AYYAMPILLY KIZHAKKEPADAM KARSHAKA SAMAJAM v KUZHUPPILLY GRAMA PANCHAYATH and others

Case / Petition Number:FAO No. 90 of 2009

Case Details & Bench

Court
High Court
Hon'ble Judges
  • T.R. Ramachandran Nair
  • K.P. Jyothindranath
Judgment Date
2015-06-01
Court Decision / Holding
Appeal dismissed; the appellants’ challenge to the Sub Court’s rejection of maintainability fails; Section 14 of the Limitation Act cannot be invoked since Ombudsman proceedings are not civil court proceedings.
Final Disposition
Appeal dismissed; parties to bear their own costs; final order confirms that Section 14 cannot be invoked against Ombudsman proceedings for this matter.

Parties to the Case

Appellants / Petitioners

  • AYYAMPILLY KIZHAKKEPADAM KARSHAKA SAMAJAM, KUZHUPPILLY VILLAGE, AYYAPPILLY P.O. KOCHI TALUK, REPRESENTED BY ITS PRESIDENT JEMES S/O.THATTATH KUZHUPPILLY VILLAGE

Respondents

  • KUZHUPPILLY GRAMA PANCHAYATH, represented by its Secretary
  • PRESIDENT, KUZHUPPILLY GRAMA PANCHAYATH
  • VICE PRESIDENT, KUZHUPPILLY GRAMA PANCHAYATH
  • C.A.WILSON, S/O.ARJUNAN, PRESIDENT OF KUZHUPPILLY GRAMA PANCHAYATH
  • KORATH S/O KOCHAKKAN ITTIRA, VICE PRESIDENT OF KUZHUPPILLY GRAMA PANCHAYATH
  • SANTHA W/O MOHANAN, SECRETARY OF KUZHUPPILLY GRAMA PANCHAYATH

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri Sreelal N. Warrier
  • • Sri B. Raghunandanan

Counsels for Respondents

  • • Sri H.B. Shenoy
  • • Sri B. Ashok Shenoy
  • • Sri Lakshmi B. Shenoy
  • • Sri Abu Mathew
  • • Sri Sobhan George
  • • Sri K.V. George

Case Synopsis & Summary

This Kerala High Court appeal arises from a Sub Court order in OP(Indigent) 22/2002, culminating in FAO 90/2009 filed by the appellants challenging the order regarding indigent status and the maintainability of a suit for damages arising from demolition of a shed and related materials on the Samajam’s property in Kuzhuppilly Village. The appellants—an association and its officers—claimed damages for illegal demolition and loss of materials intended for constructing a sluice. The Sub Court had remanded and directed consideration under Section 249(1)(b) of the Kerala Panchayat Raj Act, noting that a notice under Section 249(1)(a) was absent and that the six-month limit after accrual under 249(1)(b) might have lapsed. The appellants contended that the period should be excluded under Section 14 of the Limitation Act because proceedings before the Ombudsman (initiated 4.1.2002 and culminating 27.9.2002) and the indigent petition (19.11.2002) formed a continuum, and that Ombudsman proceedings are not courts but quasi-judicial bodies. The respondents argued there was no notice under 249(1)(a), and that the Ombudsman does not meet the test of a “civil court” for purposes of Section 14. The High Court, relying on Engineering Enterprises and Parameswaran Pillai, held that Ombudsman cannot be equated with a civil court for Section 14 purposes and that the prior proceedings cannot be treated as civil proceedings. Consequently, the appeal was dismissed with costs.

