Ayodhya Faizabad Development Authority and Anr. v. Ram Newaj and Others

Case / Petition Number:
CIVIL APPEAL NO.2916 OF 2022

Case Synopsis & Summary

This appeal concerns challenge to an Allahabad High Court order holding that three plots acquired under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (the 2013 Act) had lapsed under Section 24(2) because compensation was not deposited in court, even though it was deposited with the Treasury and possession had been taken. The Supreme Court examines whether non-deposit in court triggers lapse and whether provisos to the 24(2) provision or earlier judgments apply. The Court recognizes the evolving view, citing Delhi Development Authority v. Sukhbir Singh (2016) 16 SCC 258, but endorses the later Indore Development Authority v. Manoharlal and Others (2020) 8 SCC 129, which clarifies the interpretation of Section 24(2) and related provisions (including Sections 24(1)(a) and 24(1)(b)). It holds that the word “paid” in Section 24(2) does not include mere deposit of compensation in court; if compensation has been deposited with the Treasury and possession has been taken within the relevant window, lapse does not occur. It also explains computation of the five-year period excluding interim orders and that tender under Section 31 of the 1894 Act completes the obligation. Consequently, the appeal is allowed, the High Court’s order is quashed, and the writ petition is dismissed with no costs. The decision clarifies the conditions under which lapse may or may not be deemed.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • M. R. Shah
  • B. V. Nagarathna
Judgment Date
2022-05-20
Court Decision / Holding
Appeal allowed; the impugned judgment and order of the High Court are quashed and set aside; the writ petition preferred by the original writ petitioners is dismissed; there shall be no order as to costs.
Final Disposition
Appeal allowed; writ petition dismissed; High Court order set aside.

Parties to the Case

Appellants / Petitioners

  • Ayodhya Faizabad Development Authority
  • Anr.

Respondents

  • Ram Newaj
  • others

Provisions of Law Cited

Section 24(1)(a) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013Section 24(1)(b) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013Proviso to Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013Section 31 of the Land Acquisition Act, 1894Section 34 of the Land Acquisition Act, 1894Section 16 of the Land Acquisition Act, 1894Section 4 of the Land Acquisition Act, 1894

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contend that Section 24(2) deems lapse only if compensation has neither been paid nor deposited in court for five years; since compensation was deposited with the Treasury and possession was taken on 07.09.2005, lapse cannot be declared. Relying on Indore Development Authority v. Manoharlal (2020) 8 SCC 129, they submit that the proviso to Section 24(2) and the interpretation in para. 366 show non-deposit in court does not automatically cause lapse, and that tender under Section 31 of the 1894 Act completes the obligation. They argue the High Court erred in following Delhi Development Authority v. Sukhbir Singh (2016) 16 SCC 258 and that the appeal should be allowed.

Contentions of Respondents

The respondents contend that Section 24(2) creates a deemed lapse for failure to deposit compensation in court within the prescribed period, irrespective of possession, and the High Court correctly held that the proceedings lapsed. They rely on Delhi Development Authority v. Sukhbir Singh and other precedents to argue that the statutory scheme requires deposit in court to preserve the proceedings, and that five-year computation excludes interim orders.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Delhi Development Authority v. Sukhbir Singh and Others(2016) 16 SCC 258OverruledThe later Indore Development Authority decision clarifies that non-deposit in court does not automatically cause lapse under Section 24(2); thus the Delhi decision is not controlling law in this context.
Indore Development Authority v. Manoharlal and Others(2020) 8 SCC 129PositiveProvides the controlling interpretation of Section 24(2) and related provisions; applied by the Court to hold that lapse does not occur where possession has been taken and compensation deposited with Treasury.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,247 words•~6 min read

