Banwasi Seva Ashram v. State of Uttar Pradesh and Ors.

Case / Petition Number:
Writ Petition (Criminal) No. 1061 of 1982
Neutral Citation:[1992] 1 SCR 859

Case Synopsis & Summary

Banwasi Seva Ashram v. State of Uttar Pradesh and Ors. is a Public Interest Litigation before the Supreme Court concerning Rehabilitation of oustees affected by the Rihand Super-Thermal Power Project undertaken by NTPC in Sonebhadra district, UP. The Court had previously issued comprehensive rehabilitation directions on 20 November 1986 and appointed a Board of Commissioners to supervise their implementation. In this 1992 disposal order, the Court terminates its monitoring of the NTPC’s proceedings while preserving safeguards for oustees’ rights and compensation, directing collaboration between NTPC and the State Government to ensure a fair, comprehensive package for those displaced. The package includes housing plots (60’ x 40’ per family), shifting allowances (Rs. 1500) and rent (Rs. 3000), free transportation, a subsistence allowance (up to Rs. 750 per month for 10 years), job reservations in unskilled and semi-skilled posts, preference for oustees in class III/IV posts, employment through NTPC contractors, transfer of shops and business premises to oustees, and self-employment training programs (carpentry, weaving, sericulture, masonry, dairy farming, poultry farming, basket weaving, etc.). It also requires provision of rehabilitative facilities (roads, drainage, water, schools, health centres, Panchayat Bhavan, electricity, banks, sanitation) and the claim-based compensation framework: provisional crop and land compensation at Rs. 850 per acre per year and Rs. 10,000 per acre respectively, with District Judge, Sonebhadra, determining final compensation. Verification, list finalization, and claims deadlines are established, and Deputy Commissioner to supervise compliance. The petition is disposed of with directions to implement the package and finalize compensation expeditiously.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Kuldip Singh
  • P.B. Sawant
  • N.M. Kasliwal
Judgment Date
1992-02-19
Court Decision / Holding
The Court disposed of the proceedings concerning NTPC lands subject to Section 4 notifications, reaffirmed ongoing monitoring, and ordered a detailed rehabilitation package for evictees in possession of lands/houses: housing plots, shifting and rent allowances, transportation, subsistence payments, job reservations, employment via NTPC contractors, shops, self-employment programs, and rehabilitative infrastructure. It directed the NTPC and State to submit and verify lists of evictees, finish verification by a specified date, and have the District Judge, Sonebhadra, determine compensation with provisional rates (Rs. 850 per acre per year for crops; Rs. 10,000 per acre for land), and finalize claims expeditiously (with notices by May 15, 1992 and final decisions by March 31, 1993). The Deputy Commissioner is tasked with supervising compliance; the petition is finally disposed of.
Final Disposition
Petition disposed of

Parties to the Case

Appellants / Petitioners

  • Banwasi Seva Ashram

Respondents

  • State of Uttar Pradesh
  • National Thermal Power Corporation Limited (NTPC)

Provisions of Law Cited

Article 32, Constitution of IndiaArticle 37, Constitution of IndiaIndian Forest Act, 1927 (Section 4, Section 17, Section 20)Section 4 Notification under the Indian Forest ActSection 17 of the Indian Forest Act, 1927 (as amended by Uttar Pradesh Act 25 of 1965)Uttar Pradesh Act 25 of 1965 (amendments)

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner (Banwasi Seva Ashram) sought protection of oustees’ rights under the Court’s earlier directions and an expeditious, comprehensive rehabilitation, including housing, compensation and employment, to be guaranteed in favor of those displaced by the NTPC project. The petition argued that the rights of residents in possession of lands and houses must be determined and adequately compensated, with strict adherence to the 1986 directives and ongoing monitoring by the Court to ensure humane treatment and justice for the affected communities.

Contentions of Respondents

The respondents (State of UP and NTPC) contended that the NTPC project is essential and that the rehabilitation should be implemented in accordance with the Court’s previous orders and the policy framework. They emphasized compliance with statutory provisions and mentioned that certain lands (e.g., reserved forest areas) fall outside writ jurisdiction, while acknowledging the need to finalize rights and compensation for the affected oustees within the policy guidelines and available resources.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,420 words•~11 min read

In The Court Record

Banwasi Seva Ashram v. State of Uttar Pradesh and Ors.