Provisions of Law Cited

Kerala Panchayat Raj Act, Section 249(1)(a)Kerala Panchayat Raj Act, Section 249(1)(b)Limitation Act, Section 14Kerala Panchayat Raj Act, Section 271-GKerala Panchayat Raj Act, Section 271-FKerala Panchayat Raj Act, Section 271-JKerala Panchayat Raj Act, Section 271-KLand Acquisition Act, Section 28A

Legal Doctrines & Maxims

  • Ombudsman cannot be equated with a civil court for purposes of Section 14 of the Limitation Act
  • Exclusion of time under Section 14 of the Limitation Act requires bona fide proceedings in a court
  • Authority under Section 28A of the Land Acquisition Act cannot be equated with a civil court

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contend that the order allowing indigent status was vide OP 22/2002; remand and consideration under Section 249(1)(b) of the Kerala Panchayat Raj Act require a notice under Section 249(1)(a) and compliance with the six-month period; they argue that the Ombudsman proceedings (4.1.2002 to 27.9.2002) coupled with the indigent petition (19.11.2002) should be excluded under Section 14 of the Limitation Act, as both prior and subsequent proceedings relate to the same cause of action and were prosecuted by the same parties; they rely on Engineering Enterprises v. Principal Secretary (2008) 7 SCC 169 and Parameswaran Pillai v. State of Kerala (2014 (3) KLT 597) to justify treating time taken in Ombudsman proceedings as not fatal to maintainability. They also stress the need for a proper notice under 249(1)(a).

