Bangalore Electricity Supply Company Limited v. Hirehalli Solar Power Project LLP & Others
Case Synopsis & Summary
This Supreme Court judgment concerns three Civil Appeals arising from disputes over solar PPAs under Karnataka’s solar policy. The central issue is whether the extension of the Scheduled Commissioning Date (SCD) can be attributed to force majeure under the PPA and whether the resulting tariff reduction for the Respondents is justified. The Court upholds the Appellate Tribunal for Electricity (APTEL), and scrutinizes the Court’s appellate jurisdiction under Section 125 of the Electricity Act, 2003, emphasizing that the scope is restrictive and aims to permit regulatory bodies to develop sectoral law. The facts show that delays in project commissioning stemmed from multiple sources: land-use conversion, evacuation approvals, demonetisation, and other administrative steps, with APTEL recognizing that many delays were not attributable to the Respondents. The Court relies on Energy Watchdog v CERC for the governing law on force majeure (Sections 32 and 56 of the Contract Act, 1872) and notes that a narrowly construed force majeure clause applies. It also cites SEBI v Mega and a subsequent recognition in BSES Rajdhani on the notion of a “substantial question of law.” Ultimately, the Court concludes there is no substantial question of law to interfere with the APTEL’s findings and dismisses the appeals, with no costs.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- Pamidighantam Sri Narasimha
- Pankaj Mithal
- Judgment Date
- 2024-08-27
- Court Decision / Holding
- Appeals dismissed. No interference with APTEL’s findings; no substantial question of law; tariff restoration and late payment surcharge upheld; no order as to costs.
- Final Disposition
- Appeals dismissed; no interference with APTEL’s order; no costs.
Parties to the Case
Appellants / Petitioners
- Bangalore Electricity Supply Company Limited
Respondents
- Hirehalli Solar Power Project LLP
- Respondent No.2 (Farmer)
Legal Representation & Advocates
Counsels for Petitioners
- • K.M. Nataraj
- • Yasobant Das
- • Garima Jain
- • Arnav Khanna
- • Tushar Mahindroo
- • Mohit Singh
- • Arunav Patnaik
- • Ms. Bhabna Das
Counsels for Respondents
- • Prateek K. Chadha
- • Basava Prabhu Patil
- • Prerna Priyadarshini
- • Syed Faraz Alam
- • Atharva Gaur
- • Aayushman Aggarwal
- • Ujjal Banerjee
- • Anmol Sehgal
- • V. N. Raghupathy
- • Sreekar Aechuri
Provisions of Law Cited
Legal Doctrines & Maxims
- Doctrine of frustration
- Force majeure clause narrowly construed
- Substantial question of law as a precondition for appellate interference under Section 125 of the Act
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellants argued that force majeure must be strictly interpreted, requiring a specific pleading and written notice; they contended that no qualifying force majeure event or timely notice existed, hence tariff reductions and liquidated damages could not be justified.
Contentions of Respondents
The respondents argued that delays were caused by government processes and approvals beyond their control, and that APTEL correctly held entitlement to force majeure and an extension of time, justifying the higher tariff and avoiding liquidated damages.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (4)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Chennamangathihalli Solar Power Project LLP v. BESCOM | 2020 SCC OnLine APTEL 75 | Mentioned Only | Cited as a precedent by parties; the Court notes its existence and its influence on subsequent APTEL orders but does not adopt its ratio as binding in this case. |
| SEBI v. Mega Corporation Limited | [2022] 2 SCR 546 : 2022 SCC OnLine SC 361 | Positive | Cited to illustrate the meaning of ‘question of law’ in appellate jurisdiction under regulatory statutes. |
| Energy Watchdog v. Central Electricity Regulatory Commission | [2017] 3 SCR 153 : (2017) 14 SCC 80 | Positive | Cited as the leading authority on force majeure and the narrow construction of force majeure clauses under the Contract Act. |
| BSES Rajdhani Power Limited v. Delhi Electricity Regulatory Commission | (2023) 4 SCC 788 | Positive | Cited to acknowledge the pronouncement on ‘substantial question of law’ as a criterion for appellate interference. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Bangalore Electricity Supply Company Limited v. Hirehalli Solar Power Project LLP & Others
Related Decisions & Precedents from Supreme Court of India (2024)
Kizhakke Vattakandiyil Madhavan (Dead) Thr. Lrs. v. Thiyyurkunnath Meethal Janaki and Ors
This appeal concerns partition of a family property in Eravattur, Kozhikode, governed by pre-1956 Mitakshara succession. Madhavan died before 1910; his widow Chiruthey remarried Neelakandan, triggering Section 2 of the Hindu Widow’s Remarriage Act, 1856, which extinguishes a widow’s rights in her deceased husband’s property on remarriage. Chiruthey’s second marriage, and a sequence of instruments dated 1910–1925—back-to-back deeds creating a lease in favour of Cheriyamma and her son (Exhibits A-20 and A-1) and an assignment (Exhibit A-2)—formed the basis for Chandu (the plaintiff) and Sankaran’s successors-in-interest to seek partition in OS 157/1985. The Trial Court granted partition to the plaintiff; the First Appellate Court dismissed; the Kerala High Court restored the Trial Court’s decree. The Supreme Court, however, allowed the appeal. It held that on remarriage the widow’s title over Madhavan’s property stood lapsed under Section 2; yet the back-to-back deeds involved Nangeli (Madhavan’s mother) and Sankaran, who retained an interest. Exhibit A-20 was treated as a valid conveyance, but Chiruthey’s own title did not survive; the lease purportedly created by A-1 could not extend beyond its 12-year term. Consequently, the plaintiff’s claim for partition could not be sustained, and the appeal was allowed with the trial/decree of the lower courts set aside.