A BANWASJ SEVA ASHRAM • _v._ STATE OF U.P. AND ORS. FEBRUARY 19, 1992 [KULDIP SINGH, P.B. SA WANT AND N.M. KASLIWAL, JJ.] _Public Interest Litigation:_ _National_ _**171ennal** Power Co!]1oratio11:_ ' c _Rihand Super-Tllcrmal Power Project-Rehabilitation of evictecs-Directions issued._ This Court, by its order dated 20.11.1986, while disposing of Writ Petition (Cr!.) No. 1061 of 1982, gave comprehensive directions for rehabilitation of Adivasis/landholders affected by the Rihand.Super-TherD mat Power Project to be set up by the National Thermal Power Corporation Limited (NTPC), and appointed a Board of Commissioners to **supervise the implementation of' the said directions. Since then this Court was monitoring the project.** **Disposing of the proceedings and the monitoring-process so far as E** · the NTPC was concerned, this Court, HELO: In order to ensure that the rights of the oustees are determined in their respective holdings and they are properly and adequately compensated, the NTPC shall take, in collaboration with the State **Government, the follo,ring measures to rehabilitate the evictees who were** in actual physial possession of the lands/ houses etc. : - (i) The NTPC shall submit a list of the evictees-claimants to the District Judge, Sonebhadra who shall be the final authority to finalise the ~ F G (ii) One plot of land measuring 60' x 40' to each of the evictee-families be distributed for housing purposes through the district administration. (iii) Shifting allowance of Rs. 1500 and in addition a lumpsum rent of Rs. 3000 towards housing be given to each of the evictee-families. H 857 858 [ l992] I S.C.R. SUPREME COURT REPORTS • A . (iv) Free transportation shall be provided for shilling. B (v) Monthly subsistence allowance equivalent to loss of net income from the acquired land to be determined by the District Judge Sonebhadra subject to a maximum of Rs. 750 for a period of 10 years. The said payment shall not be linked with employment or any other compensation. (vi) Unskilled and semi-skilled_ posts in the project shall be reserved for the evictees. c (vii) The NTPC shall give preference to the oustees in employment in class Ill and IV posts under its establishment. (viii) The evictees be offered employment through the contractors employed by the NTPC. D (ix) Jobs of contractors under the administration of the NTPC be **offered to the evictees.** (x) The shops and other business premises within the NTPC campus **be offered to the evictees.** (xi) The NTPC shall operate for the benefit of the evictees selfE generating employment schemes such as carpentery training (free tools **to be provided after completion of training) carpet weaving training, sericulture, masonary training, dairy farming, poultry farming and basket weaving training etc.** (xii) The NTPC shall provide facilities in the rehabilitative area such **F as pucca roads, pucca drainage system, handpumps, wells, portable water** supply, primary school, adult education classes, health centre, Panchayat **Bhavan, sports centres, electricity connections, bank and sulabh** Sauchalaya complex etc. The Deputy Commissioner Sonebhadra shall supervise and ensure that the rehabilitation measures are fully complied with. ## G '- (xiii) As regards compensation for crops ·and land, the provisional compensation at the rate of Rs. 850 per acre per year for crops and Rs. 10,000 per acre for the land be paid to the oustees. H [pp. 861B-H; 862A-H; 863A-8] 859 SEV A ASHRAM _v._ STA TE • -.. ~·r > The District Judge, Sonebbadra shall be the authority to determine A the compensation.· The orders passed by the District Judge shall bj} treated as orders under s. 17 of the Indjan Forest Act, as amended by U.P. Act 25 of 1965. [p. 863B, F) ORIGINAL JURISDICTION: Writ Petition (Cr!.) No. 1061 of 1982. B (Under Article 37 of Constitution of India) i,. Prem Bhai and Prem Singh, Commnr. Supreme Court, Justice B.L. Loombha, Chairman, Legal Aid, Advisory Board, U.P., M.K. Ramamurthi, B. Datta, Yogeshwar Prasad, Ms. Chandan Ramamurthi, M.A. Krishnamoorthy, Ms. Rachna Joshi, D.D. Sharma, A.S. Pundir, R.P. Srivastava,[c ] S.N.Terdol, Hemant Sharma, Ms. Anil Katiyar, C.V.S. Rao and Ms. Sangeeta Aggarwal for the appeari,ng parties. The following Order of the Court was delivered: On the basis of a letter received from Banwasi Seva Ashram operat-[D ] ing in Mirzapur District of Uttar Pradesh Writ Petition (Criminal) No. 1061)82 under Article 32 of the Constitution of India was registered. Meanwhile the National Thermal Power Corporation Limited (NTPC) decided to set up a super-thermal plant on part of the lands which were subject matter of the writ petition. NTPC got itself irnpleaded as a party E in the writ petition and claimed that the completion of the project was a_ time bound-programme and as such the land earmarked for