Case Synopsis & Summary

This is a Supreme Court order in Civil Appeals arising from the Bangalore Peripheral Ring Road (PRR) project proposed by the Bangalore Development Authority (BDA) to the State Government. Writ petitions challenging land acquisition under the BDA Act were decided by the Karnataka High Court in 2014 (WP No.4550/2008 and connected matters). The High Court held that with the repeal of the Land Acquisition Act, 1894 and the enactment of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (the 2013 Act), the 2013 Act would govern compensation, and that Section 24 of the 2013 Act could render the proceedings lapsing. The BDA challenged these conclusions, contending that the BDA Act itself provides a complete, self-contained framework and that Section 36(1) read with Section 36(3) of the BDA Act borrows the LA Act provisions only “so far as they are applicable,” i.e., by incorporation, with the 2013 Act not applying to acquisitions under the BDA Act. The Court relied on Offshore Holdings and other authorities to affirm that the BDA Act is a self-contained code and that incorporation is intended, rendering the 2013 Act’s regime inapplicable to these acquisitions. The result is that the High Court’s interpretation is overruled and the application is disposed of.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • S. Abdul Nazeer
  • Sanjiv Khanna
Judgment Date
2022-01-20
Court Decision / Holding
The Court disposed of the application, holding that the LA Act continues to apply to acquisitions made under the BDA Act so far as it is applicable, by incorporation, and that the 2013 Act does not regulate such acquisitions. The judgment overruled the High Court’s conclusion that the 2013 Act governs these proceedings and clarified that the BDA Act remains a self-contained code; the decision also overruled Sri Sudhakar Hegde (WP 4550/2008) and related matters.
Final Disposition
Application disposed of; High Court’s reasoning recognizing 2013 Act as governing the PRR land acquisitions under BDA Act is overruled; LA Act continues to apply to BDA Act acquisitions as incorporated.

Parties to the Case

Appellants / Petitioners

  • Bangalore Development Authority
  • Anr.

Respondents

  • The State of Karnataka
  • Ors.

Provisions of Law Cited

Land Acquisition Act, 1894 (as applicable to the BDA Act)Bangalore Development Authority Act, 1976 (BDA Act)Section 14 of the BDA ActSection 15 of the BDA ActSection 16 of the BDA ActSection 17 of the BDA ActSection 19 of the BDA ActSection 36(1) of the BDA ActSection 36(3) of the BDA ActRight to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (2013 Act)Section 24 of the 2013 ActSection 105 of the 2013 Act

Legal Doctrines & Maxims

  • Legislation by incorporation (borrowed provisions become part of the adopting statute)
  • Self-contained code (BDA Act treated as a complete framework)

Submissions & Arguments

Contentions of Appellants / Petitioners

The BDA contended that the PRR project requires land acquisitions under the BDA Act and that Section 36 of the BDA Act embeds the LA Act provisions only to the extent they are applicable, i.e., through legislation by incorporation; the 2013 Act should not govern or invalidate the acquisition proceedings under the BDA Act. It was urged that the High Court’s reliance on the 2013 Act to regulate compensation would frustrate the BDA Act’s self-contained scheme and its budgetary implications for the project. Further, the BDA argued that Offshore Holdings (Constitution Bench) supports the interpretation that the BDA Act is a self-contained code, and that the repeal of the LA Act does not alter the incorporated provisions.

Contentions of Respondents

The respondents argued that after the repeal of the LA Act, the 2013 Act would regulate compensation and that Section 24 of the 2013 Act determines lapsing of proceedings unless kept alive by the new regime; thus, the 2013 Act should govern land acquisition proceedings under the BDA Act to the extent applicable. They relied on the High Court’s reasoning that the 2013 Act would regulate the compensation and that Section 24 can affect lapsed proceedings, pending a decision on compensation and revalidation of the acquisitions.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
Offshore Holdings Private Limited v. Bangalore Development Authority and others2013 (9) SCC 460PositiveConstitution Bench decision held that the BDA Act is a self-contained code and that Section 36 of the BDA Act mandates legislation by incorporation; borrowed provisions apply only so far as they are applicable.
Special Land Acquisition Officer KIADB, Mysore and Another v. Anasuya Bai (dead) by Legal Representatives and others2017 (3) SCC 313PositiveAffirmed that provisions like Section 11-A and 24(2) of the LA Act do not apply to acquisitions under integrated State Acts; supports the principle of incorporation and non-applicability of certain provisions to State Acts.
State of M.P. v. M.V. Narasimhan—PositiveCited for the proposition that borrowed provisions become an integral part of the subsequent Act and that the subsequent Act governs the relationship, reinforcing legislation by incorporation.
Sri L. Ramareddy v. State of Karnataka and Ors.—PositiveSupported the view that Section 24 does not apply to acquisitions initiated under acts other than the LA Act, aligning with the incorporation approach.
Girnar Traders (3)—PositiveReferenced to support the principle of legislative interpretation involving incorporation and the self-contained nature of the BDA Act.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,559 words•~17 min read

In The Court Record

Bangalore Development Authority & Anr. v. The State of Karnataka & Ors.

