Axis Bank Limited v. Naren Sheth & Anr.
Case Synopsis & Summary
This is a Civil Appeal under Section 62 of the Insolvency and Bankruptcy Code, 2016, challenging the correctness of an NCLAT order that upheld admission of a Section 7 IBC petition filed by Respondent No.2 (State Bank of India) against the Corporate Debtor, originally Universal Premises and Textiles Private Limited and later renamed Shreem Corporation Limited. The matter traces a complex payment dispute over a security deposit and a mortgage tied to a Solaris building project. The SBI declared the Corporate Debtor as an NPA on 28.06.2013, and the IBC petition was filed on 22.01.2020, with delay of 662 days (as later amended). The Adjudicating Authority admitted the petition after condoning delay; the IRP was appointed and published. Axis Bank challenged, arguing limitation barred the petition: the three-year limit for IBC filings from the NPA date (31.03.2013) expired in 2016, and the debtor’s balance-sheet and other documents could not revive time. The Respondent/ SBI argued that multiple acknowledgments and one-time settlements within the statutory extensions under Section 18 and Section 5 of the Limitation Act reset or extend the period. The Court examined the balance-sheet acknowledgment dated 31.03.2015 and three OTS proposals (16.03.2017, 01.01.2018, 16.05.2019) as valid acknowledgments, applying purposive statutory interpretation to grant time. The Supreme Court ultimately dismissed the appeal, holding the petition timely and the IBC proceedings to continue, thereby upholding the NCLAT/NCLT sequence.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- Vikram Nath
- Ahsanuddin Amanullah
- Judgment Date
- 2023-09-12
- Court Decision / Holding
- Appeal dismissed. The Supreme Court held that the IBC petition was timely due to the extensions under Section 18 and 5 of the Limitation Act, anchored by acknowledgments in the balance sheet and multiple OTS proposals within three-year windows. It upheld the Adjudicating Authority’s admission of the Section 7 petition and affirmed the NCLAT’s dismissal of the appeal, thereby allowing the CIRP to continue.
- Final Disposition
- Appeal dismissed; IBC proceedings permitted to continue; NCLAT/NCLT order upheld against the appellant.
Parties to the Case
Appellants / Petitioners
- AXIS BANK LIMITED
Respondents
- NAREN SHETH & ANR.
Legal Representation & Advocates
Counsels for Petitioners
- • Shri Sanjiv Sen, Senior Counsel (for the Appellant)
Counsels for Respondents
- • Shri N. Venkataraman, Additional Solicitor General (for Respondent No.2)
Provisions of Law Cited
Legal Doctrines & Maxims
- Purposive interpretation of statutes to advance the cause of justice
- No bar in law to amendment of pleadings in an application under Section 7 IBC (as discussed in related jurisprudence)
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellant argued that the Section 7 petition was time-barred as per the NPA date of 28.06.2013 (balance-sheet basis 31.03.2013) with a three-year period ending 31.03.2016. It contended that merely citing balance-sheet entries or external OTS proposals cannot revive limitation, and that Section 14 of the Limitation Act has no applicability because SARFAESI proceedings did not lack jurisdiction. The appellant also disputed the admissibility of late-filed documents introduced during appeal and urged a strict interpretation of Section 18 (acknowledgment) and Section 5 (extension) of the Limitation Act.
Contentions of Respondents
The Respondent No.2 contended that multiple acknowledgments and OTS proposals within the limitation window extended the period. It relied on the balance-sheet entry (31.03.2015) and three OTS proposals (16.03.2017, 01.01.2018, 16.05.2019) to claim fresh periods under Section 18, supplemented by Section 5. It argued that SARFAESI proceedings were within jurisdiction and thus Section 14 is inapplicable. The Respondent also invoked decisions like Dena Bank, Kotak Mahindra Bank Ltd., and Asset Reconstruction Co. to justify extending limitation under the IBC framework.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (15)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Jignesh Shah & Anr. v. Union of India & Anr. | 2019(10) SCC 750 | Mentioned Only | Cited by appellant for general limitation principles but not relied upon to decide the case. |
| Invent Asset Securitisation & Reconstruction Pvt. Ltd. v. M/s Girnar Fibres Ltd. | 2019(11) SCC 633 | Mentioned Only | Cited in context of limitation and acknowledgment rules but not adopted as the controlling authority. |
| Invent Assets Securitization & Reconstruction Private Limited v. Xylon Electrotechnic Private Limited | 2020(15) SCC 1 | Mentioned Only | Cited for related principles but not decisive for the outcome here. |
| Vashdeo R. Bhojwani v. Abhyudaya Co-Operative Bank Limited | 2021(10) SCC 330 | Mentioned Only | Not pivotal to the decision; cited in the discussion of acknowledgments. |
| B.K. Educational Services Private Limited v. Parag Gupta and Associates | 2019(9) SCC 158 | Mentioned Only | Referenced as part of limitation discussions but not binding on the core issue. |
| Babulal Vardharji Gurjar v. Veer Gurjar Aluminium Industries Pvt. Ltd. & Anr. | 2004(4) SCC 252 | Mentioned Only | Cited in the backdrop of related statutory interpretations; not a controlling authority here. |
| Ome Prakash Verma v. Amit Jain & Anr. | [17] | Mentioned Only | Cited in the appellant’s list but not central to the final reasoning. |
| Insolvency Law Report, March 2018 | [12] | Mentioned Only | Cited as a scholarly reference; not a binding determinant. |
| Rajendra Narottamdas Sheth v. Chandra Prakash Jain and Another | [18] | Mentioned Only | Cited in the broader discussion of legal principles; not a decisive precedent. |
| Gopal Sardar v. Karuna Sardar | [19] | Mentioned Only | Listed among authorities but not the controlling authority. |
| Serish Maji v. Nishit Kumar Dolui | [20] | Mentioned Only | Cited as background authority; not essential to the holding. |
| Dena Bank (Now Bank of Baroda) v. C. Sivakumar Reddy and Another | [24] | Positive | Recognized for allowing balance-sheet acknowledgments to extend the period under Section 18 of the Limitation Act. |
| Kotak Mahindra Bank Limited v. Kew Precision Parts Private Limited and Ors | [22] 2022 SCC 364 | Positive | Approved use of Section 18 based extensions in similar contexts. |
| Asset Reconstruction Company (India) Limited v. Bishal Jaiswal and Another | [23] 2021 SCC 366 | Positive | Support for treating acknowledgments and restructuring actions as extensions of limitation. |
| Sesh Nath Singh v. Baidyabati Sheoraphuli Co-Operative Bank Limited and Another | [25] 2021 SCC 633 | Mentioned Only | Cited within the broader limitation discussions but not essential to the decision. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Axis Bank Limited v. Naren Sheth & Anr.
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.