Babu S v. State of Kerala and Others
Case Details & Bench
- Court
- High Court of Kerala
- Hon'ble Judges
- N. Nagaresh (N. Nagareesh)
- Judgment Date
- 2021-01-27
- Court Decision / Holding
- Writ petition dismissed. The court held that the obstruction was limited in scope and did not establish fault on the part of the contractor; the termination of the contract at the risk and cost, followed by retendering, was not illegal or arbitrary given the contractor’s non-resumption. The petitioner’s claim for recovery of amounts is not adjudicated in this petition; he may pursue appropriate legal remedies for any outstanding sums. The court did not interfere with the retender proceedings.
- Final Disposition
- Writ petition dismissed; petitioner may pursue required legal remedies for any arrears through appropriate proceedings.
Parties to the Case
Appellants / Petitioners
- Babu S
Respondents
- State of Kerala
- Superintending Engineer, Minor Irrigation Circle
- The Chief Engineer, Irrigation Department
- Central Bank of India
- KalliYoor Grama Panchayat
Legal Representation & Advocates
Counsels for Petitioners
- • Sri B. Krishna Mani
Counsels for Respondents
- • Smt. Deepa Narayanan (Government Pleader for 1-3)
- • Sri K.M. Aneesh
- • Sri Adarsh Kumar
- • Sri Biju Varghese Abraham
- • Sri Dileep Chandran
- • Sri R. Gopan
- • Sri K. Santosh Kumar Kaliyanam
Case Synopsis & Summary
This writ petition (WPC No.30886/2015) filed in the Kerala High Court seeks admeasurement of Ext.P1 work completed under a NABARD-assisted RIDF XVIII scheme for Nedinjil Ela Thodu in Kalliyoor Panchayat, and payment of dues, along with permission to participate in proposed re-tendering. The petitioner, a Class-A government contractor, entered into Ext.P1 agreement, deposited security, and undertook 18 items valued at ₹44,79,163. Local resistance led by Nemom Block Member obstructed the project, prompting cessation of work. The petitioner informed respondents 2 and 3 and submitted several representations, yet the department paid part of the bill and ultimately terminated the contract on 20.09.2014, deciding to retender, with forfeiture of security deposits. The petitioner contends the obstruction was the cause of non-performance and that the respondents failed to remove impediments, making the termination at risk and cost unjustified; he also contends that only adjudicated damages can be recovered and the forfeiture was arbitrary. Respondents argue obstruction was confined to a small area; notices were issued; non-resumption occurred despite reminders; termination at risk and cost is a contractual consequence, with re-tendering to follow. The court, after considering the pleadings, finds the obstruction limited in scope and upholds the risk-and-cost termination, while instructing the petitioner to pursue any outstanding amounts through appropriate legal proceedings, ultimately dismissing the petition.
Submissions & Arguments
Contentions of Appellants / Petitioners
The petitioner contends that local resistance and obstruction in a portion of the work area prevented execution, and that the respondents failed to remove impediments, rendering non-completion not his fault. He argues that recovery should be limited to adjudicated amounts and that forfeiture of security deposits is arbitrary. He seeks admeasurement of completed work and payment, and permission to participate in re-tendering under Ext.P1.
Contentions of Respondents
The respondents contend the obstruction was limited to a small area; the department issued letters and reminders for the petitioner to proceed; despite the hindrance, a portion of the work was executed and payment made; on non-resumption, the contract was terminated at the contractor’s risk and cost and re-tendering was initiated, a usual contractual remedy under the terms of the agreement.
Cited Precedents (2)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Ponnappan K.A. v. DFO, Chalakudy and others | 1984 KLJ 853 | Distinguished | The court acknowledged the authority but found it not applicable to the present contractual context, as the case deals with different implications of damages and recovery amidst contract termination. |
| State of Kerala v. Universal Marine Agencies | 1980 KLT 187 | Distinguished | The judgment relied on by the petitioner was found not helpful to the petitioner's claim; contract terms and risk-and-cost provisions govern the outcome here. |
Diagnostic Tool
Does this judgment govern your specific facts?
Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Babu S v. State of Kerala and Others and instantly map out authorities that support, challenge, or govern your position.
Extracted Judgment Text
Exact text extracted from official judgment records.