmission towers subject to feasibility. Rental for use of such space and mounting shall be determined by the provider of such facility. Arrangements for installation, operation and maintenance of such equipment will be arrived at by mutual agreement.” ## “6.3.3 Other charges It shall not be mandatory for BSNL to provide any infrastructure to BSO which BSO himself is supposed to arrange. In case the BSO is not able to bring his interconnecting transmission link upto the BSNL’s designated exchange for the POI, BSNL may subject to availability and payment of the prescribed charges by BSO, provide inter exchange junctions on PCMs from the exchange upto which the BSO has brought its transmission link to the location of POI. These charges shall be same as prescribed by TRAI for leased lines from time to time or on R&G & conditions as the case may be. 4 For any other infrastructure like space BSNL’s building, provision of power supply, air conditioning, mounting of antenna on towers or building tops if feasible, the charges and other terms & conditions for the same shall be as prescribed by BSNL from time to time separately.” 7. The appellant, in the first instance, by circular dated 19[th] February, 2001 fixed the rental charges for providing facilities i.e. accommodation, power supply, tower space, cable ducts, etc. to the private licensed service providers and it was specifically mentioned that the appellant reserve the right to renew the charges as well as the electricity charges as and when being revised by the State Electricity Boards. In furtherance thereof, Interconnect Agreements were executed between the appellant and the respondents/service providers herein earlier on 31[st] March, 2004 and it was made explicit that the appellant has no obligation to provide infrastructure facilities and it is for the respondents/service to the same at their own and in case providers arrange infrastructure facilities are taken from the appellant, it shall be on the rates prescribed by the appellant from time to time. 8. In furtherance thereof, the appellant revised the infrastructure charges for Active Links leased to the operators by its circular dated 30[th] May, 2006 w.e.f. 1[st] April, 2006 and all such charges are to be 5 leviable upfront every year and the circular indicates the of the infrastructure based on justification revising charges classification of cities introduced by the Central Government for the purposes of determining the House Rent Allowance. The extract of the Circular dated 30[th] May, 2006, although not under challenge, but may be relevant for proper appreciation of the grievance raised by the appellant is reproduced as under: “Bharat Sanchar Nigam Ltd. (A Government of India Enterprise) 613­B, Statesman House, B­148, Barakhamba Road, New Delhi – 110001 (Commercial Branch) No. 103­1/2006­Comml. Dated: 30[th] May, 2006 ## **Subject: Infrastructure charges for Active Links of Licensed Telecom Service Providers** In view of various reference received in this office on the subject, the competent authority has reviewed the infrastructure sharing charges prescribed vide Circular No.116­14/96­PHC (pt) dated 19[th] February, 2001 and decided to revise the charges as given below:­ ## 2. **Definition of links connected to BSNL network:** a. **Active Links** : These are the links of Licensed Telecom Service Providers for which transmission equipment of service provider is installed in BSNL’s exchange premises and their network is connected through it. The rental charges of infrastructure in this case have been streamlined and are given below in Para 3. b. **Passive Links** : These are the links of Licensed Telecom Service Providers for which their transmission equipment is installed close to BSNL exchange premises and only transmission cable 6 (with/without modem) is brought in the BSNL’s telephone exchange premises. Charges for this have already been prescribed vide Circular No.103­4/2004­Comml dated 29[th] April, 2005. 3. Rental changes for infrastructure sharing have been divided into following components: - a. Charges for sharing of building space. - b. Electricity and miscellaneous charges. - c. Charges for Tower sharing. - d. Charges for duct sharing. ## a. Charges for sharing of building space: (i) To simplify rent assessment, it has been decided to classify the areas/cities based on the classification followed by Government of India for House Rent Allowance i.e. A1, A, B1, B2 and C class cities. For the sake of simplicity, it has further been decided to have only in four categories i.e. A (for A1 and A), B (for B), C (C) and Unclassified cities. (ii) Accordingly, the rates for one transmission bay (including space for one box of OF termination and DDF as required) in these categories of cities may be charged as under. The space is normally given in technical area of exchange building, which is having high specifications for installation of telecom equipments. The Licensed Telecom Service Providers are given