the project be made free from prohibitive directions of this Court in the writ petition. The writ petition was disposed of by an order dated November 20,1986. This Court issued comprehensive directions and appointed a Board of F Commissioners to supervise the implementation of the said· directions .. This Court has been monitoring the project during all these years in terms of the directions issued on November 20, 1986. By this order we are finally disposing of the proceedings and the monitoring-process so far as the NTPC is concerned. The directions dated G November 20, 1986 relevant for this purpose are as under:- -.,, "(1) So far as the lands which have already been declared as reserved forest under Section 20 of the Act, the same would not form pail of the Writ Petition and any direction made by this Court earlier, now or in future in this case would not relate H 860 SUPREME COURT REPORTS [1992] 1 S.C.R. .• A to the same. In regard to the lands declared as reserved forest, it is, however, open to the claimants to eatablish their rights, if any, in any other appropriate proceeding. We express no opinion about the maintainability of such claim.'' B c D "(5) The land sought to the acquired for the Rihand SuperThermal Power Project of the NTPC shall be freed from the ban of dispossession. Such land is said to be about 153 acres for Ash Pipe Line and 1643 acres for Ash Dyke and are located in the villages of Khamariya, Mitahanai, Parbatwa, Jheelotola, Dodhar and Jarha. Possession thereof may be taken, ........ , but such possession should be taken in the presence of one of the commissioners who are being appointed by this ord~r and a detailed record of the nature and extent of the land, the name of the person who is being dispossessed and the nt[ture of enjoyment of the land and all other relevant .Particulars should be kept for appropriate use in future. Such records shall be duly certified by the Commissioner in whose presence possession is taken and the same should be available for use in all proceedings that may be taken subsequently. E The NTPC has agreed before the Court that it shall strictly follow the policy on "facilities to be given to land oustees" as placed before the Court in the matter of lands which are subjected to acquisition for its purpose. The same shall be taken as an undertaking to the Court." F Mr .Datta learned senior advocate appearing for the NTPC has stated that the NTPC has already taken actuaVsymbolic possession of 1375 acres of land. In respect of 1004 acres of the said land a notification under Section 4 of the Indian Forest Act, 1927 (hereinafter called 'the Act') was issued and the proceedings for declaring the said area as reserved forest were undertaken. The remaining 371 acres were part of Gaon Sabha land G and ownership in the said land vested in the State Government. According to Mr.Datta this land measuring 1375 acres is under the possession of NTPC and the project-construction ·is in progress. Mr.Rarnamurthy, on the other hand, has contended that the actual possession of whole of the area is not with the NTPC and the Adivasi/land owners are still in possesH sion of their respective holdings. SEVA ASHRAM _v._ STATE 861 > Mr. Datta further states that apart from 1375 acres, mentioned A above, the NTPC has yet to obtain possession of 465 acres of land which is reserved forest under Section 20 of the Act. **In** view of the directions quoted above the lands which have been declared as reserved forest under > the Act are not the subject matter of the writ petition and as such no direction can be issued by this Court in that respect. In this order, we are B concerned with 1004 acres of land which is subject-matter of Section 4 Notification under the Act. We have tu ensure that the rights of the oustees are determined in their respective holdings and they are properly rehablitated and adequately compensated. B According to the summary of rehabilitation-package filed on the record by Mr. Datta there are 678 families which have been ousted from the land. Mr. Ramamurthy, however states that there are more than 1500 families which are likely to be affected by the take'over of 1004 acres of land by the NTPC. c We direct that the following measures to rehabilitate the evictees **D** who were in actual physical possession of the lands/houses etc. be taken by the NTPC in collaboration with the State Government: 1. The NTPC shall submit a list of the evictees-claimants to the District Judge, Sonebharda before April 15,1992. Mr. Prem Singh shall also submit the list of the evic(ees to the District Judge by April 15, 1992. The District Judge Sonebhadra shall be the authority to finalise the list of **the evictees.