BHARAT HEAVY ELECTRICALS LTD. v. TATA PROJECTS LTD.

Case / Petition Number:
Civil Appeal No. 8373 of 2014
Neutral Citation:[2014] 9 S.C.R. 479

Case Synopsis & Summary

This appeal concerns a contract dispute arising from Bharat Heavy Electricals Ltd. (BHEL) engaging Tata Projects Ltd. as a sub-contractor to erect, test and commission two 120 MW boilers. Following disputes, an Arbitral Tribunal awarded Rs. 69.22 lakh on various heads and Rs. 25.39 lakh as interest. BHEL challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996. The Calcutta High Court partly allowed the objections; on appeal the Division Bench partly reversed, notably on crane hire charges and interest. The Supreme Court examined two main issues: (i) whether crane hire charges were payable for Unit III, and (ii) the propriety of pre-award interest and the rate of post-award interest. It held that the Work Order read with the Tender Document makes it clear that the respondent was not entitled to certain crane-hire relief and that BHEL was entitled to crane hire charges for the relevant unit; the Division Bench’s disallowance of such charges was erroneous. It also held that pre-award interest could not be awarded due to clause 1.15.5 of the Agreement, following decisions including Sayeed Ahmed & Co. v. State of UP and Globe H-Fabs Ltd. The Court clarified that post-award interest at 10.5% p.a. would run from the date of the Award till payment. The appeal is allowed in part with no costs, and the order under appeal is set aside to that extent.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • FAKKIR MOHAMED IBRAHIM KALIFULLA
  • SHIVA KIRTI SINGH
Judgment Date
2014-09-01
Court Decision / Holding
The Court held that the appellant is entitled to crane hire charges and that such charges should be deducted from the Award on other heads. It held that there shall be no pre‑award interest due to clause 1.15.5 of the Agreement, and post‑award interest shall be payable at 10.5% per annum from the date of the Award to the date of payment, as already directed by the Arbitral Tribunal. The order under appeal is set aside to this extent; the appeal is allowed in part. No costs.
Final Disposition
Appeal disposed of; the appeal is allowed in part. Crane hire charges and post-award interest as determined are affirmed; pre-award interest is denied; the order under appeal is set aside to the extent of these rulings. No costs.

Parties to the Case

Appellants / Petitioners

  • BHARAT HEAVY ELECTRICALS LTD.

Respondents

  • TATA PROJECTS LTD.

Legal Representation & Advocates

Counsels for Petitioners

  • • Gourab Banerji
  • • Mayuri Raghuvanshi
  • • Charu Ambwani

Counsels for Respondents

  • • Gopal Jain
  • • Sridhar Potaraju
  • • Arjun Singh
  • • Mukunda Rao Angara

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 s.34Arbitration and Conciliation Act, 1996 s.31(7)(b)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contended that the Division Bench wrongly reversed the Single Judge’s findings on crane hire charges; Clause 12 of the Work Order read with the Tender Document/Agreement entitles the contractor to crane hire charges for Unit III, notwithstanding the Arbitral Tribunal’s partial allowance of Rs. 8.25 lakh for crane charges. On interest, the appellant confined its claim to pre‑award interest and argued that Clause 1.15.5 of the Agreement bars such interest; the post‑award interest, at 10.5%, if any, would be governed by the Award.

Contentions of Respondents

The respondents argued that crane hire charges were not rightly disallowed, urging a holistic view of the Arbitral record to justify allowances; they pressed for a higher rate of post‑award interest (18% p.a. under s.31(7)(b)) though the Tribunal had awarded 10.5% post‑award interest. They supported maintenance of the Division Bench’s view on the legal position governing pre‑award interest and post‑award interest.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (3)

Case NameCitationTreatmentExplanation
Sayeed Ahmed & Co. v. State of UP. & Ors.(2009) 12 SCC 26; 2009 (10) SCR 841PositiveCited to support the proposition that pre-award interest is barred and interest is payable from the date of the Award, consistent with the contract clause 1.15.5.
Globe H-Fabs Ltd. v. State of UP.Civil Appeal No. 7423 of 2005 (decided 12.11.2009)PositiveCited to corroborate the interpretation that interest is payable from the date of the Award in light of contractual provisions.
Union of India v. Concrete Products & Construction Co. & Ors.(2014) 4 SCC 416PositiveCited as supportive authority on post-award interest and contract-based limitations in interest claims.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,958 words•~14 min read

In The Court Record

BHARAT HEAVY ELECTRICALS LTD. v. TATA PROJECTS LTD.