space for installation of their various equipments by officer­in­charge of building on approval of equipment installation plan by Head of SSA: **==> picture [375 x 76] intentionally omitted <==** **----- Start of picture text -----**<br> Categories of City Charges<br>A Rs.36000 per bay per annum<br>B Rs.28000 per bay per annum<br>C Rs.20000 per bay per annum<br>Unclassified Rs.13000 per bay per annum<br>**----- End of picture text -----**<br> b). Miscellaneous Infrastructure service charges: These charges include the sharing of following services: 1). DCT power at – 48V up to 10A/ transmission bay; - 2). AC power for lights, fans, testing instruments etc; - 3). Air Conditioning charges (sharing of existing air conditioning system); - 4). Generator Backup; - 5). Earthing charges (Tapping from exchange earth bar is allowed) 7 ## 6) Fire equipment (Sharing in case of requirement). As the rates of electricity and capital expenditure of BSNL in developing these facilities is varying as per the size of city, the rates for one transmission bay in these categories of cities will be as under: **==> picture [376 x 91] intentionally omitted <==** **----- Start of picture text -----**<br> Categories of City Charges<br>A Rs.2,00,000 per bay per annum<br>B Rs.1,80,000 per bay per annum<br>C Rs.1,50,000 per bay per annum<br>Unclassifie Rs.1,20,000 per bay per annum<br>d<br>**----- End of picture text -----**<br> ## C. **Tower Charges:** Charges per antenna will be as under: **==> picture [375 x 121] intentionally omitted <==** **----- Start of picture text -----**<br> Sl Tower Height All Cities<br>.<br>1. Up to 30 meters Rs.1,20,000 per<br>annum<br>2. 31­60 meters RS. 2,50,000 per<br>annum<br>3. More than 60 Rs.4,00,000 per<br>meters annum<br>**----- End of picture text -----**<br> The above charges will be multiplied by no. of antennas in case multiple antennas are installed by Licensed Telecom Service Providers. d. **Duct Charges:** Permission may be granted to Licensed Telecom Service Providers to lay one 50 mm pipe inside the BSNL exchange premises to lay their OF cable. It will be the responsibility of Licensed Telecom Service Providers to restore telecom exchange building and its premises in original shape after their construction work is over which should be done within one month. A refundable security of Rs.50,000 may be obtained from Licensed Telecom Service Providers before the permission is given. BSNL will not lease its own DUCTs as far as possible. Duct rental for already leased ducts of BSNL may be continued to be charged as at present, i.e.: =[Cost of Duct x No. of Cable x 36%] /[Total no. of pipes in duct] 8 ## 4. Applicability of above charges­ a) These revised rates will be applicable w.e.f. 1[st] April, 2006 with a provision of 10% annual increase every year i.e., 01.04.2007 onwards. Billing cycle shall be from 01.04 to 31.03 of every year. Hence, billing cycle for all existing links may be shifted to the new arrangement; b) All these charges will be leviable in advance every year; c) In case of change of classification of cities, high classification will be applicable at the time of yearly renewal only. The charges will be applicable financial year wise; d) No cash refunds shall be made and any excess payments received by BSNL, due to difference in charges based on old and new formula, shall be adjusted in future bills of party concerned. (R P Bhalla) Assistant Director General (Commercial)” 9. It may further be noticed that the revised rates applicable w.e.f. 1[st] April, 2006 with a provision of 10% annual increase every year i.e. 1[st] April, 2007 onwards and the billing cycle shall be from 1[st] April to 31[st] March and the charges will be leviable upfront in advance every year with a further stipulation that in case of change of classification/categorization of cities, higher classification will be applicable at the time of yearly renewal only and charges will be applicable on each financial year. 10. The Government of India, Ministry of Finance, by its circular dated 29[th] August, 2008, revised the classification of cities effective 9 ## from 1[st] September, 2008 and the cities have been revised as follows: “2. Based on the recommendations of the Sixth Central Pay Commission, the earlier classification of cities has been revised viz., A­1 to “X”; A, B­1 & B­2 to “Y” and C & Unclassified to “Z”. In determining the revised classification, the population of Urban Agglomerate area of the city has been taken into consideration. Accordingly, the rates of House Rent Allowance shall be as under: |Classification of|Rates|of|House|Rent| |---|---|---|---|---| |Allowance||||| |Cities/Towns|as a percentage of (Basic Pay|||| |+||||| ||NPA where applicable)|||| |X||30%||| |Y||20%||| |Z||10%||| 11. The Government of India re­classified the cities w.e.f. 1[st] September, 2008 but so far as the appellant is concerned, the circular revising the infrastructure charges for telecom service providers in terms of circular