High CourtDivision BenchAppeal disposed of.

Asian Thermal Insulation (I) P. Ltd. v. Bridge & Roof Co. (I) Ltd.

Case / Petition Number:Civil Appeal No. 3696 of 2007
Neutral Citation:(2007) 8 S.C.R. 1006

Case Details & Bench

Court
High Court
Hon'ble Judges
  • Dr. Arijit Pasayat
  • K. Thakker
  • Lokeshwar Singh Pant
Judgment Date
2007-08-13
Court Decision / Holding
Appeal disposed of with no order as to costs. The appellant shall nominate its arbitrator within 30 days; the respondent shall nominate its arbitrator within 30 days; thereafter the Chief Justice of the High Court shall nominate the Presiding Arbitrator who shall be a retired Judge of any High Court.
Final Disposition
Appeal disposed of.

Parties to the Case

Appellants / Petitioners

  • Asian Thermal Insulation (I) P. Ltd.

Respondents

  • Bridge & Roof Co. (I) Ltd.

Legal Representation & Advocates

Counsels for Petitioners

  • • Kumud Lata Das

Counsels for Respondents

  • • Puneet Jain
  • • Sushil Kumar Jain
  • • H. D. Thanvi
  • • Sarad Singhania
  • • Christi Jain

Case Synopsis & Summary

Asian Thermal Insulation (I) P. Ltd. (appellant) and Bridge & Roof Co. (I) Ltd. (respondent) entered into a contract containing an arbitration clause. Disputes arose over interpretation and performance of the order dated 22 December 2003. The arbitration clause invoked the Arbitration and Conciliation Act, 1996. On an application by the respondent, the Calcutta High Court directed that the matter be placed before the Chief Justice of the High Court for naming an arbitrator. The High Court did not recall its order, and, during pendency of proceedings, the parties reached a consensual arrangement: the appellant nominated Sri J. Chawla as its arbitrator; the respondent would nominate its arbitrator within 30 days; thereafter the Chief Justice of the High Court would nominate the Presiding Arbitrator, who would be a retired judge of any High Court. The Supreme Court disposed of the appeal, noting that the arrangement is permissible and that the matter would proceed in terms of Section 11(6) of the Act. It also reaffirmed the decision in SBP & Co. v. Patel Engg. Ltd. and observed that Konkan Rly. Corpn. Ltd. v. Rani Construction (P) Ltd. has been overruled. The Court held that once an arbitral tribunal is constituted, the High Court should not lightly interfere, and the remedies would lie under Sections 16, 34, and 37 of the Act. The appeal was disposed of with no order as to costs.

Provisions of Law Cited

Arbitration and Conciliation Act, 1996, Section 11(6)Arbitration and Conciliation Act, 1996, Section 11(8)Arbitration and Conciliation Act, 1996, Section 16Arbitration and Conciliation Act, 1996, Section 34Arbitration and Conciliation Act, 1996, Section 37

Legal Doctrines & Maxims

  • The power under Section 11(6) of the Act is a judicial power, not an administrative power.
  • The power under Section 11(6) can be delegated to another Judge of the High Court or a Judge of the Supreme Court.
  • Designation of a District Judge under Section 11(6) is not warranted by the scheme of the Act.
  • Once an arbitral tribunal is constituted, the High Court would not interfere with its orders except under the Act (e.g., Sections 16, 34) and appeals lie under Article 136.
  • There can be no appeal against an order of the Chief Justice of India or a Judge of the Supreme Court designated by him while entertaining a Section 11(6) application.
  • The Konkan Rly. decision was overruled by SBP & Co., and SBP provides the controlling framework for appointments under Section 11(6).

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant challenged the legality of the High Court's order directing the matter to be placed before the Chief Justice for naming an arbitrator. During pendency, the parties agreed to a consensual arrangement: the appellant would nominate an arbitrator (Sri J. Chawla) and the respondent would nominate its arbitrator within 30 days, followed by the Chief Justice of the High Court nominating the Presiding Arbitrator (a retired judge).