[2014) 9 S.C.R. 479 A ## BHARAT HEAVY ELECTRICALS LTD. _v._ TATA PRQjECTS LTD. (Civil Appeal No. 8373 of 2014) ## SEPTEMBER 01, 2014 B [FAKKIR MOHAMED IBRAHIM KALIFULLA AND SHIVA KIRTI SINGH, JJ.] - - _Arbitration and Conciliation Act, 1996 s.34 Works_ - _contract Appel/ant-BHEL engaged respondent_ as a _sub-_ C - _contractor to erect, test and commission boilers Disputes and_ - _differences between the parties Award_ passed _by Arbitral_ - _Tribunal Objections raised by appellant, claiming payment_ - _of crane hire_ charges by the respondent Held: On facts, provisions contained in the Work Order read with the Tender_ D _Document/agreement made it clear that appellant_ was _entitled for crane hire charges which were wrongly disallowed by the_ - _order under appeal Such amount to be deducted from the amount payable to respondent under the Award on other heads._ E _Arbitration and Conciliation Act, 1996_ - s. _34_ - _Works_ - - - _contract Dispute between the parties Arbitral award Grant_ - - _of pre-Award interest Propriety Held: On facts, not proper, in view of clause 1. 15. 5 of the tender document I agreement entered into between the parties._ F - _Arbitration and Conciliation Act, 1996 ss.31(7)(b) and_ - - - _34 Works contract Dispute between the parties Arbitral award_ - _Post-Award interest granted by Arbitral Tribunal_ @ -- _10.5% Plea of respondent for enhancement of Post-Award_ G - _interest to 18% p.a. in light of s.31(7)(b) Held: Not tenable, since the Arbitral Tribunal had, already granted post-Award interest@ 10.5%_ -- _Only if the Award had not made such_ a 479 H 480 SUPREME COURT REPORTS [2014] 9 S.C.R. - A _direction, the statutory rate of interest@ 18% p.a. would have been payable from the date of the Award to the date of_ ' - _payment as per the statutory provision._ The appellant-SHEL engaged respondent as a subs contractor to erect, test and commission two 120 MW boilers (Unit II and Unit Ill) on behalf of the appellant. Pursuant to disputes and differences between the parties, an Arbitral Tribunal came to be constituted which awarded Rs.69.22 lac on various heads and Rs.25.39 lac C on account of interest. The appellant instituted proceedings under Section 34 of the Arbitration and Conciliation Act, 1996. A Single Judge of the High Court allowed the objections of the appellant in part in respect of over-run charges, crane hire charges and interest. The 0[respondent ][filed ][appeal ][which ][the ][Division ][Bench ] allowed in part- in respect of crane hire charges and interest. In the present appeal, it was contended on behalf of the appellant that the Division Bench had wrongly E reversed the order of Single Judge on the issue of crane hire charges. In respect of the issue relating to interest, the appellant confined its claim only against grant of pr~­ Award interest. ## Disposing of the appeal, the Court F HELD:1.1. On behalf of respondent, the gr.ant of preAward interest could not be successfully defended in view of clause 1.15.5 of the Agreement which provides that "no interest shall be payable by BHEL on earnest G money/security deposit or any money due to the contractor by BHEL". The ambit and scope of aforesaid clause was subject matter in Civil Appeal No.7423 of 2005 between the .appellant and M/s. Globe Hl-Fabs Ltd. decided on 12.11.2009 wherein this Court accepted and H held that in view of such a provision in the Agreement, BHARAT HEAVY ELECTRICALS LTD. _v._ TATA 481 PROJECTS LTD. interest is only payable from the date of the Award. The aforesaid legal position ought to have been accepted by the Division Bench of the High Court. Clearly the order under appeal ought not to have approved grant of any pre-Award interest. [Paras 4, 6] [484-E-G; 485-D] A B 1.2. On the issue of award of interest, the respondent tried to persuade this Court to enhance the post-Award interest granted by the Arbitral Tribunal@ 10.5% to 18% p.a. in the light of provisions in Section 31 (7)(b) of the Act. This contention cannot be accepted because the Arbitral C Tribunal has already granted post-Award interest@ 10.5%. Only if the Award had not made such a direction, the statutory rate of interest @ 18% p.a. would have been payable from the date of the Award to the date of payment as per the statutory provision. [Para 5] [485-B, CJ D _Sayeed Ahmed_ & Co. _v. State of UP._ & _Ors._ (2009) 12 SCC 26: 2009 (10) SCR 841 and _Union of India v. Concrete Products_ & _Construction_ Co. & _Ors._ (2014) 4 SCC 416 - referred to. E 2.1. So far as the issue relating to crane hire charges is concerned, Clause 12 and other sub-clauses of the Work order show that a high capacity crane (250 T) is included in the Tools and Plants which will be provided by BHEL to the respondent free of charge as per provisions of contract on availability but only upto "drum F lifting of Unit II" as specified in clause 12.2.2. There is no provision either in the Work Order or in the Agreement/ Tender Document to entitle the respondent to claim that it was not obliged to pay the nigher charges as fixed, subject to the conditions laid down by BHEL from time G to time in respect of user of crane for Unit No.Ill. To the contrary, the extracts from the Tender Document contain a clear stipulation for recovery of such charges from the contractor's bill/security deposit in one instalment. [Paras 7, 8 ] [485-E; 487-D-E] SUPREME COURT REPORTS [2014] 9 S.C.R. 482 A A 2.2. The Division Bench did not keep in mind the aforesaid provisions in the Work Order and the Tender Document. SHEL was neither required to issue any notice for exercising its right to recover crane hire charges for Unit Ill, nor was it required to deduct such charges from B the running bills of the respondeht. There is no dispute or