** **E** 2. One plot of land measuring 60' x 40" to each of the evicteefamilies be distributed for housing purposes thru)lgh the district administration. Mr. DaUa has informed us that the plots of the said measurements have already been given to 641 families. We direct that the remaining evictees be also given the plots. **F** 3. Shifting allowance of Rs. 1500 and in addition a lumpsum rent of Rs. 3000 towards housing be given to each of the evictee-families. G ## 4. Free transportation shall be provided for shifting. 5. Monthly subsistence allowance equivalent to loss of net income from the acquired land to be determined by the District Judge Sonebhadra subject to· a maximum of Rs. 750 for a period of 10 years. The said SUPREME COURT REPORTS (1992] 1 S.C.R. 862 A payment shall not be linked with employment or any other compensation. 6. Unskilled and ~emi-skilled posts in the project shall be reserved for the evictees subject to their eligibility and suitability. 7. The NTPC shall give preferene to the oustees in employment in B class III and IV posts under its administration subject to their suitability and eligibility. · 8. The evictees be offered employment through the contractors employed·by the NTPC. c 9. The jobs of contractors under the administration of the NTPC be offered to the evictees. 10. The shops and other business premises within the NTPC campus be offered to the evictees. D 11. The NTPC shall operate for the benefit of the evictees selfgenerating employment schemes such as carpentary training (free tools to be provided after completion of training), carpet weaving training, sericulture, masonary training, dairy farming, poultry farming and basket weaving **training etc.** E 12. The NTPC shall provide facilities in the rehabilitative-area such • as pucca roads, pucca drainage system, hand pumps, wells, portable water supply, primary school, health centre, Panchayat Bhavan, electricity connections, bank and Sulabh Sauchalaya complex etc. F 13. The NTPC shall also provide hospitals, schools, adult education classes and sports centres for the evictees. The Deputy Commissioner Sonebhadra shall supervise and ensure that the above rehabilitation measures directed by us are fully complied G · witll by the NTPC and other authorities. As regards compensation in respect of lands, crops etc. Mr. Datta states that crop compensation at Rs. 850 per acre per year has been paid to the oustees. He states that a sum of Rs. 16,44,529.68 paise has been paid to the oustees in this respect. He further states that Rs. 1 crore and H Rs. 507500 have further been deposited by the NTPC with the State 863 SEVA ASHRAM _v._ STATE Government on March 13, 1991 and January 20, 1992 respectively. Ac- A cording to him out of the said amount, Rs. 48,35,649.17 paise have so far been paid to the oustees as land-compensation at the rate of Rs. 10,000 per acre. It is not disputed that Rs. 850 per acre per year for the crops and Rs. 10,000 per acre for the land has been determined as provisional compensation. We direct that the provisional compensation at the above B rates be paid to the oustees, if not already paid, within 8 weeks from today. In this respect we further issue the following directions: (a) The District Judge, Sonebhadra shall be the authority to determine the compensation in respect of land, crop, house and any other legitimate claim based on existing-rights of the oustees. C (b) Mr. Prem Singh, Commissioner along with the Project Officer of the NTPC and Sarpanch of the area concerned shall verify the extent of the property of the oustees who have been or are likely to be evicted from the actual physical possession of the lands/houses etc. It has been stated before us that such verification can be done within a period of two months. D We direct that the verification be completed before April 15, 1992. The rights determined by Mr. Prem Singh and party shall be subject to the final approval of District Judge, Sonebhadra. > (c) The District Judge, Sonebhadra shall issue notices to all the E claimants before May 15, 1992 asking them to file their respective claims for compensation. The evictees, may also on their own, whether they have **received provisional compensation or not prefer their claims for compen-** sation to the District Judge Sonebhadra before August 1, 1992. ( d) The District Judge Sonebhadra shall finally decide all the compensation claims expeditiously preferably before March 31, 1993. The orders passed by the District Judge in each case shall be treated as the orders under Section 17 of the Act as amended by the Uttar Pradesh Act 25 of 1965. F (e) Any party, not satisfied with the order of the District Judge, may G have recourse to any remedy available under law. With the above directions we finally close the proceedings in respect of the lands in possession of the NTPC . ... R.P. Petition disposed of.
End of Judgment Record
Browse All Supreme Court of India (1992) Decisions
1992-01-07

