This appeal under Section 62 of the Insolvency and Bankruptcy Code, 2016 challenges the limitation position in initiation of CIRP against Veer Gurjar Aluminium Industries Pvt. Ltd. JM Financial Assets Reconstruction Company Pvt. Ltd. (as assignee of loans) moved Section 7 before NCLT in 2018. NCLT admitted the application on 09.08.2018, and NCLAT initially dismissed the appeal in 2018. This Court, in Civil Appeal No. 10710 of 2018, remanded for a decision on limitation in light of BK Educational Services, and NCLAT subsequently held the application within time. The Supreme Court then undertook a comprehensive review of limitation, holding that Section 7 petitions are governed by Article 137 of the Limitation Act, with three years to sue from the date of default, and that the right to file accrues with the Code's enactment but cannot revive time-barred debts via the balance-sheet acknowledgments or offers of one-time settlements. It concluded the debt default occurred on 08.07.2011 and that the limitation period could not be extended to sustain the petition, especially given the 238-A framework. The Court set aside the NCLT/NCLAT orders, rejected the Section 7 application as time-barred, annulled related proceedings, and left no costs. The decision narrows how limitation operates in IBC proceedings and reinforces that the Code is not a backdoor for reviving time-barred debts.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- A. M. Khanwilkar
- Dinesh Maheshwari
- Judgment Date
- 2020-08-14
- Court Decision / Holding
- The Supreme Court held that the Section 7 application is barred by limitation; set aside the NCLAT’s 14.05.2019 order and the NCLT’s 09.08.2018 admission; dismiss the Section 7 application; annul all proceedings including the interim resolution professional; moratorium lifted; no costs.
- Final Disposition
- Appeal allowed to the extent of holding the Section 7 application time-barred; NCLT/NCLAT orders set aside; Section 7 petition rejected; moratorium lifted; proceedings annulled; no costs.
Parties to the Case
Appellants / Petitioners
- Babulal Vardharji Gurjar
Respondents
- Veer Gurjar Aluminium Industries Pvt. Ltd.
- Anr.
Provisions of Law Cited
Legal Doctrines & Maxims
- The Code is a beneficial legislation aimed at revival and not merely a recovery mechanism for creditors.
- Default triggers CIRP and the right to sue accrues on the date of default.
- There is no equity about limitation in the context of IBC proceedings (no fresh lease of life to time-barred debts).
- 238-A clarificatory retrospective effect applies to Limitation Act in IBC proceedings (procedural law).
- The law of limitation applies to IBC proceedings from inception, and three-year limitation under Article 137 governs Section 7 petitions unless extended by valid grounds under Section 5 of the Limitation Act.
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellant contends that the Section 7 application was filed in March 2018 and is barred by the three-year limitation under Article 137 of the Limitation Act, as default occurred on 08.07.2011. It argues that the Code’s enactment on 01.12.2016 cannot restart limitation and relies on BK Educational Services to insist on a three-year period from default. It contends that NCLAT erred by treating balance-sheet acknowledgments, OTS communications, or 12-year mortgage-based limitations as a lifeline for time-barred claims and that Section 238-A cannot revive a time-barred debt. It also cautions against treating 238-A as a retroactive remedy to revive stale claims and emphasizes that the CIRP process is intended to revive the corporate debtor, not to enforce time-barred debts.
Contentions of Respondents
The respondents argue that limitation does not bar the petition because the debt was continuously acknowledged in balance sheets and annual reports and because OTS communications show ongoing negotiation. They rely on Article 18 of the Limitation Act for extension through acknowledgment, and on Article 61(b)’s twelve-year period for mortgage possession, while noting pending OA No. 172/2013 before the DRT. They assert that the Code’s scheme allows continuing action via related proceedings and that 238-A makes Limitation Act applicable. They contend that the right to file accrues with the Code’s enactment, and that the balance-sheet acknowledgments and OTS offer interrupt or extend the limitation period, thereby keeping the petition within time.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (13)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Innoventive Industries Ltd. v. ICICI Bank | 2018 (1) SCC 407 | Positive | Foundation for CIRP trigger, existence of debt and default; explains the Code’s scheme. |
| B.K. Educational Services Pvt. Ltd. v. Paras Gupta & Associates | AIR 2018 SC 5601 | Positive | Articulates applicability of Limitation Act to IBC proceedings and Article 137’s three-year period. |
| Jignesh Shah and Anr. v. Union of India and Anr | 2019 SCC Online 1254 | Mentioned Only | Cited for discussion on Section 18 acknowledgment; not adopted to alter BK Educational ratio here. |
| Gaurav Hargovindbhai Dave v. Asset Reconstruction Company (India) Ltd. & Anr. | 2019 SCC 572 | Positive | Disapproved reliance on Article 62 and reaffirmed Article 137 as applicable for Section 7. |
| Vashdeo R. Bhojwani v. Abhyudaya Co-operative Bank Ltd. & Anr. | 2019 SCC 158 | Distinguished | Rejects continuing cause of action as a basis to extend limitation for IBC petitions. |
| Binani Industries Ltd. v. Bank of Baroda & Anr. | Company Appeal (AT) Insolvency No. 82 of 2018 | Positive | Noted for retrospective view that I&B Code is not a mere suit; limitations context is distinct. |
| K. Sashidhar v. Indian Overseas Bank | 2019 SCC Online 257 | Positive | Restates accrual of right to sue on default; supports Article 137 applicability. |
| Swiss Ribbons Private Limited v. Union of India and Ors. | 2019 (4) SCC 17 | Positive | Affirms Code’s protective, non-adversarial intent toward corporate debtors and default focus. |
| ArcelorMittal India (P) Ltd. v. Satish Kumar Gupta & Ors. | 2019 (2) SCC 1 | Positive | Discusses CIRP framework and Code objectives; foundational to subsequent reasoning. |
| Anuj Jain v. Axis Bank Limited and Ors. | Civil Appeal Nos. 8512-8527 of 2019 | Positive | Cited in the context of Section 238-A and the broader limitation discussion. |
| Sagar Sharma & Anr. v. Phoenix Arc Pvt. Ltd. & Anr. | 2019 (10) SCC 750 | Positive | Reiterates BK Educational ratio; supports Article 137 limitation framework. |
| N. Balakrishnan v. Krishnamurthy | 1998 (7) SCC 123 | Mentioned Only | Cited for general principle that limitation rules should not defeat substantive rights; not central to the Court’s current holding. |
| Mahabir Cold Storage v. CIT, Patna | 1991 Supp (1) SCC 402 | Mentioned Only | Referenced regarding scope of Section 18 and limitations; used as argument support rather than controlling law. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Babulal Vardharji Gurjar v. Veer Gurjar Aluminium Industries Pvt. Ltd. & Anr.
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.