issue as regards quantum of such charges claimed by the' appellant but the Arbitral Tribunal allowed it only to the extent of Rs.8.25 lac although the Tribunal itself found that the respondent had failed to produce any material in c support of its defence that because the crane was out of order for a number of days when Unit No.II was under erection/instalment and, therefore, the respondent became entitled to use the crane without hire charges for Unit No.Ill. In such circumstances, the crane hire charges 0[claimed by the appellant were wrongly disallowed by the ] order under appeal passea by the Division Bench. [Para 9] (487-F-H; 488-A-8] 3. In conclusion, it is clear that the appellant is entitled for crane hire charges and, therefore, that amount needs E to be deducted from the amount payable to the respondent under the Award on other heads. Also, the appellant is not liable to pay any pre-Award interest and the interest @ 10.5% p.a. shall be payable by the appellant only from the date of Award tiH- the date of payment on F the Award amount now found payable, if any. [Para 10] [488-8-D] Case Law Reference: 2009 (10) SCR 841 referred to Para 4 G (2014) 4 sec 416 referred to Para 4 CIVIL APPELLATE JURISDICTION : Civil Appeal No. " 8373 of 2014. H From the Judgment and Order dated 12.06.2013 of the BHARAT HEAVY ELECTRICALS LTD. _v._ TATA 483 PROJECTS LTD. High Court at Calcutta partly allowing the Appeal being A.P.O. No. 60 of 2013. A Gourab Banerji, Mayuri Raghuvanshi, Charu Ambwani for the Appellant. B Gopal Jain, Srid!'Jar Potaraju, Arjun Singh, Mukunda Rao Angara for the Resp-ondent. The Judgment of the Court was delivered by SHIVA KIRTI SINGH, J. 1. Leave granted. c 2. Heard Mr. Gourab Banerji, Senior Advocate for the appellant and Mr. Gopal Jain, Senior Advocate for the respondent. The appellant was required to set up some plant or boiler units. For completing that work, appellant issued a notice inviting tender for engaging a sub-contractor to erect, test and commission two 120 MW boilers (Unit II and Unit Ill) on behalf of the appellant. The value of the contract awarded in favour of the respondent was Rs.6.99,40,000/-. Pursuant to disputes and differences, an Arbitral Tribunal consisting of three arbitrators came to be constituted. The Arbitral Tribunal awarded Rs.69.22 lac on various heads and Rs.25.39 lac on account of interest. The appellant instituted proceedings under Section 34 of the Arbitration and Conciliation Act, 1996 (for brevity, 'the Act'). That proceeding bearing A.P. No.213 of 2006 was finally decided by a learned Single Judge of the High Court of Calcutta on 04.01.2013. The objections of the appellant were allowed in part in respect of only three counts relating to overrun charges, crane hire charges and interest. D E F 3. The respondent filed an appeal being A.P.O. No.60 of G 2013. The Division Bench, by the order under appeal dated 12.06.2013, allowed the appeal in part in respect of charges, namely, crane hire charges and interest. In the present appeal only those two issues have been raised on behalf of the appellant. According to learned senior counsel for the appellant, H 484 SUPREME COURT REPORTS [2014) 9 S.C.R. - A the Division Bench has wrongly reversed the order of learned Single Judge on the issue of crane hire charges inasmuch as the claim of the appellant asking for payment of crane hire charges by the respondent for Unit Ill was based upon clause 12.2.2 of the Work Order read with clauses 2.8.11, 3.38.3 and - B 3.38.14 of the Agreement/Tender Document. In respect of second issue relating to interest, learned-senior counsel has confined the claim of the appellant only against grant of preAward interest on the oasis of clause 1.15.5 of the Tender Document/ Agreement. ## c 4. On the other hand, learned senior counsel for the respondent has submitted that the Award in respect of crane hire charges is based on an overall view of entire material available before the Arbitral Tribunal and, therefore, although the Tribunal finally concluded that "there is nothing on record of D the Arbitral Tribunal to substantiate the 'understanding' between the parties regarding swapping of crane usage days between Units II and Ill as has been pleaded by the claimant", it only allowed Rs.8.25 lac in favour of appellant's claim for such charges. According to him, for the same very reason, taking a E holistic view of the whole matter, the Division Bench in the impugned order took the same view. On behalf of respondent, the grant of pre-Award interest could not be successfully defended in view of clause 1.15.5 ·of the Ag~eement which provides that "no interest shall be payable by SHEL on earnest F money/security deposit or any money due to the contractor by SHEL". The ambit and scope of aforesaid clause was subject matter in Civil Appeal No.7423 of 2005 between the appellant and M/s. Globe Hl-Fabs Ltd. decided on 12.11.2009 wherein this Court accepted and held that in view of such a provision G in the Agreement, interest is only payable from the date of the Award. The 'aforesaid legal position ought to have been accepted by the Division Bench of the High Court in view of law settled by judgments of this Court in the case of _Sayeed Ahmed_ & Co. _v. State of UP._ & _Ors._ (2009) 12 SCC 26 and H BHARAT HEAVY ELECTRICALS LTD. _v._ TATA 485 PROJECTS LTD. [SHIVA KIRTI SINGH, J.] several other cases including the case of _Union of India_ 11. _Concrete Products_ & _Construction_ Co. & _Ors._ (2014) 4 SCC 416. A 5. On the issue of award of interest, learned senior counsel for the respondent tried to persuade us to enhance the postB Award interest granted by the Arbitral Tribunal @ 10.5% to 18% p.a. in the li~ht of provisions in Section 31 (7)(b) of the Act. We are unable to accept this contention because the Arbitral Tribunal has already granted post-Award interest @ 10.5%. Only if the Award had not made such a direction, the statutory C rate of interest @ 18% p.a. would have been payable from the date of the Award to the date of payment as per statutory provision noted above. 