of the Government of India dated 29[th] August, 2008 came to be introduced by a circular dated 12[th] June, 2012, but charges stood revised retrospectively w.e.f. 1[st] April, 2009 with a provision of 10% annual increase every year w.e.f. 1[st] April, 2010 onwards and rest of the conditions remained the same. The 10 ## impugned extract of part of the circular dated 12[th] June, 2012 is ## reproduced hereinbelow:­ “Rates & Costing Cell, Bharat Sanchar Nigam Limited Bharat Sanchar Nigam Limited, A Govt. of India Enterprises Corporate Office, Janpath, New Delhi – 110001 Bharat Sanchar Nigam Limited No.2­2/2009­R&C[CFA] Dated: 12.06.2012 ## Circular R&C – CFA No.11/11­12 ## **Subject : Infrastructure Charges for Active Links of Licensed Telecom Service Providers** In view of re­classification of cities and revision of rates of house rent vide Govt. of India Department of Expenditure letter No.2(8)/2008­E­II(B) dated 29.08.2008, the existing rental charges for Infrastructure Sharing by the other licensed service providers fixed vide BSNL HQ No.103­1/2006­Comml. Dated 30.05.2006 has been reviewed by Competent Authority and it has been decided to revise the charges w.e.f. 01.04.2009, as details given below: **1. Charges for building space.** (Rates for one transmission bay including space for one box OF transmission and DDF as required) **==> picture [357 x 76] intentionally omitted <==** **----- Start of picture text -----**<br> S.No Classification of Charges w.e.f. 01.04.2009<br>. Cities/Towns<br>1. X Rs.61,606 per annum per bay<br>2. Y Rs.47,916 per annum per bay<br>3. Z Rs.26,620 per annum per bay<br>**----- End of picture text -----**<br> **2. Misc. Infrastructure Service Charges :** These charges include the sharing of following services. 1. DC power at – 48V up to 10A/transmission bay; 2. AC power for lights, fans, testing instruments etc.; 3. Air conditioning charges (sharing of existing air conditioning system); 4. Generator Backup; 5. Earthling charges (Tapping from exchange earth bar is allowed); 11 6. Fire equipment (sharing in case of requirement). **==> picture [359 x 76] intentionally omitted <==** **----- Start of picture text -----**<br> S.No Classification of Charges w.e.f. 01.04.2009<br>. Cities/Towns<br>1. X Rs.2,95,778 per annum per bay<br>2. Y Rs.2,66,200 per annum per bay<br>3. Z Rs.1,99,650 per annum per bay<br>**----- End of picture text -----**<br> 3. The other two infrastructure Sharing rentals viz **Tower Sharing Charges and Duct Charges** , which are not dependent on re­classification of classification of city and house rent rates, shall remain unchanged and be charged as per this office letter No.103­ 1/2006­Comml. Dated 30.05.2006. 4. Other terms and conditions applicable to above charges are: - i) These revised rates will be applicable w.e.f. 01.04.2009 with provision of 10% annual increase every year i.e. 01.04.2010 onwards. Billing cycle shall be from 01.04.2004 to 31.03.2013 of every year. Hence, billing cycle for all existing links may be shifted to the new arrangement; - ii) All these charges will be leviable in advance every year; iii) In case of change of classification of cities, higher - classification will be applicable at the time of yearly renewal only. The charges will be applicable financial year wise; - iv) TAXs, duties as per Govt. orders from time to time will be levied extra. - v) This Circular is issued based on the approval of Competent Authority in NOW­CFA file No.6­9/2010­POI (Infra)(Pt.). For any Clarification/correspondence, in this regard, matter may be taken up with NOW­CFA Section, BSNL Corporate Office, Janpath, New Delhi – 110001 [Tel No.011­23711795 Fax No.011­23734135]. Sd/­ (AGM(T&C­CFA)” 12. It may be relevant to note at this stage that the circular dated 12[th] June, 2012 revised the infrastructure facilities retrospectively w.e.f. 1[st] April, 2009, however, the fact is that all the telecom service 12 providers have made their payments for the previous years in terms of the circular dated 30[th] May, 2006 according to the terms of Interconnect Agreements where the charges are leviable upfront every year and after introducing the circular dated 12[th] June, 2012 w.e.f. 1[st] April, 2009, additional bills were raised by the appellant for the previous years for which the upfront payment was made by each of the telecom service provider and that became the subject matter of challenge at the instance of the telecom service providers (respondents herein) by approaching the Tribunal. 