1 ## **REPORTABLE** **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION ­ MISCELLANEOUS APPLICATION NO(S).1614 1616 OF 2019 IN ­ MISCELLANEOUS APPLICATION NO(S).1346 1348 OF 2019 IN ­ CIVIL APPEAL NO(S).7661 7663 OF 2018** **BANGALORE DEVELOPMENT AUTHORITY & ANR.** **… APPELLANTS** **VERSUS** **THE STATE OF KARNATAKA & ORS.** ## **… RESPONDENTS** ## **ORDER** ## **S. Abdul Nazeer, J.** ## I.A.No.147134 of 2021 (1) A peripheral ring road (for short, ‘PRR’) encircling Bangalore City for the length of 116 Kms. was proposed vide Letter dated 27.11.2006 by the Bangalore Development Authority (‘BDA’ for short) to the State Government. The scheme was sanctioned by the Government of Karnataka vide Signature Not Verified Digitally signed by UDD 399 MNX 2006 Bangalore dated 23.04.2007. This PRR is Anita Malhotra Date: 2022.01.22 10:34:44 IST Reason: to provide connectivity to various destinations in all the 2 directions for onward traffic without entering the city of Bangalore and thus minimising the congestion on the outer ring road as well as on the internal roads of the city. The affidavit filed by the Additional Chief Secretary before this Court dated 09.11.2021 highlights the importance of construction of PRR as under: ## “PROJECT NECESSITY 2. At the outset it is submitted that the Bengaluru City needs the Peripheral Ring Road (PRR) more than ever in view of the phenomenal growth of the city in all directions. The geographical extent of the city has grown to 2196 sq. kms. The vehicle count as of 2019 was over 80 lakhs. Bengaluru being the capital city, thousands of vehicles come in every day from various parts of the state as well as outside the state. There is enormous pressure on city roads and public transport system is overstressed. The PRR will greatly reduce the stress and congestion in the city roads. The Government is very keen to facilitate the early execution of the PRR.” 2. Notifications, both preliminary and final, have been issued by the BDA for acquisition of the lands for the PRR and several writ petitions were filed before the High Court of Karnataka challenging these notifications. One such writ petition was W.P.No.4550 of 2008 ( **Sri Sudhakar Hegde and others vs. the State of Karnataka and others** ). Several other similar 3 matters were clubbed along with the said writ petition. Learned Single Judge of the Karnataka High Court decided these matters on 22.07.2014. The questions formulated in the said cases were as under: “(a) Whether the repeal of the Land Acquisition Act 1894, has the effect of frustrating any proceedings with reference to Section 36 of the BDA Act. (b) Whether the acquisition proceedings can be said to have lapsed by virtue of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 having come into force.” 3. On the first question, learned Single Judge held that the provisions of the Land Acquisition Act, 1894 (for short, ‘LA Act’) that are made applicable to the BDA, are in the nature of legislation by reference. It was further held that in view of the repeal of the LA Act by coming into force of Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (for short, ‘2013 Act’) during the pendency of the writ petitions, it would be the corresponding provisions under the 2013 Act in so far as they are applicable which would regulate the acquisition proceedings. Learned Judge further held that the repeal of LA Act and coming into force of 2013 Act would not frustrate 4 further proceedings under the Bangalore Development Authority Act (for short ‘the BDA Act’). 4. However, on the second question, the Court observed that “it cannot therefore be said that by virtue of Section 24 of 2013 Act, the proceedings stood lapsed.” The Court held that the procedure that would regulate the proceedings would be as per the provisions of 2013 Act in so far as they are applicable. This would include the determination of compensation in accordance with the 2013 Act as no award had been passed in the present proceedings. 5. BDA has filed the above application contending that the direction in the above cases has totally upset the budget calculation of the project. It is further contended that the High Court has failed to refer and to consider the Constitution Bench judgment of this Court in **Offshore Holdings Private Limited v. Bangalore Development Authority and others[1] .** It is also contended that Section 36 of the BDA Act clearly mandates legislation by incorporation. BDA has filed this application seeking mainly the following relief: “Hold that the 2013 Act is not applicable to the BDA Act and the Judgment of the learned Single Judge dated 11/07/2014 in WP 4550/2008 and connected matters is per in-curium, otiose and unenforceable.” 1(2011) 3 SCC 139 5 6. We have heard the learned counsel for the parties. 