6. In the. light of aforesaid discussion, we are constrained to hold that the order under appeal ought not to have approved D grant of any.pre-Award interest. ' 7. So far as the issue relating to crane hire charges is concerned, before expressing our views we think it proper to extract the relevant clauses of the Work Order, i.e., clause 12, E 12.2, 12.2.1 and 12.2.2 as well as the relevant clauses of the Tender Document/Agreement : "Relevant extract of Work Order dated 16.03.1999 Terms and conditions F 12.0 TOOLS & PLANTS AND CONSUMABLES You shall provide all necessary consumables and T & Ps (other than those specified below), measuring instruments, handling equipments as G per provision of contract for timely completion of the total job· as per contract within the accepted rates. 12.2 Following T & Ps will be provided by BHEL to you H SUPREME COURT REPORTS [2014] 9 S.C.R. 486 A free of charge as per provision of contract on availability. |||charge<br>availability.|perprovision|provision| |---|---|---|---|---| ||SI.|Description|Capacity|Quantity| ||01.|01.<br>Electric winches|10 MT|2 nos.| |S||||| ||02. 10 Sheave pulley block|02. 10 Sheave pulley block|100 MT|4 nos.| ||03. Hydro test pump|03. Hydro test pump||1 no.| |c|04. High Capacity crane (250 T)*|04. High Capacity crane (250 T)*||1 no.| c - 12.2.1 The above T & Ps will be made available for the project. You may make use of the T & Ps as per the provision of tender document. D - 12.2.2 * In case of 250 T capacity crane, operator and consumable shall be provided by SHEL. However, the fuel for operation of this crane shall have to be arranged by you. 250 T Crane shall be available only upto 'drum lifting of Unit-2' ." E ## "RELEVANT EXTRACT OF TENDER DOCUMENT ## NO.PSER:SCT:JSA:S2 F G - 2.8.11 It is not obligatory on the part of SHEL to supply any tools and tackles or other materials other than those specifically agreed to do so by SHEL, however, depending upon the availability, SHEL's customer's handling equipment and other plants may be made available to the contractor on payment of the hire charge as fixed, subject to the conditions laid down by SHEU customer from time to time. Unless paid to advance such hire charges, if applicable shall be recovered from contractor's bill/ security deposit in one instalment. H - 3.38.3 The operation of all SHEL equipment (except BHARAT HEAVY ELECTRICALS LTD. _v._ TATA 487 PROJECTS LTD. [SHIVA KIRTI SINGH, J.] 250 T Crane) will be in the scope of the contractor. A BHEL will provide free of cost (including operator and consumables) one number 250 T Crane only upto the Drum Lifting Milestone of Unit 11 only. However the Fuel for operating this 250 T Crane shall have to be arranged by the contractor. B B 3.38.14 BHEL will provide free of cost (including operator, fuel and consumables) 250 MT Crane only for the first unit (Unit-2)." 8. Clause 12 and other sub-clauses thereunder as C extracted above show that a high capacity crane (250 T) is included in the Tools and Plants which will be provided by BHEL to the respondent free of charge as per provisions of contract on availability but only upto "drum lifting of Unit II" as specified in clause 12.2.2. There is no provision either in the Work Order D or in the AgreementfTender Document to entitle the respondent to claim that it was not obliged to pay the higher charges as fixed, subject to the conditions laid down by BHEL from time to time in respect of user of crane for Unit No:lll. To the contrary, the extracts from the Tender Document contain a clear E stipulation for recovery of such charges from the contractor's bill/security deposit in one instalment. 9. On going through the order under appeal, we find that the learned Division Bench has not kept in mind the aforesaid F provisions in the Work Order and the Tender Document. BHEL was neither required to issue any notice for exercising its right to recover crane hire charges for Unit Ill, nor was it required to deduct such charges from the running bills of the respondent. There is no dispute or issue as regards quantum of such charges claimed by the appellant but the Arbitral Tribunal G allowed it only to the extent of Rs.8.25 lac although the Tribunal itself found that the respondent had failed to produce any material in support of its defence that because the crane was out of order for a number of days when Unit No.II was under H 488 SUPREME COURT REPORTS [2014] 9 S.C.R. A erection/instalment and, therefore, the respondent became entitled to use the crane without hire charges for Unit No.Ill. In such circumstances, we find that the crane hire charges claimed by the appellant were wrongly disallowed by the order under appeal passed by the Division Bench. B 10. As a result, it is held that appellant is entitled for crane hire charges and, therefore, that amount needs to be deducted from the amoun1.payable to the respondent under the Award on other heads. It is also held that the appellant is not liable to C pay any pre-Award interest and the interest@ 10.5% p.a. shall be payable by the appellant only from the date of Award till the date of payment on the Award amount now found payable, if any. We order accordingly. The order under appeal is set'aside to the a~oresaid extent. The appeal is allowed accordingly. No costs. D Bibhuti Bhushan Bose Appeal disposed of.
End of Judgment Record
Browse All Supreme Court of India (2014) Decisions
2014-07-01