Banshidhar Construction Pvt. Ltd. v. Bharat Coking Coal Limited & Others
Banshidhar Construction Private Limited (the appellant) challenged Bharat Coking Coal Limited’s tender for a mega project to salvage, develop, and operate a coal mine under a revenue-sharing arrangement for 25 years. The tender NIT dated 16.08.2023 imposed stringent eligibility criteria, including Clause 10 requiring financial capacity documentation and a Power of Attorney for signing bids. The appellant contended that its Power of Attorney (dated 07.11.2023 and notarised 14.11.2023) was valid, and its bid documents were uploaded before the last submission date (01.12.2023). Technical bids opened on 04.12.2023, yet the appellant was declared technically disqualified on 06.05.2024 on grounds that it did not meet Clause 10. Meanwhile, Respondent No.8 was declared technically qualified and later found to be the successful bidder after financial bids were opened on 07.05.2024, despite non-compliance with the “mandatory” Clause 10 documents, including delayed Audited Balance Sheets. The High Court dismissed the writ petition. The Supreme Court, while acknowledging limited review in mega-project tenders, held that public authorities must act with fairness, transparency, and without arbitrariness or malafides. It held that the Power of Attorney requirement was satisfied and that accepting the non-compliant Respondent No.8 while rejecting the appellant was arbitrary. The Court set aside the impugned decision and permitted a fresh tender process in accordance with law, reaffirming that Article 14 requires equal treatment and non-arbitrariness in public procurement.
Union of India v. M/s Indian Oil Corporation Ltd.
This Supreme Court judgment concerns an appeal by the Union of India challenging a batch of Allahabad High Court orders that directed refunds to IOCL for a difference of approx. 110 km in freight charges on the Baad–Hisar route. IOCL had been charged on the basis of a distance of 444 km under the old Local Distance Table; following Railway Ministry circulars in 2004 and 2005 rationalizing the rounding-off of chargeable distance, the distance was reduced to 333.18–334 km in practice. IOCL issued notices under Section 106 of the Railways Act, 1989 (formerly Section 78-B of the Railways Act, 1890) seeking refunds of the alleged overcharge, and 122 consignments were paid at the old distance before the authorities corrected the distance. The Railway Claims Tribunal dismissed most claims as time-barred, while the Allahabad High Court allowed IOCL’s appeals, holding that the original 444 km charge was an “illegal charge” rather than an overcharge, and thus protected by equity. The Union of India challenged this, arguing that Section 106(3) only covers refunds of overcharges and not illegal charges; that the change in distance stemmed from policy rationalization and circulars, not an erroneous charge. The Court distinguishes Hindustan Petroleum, clarifies the overcharge/illegal charge distinction, and ultimately holds that the 444 km distance was illegal. As a result, the Union’s appeals are dismissed, and IOCL’s refunds for the difference would be payable to IOCL. The matter underscores the nuanced interplay between statutory time limits, chargeable distance, and the nature of the charge in refund claims.
Gene Campaign & Anr. v. Union of India & Ors.
This is a batch of writ petitions initiated in 2004–2005 addressing the environmental and regulatory treatment of GM crops, specifically the environmental release of transgenic mustard DMH-11 (Dhara Mustard Hybrid-11). The Supreme Court examined whether GEAC’s 18.10.2022 conditional approval and the 25.10.2022 decision were legally sound, whether they violated Article 21 (right to a safe environment) and whether the precautionary principle was properly applied. The court undertook a comprehensive review of the regulatory framework under the Environment Protection Act, 1986 and the 1989 Rules, as well as the Technical Expert Committee (TEC) reports and Parliamentary Standing Committee recommendations. A key feature is the dual opinions: Justice Nagarathna (with Justice Karol concurring but delivering a separate opinion) upheld a robust judicial review of executive policy in GM regulation and found serious irregularities in the decision-making process, quashing the impugned approvals and directing a national policy on GM crops, greater public transparency, and safe-guarded field testing. Justice Karol, in a separate opinion, while endorsing the need for precaution, cautioned against an outright ban on HT crops and emphasized policy matters be left to the legislature. The judgment thus emphasizes environmental rule of law, public trust, intergenerational equity, and a precautionary approach, while mandating further regulatory reform and public participation.