Contentions of Respondents

The respondents submit that no notice under Section 249(1)(a) was issued and that the suit must be instituted within six months after accrual under Section 249(1)(b); they argue Ombudsman cannot be equated with a civil court, hence Section 14 cannot be invoked to extend limitation; consequently, the appeal should be dismissed on the ground of maintainability and compliance.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Engineering Enterprises v. Principal Secretary, Irrigation Department and other connected matters(2008) 7 SCC 169PositiveCited to explain the test for excluding time under Section 14 of the Limitation Act and that bona fide proceedings in a court without jurisdiction may not be treated as a civil proceeding.
Parameswaran Pillai v. State of Kerala2014 (3) KLT 597Mentioned OnlyCited in connection with discussions around whether certain proceedings can be treated as civil for limitation purposes; the main reasoning rests on Engineering Enterprises rather than this case.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against AYYAMPILLY KIZHAKKEPADAM KARSHAKA SAMAJAM v KUZHUPPILLY GRAMA PANCHAYATH and others and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT: THE HONOURABLE MR.JUSTICE T.R.RAMACHANDRAN NAIR & THE HONOURABLE MR. JUSTICE K.P.JYOTHINDRANATH MONDAY, THE 1ST DAY OF JUNE 2015/11TH JYAISHTA, 1937 FAO.No. 90 of 2009 ( ) ----------------------- AGAINST THE ORDER/JUDGMENT IN OP 22/2002 of PRINCIPAL SUB COURT,NORTH PARAVUR DATED 30-06-2008 APPELLANT(S)/PETITIONERS: ----------------------------------------------- 1. AYYAMPILLY KIZHAKKEPADAM KARSHAKA SAMAJAM, KUZHUPPILLY VILLAGE, AYYAPPILLY P.O. KCHI, REP. BY ITS, PRESIDENT JEMES S/O.THATTATH KUZHUPPILLY VILLAGE, KOCHI TALUK. 2. SECRETARY, M.M.POULOSE, S/O.MATHEW, KILLIYANTHIPARAMBIL, AYYAMPILLY KUZHUPPILLY VILLAGE, KOCHI TALUK, AND 3. TREASURER, MURALI, S/O.SREEDHARAN, KOLUPURATH VEETTIL, AYYAMPILLY KUZHUPPILLY VILLAGE, KOCHI TALUK. BY ADVS.SRI.SREELAL N.WARRIER SRI.B.RAGHUNANDANAN RESPONDENT(S):RESPONDENTS ---------------------------- 1. KUZHUPPILLY GRAMA PANCHAYATH, AYYAMPILLY P.O., ERNAKULAM DISTRICT REP. BY ITS SECRETARY. 2. PRESIDENT, KUZHUPPILLY GRAMA PANCHAYATH, AYYAMPILLY P.O., ERNAKULAM DISTRICT. 3. VICE PRESIDENT, KUZHUPPILLY GRAMA PANCHAYATH, AYYAMPILLY P.O., ERNAKULAM DISTRICT. 4. C.A.WILSON, S/O.ARJUNAN, PRESIDENT OF KUZHUPPILLY GRAMA PANCHAYATH CHERUPARAMBIL HOUSE, AYYAMPILLY P.O. ERNAKULAM DISTRICT. 5. KORATH, S/O.KOCHAKKAN ITTIRA, VICE PRESIDENT OF KUZHUPPILLY GRAMA PANCHAYATH KOCHAKKAN (PATHIYIL), MANAPPILLY KARA, AYYAMPILLY P.O. ERNAKULAM DISTRICT. 6. SANTHA, W/O.MOHANAN, SECRETARY OF KUZHUPPILLY GRAMA PANCHAYATH MATTACKAL HOUSE, AYYAMPILLY P.O., ERNAKULAM DISTRICT. R,R1 BY ADV. SRI.H.B.SHENOY,SC,KUZHUPPALLY G.PANCHAY R,R1 BY ADV. SRI.B.ASHOK SHENOY R,R1 BY ADV. SMT.LAKSHMI B.SHENOY R,R1 BY ADV. SRI.ABU MATHEW R,R1 BY ADV. SRI.SOBHAN GEORGE R,R1 BY ADV. SRI.K.V.GEORGE THIS FIRST APPEAL FROM ORDERS HAVING BEEN FINALLY HEARD ON 01-06-2015, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING: ## **T.R. RAMACHANDRAN NAIR & K.P. JYOTHINDRANATH, JJ.** **- - - - - - - - - - - - - - - - - - - - - - - - -** ## **F.A.O.No.90 of 2009** **- - - - - - - - - - - - - - - - - - - - - - - - - Dated this the 1[st] day of June, 2015** ## **JUDGMENT** ## **Ramachandran Nair, J.** This appeal is filed by the appellants aggrieved by the order passed by the Principal Sub Court, North Parur in O.P.(Indigent) No.22/2002. 2. We heard Shri Sreelal Warriar, learned counsel for the appellants and Shri Asok Shenoy learned counsel for the respondents. 3. The original petition was filed by the appellants claiming damages for the illegal demolition of the shed, wooden materials stored for constructing sluice, etc. owned by the Samajam in its property having an extent of 4.018 cents comprised in Sy. No.238/2 of Kuzhuppilly Village, against the first respondent Panchayat. The application for permission to sue as indigent person was once allowed as per order dated 31.5.2005 which was challenged by the respondents FAO 90/2009 2 in W.P.(C) No.32401/2005 before this Court. The order was set aside and the matter was remanded back for fresh consideration. While remanding the matter, this Court directed the court below to consider the maintainability of the suit in view of Section 249 (1)(b) of the Kerala Panchayat Raj Act. In the said section, pre conditions have been prescribed by the statute for maintaining the suit of the present nature by way of a notice and the period for institution of the suit has also been provided as six months next after the accrual of the cause of action. 4. The court below, by the impugned order, found that no notice was issued under Section 249(1)(a) of the Panchayat Raj Act. It was also found that as per Section 249(1)(b) as the suit has to be instituted within six months after accrual of the cause of action and, there is noncompliance of the same. 5. In the course of the argument, it was also contended that the appellants had approached the Ombudsman for Local Self Government Institutions and the said period is liable to be excluded under Section FAO 90/2009 3 14 of the Limitation Act. All these contentions were rejected by the Sub Court, against which the present appeal is filed. 