High Court of KeralaKerala High Court · 2009Division BenchAppeals Allowed; Cross Objection Dismissed; Ref...

Badagara Municipality v Kandiyil Sudhakar Kurup and The Special Tahasildar (LA), Quilandi

Case / Petition Number:
LA.App. No. 403 of 2007; LAR.20/2003 of Sub Court, Vadakara; L.A.A. Nos.317/2007, 322/2007, 324/2007, 326/2007, 339/2007, 347/2007, 350/2007, 353/2007, 366/2007, 367/2007, 377/2007, 397/2007, 419/2007
Neutral Citation:/null

Case Synopsis & Summary

This batch comprises Land Acquisition Appeals arising out of the 1999 Section 4(1) notification for acquiring land to construct a link road from the C.C. Road to Viliappilly Road by Badagara Municipality. The Reference Court and the Subordinate Judge had fixed compensation by relying on Ext.A2 and Ext.B8 judgments (relating to earlier acquisitions on the same project) and, importantly, the Sub Judge added a uniform 10% per year for the 10-year interval between the two notification dates, pushing the market value to a much higher figure. The appellants argued that the rural nature of the area and the need to raise lands by five metres did not justify such steep increments, and they challenged the 10% annual addition as unsound. The claimants and the Ist Respondent contended that the higher compensation and the comparables (Ext.A2, Ext.B8) were appropriate, while criticizing Ext.A1 (produced by a Co‑operative Society) and its reliance as unreliable due to its executant. The High Court undertook a careful reappraisal, disallowing Ext.A1 for lack of comparability, and determining that Ext.A2 and Ext.B8 were the safe base for valuation. It held that the area could not be categorized as urban; the permissible annual increase should follow the ratio stated in a Supreme Court decision (5–7.5% rural, up to 15% urban). It ultimately refixed the market value at Rs. 31,000 per cent, allowing the appeals and dismissing the cross objection, with statutory benefits under the Land Acquisition Act. The decision underscores cautious use of time-related increments and reliance on relevant comparables in rural development contexts.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • Pius C. KuriaKose
  • K. Surendra Mohan
Judgment Date
2009-09-29
Court Decision / Holding
The appeals are allowed. The Subordinate Judge’s method of applying a uniform 10% per year addition for 10 years is not accepted. The court agrees that Ext.A2 and Ext.B8 are the safe bases for valuation, rejects Ext.A1, and refixes the market value at Rs. 31,000 per cent after applying a maximum annual increase compatible with the Supreme Court’s ratios (5–7.5% in rural areas; up to 15% in urban areas). The cross objection is dismissed. Parties bear their own costs. On the enhanced compensation, claimants will receive all statutory benefits under Section 23(1A), 23(2) and 28 of the Land Acquisition Act.
Final Disposition
Appeals Allowed; Cross Objection Dismissed; Refixed market value Rs.31,000 per cent; Enhanced compensation with statutory benefits under the Land Acquisition Act.

Parties to the Case

Appellants / Petitioners

  • The Secretary, Badagara Municipality, Badagara, Kozhikode District

Respondents

  • Kandiyil Sudhakar Kurup
  • The Special Tahasildar (LA), Quilandi, Kozhikode District

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri.P.K.Vijayamohan
  • • Sri.O.V.Maniprasad

Counsels for Respondents

  • • Sri.P.K.Babu
  • • Sri.K.Rakesh Roshan
  • • Sri.Thushara.V

Provisions of Law Cited

Land Acquisition Act, Section 4(1)Land Acquisition Act, Sections 23(1A) & 23(2)Land Acquisition Act, Section 28

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants submitted that the Sub Judge erred in applying a uniform 10% annual enhancement for the 10-year gap between notification dates. They argued the area was rural/under development and that the percentage of increase should be limited (per governing precedent) rather than fixed at 10% yearly. They contended Ext.A2 and Ext.B8 provide the appropriate comparables, and that Ext.A1 is not reliable due to lack of comparability, hence should not form the basis for refixation.