7. The BDA Act was enacted by the Legislature of the State of Karnataka to provide for the establishment of a Development Authority for the development of city of Bangalore and the areas adjacent thereto and for matters connected therewith. The objects and reasons for enacting the Bangalore Development Act, 1976 are as under: ## “STATEMENT OF OBJECTS AND REASONS KARNATAKA ACT, NO.12 OF 1976 Karnataka Gazette, Extraordinary, dated 5-2-1976 At the conference of the Ministers for Housing and Urban Development held at Delhi in November, 1971, it was agreed that a common Authority for the development of metropolitan cities should be set up. Bangalore City with its population (as per last census) is a Metropolitan City. Different Authorities like the City of Bangalore Municipal Corporation, the City Improvement Trust Board, the Karnataka Industrial Area Development Board, the Housing Board and the Bangalore City Planning Authority are exercising jurisdiction over the area. Some of the functions of these bodies like development, planning, etc., are overlapping creating thereby avoidable confusion, besides hampering co-ordinated development. It is, therefore, considered necessary to set up a single authority like the Delhi Development Authority for the city areas adjacent to it which in course of time will become part of the city. For the speedy implementation of the above said objects as also the 20-point programme and for establishing a coordinating Central Authority, urgent action was called for. Moreover, the haphazard and irregular growth would continue unless checked by the Development Authority and it may not be possible to rectify or correct mistakes in the future. 6 It was therefore necessary to issue the measure in the form of an Ordinance. The Bill seeks to replace the said Ordinance.” ## 8. Section 14 of the BDA Act underlines the object of the Authority in the below terms: “14. **Objects of the Authority** :- The objects of the authority shall be to promote and secure the development of the Bangalore Metropolitan Area and for that purpose the authority shall have the power to acquire, hold, manage and dispose of movable and immovable property, whether within or outside the area under its jurisdiction, to carry out building, engineering and other operations and generally to do all things necessary of expedient for the purpose of such development and for purposes incidental thereto.” 9. Chapter III of the BDA Act provides for the power of the Authority to take up execution of development schemes for the development of the Bangalore Metropolitan area. Section 15 empowers the BDA to frame development schemes with the previous permission of the government to execute the same. Section 16 enumerates the particulars to be provided in such schemes. After preparation of the scheme under Section 17, the Authority shall draw up a notification furnishing the particulars of the scheme and the place where the lands proposed for acquisition. Within 30 days, notice shall be issued to the concerned persons inviting objections, if any, for the proposed acquisition. After considering the representations received in 7 that regard, the scheme shall be submitted to the government for sanction with modifications, if any, together with the plan, estimates and other particulars. After considering the proposals, the Government has to sanction the same. Upon sanction of the scheme under Section 19, the Government shall publish declaration that the lands are required for the public purpose. These are the formalities required to be complied with before proceeding further in the matter of execution of the scheme. 10. Chapter IV of the BDA Act deals with “Acquisition of Land”. This chapter contains Sections 35 and 36. The relevant provision for the purpose of the present case is sub-section (1) of Section 36 which is as under: “ **36. Provisions applicable to the acquisition of land otherwise than by agreement** – (1) The acquisition of land under this Act otherwise than by agreement within or without the Bangalore Metropolitan Area shall be regulated by the provisions, so far as they are applicable, of the Land Acquisition Act. 1894.” 11. Sub-section (3) of Section 36 of the BDA Act states that after the land vests in the Government under Section 16 of the LA Act, then the Government upon payment of cost of acquisition and upon the Authority agreeing to pay any further cost which may be incurred on the acquisition, shall transfer the land to the Authority whereupon it shall vest in the Authority. 8 12. The primary object of the BDA Act is to carry out a planned development and acquisition, is merely incident of such planned development. It is also clear that the provisions of the LA Act would be attracted only insofar as they are applicable to the BDA Act. Where there are specific provisions under the BDA Act, the provisions of the LA Act will not be attracted. The BDA Act has provided a complete process for determination of rights. For the purpose of the claims in regard to the matters which are not specifically dealt with in the BDA Act, reference to the LA Act in terms of Section 36 has been made. The intention of the Legislature is to take recourse for the provisions of the LA Act to a limited extent and subject to the supremacy of the provisions of the BDA Act. This is evident from the expression “so far as they are applicable” employed in sub-section (1) of Section 36. In **Offshore Holdings Private Limited** (supra), a Constitution Bench of this Court, after considering the scheme of the BDA Act and having regard to the language employed in Section 36, held that it is a legislation by incorporation. 