Duryodhan Rout v. State of Orissa

These appeals challenge a common judgment convicting Duryodhan Rout of rape and murder of a 10-year-old girl, Subhasini Bhoi. The trial court convicted him under IPC sections 376(f), 302, and 201 and sentenced him to death; on reference, the High Court remitted the death sentence for the 302 offence to life imprisonment while keeping the other sentences unchanged. The prosecution's case rested solely on circumstantial evidence. PW-1 and PW-2 saw the accused with the victim on a bicycle around 4 p.m. and returning alone about an hour later; PW-5 (father) and PW-6 (mother) testified that the child was taken on the pretext of talking on the phone. In custody, the accused confessed before PW-3 and PW-4, and under Section 27 of the Evidence Act the recovery of the body and the underwear was recorded; the autopsy by PW-9 indicated throttling and injuries consistent with rape. The chain of circumstances — last-seen with the victim, recovery of the corpse in the jungle, and the forensic findings — formed a robust basis for conviction. The central legal issue was whether sentences for multiple offences should run consecutively. The Court held that life imprisonment is the remainder of a convict's natural life, and the proviso to Section 31(2) Cr.P.C. prevents aggregation beyond fourteen years, thus consecutive sentences cannot be imposed where life imprisonment is one of the terms. Consequently, all IPC sentences should run concurrently; the death sentence for the 302 offence was replaced by life imprisonment, and the appeal was allowed in part.