13. The learned Tribunal, after taking note of the submissions and the pleadings on record, arrived to a conclusion that the appellant is well within its rights to revise the rates according to classification of cities and it was for the respondents to continue to use the resources of the appellant at the revised rates or take the same from other resources if available and it was open to the service provider to avail the infrastructure facilities such as building space, etc. either from the appellant or from any other service provider, if any. 13 14. The limited question which the Tribunal considered was regarding the rates prescribed by the appellant under the circular dated 12[th] June, 2012 could have been made applicable retrospectively w.e.f. 1[st] April, 2009 and taking into consideration the backdrop of the matter, while upholding the right of the appellant (BSNL) to revise the rates of the infrastructure facilities in question held that the circular dated 12[th] June, 2012 of the appellant shall be applicable prospectively w.e.f. 1[st] April, 2013, which is the next financial year instead of 1[st] April, 2009 and upto 31[st] March, 2013, the infrastructure facilities provided by the appellant to the telecom service providers shall be charged at the rates and as per classification of cities prescribed in the circular dated 30[th] May, 2006 and the consequential effect is either for refund or for realization of charges, if any, the same may be accounted for by the appellant in terms of the judgment impugned dated 20[th] August, 2014. Relevant extract of the judgment dated 20[th] August, 2014 is reproduced hereinbelow: “In view of the aforesaid circumstances, while upholding the right of the respondent­BSNL to revise the rates of the infrastructure facilities in question, we direct that the revised rates as per the circular dated 12.06.2012 of the Respondent shall be applicable 14 with effect from 01.04.2013 which is the next financial year. Up to 31.03.2013, the infrastructure facilities provided by the respondent to the petitioners shall be charged at the rates and as per classification of cities as prescribed in the circular dated 30.05.2006. The excess rates, wherever realised from the petitioners, shall be refunded back to the petitioners along with interest at the rate as is prescribed in the interconnect agreements for delayed payments from the date of realization of these amounts and till the time of filing of the petitions along with pendente lite and future interest @9% till the payment is made. The refunds shall be made within a period of four weeks. If any amount is found payable by the petitioners in terms of this order, the same shall also be paid along with interest, as payable in case of refunds, and shall be paid within four weeks.” 15. The appellant, at this stage, filed an application before the Tribunal seeking clarification of the judgment and order dated 20[th] August, 2014 on the premise that the rate of infrastructure charge for active links of licensed telecom service providers indicated in the circular dated 12[th] June, 2012 has become effective from 1[st] April, 2013 instead of 1[st] April, 2009. In the given circumstances, the 10% notional increase per annum between 1[st] April, 2009 to 31[st] March, 2013 is leviable and can be charged from 1[st] April, 2013 but that application was dismissed by the Tribunal by its later order dated 14[th] October, 2014 with a clarification that the revised rates as per the circular dated 12[th] June, 2012 shall be applicable w.e.f. 1[st] April, 2013 and the rates which were applied w.e.f. 1[st] April, 15 2009 are to be applied w.e.f. 1[st] April, 2013 without any notional increase and consequently disposed of the application filed by the appellant. Relevant extract of the order dated 14[th] October, 2014 is reproduced hereinbelow: “We, however, do not find any such direction in the judgment. On the contrary, if the rates mentioned in this circular are to be taken w.e.f. 01.04.2009 and then notionally increased by certain percentage every year to arrive at a rate to be applicable from 01.04.2013, it will be contrary to the letter and spirit of the judgment. The direction in the judgment is clear that revised rates as per the circular dated 12.06.2012 shall be applicable w.e.f. 01.04.2013 and, therefore, the rate which was applied as per the circular w.e.f. 01­04­2009 is to be applied w.e.f. 01.04.2013 without any notional increase. We, however, make it clear that this will be without prejudice to the right of the respondent­BSNL to revise the rates prospectively, and in accordance with the agreement between the parties.” 16. That both the orders passed by the Tribunal dated 20[th] August, 2014 and 14[th] October, 2014 became the subject matter of challenge in the instant batch of appeals before us. 17. It may be further noticed that in furtherance of the circular dated 12[th] June, 2012, circular dated 13[th] May, 2015 has been notified revising the infrastructure charges for active links of licensed telecom service providers w.e.f. 1[st] April, 2015 leviable in advance for the year 2015­16 onwards and the justification tendered by the appellant was that it is based on commercial 16 viability and enhanced maintenance cost and the appeals filed by the service providers assailing the circular dated 13[th] May, 2015 came to be dismissed by the Tribunal by judgment dated 18[th] October, 2019 and the appeal preferred against the judgment of the Tribunal came to be dismissed by this Court by an order date 17[th] February, 2020 in Civil Appeal No.1438 of 2020. 