Contentions of Respondents

The respondents contended that Ext.A2 and Ext.B8 reflect reasonable market values, and the Reference Court’s approach was justified. They urged maintaining the established enhancements where development and urban potentials exist, and they supported the higher values claimed by claimants, including the cross-objector’s Rs.1,00,000 per cent demand, while denying Ext.A1’s credibility.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
G.M. Oil & Natural Gas Corporation Ltd. v. R. Jivanbhai Patel & another2008 SAR (Civil) 894PositiveCited to justify the permissible rate of increase for time passage; the court adopts the 5–7.5% rural (up to 15% urban) framework from this decision.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,508 words•~7 min read

In The Court Record

Badagara Municipality v Kandiyil Sudhakar Kurup and The Special Tahasildar (LA), Quilandi

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE PIUS C.KURIAKOSE & THE HONOURABLE MR. JUSTICE K.SURENDRA MOHAN TUESDAY, THE 29TH SEPTEMBER 2009 / 7TH ASWINA 1931 LA.App..No. 403 of 2007() ------------------------LAR.20/2003 of SUB COURT, VADAKARA .................... APPELLANT(S): RESPONDENT NO.2 ----------------------------- THE SECRETARY, BADAGARA MUNICIPALITY, BADAGARA, KOZHIKODE DISTRICT. BY ADV. SRI.P.K.VIJAYAMOHANAN SRI.O.V.MANIPRASAD RESPONDENT(S): CLAIMANTS & THE IST RESPONDENT --------------------------------------------- 1. KANDIYIL SUDHAKARA KURUP, S/O.AMMALU AMMA, RESIDING AT KANDIYIL NEAR PUBLIC LIBRARY, BADAGARA. 2. THE SPECIAL TAHASILDAR (LA), QUILANDI, KOZHIKODE DISTRICT. GOVERNMENT PLEADER SRI.P.K.BABU FOR R2 SRI.K.RAKESH ROSHAN FOR R1 SMT.THUSHARA.V FOR R1 THIS LAND ACQUISITION APPEAL HAVING BEEN FINALLY HEARD ON 29/09/2009, ALONG WITH LAA NO. 419/2007 & CONNECTED CCASES THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING: ## **PIUS C.KURIAKOSE & K.SURENDRA MOHAN, JJ.** ## **-----------------------L.A.A.Nos.317, 322,324, 326,339,347,350,353, 366,367,377,397,403 & 419 of 2007 ------------------------** Dated this the 29[th] day of September, 2009 ## **JUDGMENT** Pius C.Kuriakose, J. All these appeals have been preferred by the Badagara Municipality, the requisitioning authority. The acquisition was for the purpose of construction of a link road connecting the C.C.Road to Viliappilly Road. Relevant Section 4 (1) notification was published on 27/4/1999. The award was passed on 29/5/2002. The Land Acquisition Officer awarded land value at the rate of Rs.7612.53/- per cent. The claimants produced various documents including Ext.A2 judgment of the same Reference Court in acquisition pertaining to other reaches of the same road, but pursuant to a notification published 10 years earlier. The Government produced Ext.B8 judgment, which was a judgment of the Reference Court pertaining to the acquisition for the same purpose pursuant to a notification published 10 years earlier. The learned Sub Judge did not become inclined to L.A.A.No.317/2007 & others. 2 place reliance on any of the documents produced by the claimants. What the learned Subordinate Judge did was to notice that under Ext.A2, the land value had been refixed at Rs.20,000/- per cent and that under Ext.B8, the land value had been refixed at Rs.15,000/- per cent. The learned Sub Judge took an average and concluded that as on the date of Exts.A2 and B8, value of the property as per those judgments was Rs.17,500/-. The learned Subordinate Judge would add at the rate of 10% every year for the period of 10 years which passed from the date of Section 4(1) notification relating to Exts.A2 and B8 till the date of Section 4(1) notification pursuant to which, the acquisition was made. Thus, the land value was refixed at Rs.35,000/- per cent. In these appeals, the requisitioning authority challenges the value refixed by the learned Sub Judge as excessive. It is urged that the lands were low lying lands and that they had to be raised by 5 metres, so as to enable the Municipality to accomplish its purpose of constructing the link L.A.A.No.317/2007 & others. 3 road. The action of the learned Sub Judge in making additions at the uniform rate of 10% every year is also comes up for strong attack in all these appeals. 2. The memorandum of Cross Objection (C.O. No.82/2007) has been filed by the claimant in L.A.A. No.322/2007, the appeal preferred by the requisitioning authority against the judgment and decree in L.A.R No.23/2003. In memorandum of Cross Objection, the decision of the learned Subordinate Judge is challenged and it is contended that the enhancement granted by the Reference Court is inadequate. In the cross objection it is claimed that the market value should have been refixed at Rs.1,00,000/- per cent as claimed in the claim statement filed before the Land Acquisition Officer and the Reference Court. 3. We have heard the submissions of Sri. Allen Pappali, learned counsel for the appellant, Sri.Parthasarathy, learned counsel for the Cross objector in L.A.A. No.322/2007, Sri.M.Gopikrishnan Nambiar and Sri.K.Rakesh Roshan, learned L.A.A.No.317/2007 & others. 4 counsel appearing for the various claimants and Sri.P.K.Babu, learned senior Government Pleader appearing for the Government. 