In The Court Record

Ayodhya Faizabad Development Authority and Anr. v. Ram Newaj and Others

## **REPORTABLE** IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION ## **CIVIL APPEAL NO.2916 OF 2022** Ayodhya Faizabad Development Authorityand Anr. ..Appellants Versus Ram Newaj and others ..Respondents ## **J U D G M E N T** **M. R. Shah, J.** 1. Feeling aggrieved and dissatisfied with the impugned judgment and order dated 19.07.2017 passed by the High Court of Judicature at Allahabad, Lucknow Bench, Lucknow in Miscellaneous Bench No.3962 of 2005 by which the High Court has allowed the said writ petition preferred by the respondents herein – original writ petitioners and has held that the acquisition proceedings in respect of the three plots in question Signature Not Verified pertaining to the original writ petitioners stand lapsed under sub­ Digitally signed by Jatinder Kaur Date: 2022.05.20 17:14:33 IST Reason: section (2) of Section 24 of the Right to Fair Compensation and 1 Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as ‘the Act 2013’) , the Ayodhya Faizabad Development Authority and another has preferred the present appeal. 2. We have heard learned counsel for the respective parties at length. We have perused the impugned judgment and order passed by the High Court. 3. By the impugned judgment and order the High Court has held that the acquisition proceedings with respect to the three plots in question shall stand lapsed under sub­section (2) of Section 24 of the Act, 2013 solely on the ground that, though the deposit of the compensation was made in the Treasury, but the same was not deposited in the Court and consequently the payment of compensation of the amount was not made to the land owners. The High Court has relied upon the decision of this Court in the case of **Delhi Development Authority versus Sukhbir Singh and others, (2016) 16 SCC 258.** However, in view of the subsequent decision of this Court in the case of **Indore Development Authority versus Manoharlal and others,** **(2020) 8 SCC 129,** the impugned judgment and order passed by 2 the High Court is unsustainable. In paragraph 366 of the aforesaid judgment this Court has observed and held as under: **“366.** In view of the aforesaid discussion, we answer the questions as under: **366.1.** Under the provisions of Section 24(1)( _a_ ) in case the award is not made as on 1­1­2014, the date of commencement of the 2013 Act, there is no lapse of proceedings. Compensation has to be determined under the provisions of the 2013 Act. **366.2.** In case the award has been passed within the window period of five years excluding the period covered by an interim order of the court, then proceedings shall continue as provided under Section 24(1)( _b_ ) of the 2013 Act under the 1894 Act as if it has not been repealed. **366.3.** The word “or” used in Section 24(2) between possession and compensation has to be read as “nor” or as “and”. The deemed lapse of land acquisition proceedings under Section 24(2) of the 2013 Act takes place where due to inaction of authorities for five years or more prior to commencement of the said Act, the possession of land has not been taken nor compensation has been paid. In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly, if compensation has been paid, possession has not been taken then there is no lapse. **366.4.** The expression “paid” in the main part of Section 24(2) of the 2013 Act does not include a deposit of compensation in court. The consequence of non­deposit is provided in the proviso to Section 3 24(2) in case it has not been deposited with respect to majority of landholdings then all beneficiaries (landowners) as on the date of notification for land acquisition under Section 4 of the 1894 Act shall be entitled to compensation in accordance with the provisions of the 2013 Act. In case the obligation under Section 31 of the Land Acquisition Act, 1894 has not been fulfilled, interest under Section 34 of the said Act can be granted. Non­deposit of compensation (in court) does not result in the lapse of land acquisition proceedings. In case of non­ deposit with respect to the majority of holdings for five years or more, compensation under the 2013 Act has to be paid to the “landowners” as on the date of notification for land acquisition under Section 4 of the 1894 Act. **366.5.** In case a person has been tendered the compensation as provided under Section 31(1) of the 1894 Act, it is not open to him to claim that acquisition has lapsed under Section 24(2) due to non­payment or non­deposit of compensation in court. The obligation to pay is complete by tendering the amount under Section 31(1). The landowners who had refused to accept compensation or who sought reference for higher compensation, cannot claim that the acquisition proceedings had lapsed under Section 24(2) of the 2013 Act. **366.6.** The proviso to Section 24(2) of the 2013 Act is to be treated as part of Section 24(2), not part of Section 24(1)( _b_ ). **366.7.** The mode of taking possession under the 1894 Act and as contemplated under Section 24(2) is by drawing of inquest report/memorandum. Once award has been passed on taking possession 4 under Section 16 of the 1894 Act, the land vests in State there is no divesting provided under Section 24(2) of the 2013 Act, as once possession has been taken there is no lapse under Section 24(2). **366.9.** Section 24(2) of the 2013 Act does not give rise to new cause of action to question the legality of concluded proceedings of land acquisition. Section 24 applies to a proceeding pending on the date of enforcement of the 2013 Act i.e. 1­1­2014. It does not revive stale and time­ barred claims and does not reopen concluded proceedings nor allow landowners to question the legality of mode of taking possession to reopen proceedings or mode of deposit of compensation in the treasury instead of court to invalidate acquisition. **366.8.** The provisions of Section 24(2) providing for a deemed lapse of proceedings are applicable in case authorities have failed due to their inaction to take possession and pay compensation for five years or more before the 2013 Act came into force, in a proceeding for land acquisition pending with the authority concerned as on 1­1­2014. The period of subsistence of interim orders passed by court has to be excluded in the computation of five years.” 3.1 Applying the law laid down by this Court in the case of **Indore Development Authority (supra)** and in the present case as the amount of compensation was deposited with the Treasury and even the possession was already taken over on 07.09.2005, 5 the impugned judgment and order passed by the High Court holding that the land acquisition proceedings with respect to the lands in question are deemed to have lapsed deserves to be quashed and set aside. 4. In view of the above discussion and for the reasons stated above present appeal succeeds. The impugned judgment and order passed by the High Court is hereby quashed and set aside. Consequently, the writ petition preferred by the original writ petitioner before the High Court stands dismissed. In the facts and circumstances of the case, there shall be no order as to costs. …………………………………J. **==> picture [171 x 14] intentionally omitted <==** …………………………………J. ## **(B.V. NAGARATHNA)** New Delhi, May 20, 2022. 6
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.