18. Counsel for the appellant in the first instance has tried to persuade this Court that the rate of infrastructure charges stood revised on the basis of the circular issued by the Government of India, Ministry of Finance, revising the classification of cities vide its circular dated 29[th] August, 2008 and that became effective from 1[st] September, 2008 and it was the reason for which the circular dated 12[th] June, 2012 became effective in revising the infrastructure charges for telecom service providers w.e.f. 1[st] April, 2009. The appellant revised the rates based on the classification of cities and such revision was permissible in relation to commercial agreements duly supported with the evidence on record. 19. Counsel for the appellant further contended that once the competence of the appellant in laying down the charges has been 17 upheld by the Tribunal, retrospective application to the circular dated 12[th] June, 2012 should not have been interfered with by the Tribunal, but in the next breath, has submitted that if the retrospective applicability of the circular dated 12[th] June, 2012 effective from 1[st] April, 2009 is not sustainable, at least the appellant is within its rights to make the charges leviable after notional fixation by increase of 10% every year w.e.f. 1[st] April, 2009 and, to this extent, the finding of the Tribunal is not legally sustainable and deserves to be interfered with by this Court. 20. Counsel further submits that so far as the notional fixation of charges to be effective from 1[st] April, 2013 is concerned, in terms of circular dated 12[th] June, 2012, there is a provision of 10% annual increase every year w.e.f. 1[st] April, 2010 onwards and, in the given circumstances, even if the infrastructure charges as levied by the appellant to be charged from service providers at the revised rates applicable w.e.f. 1[st] April, 2009 are not chargeable because of the impugned judgment of the Tribunal still the service providers are under an obligation to pay w.e.f. 1[st] April, 2013 the notional increase of charges based on 10% annual increase and this was a 18 manifest error which the Tribunal has committed in passing the judgment impugned and the same needs to be interfered with by this Court. 21. Counsel for the respondents, on the other hand, submits that the right of the appellant to revise the rate of infrastructure facilities indeed after the finding has been recorded by the Tribunal has not been questioned by the respondents in the later proceedings, but if the circular dated 12[th] June, 2012 could not be given retrospective effect w.e.f. 1[st] April, 2009, at least no notional increase of 10% every year could have been permissible to be charged from the service providers w.e.f. 1[st] April, 2013 and if that is being made permissible, what could not have been directly chargeable from the service providers can be indirectly charged at the rates which the appellant is entitled to claim as the infrastructure charges w.e.f. 1[st] April, 2013 and that was the reason the Tribunal intervened in the matter and clarified in its latter order that there shall be no notional increase of 10% every year as being indicated in the circular dated 12[th] June, 2012 and the appellant is under an obligation to charge the rates as applicable on 1[st] April, 2009 to be applied w.e.f. 1[st] 19 April, 2013 without any notional increase. The circular dated 12[th] June, 2012 applicable prospectively w.e.f. 1[st] April, 2013 was to be purposively interpreted and the plea of notional increase by 10% every year in revising the rates, to be charged from 1[st] April, 2013 is not legally sustainable. 22. Counsel for the respondents, while supporting the finding recorded by the Tribunal under the impugned judgment, further submits that if what is being prayed for by the appellant is accepted by this Court, each service provider will have to bear the additional financial burden for the period for which they have not charged any additional charge from their customers and since the respondents have not charged from their customers for the previous years from 1[st] April, 2009 onwards, it will carry a financial burden on the service providers for which they are not at fault. 23. As a matter of fact, the present dispute survives regarding payment of infrastructure charges for the limited period of two years i.e. from 1[st] April, 2013 to 31[st] March, 2015. 24. We have heard learned counsel for the parties and with their assistance perused the material available on record. 20 25. That the authority of the appellant in revising the infrastructure charges for active links leased to telecom operators is not a subject matter of challenge and none of the respondents have questioned the authority of the appellant in revising the infrastructure charges for active links leased to telecom operators. 