4. Sri.P.K.Babu, learned senior Government Pleader would support all the submissions of Sri.Pappalli. The learned counsel Sri.Papalli submitted that the court below was not justified in making additions at a uniform rate of 10% for each year which passed after section 4(1) notification relating to the acquisition in question. This part of the Vadakara Municipality was actually rural area and that addition exceeding 5% per year was not at all justified, according to the learned counsel. The learned counsel submitted that lands were low lying lands and that huge amounts had to be expended by the Municipality, so that the Municipality's purpose of constructing link road could be accomplished. Sri.Parthasarathy, learned counsel for the cross objector would submit that the market value fixed by the L.A.A.No.317/2007 & others. 5 Reference Court is inadequate. According to him, having regard to the importance of the locality, which is in evidence, there was justification for refixing the value at Rs.1,00,000/- per cent. He would submit that it is not correct to say that this part of the Vadakara Municipality was rural and became urban only recently. Though it is true that no building existed on the lands under acquisition, in close proximity to the lands where existed commercial buildings and land under acquisition had commercial potentiality. The learned counsel pointed out that on account of the acquisition and the emergence of the Link Road at 5 metres away from the levels of the remainder land, the value of the remainder land has become reduced considerably. The counsel submits that this court may keep in mind this aspect of the matter while refixing the compensation. Sri.Rakesh Roshan and Sri.Gopikrishnan Nambiar would support all the submissions of Sri.Parthasarathy. Sri.Rakesh Roshan in particular would submit that the Land Acquisition Officer, who was examined as RW1, had L.A.A.No.317/2007 & others. 6 no answer when it was suggested to him in cross examination that land value was increasing in the area till 1989 at 15 to 20% every year. Referring to Ext.A1, the learned counsel submitted that Ext.A1 reveals land value of Rs.1,78,000/- per cent. Ext.A1 was executed by s Co-operative Society. The reasoning of the learned Sub Judge for rejecting Ext.A1 that it is executed by the Co-operative Society in favour of two of its members is not a sound reasoning at all. 5. We have very anxiously considered the rival submissions addressed at the Bar. We have made a through reappraisal of the evidence which was available before the court below. Even though the reasoning of the court below that Ext.A1 document cannot be relied on for the reason that a Co-operative Society is the executant of that document and that the document is in favour of two of its members, is not a sound reasoning, we are able to approve the action of the learned Subordinate Judge in L.A.A.No.317/2007 & others. 7 not placing reliance on Ext.A1. This is because there is no acceptable evidence regarding the comparability of the property under acquisition and the property covered by Ext.A1. On the available evidence it can be held that the property under acquisition was much inferior in value as well as quality to the property covered by Ext.A1. According to us also, the only documents which could have been safely relied on were Exts.A2 and Ext.B2 and the court below was justified in taking the average of the value reflected in these documents ( Rs.17,500/-.) as the basic figure. At the same time, we cannot approve the action of the learned Subordinate Judge in making additions at the rate of 10% per Are for passage of 10 years period between the date of Section 4(1) notification relating to Ext.A2 and Ext.B8 till date of Section 4 (1) notification in the present case. The Supreme Court in a recent decision in G.M.Oil & Natural Gas Corporation Ltd. v. R.Jivanbhai Patel & another (2008 SAR (Civil) 894) observed that the proper percentage to be added in rural L.A.A.No.317/2007 & others. 8 areas for passage of time is between 5 to 7.5% and that in urban area the same can be upto 15%. According to us, the area of the property under acquisition cannot be branded as an urban area. It was only rural area under the process of development as urban. The maximum percentage which could have been added per year in this case was 7.5% and when additions were made in that way the market value of the land will come to Rs.30,625/which we round off to Rs.31,000/-. The result of the above discussion is that the market value of the land under acquisition is refixed at Rs.31,000/- in modification of the fixation done under the impugned judgment. The appeals are allowed as above. The Cross Objection is dismissed. The parties will suffer their respective costs. It is, however, made clear that on the total enhanced compensation to which the claimants become entitled by virtue of the refixation done under this judgment, the claimants will be entitled for all L.A.A.No.317/2007 & others. 9 statutory benefits admissible under Section 23 (1A), 23(2) and 28 of the Land acquisition Act. **PIUS C.KURIAKOSE,JUDGE** **K.SURENDRA MOHAN, JUDGE** dpk
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.