Contentions of Respondents

The respondent joined in the consensual arrangement to expedite arbitration, agreeing to nominate its arbitrator within 30 days and permitting the Chief Justice to appoint the Presiding Arbitrator.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
SBP & Co. v. Patel Engineering Ltd. & Anr.(2005) 8 SCC 618PositiveCited as establishing the judicial nature of the power under Section 11(6) and guiding the approach to appointing arbitrators under the Act.
Konkan Rly. Corpn. Ltd. v. Rani Construction (P) Ltd.(2002) 2 SCC 388OverruledNoted as overruled by SBP & Co.; the SBP framework governs the issue and Konkan Rly. is no longer good law in this context.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against Asian Thermal Insulation (I) P. Ltd. v. Bridge & Roof Co. (I) Ltd. and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

_f·_ A ASIAN THERMAL INSULATION (I) P. LTD. _v._ BRIDGE & ROOF CO. (I) LTD. ## AUGUST 13, 2007 B [DR. ARIJIT PASAYA T, £.K'.. THAKKER AND LOKESHWAR SINGH PANT A, JJ.] ,[.. ] _Arbitration and Conciliation Act, I 996-s. I I (6)-Dispute between_ c _Company and the Contractor-Agreement between them contained an arbitration clause-Issue of appointing arbitrator-On application of Company, High Court directing the matter to be placed before the Chief Justice-Appeal by Contractor before Supreme Court-Contractor had already nominated its arbitrator-Parties agreed on a consensual_ D _[arrangement-Appeal accordingly disposed. of-Company ][to ][nominate ][its ] arbitrator within 30 days-Thereafter Chief Justice of High Court to nominate the Presiding Arbitrator._ Respondent-company had entered into an agreement with Appellantcontractor. The agreement contained an arbitration clause. Disputes arose E[between the parties. ][Order ][was passed by the High Court on the application ] filed by Respondent. The matter was directed to be placed before the Chief Justice of High Court for naming an arbitrator. High Court declined to recall the order on the Appellant's petition. ~ _......_ ,, . >< During pendency of appeal before this Court, the parties agreed on a F consensual arrangement. Disposing of the appeal, the Court _-I_ HELD: Though arguments were advanced in support of the respective stand about the legality of the impugned order, it was agreed to by the parties G that following arrangement can be made : The appellant has nominated one Sri J. Chawla to be its arbitrator. Within a period of 30 days the respondent shall nominate its arbitrator. Thereafter the Chief Justice of the High Court shail nominate the Presiding A.rbitrator who shall be a retired Judge of any High Court. [Para 6) (1008-B-C) _·r_ H 1004 ASIAN THERMAL INSULATION (I) P. LTD .... BRIDGE & ROOF CO. (l)LTD. (PASAYAT. J.) } 005 ~ _SBP & Co._ v. _Patel Engineering Ltd & Anr.,_ (2005) 8 SCC 618, relied A on. _Konkan Rly. Corpn. Ltd._ v. _Rani Construction (P) Ltd,_ (2002) 2 SCC 388, referred to. > CIVIL APPEL LA TE JURISDICTION : Civil Appeal No. 3696 of2007. B From the Order dated 19.9.2005 of the High Court of Calcutta in A.P. No. 209 of2005. __.r:--<_ Kumud Lata Das for the Appellant. c Puneet Jain, Sushi! Kumar Jain, H.D. Thanvi, Sarad Singhania and Christi Jain for the Respondent. > The Judgment of the Court was delivered by DR. ARIJIT PASAYA T, J. I. Leave granted. D 2. Controversy lies within a very narrow compass. ' . .. 3. The factual background as projected by the appellant is as follows: On 22.12.2003 work order was issued by the respondent to the appellant. E There was a clause for arbitration in the agreement which was to the following effect: ## "4 l. _ARB/TRA TION_ B&R confidently feel that there shall not arise any disputes or differences during execution and completion of this order by the Contractor. ~ ~ However, in the event of any disputes or differences arise between Company (B&R) and Contractor (hereinafter called the said parties) touching or concerning the interpretation of the terms and conditions G as performance of the order or in connection therewith or the rights and liabilities of either of the said parties hereto, the said parties shall endeavour to settle the same amicably through mutual agreement between them, but ifthe mutual settlement is not possible between the Company and the Contractor, the provisions of the Indian Arbitration & Conciliation Act, 1996 and all statutory re-enactment and H "' SUPREME COURT REPORTS [2007) 8 S.C.R. 1006 A B c modifications thereof and the rules made thereunder shall apply to such arbitrations." > 4. On 27.11.2004 a notice of demand was sent to the site of the respondent and it was returned with the p.ostal endorsement "refused". On 30.6.2005 the request was reiterated. On 9.8.2005 an order was passed by the High Court on the application filed by the respondent. The matter was directed to be placed before the Chief Justice of the High Court for naming an arbitrator. On 19.9.2005 the High Court refused to recall its order dated 9.8.2005 on the appellant's petition. On 26. l 