B. Suresh v. State of Kerala and Others
Case Details & Bench
- Court
- High Court of Kerala
- Hon'ble Judges
- P. V. Kunhikrishnan, J.
- Judgment Date
- 2023-01-20
- Court Decision / Holding
- Exts.P5, P7 and P8 are quashed. The 4th respondent is to reconsider the matter after giving the petitioner an opportunity of hearing.
- Final Disposition
- Writ petition allowed in part; Exts.P5, P7 and P8 quashed; direct the 4th respondent to reconsider after granting hearing to the petitioner.
Parties to the Case
Appellants / Petitioners
- B. Suresh
- Anitha Suresh (Addl.2)
Respondents
- State of Kerala represented by District Collector, Pathanamthitta
- Deputy Tahsildar Revenue Recovery, Taluk Office, Adoor
- Chief Engineer, Kerala State Electricity Board, Thiruvananthapuram
- Executive Engineer, Office of the Executive Engineer (KSEB), Transmission Division, PathanamthittA
- Assistant Executive Engineer, Transmission Sub Division (KSEB), Pathanamthitta
- Assistant Engineer In Charge, Transmission Sub Division (KSEB), Pathanamthitta
- M. Biju
Legal Representation & Advocates
Counsels for Petitioners
- • Sri. Jacob P. Alex
- • Sri. Joseph P. Alex
- • Manu Sankar P.
Case Synopsis & Summary
The petition challenges Ext.P5 (risk and cost), Exts.P7 and P8 (revenue-recovery notices) issued under the Kerala Revenue Recovery Act, following termination of a contract for yard leveling and metaling under tender Exh P1/P2. The agreement (Exh P2) dated 23.12.2009 was for yard leveling and metaling; work could not commence on time because the 7th respondent conducted cable trench work at the same site, delaying handover. The 4th respondent quantified risk and cost at Rs. 1,50,749 under Ext.P5 without giving the petitioner an opportunity of hearing. The petitioner contends this unilateral computation is impermissible and refers to Clause 14 of the tender specification, which suggested referral to the 3rd respondent. Ext P7 and P8 were issued under Sections 7 and 34 of the Kerala Revenue Recovery Act. The petitioner sought quashing of these orders, and reliance was placed on Kaikkara Construction Company v. State of Kerala and Another (2022 (2) KHC 541) to argue that damages arising from a contractual breach cannot be assessed unilaterally in the presence of a dispute, requiring independent adjudication. The Government Pleader cited decisions (Gangotri Enterprises Ltd. v. Union of India; Raman Iron Foundry; Kamaluddin Ansari; State of Gujarat v. Amber Builders) to justify the prior approach. The Court allowed the petition in part, quashing Ext.P5, Exts.P7 and P8, and directed the 4th respondent to reconsider after providing an opportunity of hearing to the petitioner.
Provisions of Law Cited
Legal Doctrines & Maxims
- In contract disputes, unilateral assessment of damages by one party is impermissible where a dispute exists; independent adjudication is necessary (Kaikkara Construction Co. v. State of Kerala).
Submissions & Arguments
Contentions of Appellants / Petitioners
The petitioners argue that Ext.P5 (risk and cost) was issued without any opportunity of hearing, based on unilateral quantification amid a delay caused by the 7th respondent’s cable trench work at the site. They contend that the tender terms and clause 14 required referral to the 3rd respondent and that the unilateral computation of damages is illegal. They rely on the Kaikkara judgment to insist on independent adjudication when a dispute exists.
Contentions of Respondents
The respondents contend that the law and prior decisions allow for other processes of quantifying damages in contracts; they argued the earlier dicta (Gangotri Enterprises Ltd., Raman Iron Foundry, Kamaluddin Ansari, Amber Builders) were not touched upon by the court and that remedies through revenue recovery and notices under the Revenue Recovery Act are consistent with statutory and contractual provisions.
Cited Precedents (5)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Kaikkara Construction Company v. State of Kerala and Another | 2022 (2) KHC 541 | Positive | Cited and relied upon to support the proposition that unilateral damages determination in a dispute requires independent adjudication. |
| M/s. Gangotri Enterprises Ltd. v. Union of India | 2016 (11) SCC 720 | Mentioned Only | Referenced in the Government Pleader’s argument as part of the prior jurisprudence but not adopted by the court in this decision. |
| Raman Iron Foundry's case | — | Mentioned Only | Cited in discussions about prior dicta on unilateral damages but not treated as binding in this judgment. |
| Kamaluddin Ansari's case | — | Mentioned Only | Cited in context of overruled arguments; court rejects the contention that it overruled earlier dicta. |
| State of Gujarat v. Amber Builders | 2020 (2) SCC 540 | Mentioned Only | Cited in debate about earlier dicta; not adopted as controlling in this case. |
Diagnostic Tool
Does this judgment govern your specific facts?
Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against B. Suresh v. State of Kerala and Others and instantly map out authorities that support, challenge, or govern your position.
Extracted Judgment Text
Exact text extracted from official judgment records.