13. Incorporation of an earlier Act into the later Act is a legislative device for the sake of convenience in order to avoid verbatim reproduction of the provisions of the earlier Act into 9 the later Act. Once the incorporation is made, the provisions of incorporated statute become an integral part of the statute in which it is transferred and thereafter there is no need to refer to the statute from which incorporation is made and any subsequent amendment made in it has no effect on the incorporating statute. (See: **C.N. Paramasivam and Another vs. Sunrise Plaza Through Partner and Others[2]** ) ## 14. In **Offshore Holdings Private Limited** (supra), it was held as under: **”43.** All these provisions show that the BDA Act has provided for a complete adjudicatory process for determination of rights and claims. Only in regard to the matters which are not specifically dealt with in the BDA Act, reference to the Land Acquisition Act, in terms of Section 36, has been made, for example, acquisition of land and payment of compensation. This also is a pointer to the BDA Act being a self-contained Act. ## XXX XXX XXX **50.** Applying the above principle to the facts of the case in hand, it will be clear that the provisions relating to acquisition like passing of an award, payment of compensation and the legal remedies available under the Central Act would have to be applied to the acquisitions under the State Act but the bar contained in Sections 6 and 11-A of the Central Act cannot be made an integral part of the State Act as the State Act itself has provided specific time-frames under its various provisions as well as consequences of default thereto. The scheme, thus, does not admit such incorporation. ## XXX XXX XXX **57.** The sequitur to the above principle is that the BDA Act has already been held to be a valid law by this Court not 2 2013 (9) SCC 460 10 repugnant to the Land Acquisition Act as they operate in their respective fields without any conflict. For the reasons aforereferred as well as the detailed reasons given by us in Girnar Traders (3 ~~)~~[5] ~~,~~ which reasoning would form part of this judgment, we have no hesitation in concluding that the BDA Act is a self-contained code. The language of Section 36 of the BDA Act clearly mandates legislation by incorporation and as per the scheme of the two Acts, effective and complete implementation of the State law without any conflict is possible. The object of the State law being planned development, acquisition is merely incidental thereto and, therefore, such an approach does not offend any of the known principles of statutory interpretation.” (emphasis supplied) 15. In **Special Land Acquisition Officer, KIADB, Mysore and Another vs. Anasuya Bai (dead) by Legal Representatives and others[3]** this Court was considering an identical question. There it was held that Section 11-A of the LA Act and Section 24(2) of 2013 Act are not applicable for acquisition made under KIADB Act. It was held thus: **“30.** Having regard to the aforesaid raison d’être for nonapplication of the old LA Act, on the parity of reasoning, provision of Section 24(2) of the new LA Act making Section 11-A of the old LA Act would, obviously, be not applicable. We would like to refer to the judgment in State of M.P. v. M.V. Narasimhan[4] in this behalf where following proposition is laid down: (SCC p. 385, para 15) “15. … ‘Where a subsequent Act incorporates provisions of a previous Act, then the borrowed provisions become an integral and independent part of the subsequent Act and are totally unaffected by any repeal or amendment in the previous Act. This principle, however, will not apply in the following cases: (a) where the subsequent Act and the previous Act are supplemental to each other; (b) where the two Acts are in pari materia; 3 2017 (3) SCC 313 4 2011 (3) SCC 1 11 (c) where the amendment in the previous Act, if not imported into the subsequent Act also, would render the subsequent Act wholly unworkable and ineffectual; and (d) where the amendment of the previous Act, either expressly or by necessary intendment, applies the said provisions to the subsequent Act.’” ## 16. On 3.12.2020 this Court in this very case has held as ## under: “Needless to state that the acquisition of the land under the BDA Act is regulated by the provisions of the LA Act so far as they are applicable. (See: Section 36 of the BDA Act). The borrowed provisions of LA Act, became an integral part of the BDA Act and are totally unaffected by the repeal of the LA Act. In other words, the provisions of the LA Act are incorporated into the BDA Act so far as they are applicable. Of course, the bar contained in Section 6 and 11-A of the LA Act, are not applicable to the BDA Act. We have discussed this aspect of the matter in our main judgment dated 03/08/2018. It is also clear that the provisions of the Right of Compensation and Transparency in Land Acquisition, Rehabilitation & Resettlement Act, 2013 are not applicable for the acquisition made under the BDA Act. Final notification has also been issued after the pronouncement of judgment by this Court in Civil Appeal No(s). 7661-7663 of 2018 dated 03/08/2018. We direct the BDA to proceed with the acquisition of the land as proposed in the notification.” 