Jaiswal v. Debi Mukherjee

Dr. P. K. Jaiswal challenged a UPSC process for the post of Assistant Director General (Prevention of Food Adulteration). The Union Government had initially asked UPSC to fill the post by direct recruitment but, before advertisements, informed it to withhold the process while examining possible promotion from Assistant Secretary and amending recruitment rules to create higher tiers. Despite this, the UPSC advertised the post and the appellant was interviewed. Debi Mukherjee, then Assistant Secretary and seeking promotion upon the rule-amendment, obtained an interim stay from the Central Administrative Tribunal and later a direction to provide promotional avenues. In the meantime, two higher-pay tiers were created, without separate designations, under an amendment directed by the Court in a related matter. The appellant argued that once the selection process begins, the Government and Tribunal cannot freeze it and that the Commission should complete the selection; and that overlooking the two new layers amended later was erroneous. The respondents contended on points of vested rights and the proper policy- and rule-based framework for promotions versus direct recruitment. The Supreme Court held that the Government can withdraw the requisition before the advertisement if it intends to amend rules to permit promotion, that the Government’s pre-advertisement decision is permissible, and that a right to be considered for selection crystallizes only after advertisement and interview. The appeal was dismissed.

1992-09-24

S.B. Dogra v. State of Himachal Pradesh and Ors.

This Civil Appeal concerns the seniority of S.B. Dogra in the Himachal Pradesh Police Service in the wake of the demobilised armed forces concession. After HP State was formed, Rule 5(1) of the Demobilised Armed Forces Personnel (Reservation of Vacancies in the HP State Non-Technical Services) Rules, 1972, provided that the seniority of officers appointed against reserved vacancies shall be determined on the assumption that they joined the service at the first opportunity after their military service or training prior to commission. Dogra, who had military service and later joined the HP Police Service against a reserved vacancy for Demobilised Armed Forces Personnel, was placed with a notional entry year (1964) and thus ahead of some officers, including Durga Shanker Amist. The dispute escalated through High Court proceedings and a Central Administrative Tribunal decision relying on earlier cases. The Supreme Court, comparing Rule 5(1) with Punjab/Haryana rules and distinguishing the applicable statutory framework, held that the Tribunal erred in confining the seniority to the period of actual military service during the emergency. It noted that the rules are not pari materia with Haryana’s rules and that the language of Rule 5(1) permits a broader interpretation for notional entry. The Court distinguished certain earlier rulings (A.S. Parmar; Narendra Nath Pandey) as inapplicable here, while applying the State of Madhya Pradesh v. Rameshwar Prasad approach to preserve fair seniority. Ultimately, the appeal was allowed, the Tribunal’s seniority order was set aside, and the prior position was restored with directions for implementation of the judgment.

1992-12-11

State of Maharashtra v. Rattanlal

This is a Supreme Court decision interpreting the revisional powers of the State Government under the Maharashtra Agricultural Land (Ceiling and Holdings) Act, 1961. The respondent-declarant had a declaration under Sec. 12; the Surplus Land Determination Tribunal found surplus land (9 acres 8 guntas). On appeal, the Revenue Tribunal modified the resumption from Survey No. 11 to Survey No. 29, which was upheld. Later, after undisclosed lands came to light, the Additional Commissioner issued a show cause, remitted the matter to the primary Tribunal for redetermination and delimitation, and the High Court held that once an appeal under Sec. 21 is filed and an order is made, the Commissioner or the State Government lacks jurisdiction to determine the ceiling area. The State Government challenged this view. The Court held that under Sec. 45(2) and (3), the Commissioner has revisional powers, either suo motu or on an aggrieved person’s application, to call for records of inquiries under Secs. 17–21 and to pass orders after a hearing, subject to provisos including time limits and restrictions when appeals are pending. The decision also clarifies that suo motu revisional action can correct fraud or suppression of material facts, and that finality does not bar such action in cases of concealed lands. The High Court’s view was set aside and the Commissioner's order restored, with the appeal allowed along with costs.

1992-10-13

State of Madhya Pradesh and Anr. v. Syed Naseem Zahir and Others

State of Madhya Pradesh and Anr. v. Syed Naseem Zahir and Others concerns the legality and timing of the 'sealed cover' procedure used by the Departmental Promotion Committee (DPC) for recommending promotions when disciplinary proceedings were contemplated. Syed Naseem Zahir, who rose to Superintending Engineer, was included in a 1987 panel for promotion to Chief Engineer, but his name was kept in sealed cover due to potential misconduct. A charge-sheet was issued in 1988. The Madhya Pradesh Administrative Tribunal later directed promotion based on the sealed-cover recommendation, prompting the State's special leave appeal. The Supreme Court held that the departmental enquiry had been completed and the charges proved, and while it emphasized that Jankiraman's case governs sealed-cover use, the peculiar facts allowed keeping the sealed cover unopened until the disciplinary proceedings concluded. The Court outlined that if exonerated, the sealed-cover would be opened and the respondent would be notionally promoted from the date a junior was promoted, with consequential benefits, including back wages; if punished, action would be taken in accordance with Jankiraman's guidelines. The Court set aside the Tribunal's order and allowed the State's appeal, directing that no promotion be granted until proceedings end, and that the sealed-cover mechanism be used consistent with the facts.