6. The contention raised by the learned counsel for the appellants is that the application was filed before the learned Ombudsman as O.P.No.7/2002 on 4.1.2002. The alleged demolition was on 16.1.2001. The final order passed by the learned Ombudsman is dated 27.9.2002 whereby the appellants were directed to approach the civil court. It is thereafter the Indigent O.P. was filed admittedly, i.e. on 19.11.2002. 7. For the application of Section 14 of the Limitation Act, various conditions are to be satisfied. One of the main aspect to be considered is whether the appellants have been prosecuting with due diligence “another civil proceeding”, whether in a court of first instance or of appeal or revision. 8. A Division Bench of this Court had occasion to consider the matter in the light of the question whether the authority under Section 28A of the Land Acquisition Act can be equated with a civil court as contemplated under Section 14 of the Limitation Act, in the decision FAO 90/2009 4 reported in **Parameswaran Pillai v. State of Kerala** (2014 (3) KLT 597). We need only consider the following extract from paragraph 12. After referring to the decision of the Apex Court in **Engineering** **Enterprises v. Principal Secretary, Irrigation Department and other connected matters** {(2008) 7 SCC 169}, the Division Bench has extracted paragraph 21 of the Apex Court decision which we reproduce below: “21. Section 14 of the Limitation Act deals with exclusion of time of proceeding _bona fide_ in a court without jurisdiction. On analysis of the said Section, it becomes evident that the following conditions must be satisfied before Section 14 can be pressed into service: (1) Both the prior and subsequent proceedings are civil proceedings prosecuted by the same party; (2) The prior proceeding had been prosecuted with due diligence and in good faith; (3) The failure of the prior proceeding was due to defect FAO 90/2009 5 of jurisdiction or other cause of like nature; (4) The earlier proceeding and the latter proceeding must relate to the same matter in issue and; (5) Both the proceedings are in a court.” Going by the same, both the prior and subsequent proceedings should be civil proceedings and both the proceedings should be in a court also. Finally, the Division Bench found that the authority under Section 28A of the Land Acquisition Act cannot be equated with a civil court. Similar is the position herein also. We are of the view that Ombudsman cannot be equated with a court for the purpose of Section 14 of the Limitation Act. Apart from the same, both the proceedings cannot be said to be civil proceedings. 9. The institution of Ombudsman is one created under Section 271-G of the Panchayat Raj Act. There, the proceedings initiated should be in the nature of a complaint, going by the definition under Section 271F, especially sub-clause (c). An Ombudsman can be approached by filing a complaint raising an allegation that a public FAO 90/2009 6 servant or a local self Government institution is guilty of corruption or mal administration. Going by the functions of the learned Ombudsman provided under Section 271-J: (i) He can investigate into any allegation contained in a complaint or on a reference from Government or that has come to the notice of the learned Ombudsman; and (ii) enquire into any complaint in which corruption or mal administration of a public servant or a Local Self Government Institution is alleged. Sub-section (iii) provides the manner in which an order can be passed. Sub-clause (b) therein will indicate that where the irregularity causes loss or inconvenience to a citizen, the Ombudsman can direct the Local Self Government Institution to give him compensation and to reimburse the loss from the person responsible for the irregularity. Even though under Section 271-K of the Act, it is stated that the Ombudsman shall, for the purpose of any investigation or enquiry under the Act, have the same powers as are vested in a civil court while trying a suit under the Code of Civil Procedure, 1908, in respect of the enumerated matters (a) to (f) FAO 90/2009 7 therein, those are only procedural provisions which could be made use of by the Ombudsman for the purpose of investigation or enquiry. That will not alter the position. 10. We find no reason to equate the said power as equal to the power of civil court in a case where damages are claimed from the respondents. Herein, if mal administration is found by the learned Ombudsman, he can award compensation. As far as the present claim is concerned, the same is termed as claim for damages for demolishing a shed. For all these reasons, we find that the appellant will not be entitled to rely upon Section 14 of the Limitation Act. On the said sole ground, the appeal fails and the same is dismissed. The parties will suffer their costs in the appeal. ## **(T.R. RAMACHANDRAN NAIR, JUDGE.)** ## **(K.P. JYOTHINDRANATH,, JUDGE.)** **kav/**