0.2005, this Court in _SBP & Co._ v. _Patel Engineering Ltd. & Anr.,_ [2005] 8 SCC 618 has dealt with the nature of power exercised by the Chief .Justice of High Court or Chief Justice of India, as the case may be, under the Arbitration and Conciliation Act, 1996 (in short the 'Arbitration Act') and held that same is a judicial power and not an administrative power. The decision in _Konkan Rly. Corpn. Ltd._ v. _Rani Construction (P) Ltd.,_ [2002] 2 SCC 388 was overruled in _SBP & Co._ (supra). The conclusions per majority were as follows: _Y)-.._ ·"\ - D "47. We, therefore, sum up our conclusions as follows: - (i) The power exercised by the Chief Justice of the High Court or the Chief Justice of India under Section 11 (6) of the Act is not an administrative power. It is a judicial power. E - (ii) The power under Section 11(6) of the Act, in its entirety, could be delegated, by the Chief Justice of the High Court only to another Judge of that Court and by the Chief Justice of India to another Judge of the Supreme Court. - (iii) In case of designation of a Judge of the High Court or of the Supreme Court, the power that is exercised by the designated Judge would be that of the Chief Justice as conferred by the . statute. F - (iv) The Chief Justice or the designated Judge will have the right to decide the preliminary aspects as indicated in the earlier part of - G this judgment. These .will be his own jurisdiction to entertain the request, the existence of a valid arbitration agreement, the existence or otherwise of a live claim, the existence of the condition for the exercise of his power and on the qualifications of the arbitrator or arbitrators. The Chief Justice or the designated Judge would be entitled to seek the opinion of an institution in the matter of H ... _1_ 'T ... / ASIAN THERMAL INSULATION (I) P. LTD _v._ BRIDGE & ROOF CO. (I) LTD. [PASAYAT, J] 1007 .,,, nominating an arbitrator qualified in terms of Section 11 (8) of the A Act if the need arises but the order appointing the arbitrator could only be that of the Chief Justice or the designated Judge. - (v) Designation of a District Judge as the authority under Section 11(6) of the Act by the Chief Justice of the High Court is not warranted on. the scheme of the Act. B _-.,,,---r_ - (vi) Once the matter reaches the Arbitral Tribunal or the sole arb;trator, . the High Court would not interfere with the orders passed by the arbitrator or the Arbitral Tribunal during the course of the arbitration proceedings and the parties could approach the Court only in terms of Section 3 7 of the Act or in terms of Section 34 c of the Ac.t. - (vii) Since an order passed by the Chief Justice of the High Court or by the designated Judge of that Court is a judicial order, an appeal will lie against that order only under Article 136 of the Constitution to. the Supreme Court. D _-4_ - (viii) There can be no appeal against an order of the Chief Justice of India or a Judge of the Supreme Court designated by him while entertaining an application under Section 11(6) of the Act. - (ix) In a case where an Arbitral Tribunal has been constituted hy the parties without having recourse to Section 11(6) of the Act, the E Arbitral Tribunal will have the jurisdiction to decide all matters as contemplated by Section 16 of the Act. - (x) Since all were guided by the decision of this Court in _Konkan Rly. Corpn. Ltd._ v. _Rani Construction (P) Ltd._ and orders under Section 11(6) of the Act have been made based on the position F adopted in that decision, we clarify that appointments of arbitrators or Arbitral Tribunals thus far made, are to be treated as valid, all objections being left to be decided under Section 16 of the Act. As and from this date, the position as adopted in this judgment - will govern even pending applications under Section 11 ( 6) of the G - Act. - (XI) Where District Judges had been designated by the Chief Justice of the High Court under Section 11(6) of the Act, the appointment orders thus far made by them will be treated as valid; but applications if any pending before them as on this date will stand H ||1008|SUPREME COURT REPORTS<br>(2007] 8 S.C.R.| |---|---|---| |A||transferred, to be dealt with by the Chief Justiceofthe High| |||Court concerned or a Judgeofthat Court designated by the Chief| |||Justice.| |||(xit)The decisionin_Konkan Rly. Corpn. Ltd_v._Rani construction_| |||_(P)Ltd_isoverruled".| |B||5.Though arguments were advancedinsupportofthe respective stand| ||about the legality|about the legalityofthe impugned order,itwas agreed to by learned counsel| ||for thepartie~that following arrangement can be made.|| |||"The appellant has nominated one SriJ.Chawla tobeits arbitrator.| |c||Within a periodof30 days the respondent shall nominate its arbitrator.| |||Thereafter the Chief Justiceofthe High Court shall nominate the| |||Presiding Arbitrator who shall be a retired Judgeofany High Court."| |||7.Appealisaccordingly disposedofwith no order as to costs.| |J)|B.B.B.<br>Appeal disposed of.||