26. The limited question which has been raised for our consideration is as to whether the rates prescribed by the appellant under the circular dated 12[th] June, 2012 could be applied retrospectively w.e.f. 1[st] April, 2009 or be effective from 1[st] April, 2013, as observed by the Tribunal and whether the appellant is entitled to claim 10% notional increase every year from 1[st] April, 2009 to be applicable from 1[st] April, 2013. 27. So far as the impugned circular dated 12[th] June, 2012 is concerned, it stipulates that it shall be made effective from 1[st] April, 2009 and the rates would revise from 1[st] April, 2009 with 10% annual increase w.e.f. 1[st] April, 2010, particularly, in the circumstances when all the infrastructure and other charges are being paid upfront every year. 21 28. It is not disputed that each of the service provider has paid upfront for the previous years from 1[st] April, 2009 in terms of the earlier circular dated 30[th] May, 2006 until the circular dated 12[th] June, 2012 was introduced. 29. It is a settled principle of law that it is the Union Parliament and State Legislatures that have plenary powers of legislation within the fields assigned to them, and subject to certain constitutional and judicially recognized restrictions, they can legislate prospectively as well as retrospectively. Competence to make a law for a past period on a subject depends upon present competence to legislate on that subject. By a retrospective legislation, the Legislature may make a law which is operative for a limited period prior to the date of its coming into force and is not operative either on that date or in future. 30. The power to make retrospective legislations enables the Legislature to obliterate an amending Act completely and restore the law as it existed before the amending Act, but at the same time, administrative/executive orders or circulars, as the case may be, in the absence of any legislative competence cannot be made 22 applicable with retrospective effect. Only law could be made retrospectively if it was expressly provided by the Legislature in the Statute. Keeping in mind the afore­stated principles of law on the subject, we are of the view that applicability of the circular dated 12[th] June, 2012 to be effective retrospectively from 1[st] April 2009, in revising the infrastructure charges, is not legally sustainable and to this extent, we are in agreement with the view expressed by the Tribunal under the impugned judgment. 31. So far as the submission made by the appellant with regard to the notional increase of charges by a certain percentage every year as being referred to in the circular dated 12[th] June, 2012 is concerned, we have not been able to persuade ourselves with the finding recorded by the Tribunal. The reason is that the appellant might not be justified in making the circular dated 12[th] June, 2012 effective from 1[st] April, 2009, but once the competence of the appellant in fixing the rates of infrastructure charges in question stands affirmed and is not a subject matter of challenge, the appellant is well within its rights to make their charges leviable on notional fixation by increase of charges by a certain percentage 23 every year in terms of circular dated 12[th] June, 2012 from each of the service provider as being notionally applicable from 1[st] April, 2013. In other words, the service provider is not under an obligation to pay any additional infrastructure charges which was prescribed by the appellant under its circular dated 12[th] June, 2012 for the previous years, effective from 1[st] April, 2009, but at the same point of time, it was open for the appellant to notionally fix the charges to be computed and became payable from 1[st] April, 2013, based on 10% annual increase every year or by any other mechanism which may have a reasonable justification. That such notionally increased charges can indeed be leviable on the service providers and to this extent, the order passed by the Tribunal, in our considered view, is not sustainable in law and deserves to be set aside. 32. Consequently, the appeals stand partly allowed. The order of the Tribunal dated 20[th] August, 2014 followed by the order dated 14[th] October, 2014 are hereby modified and the appellant is at liberty to revise the notional rates based on 10% increase every year in terms of circular dated 12[th] June, 2012 as applicable on 1[st] April, 2013 and to raise its additional demand/bills based on notional 24 increase of infrastructure charges effective as on 1[st] April, 2013 to the service providers/respondents herein and if the service providers/ respondents fail to pay, consequences in terms of the agreements executed between the parties shall follow. 33. Pending application(s), if any, shall stand disposed of. **…………………………….J. (AJAY RASTOGI)** **…………………………….J. (B.V. NAGARATHNA)** **NEW DELHI SEPTEMBER 22, 2022.** 25
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.