17. Therefore, the provisions of the LA Act continue to apply for acquisitions made in the BDA Act so far as they are applicable as it is a legislation by incorporation having regard to Section 36 of the BDA Act. 18. The question may also be examined from a different angle. Section 24 of the 2013 Act expressly refers to the land 12 ## acquisition proceedings initiated under the LA Act. Sub-section ## (1) of Section 24 of the 2013 Act is as under: **“24. Land acquisition process under Act No. 1 of 1984 shall be deemed to have lapsed in certain cases -** (1) Notwithstanding anything contained in this Act, in any case of land acquisition proceedings initiated under the Land Acquisition Act, 1894,-- - (a) where no award under section 11 of the said Land Acquisition Act has been made, then, all provisions of this Act relating to the determination of compensation shall apply; or - (b) where an award under said section 11 has been made, then such proceedings shall continue under the provisions of the said Land Acquisition Act, as if the said Act has not been repealed. (2) Notwithstanding anything contained in sub-section (1), in case of land acquisition proceedings initiated under the Land Acquisition Act, 1894 (1 of 1894), where an award under the said section 11 has been five years or more prior to the commencement of this Act but the physical possession of the land has not been taken or the compensation has not been paid the said proceedings shall be deemed to have lapsed and the appropriate Government, if it so chooses, shall initiate the proceedings of such land acquisition afresh in accordance with the provisions of this Act: Provided that where an award has been made and compensation in respect of a majority of and holdings has not been deposited in the account of the beneficiaries, then, all beneficiaries specified in the notification for acquisition under section 4 of the said Land Acquisition Act, shall be entitled to compensation in accordance with the provisions of this Act.” 19. The 2013 Act repeals only the LA Act and not any other Central or State enactment dealing with acquisition. Therefore, what is sought to be saved under Section 24 of the 2013 Act is only acquisitions which had been initiated under the LA Act and 13 not those acquisitions which had been initiated under any other Central or State enactment. The expression contained in Section 24 of the LA Act cannot be given extensive interpretation by adding words into the provision, in the absence of the provision itself giving rise to any such implication. We are of the view that 2013 Act would not regulate the acquisition proceedings made under the BDA Act. 20. Section 105 of the 2013 Act states that the provisions of the 2013 Act shall not apply to the enactments in the Fourth Schedule or are to apply with modifications in terms of notification issued by the Central Government under Section 105(3) of the 2013 Act. Section 105 does not apply to the present case. 21. Recently, a Division Bench of the Karnataka High Court in **Sri. L. Ramareddy vs. the State of Karnataka and Ors.[5]** has considered identical questions in great detail and has concluded as under: “ **44** . In the circumstances, it is concluded and held that Section 24 does not take within its scope nor does it apply to acquisitions which have been initiated under the provisions of any other enactment particularly, State enactment, such as, BDA Act. The said Section is restricted to only those acquisitions which have 5 W.A. No.1415/2018 (LA-BDA) disposed of on 1[st] December, 2020 14 been initiated under the provisions of the LA Act, 1894 only. Subject to compliance of the conditions mentioned under subsection (2) of Section 24, the land owner would be entitled to the deeming provision regarding lapse of acquisition and not otherwise.” We are in complete agreement with this judgment of the High Court. 22. We may also notice here that the learned Single Judge of the High Court has not followed the judgment in **Offshore Holdings Private Limited** (supra) wherein it was clearly held that the provisions of the LA Act are applicable to the BDA Act by incorporation. 23. In view of the above, the Learned Judge of the High Court in **Sri Sudhakar Hegde** (supra) was not justified in holding that the provisions of LA Act that are made applicable to the BDA Act are in the nature of legislation by reference. The learned Judge has also erred in holding that in view of the repeal of LA Act by coming into force of 2013 Act, the corresponding provisions of 2013 Act would regulate acquisition proceedings under the BDA Act and that this would include determination of compensation in accordance with 2013 Act. It is hereby clarified that since LA Act has been incorporated into the BDA Act so far as they are applicable, the provisions of 15 2013 Act are not applicable for the acquisitions made under the BDA Act. Therefore, the judgment of the learned Single Judge of the High Court in **Sri Sudhakar Hegde** (supra) and other connected matters is hereby overruled. 24. Application is accordingly disposed of. **…..……………………..…J. (S. ABDUL NAZEER)** **….…………………………J. (SANJIV KHANNA)** **New Delhi; January 20, 2022**
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.