2014-12-16

Nand Kishore v. State of Madhya Pradesh

This is a criminal original jurisdiction writ petition under Article 32 challenging the continued incarceration of a convict under Section 302 IPC, with the petitioner contending entitlement to the Juvenile Justice (Care and Protection of Children) Act, 2000 (JJC Act) protections on the ground that he was a juvenile at the time of the offence (born 14 April 1980; incident on 18 June 1997). The Court scrutinized documentary and oral evidence from the Juvenile Justice Board indicating the petitioner’s true date of birth and concluded that on the date of occurrence he was 17 years 2 months 4 days old, thereby satisfying the juvenile criteria. The judgment clarifies a central legal question: whether the protections and benefits under the JJC Act, enacted in 2000, can be extended to those convicted before its coming into force if they were juveniles at the time of the offence. Relying on earlier decisions such as Hariram v. State of Rajasthan and Ajay Kumar v. State of Madhya Pradesh (and others), the Court held that a person who had not completed 18 years on the date of offence is entitled to the Act’s benefits as if the provisions had always existed, effectively retroactively applying the protective regime. The petition was allowed; the petitioner is to be released forthwith, with bail bonds and sureties discharged, reflecting the Court’s protective stance for juveniles in criminal proceedings.

2014-04-24

Vishal Goyal & Ors. v. State of Karnataka & Ors.

This batch of writ petitions under Article 32 concerns admissions to Post Graduate Medical and Dental courses in government medical/dental colleges and the state quota in private colleges in Karnataka for the 2014-2015 academic year. The petitioners, who completed MBBS/BDS in Karnataka, challenged sub-clause (a) of clause 2.1 of two National Board of Examinations Information Bulletins (PGET-2014) which defined “Karnataka Origin” to permit admission only to those who satisfy certain criteria, effectively excluding many who studied in Karnataka institutions. They argued this violates Article 14 (equality before law and equal protection of laws) and undermines merit-based selection for postgraduate courses. They invoked Dr. Pradeep Jain & Others v. Union of India (1984) to contend that institutional preference may be permissible but must conform to equality; Magan Mehrotra v. Union of India (2003), Saurabh Chaudhri v. Union of India (2003), and Nikhil Himthani v. State of Uttarakhand (2013) were cited to support the continuing emphasis on merit and equality. The State countered that Article 371J allows reservation for the Hyderabad-Karnataka region and argued that the Pradeep Jain framework applies only to government or state-instrumentality institutions and not to private colleges. The Court held sub-clause (a) ultra vires Article 14, directed fresh Information Bulletins, and ordered admissions in accordance with the law on the basis of existing entrance test results, with the general counselling schedule from Dr. Fraz Naseem & Ors. not applying for 2014-2015 Karnataka admissions.

2014-08-21

SINGH RAM (D) THR. L.Rs. v. SHEO RAM & ORS.

This is a Supreme Court of India decision on the limit of time within which a usufructuary mortgagee can seek relief, and the corresponding equity of redemption for the mortgagor. The appellants challenged the Punjab and Haryana High Court Full Bench’s view that there is no fixed time for redemption in a usufructuary mortgage and that the right to seek redemption arises on payment/deposit of mortgage money, irrespective of the mortgage date. The HP High Court’s decision was later reversed by a larger bench of this Court in the context of reconciling conflicting precedents such as Sampuran Singh, Prabhakaran and Jayasingh Dhyanu Mhoprekar, Parichhan Mistry and Harbans etc., emphasizing that Section 62 of the Transfer of Property Act confers a special right on the usufructuary mortgagor to recover possession, which begins only when the mortgage money is paid out of rents and profits or when paid/deposited by the mortgagor. Article 61 of the Limitation Act governs the period for redeeming or recovering possession (30 years from accrual of the right, unless restricted). The Court reaffirms the principle ‘once a mortgage, always redeemable’ and rejects a blanket 30-year extinguishment rule for usufructuary mortgages, upholding the Full Bench view of the Punjab and Haryana High Court and dismissing the appeals. The decision emphasizes equity, statutory recognition under Section 62, and the distinctive treatment of usufructuary mortgages.